28
March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18, 2011 Betty Day

March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

Embed Size (px)

DESCRIPTION

3 Overall Activity Transaction Type Switches115,861 Move - Ins 318,528 Move Out CSA39,192 Total641,199 Since June 1, ,022,791 Retail Transactions Summary 02/28/ , ,894 69, ,929 02/28/ , ,509 78,127 17, , , ,765 83,829 30, , YTDFebruary 160, ,726 Mass Transition7, (Continuous Service Agreement) ERCOT Board of Directors March 22, 2011

Citation preview

Page 1: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

March 22, 2011ERCOT Board of Directors

Commercial Market Operations Version 2 - Updated on March 18, 2011

Betty Day

Page 2: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

2 ERCOT Board of Directors March 22, 2011

SummaryRetail Activity• Overall Activity – Activity continues to follow recent trends. A Mass Transition occurred during February; 99.75% of the customer transitions were

complete within 2 days and all transitions were complete within 5 days.• Transaction Performance Measures – Generally good performance in February. One system issue did cause some measures to fall below the

98% target.• Advanced Metering – Over 2.4M ESIIDs are now settled using advanced meter data with around 99% having actual data available for initial

settlement.

Wholesale Activity • Settlements & Billing Performance – Perfect performance in February.• Settlement Dollars – Excluding the extreme weather event, the average dollars transacted were similar to prior months since go-live (around $7M).

The extreme weather days averaged around $65M with the highest day (2/2/11) at $190M.• Reliability Services – February RUC Make Whole Payments to generators were much  higher than seen in prior months, but were offset by even

higher RUC Clawback Charges which resulted from the high prices on the cold weather days. • Capacity Services – due to the weather events, capacity service costs for February were substantially higher with the most dramatic increases in

Responsive Reserve and Non-Spinning Reserve.• Congestion Management – Due to the weather events, congestion payments for February were substantially higher than prior months, totaling over

$80M• Verifiable Costs – Approximately half of the available capacity is supported by approved verifiable costs.• DAM Resettlement - ERCOT resettled the DAM for 2/8/2011.  The resettlement was necessary to achieve revenue neutrality in the Balancing

Account Closure process because of a procedure failure in ensuring that the 2/8 RTM Settlement Point Price corrections were used by the 2/8 DAM Settlements. 

• Market Short-pay -  Multiple RTM Invoice short-payments by Abacus Resources Energy LLC causing partial payments to the market.  To-date, the total Abacus short-payment is in the amount of $731,420.  The default uplift to the market will occur no earlier than September 2011.

• Market Extracts and Reports – Over 1.7M extracts/reports posted during February; over 15.6M extracts/reports downloaded• Disputes – Dispute volumes have increased somewhat but continue to be lower than anticipated.• REPs and QSEs Added/Terminated

– 1 new REPs – 3 terminated REP– 2 new QSEs – 1 terminated QSEs

Page 3: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

3

Overall Activity

Transaction TypeSwitches 115,861

Move - Ins 318,528

Move Out

CSA 39,192

Total 641,199

Since June 1, 2001 41,022,791

Retail Transactions Summary

02/28/2011104,467

329,894

69,842

682,929

02/28/201053,219

161,509

78,127

17,870

317,916

2011 52,663

162,765

83,829

30,503

329,760

2010YTD February

160,427 178,726

Mass Transition 7,191 0 7,191 0(Continuous Service Agreement)

ERCOT Board of Directors March 22, 2011

Page 4: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

4

Retail Transactions SummarySwitches Move-Ins

Move-Outs Mass Transition

ERCOT Board of Directors March 22, 2011

Page 5: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

5

Retail Performance Measures – 2011 Switch 1st Quarter 2nd Quarter

3rd Quarter 4th Quarter

ERCOT Board of Directors March 22, 2011

Page 6: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

6

1st Quarter 2nd Quarter

3rd Quarter 4th Quarter

Retail Performance Measures – 2011 Move-In / Priority

ERCOT Board of Directors March 22, 2011

Page 7: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

7

1st Quarter 2nd Quarter

3rd Quarter 4th Quarter

Retail Performance Measures – 2011 Move-In / Standard

ERCOT Board of Directors March 22, 2011

Page 8: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

8

Migration from Native Affiliate REP

March 22, 2011 ERCOT Board of Directors

Residential

Small Non-Residential

Large Non-Residential

% of ESI IDs% of Load 1

at1/31/11

at1/31/11

at1/31/10

1 - Percent of Deregulated (Non-NOIE) ESI IDs and Load. Usage based on monthly settlement results.

49%

56%

77%

53%

60%

79%

55%

83%

78%

at1/31/10

50%

79%

76%

Page 9: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

9 ERCOT Board of Directors March 22, 2011

Advanced Meter Settlement

Now settling almost 2.5M ESIIDs with Advanced Meter Data

Data loading issues for one TSP resulted in a reduced amount of actual data available for settlement on 2/17/11

Page 10: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

10

Settlements and Billing Performance Measures – February 2011

ERCOT Board of Directors March 22, 2011

To Date February02/28/11 2011

Settlement Statements:Zonal 27,881 5,111Day Ahead Market 16,129 5,181Real Time Market 22,200 11,526Total 66,210 21,818Late 0 0Balance 66,210 21,818% Within Protocol 100.00% 100.00%

Invoices:Zonal 2,436 720Day Ahead Market 16,129 5,181Real Time Market 2,210 660

CRR Auction

234

85

Balancing Account

346

172 CRR Auction Revenue Disbursement (CARD)

200

99

Total

21,555

6,917

Late

-

-

Balance

21,555

6,917 % Within Protocol 100% 100%

Page 11: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

11

February 2011 Market Total Settlement Dollars

March 22, 2011 ERCOT Board of Directors

Totals represent the total charges to QSEs and CRRAHs for each Operating Day

Page 12: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

12

Reliability Services

March 22, 2011 ERCOT Board of Directors

February2011

($'s in millions)Reliability Unit Commitment

• Make Whole Payments ($5.53)

• Claw Back Charges $7.93

  Total Reliability Unit Commitment $2.40      

• Capacity Short Charges $5.53

• Make Whole Uplift $0.00

• RUC Decommitment Payments $0.00

Note:Positive amounts are a charge to the Market ParticipantNegative amounts are a payment to the Market Participant

Page 13: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

13

Capacity Services - Cost

March 22, 2011 ERCOT Board of Directors

February February

2010 2011

Capacity Services**: ($'s in millions) ($'s in millions)

Reg Up $5.3   $14.5

Reg Down $7.0   $4.8

Responsive Reserve $9.6   $50.0

Non-Spinning Reserve $4.3   $40.1

Black Start $0.4   $0.4

RMR Capacity* $0.5   $0.0

Voltage Services - Reactive Power n/a   $0.0

Voltage Services - Lost Opportunity n/a   $0.0

TOTAL CAPACITY SERVICES $27.1 $109.8

* Includes Stand-by, Energy, and Non-Performance**Includes Day-Ahead Market and Supplementary Ancillary Service Markets

Page 14: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

14

Capacity Services - Volumes

March 22, 2011 ERCOT Board of Directors

Reg Up*: February 2010 February 2011  Required (MW) 557,712   330,123   Self Arranged (MW) 108,424   8,376            Procured DAM (MW)    321,747   Procured RTM (MW)    -   Failure to Provide (MW)    60   Total Procured 450,876   321,747   % Procured 81%  97%Reg Down*:  Required (MW) 621,291   324,827   Self Arranged (MW) 128,575   17,028            Procured DAM (MW)    307,800   Procured RTM (MW)    1,524   Failure to Provide (MW)    1,571   Total Procured 494,285   309,324   % Procured 80%  95%Responsive Reserve:  Required (MW) 1,543,517   1,545,507   Self Arranged (MW) 575,224   286,064            Procured DAM (MW)    1,259,443   Procured RTM (MW)    1,326   Failure to Provide (MW)    2,891   Total Procured 970,376   1,260,769   % Procured 63%  82%Non-Spinning Reserve:  Required (MW) 1,232,447   1,344,003   Self Arranged (MW) 154,358   28,944            Procured DAM (MW)    1,315,059   Procured RTM (MW)    1,410   Failure to Provide (MW)    89   Total Procured 1,080,218   1,316,469   % Procured 88%  98%

*A/S Methodology changed in Dec 2010

Page 15: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

15

Energy Settlement

March 22, 2011 ERCOT Board of Directors

February 2011 ($'s in millions)

• Day Ahead Market Energy SettlementEnergy Purchases $470.28 Point to Point Obligations Purchases $38.85 RMR Day Ahead Revenue $0.00 Energy Sales ($443.60) Day Ahead Congestion Rent $65.53

Day Ahead Make Whole Payments ($0.09)

• Real Time Market Energy SettlementReal Time Energy Imbalance  ~Resource Node Settlement Points ($1,107.15)~Load Zone Settlement Points $1,509.25 ~ Hub Settlement Points ($285.09)Real Time Congestion from Self Schedules $11.50 Block Load Transfers and DC Ties ($24.52)Energy Settlements Impact to Revenue Neutrality $103.99

Emergency Energy Payments ($0.43)Base Point Deviation $2.51

(MWh in millions)Real Time Metered Generation 23.49

Note:Positive amounts are a charge to the Market ParticipantNegative amounts are a payment to the Market Participant

Page 16: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

16

Congestion Management

March 22, 2011 ERCOT Board of Directors

February 2011

($'s in millions)Auction DisbursementsAnnual Auction $0.00 Monthly Auction ($14.98)Total Disbursements ($14.98)

CRR SettlementDay Ahead CRR Settlement ($60.70)Day Ahead CRR Short Charges $6.24 Day Ahead CRR Short Charges Refunded ($6.24)Real Time CRR Settlement ($19.56)Real Time CRR Short Charges $0.64 Real Time CRR Short Charges Refunded ($0.64)Total Proceeds ($80.26)

PTP Obligations Acquired in DAMDay Ahead Point to Point Obligation Settlement $38.85 Real Time Point To Point Obligation Settlement ($84.49)Net Settlement ($45.64)

Note:Positive amounts are a charge to the Market ParticipantNegative amounts are a payment to the Market Participant

Page 17: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

17

Net Impact to Load

March 22, 2011 ERCOT Board of Directors

February 2011

($'s in millions)

  Market-Based Fees    Auction Disbursements ($14.98)  Balancing Account Proceeds ($4.82)  Net Reliability Unit Commitment ($2.40)  Capacity Services* $109.81   Real Time Revenue Neutrality $0.05   Emergency Energy Payments $0.43   Base Point Deviation Charge ($2.51)  ERCOT Fees    ERCOT Administrative Fee $9.90   Net Impact to Load $95.46

* RMR included in Capacity Services

Note:Positive amounts are a charge to the Market ParticipantNegative amounts are a payment to the Market Participant

Page 18: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

18

Revenue Neutrality

ERCOT Board of Directors March 22, 2011

Page 19: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

19

Market Based Fees

ERCOT Board of Directors March 22, 2011

Page 20: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

20

Daily DAM and RTM Activity

ERCOT Board of Directors March 22, 2011

Page 21: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

21

Verifiable Costs

March 22, 2011 ERCOT Board of Directors

Page 22: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

22

Extract & Report Postings

ERCOT Board of Directors March 22, 2011

TOTAL POSTINGS TOTAL FILE SIZE (GB)1,721,153 158.51

Market Extract & Report PostingsRun on Mar 7, 2011 5:13:30 PM

Start Date: Feb 1, 2011End Date: Feb 28, 2011

Posting Classifications:Certified = Available only to the Market Participant owning that dataSecure = Available to any Market Participant with a digital certificatePublic = Available to all Market Participants & general public (via ERCOT.com)

Page 23: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

23

Extract & Report Postings

ERCOT Board of Directors March 22, 2011

Top 10 Market Extract & Report Postings Run on Mar 7, 2011 5:36:39 PM

Start Date: Feb 1, 2011End Date: Feb 28, 2011

PUBLISH COUNT

Page 24: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

24

Extract & Report Downloads

ERCOT Board of Directors March 22, 2011

Market Extract & Report DownloadsRun on Mar 7, 2011 4:32:21 PM

Start Date: Feb 1, 2011End Date: Feb 28, 2011

TOTAL DOWNLOADS TOTAL FILE SIZE (GB)15,653,190 1,180.01Posting Classifications:

Certified = Available only to the Market Participant owning that dataSecure = Available to any Market Participant with a digital certificatePublic = Available to all Market Participants & general public (via ERCOT.com)

Page 25: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

25

Extract & Report Downloads

ERCOT Board of Directors March 22, 2011

Top 10 Market Extract & Report DownloadsRun on Mar 7, 2011 5:34:30 PM

Start Date: Feb 1, 2011End Date: Feb 28, 2011

DOWNLOAD COUNT

Page 26: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

26

ERCOT Wholesale Market Settlement Dispute Report

ERCOT Board of Directors March 22, 2011

  CRR Market Day-Ahead Mkt Real Time Mkt

 Current Month*

SinceDec 1, 2010

Current Month*

SinceDec 1, 2010

Current Month*

SinceDec 1, 2010

Received  13 13 10 46  80 151

Granted  0   0   0 0  3  6

Granted w/Exception  0  0  0 0   1 2

Denied  12  12 17 30  3 16

In Process 1 1 16 16 127 127

February 2011

*Some current month activity is on disputes that were received in prior months.

Page 27: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

27

REPs and QSEs Added/Terminated – as of February 28, 2010

• Added REPs • Added QSEs Entrust Energy Inc. (LSE)

• Terminated REPs • Terminated QSEs Abacus Resources Energy LLC (LSE) Abacus Resources Energy LLC dba

Abacus Resources Energy (LSE) Mpower Retail Energy LP (LSE)

Abacus Resources Energy LLC (QSE – L2)

ERCOT Board of Directors March 22, 2011

Levels of QSE QualificationQSE without Resources:Level 1:  Qualified to perform Inter-QSE trades only; does not have direct representation of Load Serving Entities or Resource Entities.Level 2:  Qualified to represent Load serving Entities; does not have direct representation of Resource Entities.QSE with Resources    Level 3:  Qualified to represent Load Serving Entities and/or Resource Entities without providing Ancillary Services; may also perform QSE without Resources activities.  QSE with Resources-AS Qualified        Level 4:  Qualified to represent Load Serving Entities and/or Resource Entities and provide Ancillary Services; may also perform level QSE without Resources activities.

Met Texas Virtual LP (QSE – L1) Envapower Inc. (QSE – L1)

Page 28: March 22, 2011 ERCOT Board of Directors Commercial Market Operations Version 2 - Updated on March 18,…

Questions?