17
Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris C. Maye, P.E. Manager, Environmental Services

Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Embed Size (px)

Citation preview

Page 1: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Managing Environmental Issues with Hospital Expansion Projects

Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective

Chris C. Maye, P.E.Manager, Environmental Services

Page 2: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Case Study – CUP Expansion Plan

• Generator Installation: 4 months– 2 1,500-kW Generators (Diesel)– 1 2,000-kW Generator (Diesel)

• Boiler Installation: 5 months– 4 Dual Fuel, ~29 MMBTU/Hr (700 bhp) each

• Fuel Oil Tanks Installation: 4 months– 1 30,000-gallon Diesel Tank (EGENS)– 1 20,000-gallon #2 Fuel Oil Tank (Boilers)

Page 3: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Generators• Typical diesel-fired, 300-2,000 kW

• Equipment: Engine and Tank

• Applicable Regulatory Considerations: – Air Permitting– Tank Permitting– Spill Prevention

Page 4: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Generators - Air Requirements

• Federal Requirements (MACT/NSPS)– Need Manufacturer Specifications (EPA Certified Engine,

Emission Rates, Horsepower rating, fuel source, etc.)– Emission standards and hour limitations depend on use of

unit (emergency, peak shaving, demand response, etc.)

• State Requirements – Air Emission Limitations

• Only applies to engines rated at greater than 1,000 horsepower and located in Bucks, Chester, Delaware, Montgomery or Philadelphia County

– Tank Requirements

Page 5: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Generators – PA Air Permitting

• Permit Exemption/Request for Determination: Allows installation without a permit– Time to Decision: ~10-14 days– Applicable if site wide actual NOx emissions below exemption

thresholds

• General Permit (GP-9)– Time to Approval: ~30 days– Stack Testing required for engines of certain size

• Plan Approval– Time to Issuance: ~3-6 months– No real limitations; Emission standards apply, other

requirements negotiable

Page 6: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Tanks

• Tank Permitting: Depending on size (>1,100 gallons), “belly” tanks or standalone may require tank registration under DEP’s Storage Tank Program.– Registration – Site-Specific Installation Permit

(larger tanks)

• Spill Planning– Site likely needs to update existing Oil Spill Prevention, Control,

and Countermeasure (SPCC) Plan– If Site has >21,000 gallons of registered storage, Spill

Prevention and Response (SPR) Plan Required prior to submission of application.

Page 7: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Generators and Tanks – Case Study

• In order to meet the construction deadline:– RFD filed for new generators (approved in 15 days)– SSIP for 30,000-gallon Diesel Tank

• Application: 4 weeks to prepare

• Approval: 3 months from submittal

– SPCC/SPR (includes existing and boiler tank installation) updated as well.

Page 8: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Boiler Installations

• Typical Unit: dual-fuel (natural gas with (fuel oil backup) 10-50 MMBTU/Hr

• Equipment: Burner and Tank

• Applicable Regulatory Considerations – Air Permitting– Tank Permitting– Spill Prevention

Page 9: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Boiler Regulations

• Federal– New Source Performance

Standards– National Emissions Standards for

Hazardous Air Pollutants– Oil Spill Prevention

• State– Emission Limitations– Tank Requirements

Page 10: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Boiler Air Issues

• Need Manufacturer Data (Emission Rates, etc.)

• Air Permitting (PA): 2 options– General Permit (GP-1)

• Time to Issuance: ~30 days• Potential to Emit must below major source thresholds

– Plan Approval• Time to Issuance: ~3-6 months• No real limitations; can be used only for the operation

of a boiler on fuel oil.

Page 11: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Boilers – Case Study• To meet construction timeline, Air Permitting

performed included:– Obtain Coverage under General Permit (GP-1)

for natural gas only: Approval allowed construction to begin 3 weeks after submittal

– Simultaneously file Plan Approval for firing #2 fuel oil: Approval received 5 months after filing

• After units installed, need to:– Stack Test (GP-1 Condition)– Consolidate into an Operating Permit– Prepare regulatory notifications under applicable rules

• No Tank Permitting Required• SPCC Plan required updating

Page 12: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Boiler Tank Issues

• Tank Permitting:– For aboveground tanks:

Not applicable for #2 Fuel Oil ASTs based on exemption for on-site consumptive use of non-motor fuel in tanks <30,000 gallons.

– For underground tanks: Not applicable for #2 Fuel Oil USTs based on exemption for on-site consumptive use of “heating oil.”

Page 13: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Case Study - Results• ON-TIME: Each authorization was obtained on-time,

causing no construction delays for environmental issues

• RIGHT EQUIPMENT: Proper instrumentation for fuel consumption communicated and verified early in design.

• RIGHT SETTING: Tank construction and fuel unloading area design reviewed and confirmed compliant prior to start of project

• STILL WORK TO DO: Additional Follow-up still pending (stack testing, air permit consolidation, etc.)

• COMMUNICATION! Frequent and clear communication of when the facility could install/use equipment critical to maintaining compliance

Page 14: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Case Study - Conundrum

• Why Communication on Approval Status is essential!

– Month 2 after applications were filed, approval status was such that:

• Generators could be run, but no fuel could be added to supply tank

• On #2 Fuel Oil, the boilers could not be run, but fuel could be added to supply tank

Page 15: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Lessons Learned/Key Points Pre-Construction

• PLAN AHEAD: Get detailed equipment and installation information as early as possible

• MONITORING = INSTRUMENTATION: Know what monitoring/recordkeeping will be required to ensure proper instrumentation (fuel consumption, etc.) are part of the project design.

• GET THE RIGHT SUBS: If tanks require registrations, ensure certified tank installers are part of the construction team.

• COMMUNICATION: Ensure timing is communicated so that environmental permitting does not slow you down and compliance is maintained.

Page 16: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

Lessons Learned/Key Points Post-Construction

• NEW EQUIPMENT = NEW RECORDS: New Air Quality Emissions, Fuel, and Hours of Operation Recordkeeping must be addressed.

• NEW RULES = NEW RECORDS & REPORTS: New Standards (Boiler Area Source MACT, RICE MACT/NSPS) may require additional recordkeeping, notifications, and reporting.

• UPDATE EXISTING INSPECTIONS: Spill Planning Document Updates will include additional inspection requirements once units are installed.

Page 17: Managing Environmental Issues with Hospital Expansion Projects Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective Chris

References

• DEP Generator Tank Registration:– http://files.dep.state.pa.us/

EnvironmentalCleanupBrownfields/StorageTanks/StorageTanksPortalFiles/Emergency%20Generator%20Tanks.ppt

• DEP Air Quality General Permits:– http://www.dep.state.pa.us/dep/deputate/AIRWASTE/

AQ/permits/gp.htm

• EPA Generator MACT Air Standard:– http://www.epa.gov/ttn/atw/rice/ricepg.html

• EPA Area Source Boiler NESHAP Standard:– http://www.epa.gov/boilercompliance/