Upload
aubrey-richards
View
217
Download
0
Tags:
Embed Size (px)
Citation preview
Managing Environmental Issues with Hospital Expansion Projects
Tank, Generator, and Boiler Installations from an Environmental Permitting Perspective
Chris C. Maye, P.E.Manager, Environmental Services
Case Study – CUP Expansion Plan
• Generator Installation: 4 months– 2 1,500-kW Generators (Diesel)– 1 2,000-kW Generator (Diesel)
• Boiler Installation: 5 months– 4 Dual Fuel, ~29 MMBTU/Hr (700 bhp) each
• Fuel Oil Tanks Installation: 4 months– 1 30,000-gallon Diesel Tank (EGENS)– 1 20,000-gallon #2 Fuel Oil Tank (Boilers)
Generators• Typical diesel-fired, 300-2,000 kW
• Equipment: Engine and Tank
• Applicable Regulatory Considerations: – Air Permitting– Tank Permitting– Spill Prevention
Generators - Air Requirements
• Federal Requirements (MACT/NSPS)– Need Manufacturer Specifications (EPA Certified Engine,
Emission Rates, Horsepower rating, fuel source, etc.)– Emission standards and hour limitations depend on use of
unit (emergency, peak shaving, demand response, etc.)
• State Requirements – Air Emission Limitations
• Only applies to engines rated at greater than 1,000 horsepower and located in Bucks, Chester, Delaware, Montgomery or Philadelphia County
– Tank Requirements
Generators – PA Air Permitting
• Permit Exemption/Request for Determination: Allows installation without a permit– Time to Decision: ~10-14 days– Applicable if site wide actual NOx emissions below exemption
thresholds
• General Permit (GP-9)– Time to Approval: ~30 days– Stack Testing required for engines of certain size
• Plan Approval– Time to Issuance: ~3-6 months– No real limitations; Emission standards apply, other
requirements negotiable
Tanks
• Tank Permitting: Depending on size (>1,100 gallons), “belly” tanks or standalone may require tank registration under DEP’s Storage Tank Program.– Registration – Site-Specific Installation Permit
(larger tanks)
• Spill Planning– Site likely needs to update existing Oil Spill Prevention, Control,
and Countermeasure (SPCC) Plan– If Site has >21,000 gallons of registered storage, Spill
Prevention and Response (SPR) Plan Required prior to submission of application.
Generators and Tanks – Case Study
• In order to meet the construction deadline:– RFD filed for new generators (approved in 15 days)– SSIP for 30,000-gallon Diesel Tank
• Application: 4 weeks to prepare
• Approval: 3 months from submittal
– SPCC/SPR (includes existing and boiler tank installation) updated as well.
Boiler Installations
• Typical Unit: dual-fuel (natural gas with (fuel oil backup) 10-50 MMBTU/Hr
• Equipment: Burner and Tank
• Applicable Regulatory Considerations – Air Permitting– Tank Permitting– Spill Prevention
Boiler Regulations
• Federal– New Source Performance
Standards– National Emissions Standards for
Hazardous Air Pollutants– Oil Spill Prevention
• State– Emission Limitations– Tank Requirements
Boiler Air Issues
• Need Manufacturer Data (Emission Rates, etc.)
• Air Permitting (PA): 2 options– General Permit (GP-1)
• Time to Issuance: ~30 days• Potential to Emit must below major source thresholds
– Plan Approval• Time to Issuance: ~3-6 months• No real limitations; can be used only for the operation
of a boiler on fuel oil.
Boilers – Case Study• To meet construction timeline, Air Permitting
performed included:– Obtain Coverage under General Permit (GP-1)
for natural gas only: Approval allowed construction to begin 3 weeks after submittal
– Simultaneously file Plan Approval for firing #2 fuel oil: Approval received 5 months after filing
• After units installed, need to:– Stack Test (GP-1 Condition)– Consolidate into an Operating Permit– Prepare regulatory notifications under applicable rules
• No Tank Permitting Required• SPCC Plan required updating
Boiler Tank Issues
• Tank Permitting:– For aboveground tanks:
Not applicable for #2 Fuel Oil ASTs based on exemption for on-site consumptive use of non-motor fuel in tanks <30,000 gallons.
– For underground tanks: Not applicable for #2 Fuel Oil USTs based on exemption for on-site consumptive use of “heating oil.”
Case Study - Results• ON-TIME: Each authorization was obtained on-time,
causing no construction delays for environmental issues
• RIGHT EQUIPMENT: Proper instrumentation for fuel consumption communicated and verified early in design.
• RIGHT SETTING: Tank construction and fuel unloading area design reviewed and confirmed compliant prior to start of project
• STILL WORK TO DO: Additional Follow-up still pending (stack testing, air permit consolidation, etc.)
• COMMUNICATION! Frequent and clear communication of when the facility could install/use equipment critical to maintaining compliance
Case Study - Conundrum
• Why Communication on Approval Status is essential!
– Month 2 after applications were filed, approval status was such that:
• Generators could be run, but no fuel could be added to supply tank
• On #2 Fuel Oil, the boilers could not be run, but fuel could be added to supply tank
Lessons Learned/Key Points Pre-Construction
• PLAN AHEAD: Get detailed equipment and installation information as early as possible
• MONITORING = INSTRUMENTATION: Know what monitoring/recordkeeping will be required to ensure proper instrumentation (fuel consumption, etc.) are part of the project design.
• GET THE RIGHT SUBS: If tanks require registrations, ensure certified tank installers are part of the construction team.
• COMMUNICATION: Ensure timing is communicated so that environmental permitting does not slow you down and compliance is maintained.
Lessons Learned/Key Points Post-Construction
• NEW EQUIPMENT = NEW RECORDS: New Air Quality Emissions, Fuel, and Hours of Operation Recordkeeping must be addressed.
• NEW RULES = NEW RECORDS & REPORTS: New Standards (Boiler Area Source MACT, RICE MACT/NSPS) may require additional recordkeeping, notifications, and reporting.
• UPDATE EXISTING INSPECTIONS: Spill Planning Document Updates will include additional inspection requirements once units are installed.
References
• DEP Generator Tank Registration:– http://files.dep.state.pa.us/
EnvironmentalCleanupBrownfields/StorageTanks/StorageTanksPortalFiles/Emergency%20Generator%20Tanks.ppt
• DEP Air Quality General Permits:– http://www.dep.state.pa.us/dep/deputate/AIRWASTE/
AQ/permits/gp.htm
• EPA Generator MACT Air Standard:– http://www.epa.gov/ttn/atw/rice/ricepg.html
• EPA Area Source Boiler NESHAP Standard:– http://www.epa.gov/boilercompliance/