Upload
cra-europe
View
225
Download
0
Embed Size (px)
DESCRIPTION
As part of our newsletter service over the past few months, CRA delivered a series of short articles where we explored some of the more common questions that can arise before or during the permitting process and with the environmental permit itself. Following on from those five articles, CRA has now compiled this summary in the form of an e-booklet for your future reference. Topics include: 1. Seven things you should know about environmental permits; 2. Do you require an environmental permit? 3. Why your environmental permit may be invalid; 4. Eight things to consider before completing an environmental permit application; and 5. Pitfalls to avoid when applying for an environmental permit.
Citation preview
Understanding the Issues and Pitfalls
This report was prepared by: Bryan Hughes and reviewed by: Nigel Leehane
Environmental Permitting
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
1
TABLE OF CONTENTS
1.0 Introduction
1.1 Background
1.2 Where can you find out more?
2
2
2
2.0 Seven things you should know about environmental permits 3
3.0 Do you require an environmental permit? 5
4.0 Why your environmental permit may be invalid 7
5.0 Eight things to consider before completing an environmental permit application
5.1 The Regulated Facility
5.2 The Permitting Process
5.3 The Permit Application Forms
5.4 The Overall Timeframe
5.5 The Overall Cost
5.6 Available Technical Guidance
5.7 Supporting Information and Data
5.8 Outsourcing and In-house capability
8
8
8
8
8
9
9
9
10
6.0 Pitfalls to avoid when applying for an environmental permit
6.1 Non-alignment with Business Strategy
6.2 Insufficient Planning
6.3 Procurement Disconnect
6.4 Non-alignment with “Regulator Thinking”
6.5 Conflicting Legislation
11
11
11
11
12
12
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
2
1.0 INTRODUCTION
1.1 Background
CRA’s clients and newsletter readers often ask if
we have experienced, or have experience with,
certain issues relating to the Environmental
Permitting regime (as applied in England and
Wales) or the similar legislation that is applicable in
both Scotland and Northern Ireland.
As part of our newsletter service over the past few
months, CRA delivered a series of short articles
where we explored some of the more common
questions that can arise before or during the
permitting process and with the environmental
permit itself. Following on from those five articles,
CRA has now compiled this summary in the form of
an e-booklet for your future reference. Topics
include:
1. Seven things you should know about
environmental permits;
2. Do you require an environmental permit?
3. Why your environmental permit may be invalid;
4. Eight things to consider before completing an
environmental permit application; and
5. Pitfalls to avoid when applying for an
environmental permit.
1.2 Where can you find out more?
Please contact Bryan Hughes
on [email protected] or 0151 207 7848 if you
would like to know more about environmental
permits, the permitting process, and the
implications for your organisation. Alternatively,
please visit the environmental permitting web page
on our website www.cra.co.uk.
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
3
2.0 SEVEN THINGS YOU SHOULD KNOW ABOUT ENVIRONMENTAL
PERMITS
Frequently asked questions (FAQs) formed the
basis for this first short article where we explore
some of the issues that can arise with the
permitting process in England and Wales. CRA
gathered what we believe to be seven key features
of the permitting process that we think should be
more widely known.
1. The need for an Environmental Permit is
determined by the Environmental Permitting
Regulations 2010, as amended, that applies
only to England and Wales.
Similar but separate legislation and terminology
apply in Scotland and Northern Ireland. The
legislation does not affect the Isle of Man or the
Channel Islands.
2. Under the updated Regulations, regulated
facilities (see later) may overlap, ‘stand
alone’ or form part of the operation of other
facilities.
For example, polluting water discharges that
also contain radioactive material will be both a
water discharge activity and a radioactive
substances activity; waste operations which
might lead to a discharge to groundwater will be
both a waste operation and a groundwater
activity.
3. The operator of a regulated facility requires
an environmental permit for activities
carried out onshore and at offshore
locations within UK territorial waters.
The Regulations also extend to offshore
locations that are beyond territorial waters,
where activities involve radioactive substances.
This is for oil and gas installations within the
English area of the continental shelf. The
legislation also applies to activities carried out
both underground and above ground. The only
exceptions are in Section 1.1 Part A(1) of
Schedule 1 of the current Regulations where
certain offshore platforms are excluded, and
Section 3.5 Part B of the Regulations, where
underground activities are excluded in a similar
way.
4. An environmental permit is location
specific; unless applied to mobile plant.
If premises involving a regulated facility are
sold, the permit cannot be moved with the
activity to the new location. The permit will need
to be transferred to the new owners or an
application made for a new permit (preferably
before implementation of location plans) to
allow continuation of the activity at the new or
proposed location.
5. A permit application that is deemed to be
potentially contentious or high profile can
require two rounds of public participation
consultation before the Environment
Agency (EA) finalise a permit.
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
4
The EA’s considered reasoning behind the
determination of a permit application and the
permit itself will become a matter of public
record. A permit application and the details
used within it, also form an integral part of that
permit.
6. The Permitting process can take much
longer to conclude than envisaged.
The process can take up to a year or more for
the more complex processes. An appropriate
timeframe should be allowed to obtain an
environmental permit and to integrate it into
other developmental plans, needs and permits.
7. The boundary of a permitted facility (the
Regulated Facility) need not necessarily be
the same as the site boundary.
The boundary of a permitted facility can be
significantly smaller than the overall site
boundary. Indeed it can sometimes extend onto
other people’s land and therefore be larger;
highlighting that a Permit applies to an operator
and not the site or land owner. Where there is
more than one environmental permit at the
same location, an application can be made to
have them consolidated. If a permit or part of a
permit is no longer needed, they can be
surrendered in order to remove a facility or
reduce the land area covered.
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
5
3.0 DO YOU REQUIRE AN ENVIRONMENTAL PERMIT?
In April 2013 the EA updated Regulatory Guidance
Note 2 (RGN 2) aimed at helping operators decide
if an activity was part of a regulated facility requiring
an environmental permit.
A ‘regulated facility’ is a collective term used to
describe different operations or activities specified
under the Environmental Permitting Regulations
that has been amended annually since 2010. The
following are ‘types’ of facility that the regulations
are directed towards:
1. Installations consisting of one or more activities
listed in the regulations and other unlisted but
directly associated activities. These comprise
activities that are the subject of Integrated
Pollution Prevention and Control (IPPC) and
activities that are the subject of air pollution
control only. Activities include:
SECTOR TYPES OF ACTIVITY
Energy Combustion, gasification,
liquefaction and refining.
Metals and
Surface
Treatment
Ferrous and non-ferrous metals,
surface treating metals and
plastic materials.
Minerals Cement & lime, activities
involving asbestos, manufacture
of glass and glass fibre, other
minerals, ceramics.
Chemicals Organic and inorganic
chemicals, production of
pharmaceuticals, fertilisers, plant
SECTOR TYPES OF ACTIVITY
health products and biocides,
explosives, storage in bulk and
manufacture involving ammonia.
Waste
Management
Incineration and co-incineration,
landfills, and other forms of
disposal, waste recovery,
temporary or underground
storage of hazardous waste and
also waste water treatment.
Other Paper, pulp and board
manufacture, carbon, tar and
bitumen, coating activities,
printing and textile treatments,
dyestuffs, timber, rubber, food
industries, and intensive
farming.
2. Waste management activities not forming part
of an installation; including those activities that
are technically linked. However, some specific
waste operations are ‘excluded’ from the
regulations, whilst other waste operations are
‘exempt’. Those operations, which are
‘excluded’ or ‘exempt’, cannot be regulated in
their own right but can potentially form part of
an installation and its associated permit.
Exempt facilities and excluded waste
operations are not deemed to be regulated
facilities.
3. Mobile plant used to carry out a waste
operation or other listed activity.
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
6
4. Mining operations or more specifically their
management of extractive waste.
5. Water discharge activities not involving
discharges made to foul sewer that come under
separate legislation.
6. Activities involving groundwater.
7. Activities involving radioactive substances,
including mobile radioactive equipment.
8. Waste incineration plant which is below the
capacity thresholds specified in the regulations
and which is not classed as an installation.
9. Activities involving the emission of solvents.
Some of the above activities may be carried out
within what is termed a “Standard Facility”. This is a
regulated facility having to meet the requirements of
Standard Rules for a Standard Permit.
An ‘exempt facility’ can only mean an exempt waste
operation, an exempt water discharge activity or an
exempt groundwater activity.
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
7
4.0 WHY YOUR ENVIRONMENTAL PERMIT MAY BE INVALID
Once an environmental permit application has been
submitted and “Duly Made” by the EA, this is a
formal recognition that an application meets the
minimum criteria and scope required by the EA for
the Environmental Permitting Regulations.
The information submitted will be reviewed by the
Regulators and, through dialogue with the applicant
during the determination period, technical aspects
of the information will be refined to a point where
the permit is issued as a draft and then as the
actual permit itself. From that point in time, the
conditions and requirements pertaining to the
permit are essentially fixed and cannot be changed
without permission being obtained from the EA.
It is important to realise that the fixed nature of a
permit and any need to modify it can be an involved
process, largely dependent upon the nature of the
change required, and not without significant costs.
The permit is also a “living document” that should
be reviewed periodically to ensure its
appropriateness and accuracy. Indeed, the EA will
take it upon itself to review permits approximately
every 4 years, but in the intervening period it is
important to monitor the suitability of the permit.
Some common causes behind a permit
becoming unsuitable include:
Activities, plant and equipment are changed or
added to. Such changes or additions have not
been pre-notified to the EA and their agreement
received beforehand;
Corporate identification and contact details
displayed on the permit are incorrect;
The activity, or part of the facility, becomes the
responsibility of another party; Permitted
activities may be within what is termed a
“Standard Facility”; but the activities fail to meet
the conditions of Standard Rules for a Standard
Permit at that facility;
Former permits, licences, consents and
authorisations may have been superseded, or
replaced, by a newer environmental permit;
New legislation relevant to the regulated facility
may have been introduced and where
compliance has not been implemented or
factored into the permit’s demands;
The operator carries out activities that are not
allowable within the conditions and
requirements of the permit or they are outside
the scope and/or details presented;
Having licences or registrations, which are
complimentary to the environmental permit, that
are out of date, not being complied with, or that
have been revoked;
Storing, receiving or producing materials that
are not within the scope of permit; and
Not carrying out specific actions within required
timescales agreed with the EA.
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
8
5.0 EIGHT THINGS TO CONSIDER BEFORE COMPLETING AN
ENVIRONMENTAL PERMIT APPLICATION
Continuing with the theme of trying to reduce the
risk of having to make avoidable and potentially
costly changes, we now look at a selection of
issues to consider before completing an
environmental permit application. We assume here
that a site activity requires an environmental permit
as part of a Regulated Facility (see the first article
in our series “Seven things you should know about
environmental permits”) and that the activity is not
‘excluded’ or ‘exempt’ from the Environmental
Permitting Regulations. These issues can also be
relevant to applications being considered for permit
variations where similar matters can arise.
5.1 The Regulated Facility
It is important to recognise which type of
environmental permit or variation should be applied
for, particularly the significance of what is being
proposed; how long the overall process might take;
and what technical issues could arise, particularly if
the application has to integrate the demands and
possible conflicts from other legislation such as
planning and EIA.
5.2 The Permitting Process
Determining the type of environmental permit
application and the significance of what is to be
proposed will typically govern the regulatory route
and, to an extent, the time it will take for an
operator to be in receipt of an environmental permit
or variation.
Failure to recognise the type of permit needed or its
significance could add considerable time and cost
to a project; it might also introduce elements of risk
e.g. planned or actual site activities having to be
halted as a result.
Before embarking on an application, it is also good
practice to check that relevant environmental
legislation has not recently changed or about to be
changed. The requirements of such changes would
need to be considered and factored into the
application as appropriate.
5.3 The Permit Application Forms
There are a range of permit application forms to
choose from and also software applications to
assist with some technical assessments. The
correct combination of forms should be selected,
completed in full, and supported by sufficient
information and data that is both robust and
accurate.
The overall level of information should be at least
sufficient to achieve the minimum needs of the EA
and the other regulators who they liaise with as part
of the process. Beyond that, the amount of
information supplied to the EA should be at a level
that an organisation is happy to tolerate in terms of
general business risk.
The latter can be especially relevant for the
requirements of site condition reports, which will be
used as the benchmark when a site is eventually
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
9
returned to their pre-permit condition at permit
surrender.
5.4 The Overall Timeframe
The type and significance of a permit application
and the regulatory route will largely determine the
time taken to be in receipt of an environmental
permit or a variation. That timeframe will also be
governed by other factors, such as the amount of
accurate information submitted and its robustness;
something that can be audited and/or verified by
technical specialists appointed by or available
within the EA.
The extent of any further information and data
supplied can also influence the speed at which a
permit application is determined, but it should be
noted that it will usually be information released into
the public domain and at a level that an
organisation must be able to tolerate in terms of
business risk.
The timeframe will also be governed by the
availability of specialist EA staff and the number of
public consultations. As highlighted in our second
article in this series (“Do you require an
environmental permit?”), a permit application that is
deemed to be potentially contentious or high profile
can require two rounds of public consultation that
adds to the time.
5.5 The Overall Cost
Costs are more than just the EA’s application fee.
The cost of a permit application will also incorporate
an annual fee that, in most instances, will be
determined by the environmental risk posed by the
activity at a particular site. This rating will be in the
context of the risk caused by the site location and
also the robustness of environmental management
techniques used or proposed to reduce the threat of
pollution and any resulting environmental damage.
Notwithstanding the time and cost to prepare a
permit application and the demands from that
permit, there will be the various ongoing costs
associated with, for example, having to gather
information and data through rigorous monitoring
and sampling.
There will also be the costs attributable to staff
training and ensuring that competency progression
is maintained. It should not be forgotten that
resources to facilitate the routine and periodic
reporting of statutory information and data to the EA
will also be required.
When there are plans to cease an activity at a
regulated facility, there will be the fees charged by
the EA for permit surrender and there will be the
potentially significant costs associated with the
decommissioning, decontamination, dismantling,
and demolition of plant and equipment.
5.6 Available Technical Guidance
The information required to demonstrate that
technical proposals will protect the environment and
not harm human health is generally explained
within an array of guidance, such as: Technical
Sector; Horizontal (cross-sector); and general
regulatory. These are underpinned by “BREF
notes” issued by the European Community. Where
specific guidance is unavailable, the Environmental
Permitting Regulations allow guidance to be drawn
from other recognised sources.
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
10
When a permit application is being prepared, it is
good practice to check that relevant guidance has
not been updated or superseded during that time.
New or updated guidance has been known to
“arrive unannounced” with resulting permit
applications having to be reworked. An application
using superseded guidance risks being rejected
and the associated fees to the EA being lost.
5.7 Supporting Information and Data
There can be a direct ‘tie-in’ between permit
applications and the demands of Environmental
Impact Assessments (EIA) from the Planning
Authority, as well as other regulatory regimes. It is
as important to identify the potential conflicts posed
by these processes, as it is to use the information
that they offer.
Similarly, it could be argued that the EIA and
planning process should, in turn, recognise
potential conflicts and information offered by the
environmental permitting process.
5.8 Outsourcing and In-house Capability
In planning for a permit application and the
permitting process, it is considered prudent to
continually reflect on what in-house resources will
be both available, and also capable of, effectively
supplying information needed to fully support a
permit application.
It is important to identify the external support and
/or capability that will be needed when/where there
are shortfalls. The timely availability of an internal
resource will vary from operator to operator, but
some level of external support could well be
required for many permit applications.
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
11
6.0 PITFALLS TO AVOID WHEN APPLYING FOR AN ENVIRONMENTAL
PERMIT
The following suggestions can be utilised to avoid
potential pitfalls that may arise before, or when
applying for, an Environmental Permit or Variation.
Such pitfalls, which are avoidable, can result in:
Delays to the project programme;
Permit applications that fail or which are
delayed, e.g. not Duly Made;
A need for retrofitted equipment etc; and
Additional costs that could be significant.
6.1 Non-alignment with Business
Strategy
Considering the need to embark on an
Environmental Permit or a Permit Variation
application, like any other decision-making process
in business management, should:
Form part of an organisation’s ongoing
assessment and perception of business risk;
Be seen as part of an investment cost and not
necessarily as a Regulatory burden;
Fully consider and assess “make-buy”
decisions for operations at the site; and,
Determine the other requirements and
potential conflicts that may need to be factored
into the above as a result.
6.2 Insufficient Planning
As with any project, timely and effective planning is
absolutely key to preparing a strong and potentially
successful permit application. Full consideration
should be given to operational requirements,
resource availability (both internal and external;
including the need for specialist and general
technical skills); budget availability including spend
profiles/phasing and procurement (see below).
An assessment of business risk should be
undertaken to identify the resulting impacts on or
from other areas of the business. Examples might
include the effects of:
Other legislation such as general Health &
Safety requirements;
Other environmental legislation such as the
Environmental Damage Regulations (where
permit holders have strict liability);
Legislation and/or guidance that has been
recently updated or revised or which is about
to be changed;
The responsibilities of other regulatory bodies,
e.g. Trade Effluent Discharge consents for
discharges made to foul sewer, which are the
responsibility of the appropriate sewerage
undertaker; and
Operational factors including lack of access to
and/or inadequate observational control of
areas supporting core operations, in particular
outside of operational hours and those areas
not normally manned.
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
12
6.3 Procurement Disconnect
Part of the Regulator’s determination of a permit
application is to decide whether plant and
equipment will continue to meet the technical
requirements of “Indicative BAT” (Best Available
Techniques) as a minimum. Notwithstanding
maintenance and installation requirements and the
need for an operator to have trained and capable
staff, it is considered sensible to review all
significant plant procurement needs against
“Indicative BAT” as applicable to each sector.
It should be noted that guidance published for BAT
in particular industrial sectors (not forgetting
European BREF notes), can be outdated by the
changing pace of technology. At an early stage,
the procurement process should determine if newer
technologies can fulfil the same operational duty
whilst enhancing environmental protection.
Regulators can and do challenge the selection of
plant and equipment where there is an
environmental impact!
It must not be forgotten that any significant change
from a production perspective, which results in the
alteration of emissions or other environmental
impacts, will need to be authorised by the
Regulators. Again, a similar early review of BAT is
best undertaken as part of the procurement process
and before commitment is made to purchase any
plant and equipment. Organisations should be
satisfied that such plant and equipment will satisfy
regulatory scrutiny throughout the whole permitting
process.
6.4 Non-alignment with “Regulator
Thinking”
It is generally advisable for an operator to have a
pre-application discussion with the Regulator before
preparing and submitting an application. This
approach will help with getting a permit or variation
application “right first time” and raise issues of
concern early; ultimately reducing time and cost.
The key point here is to consider at what point
should that meeting occur, who needs to be
involved, and what information will or may be
needed (see also below)?
Considering a single point of contact for the
Regulator is also worthwhile and indeed is required
on the application form. That person does not need
to be part of the operator’s internal team but should
be reasonably available during normal working
hours and effect good communication.
The first and possibly subsequent meetings will
typically be with the local inspector (one may have
been appointed) and involve regional technical
specialists as appropriate. It is worth noting that
views put forward locally or regionally by
Regulators concerning applications, particularly for
installations, have been known to be overturned by
the Regulator’s central permitting team.
6.2 Conflicting legislation
There can be a direct ‘tie-in’ between Permit
applications and the demands of other directly
related regulatory regimes such as COMAH, EIA,
and the planning process (planning conditions from
the Planning Authority). It is as important to identify
potential conflicts posed by these processes.
Environmental Permitting Understanding the Issues and Pitfalls
December 2013
13
The key point here is that the pitfalls may be
associated with other legislation. It has been known
for unexpected pieces of legislation to potentially
conflict with the requirements of permit applications.
These have included Civil Aviation Authority
requirements, Port Authority needs (including
navigational and pilotage demands), and legislation
that is applicable to neighbouring facilities, which on
one occasion included counter terrorist measures!
It should also be noted that being convicted of a
relevant offence under other legislation can cause
complexities and delays to a permit application.
This is applicable to organisations and individuals
convicted under, but not limited to, legislation linked
to environmental protection.
The above reinforces the need to meet the
Regulator early in the process and to remember
that when a Permit application is being prepared, it
is very good practice to check that all relevant =
guidance has not been updated or superseded with
new or updated editions.
Bringing sustainability and safety to the world’s most complex environments
CRA Europe
Synergy House, Unit 1, Calverton Business Park, Hoyle Road, Calverton, Nottingham, UK NG14 6QL
T: +44(0)1159656700 F: +44(0)1159655282E: [email protected] W: www.cra.co.uk