DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN 1-1 ICP Requirement Document ICP Projects Negotiation ICP Agreements ICP Recipient Audit Surveillance Audit Post Implementation Audit Proposal clarification and identify potential recipients ICP Monitoring & Reporting ICP Implementation Verification Maximize socio economics returns and support onto knowledge based economy Agree on the ICP deliverables and expected impact within time & cost limits ICP monitoring on agreed programme Ensure performance within agreed parameters Assessment on the performance of ICP Programme ICP Proposal and Evaluation Relief from obligation upon completion ICP Program Completion Market and Industry Database ICP Strategy Pre-Implementation Implementation Post-Implementation ATTACHMENT 1 Articulate ICP strategies and formation of relevant ICP committees MALAYSIAN ICP MANAGEMENT FRAMEWORK

MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

  • Upload
    others

  • View
    9

  • Download
    2

Embed Size (px)

Citation preview

Page 1: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

1-1

ICPRequirement Document

ICPProjects

Negotiation

ICPAgreements

ICP Recipient Audit Surveillance Audit Post Implementation Audit

Proposal clarification and identify potential recipients

ICP Monitoring & Reporting

ICP Implementation

Verification

Maximize socio economics returns and support onto knowledge based economy

Agree on the ICP deliverables and expected impact within time & cost limits

ICP monitoring on agreed programme

Ensure performance within agreed parameters

Assessment on the performance of ICP Programme

ICPProposal

and Evaluation

Relief from obligation upon completion

ICPProgram

Completion

Market and Industry Database

ICPStrategy

Pre-Implementation Implementation Post-Implementation

ATTACHMENT 1

Articulate ICP strategies and formation of relevant ICP committees

MALAYSIAN ICP MANAGEMENT FRAMEWORK

Page 2: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

1-2

Pre-Implementation(Clause 4.2)

Implementation(Clause 4.3)

Post Implementation(Clause 4.4)

Pre-ICP(Clause 5)

Penalty Process

(Clause 2.4.6)

Penalty? Relief of Obligation

(Clause 4.4.3)

Yes

No

Approval

GovernmentProcurement

Start

End

SUMMARY OF MALAYSIAN ICP MANAGEMENT FLOW CHART

Page 3: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

1-3

Process Flow (Carta Alir):

TASKRESPONSIBILITIES

DESCRIPTIONAgency ICP

Provider IMU TDA IC MIEC

Develop ICP Strategy Document (ISD)

ICP Committee (IC) formation

ICP Management Unit (IMU) establishment

ICP Requirement Document (IRD) Development

ICP Strategies

Procurement

IMU Appointment

IC Formation

A

Start

IRD Development

Tender Issuance

Procurement triggered by Procuring Agency.

TDA is to develop the ICP Strategy Document (ISD) to be used for the ICP Requirement Document (IRD) development.

With assistance from TDA, the Procuring Agency shall appoint ICP Management Unit (IMU) and form an ICP Committee (IC).

With assistance from TDA, the IMU shall develop an IRD for approval by IC.

Page 4: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

1-4

TASKRESPONSIBILITIES

DESCRIPTIONAgency ICP

Provider IMU TDA IC MIEC

Form an ICP Evaluation Committee

ICP proposal submission with tender document

Consolidation by IMU and Procuring Agency

Appointment by Procuring Agency

ICP Projects Negotiation

Proposal

ICP Evaluation

ICP Evaluation Report

A

Successful Tenderer

Appointment

ICP Projects Negotiation

ICP Recipient Audit

IC Approval

ICP Agreement Preparation

The IEC evaluates, prepares and submit evaluation report.

The tenderers submit the ICP proposal as part of the tender document for evaluation.

Procuring Agency appoint successful tenderer.

IMU and ICP Provider negotiate on ICP projects, ICV and potential ICP Recipients.

IRA shall be conducted to all Potential ICP Recipients.

Agreements and Schedule A to be prepared and reviewed by related parties.

B

Page 5: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

1-5

TASKRESPONSIBILITIES

DESCRIPTIONAgency ICP

Provider IMU TDA IC MIEC

Periodical monitoring and reporting

First and Second Tier Agreement

B

Agreement Signing

Implementation Monitoring

Periodical Progress Report

Surveillance Audit

(if required)

Reporting

C

Signing parties involves Government of Malaysia, Procuring Agency, ICP Provider, TDA and ICP Recipient, depending on the type of agreement.

IMU monitor the ICP implementation periodically.

Surveillance Audit will be conducted as an when required.

ICP Provider shall submit a progress report to IMU periodically.

IMU shall submit a quarterly report to Procuring Agency and TDA

Page 6: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

1-6

TASKRESPONSIBILITIES

DESCRIPTIONAgency ICP

Provider IMU TDA IC MIEC

ICV Claim, Post Implementation Audit, Programme Closure, Penalty, Relief of Obligation, ICV Banking

ICV Claim

C

ICV Verification and Post

Implementation Audit

Post Implementation

Audit Report

Review ICV

Claim

Acknowledge & Recommend

Programme Closure

Approve

Penalty

Relief of Obligation

EndICV

Banking

ICP Provider to submit ICV claim upon project/programme completion.

IMU to review the submission prior to ICV verification and post implementation audit.

Recommendation from post implementation audit report on achieved ICV to be acknowledged by IC.

Upon completion of ICP obligation by ICP Provider, IC to recommend for Relief of Obligation.

MIEC to approve for Relief of Obligation or Penalty (if applicable).

TDA to update ICV Banking Account (if any).

Page 7: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

1-7

TASKRESPONSIBILITIES

DESCRIPTIONAgency ICP

Provider IMU TDA IC MIEC

Pre-ICP Credit Banking

Pre-ICP Credit Banking Proposal

Proposal Evaluation

Proposal ApprovalPre-ICP Agreement

Implementation

Pre-ICV Claims ICV Verification and Post

Implementation Audit

ICV Approval

ICV Banking

End

OEM requests for Pre-ICP credit banking.

TDA evaluate the proposal prior to MIEC approval.

Pre-ICP Agreement and project details to be prepared, reviewed and signed by OEM and TDA.

OEM to implement the project and monitored by TDA.

OEM to submit ICV claim upon project completion.

Recommendation from post implementation audit report on achieved ICV to be approved by MIEC.

TDA to update ICV Banking Account.

Monitoring

Page 8: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-1

ICP Credit Value (ICV) Calculation

ICV = ∑ ICV Projects (i)i=1

n

Where:n is number of agreed projects

Program

EEP = Direct and/or Indirect Economic Enhancement Program

Offset = Direct and/or Indirect Offset

CT = Countertrade

Program is defined either one of the following;

1. ICV PROGRAM

ICVCT

= NV � MultiplierCT

ICV = ∑ ICVDirect Offset project (i)i=1

n

Offset ∑ ICVIndirect Offset project (i)i=1

n

+

ICV = ∑ ICVDirect EEP project (i)i=1

n

EEP ∑ ICVIndirect EEP project (i)i=1

n

+

ATTACHMENT 2

Page 9: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-2

ICP Credit Value (ICV) Calculation

2. ICV DIRECT

ICV =Direct Offset/EEP ∑ ICVDirect project (i)

i=1

n

where

ICV Direct project= ∑ ICVNon-LC

+ ∑ ICVLC

= ∑ [NV × M ]Non-LC Category ∑ [NV × M ]LC Cat(k)+

NV = Nominal Value is the actual cost of the proposed project

LC = Local Content

* The formula is applicable for both EEP and Offset

M = Multiplier based on Category as specified in the Multiplier tableCategory

M =Cat(k)Multiplier based on Cat A, Cat B, Cat C, Cat D, Cat E and Cat F as per LC Multiplier table

Page 10: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-3

ICP Credit Value (ICV) Calculation

3. ICV INDIRECT

ICV =Indirect Offset/EEP ∑ ICVIndirect project (i)

i=1

n

where

=∑ [NV × M × (1 + µ)] + ∑ [NV × M × (1 + µ)] Category LC Cat(k)

µ ,impact coefficient ≤ 0.5; comprises of 30% from NKEA, 30% from Economic Corridor, and 40% from Offset Objectives factors or 100% from any other initiatives deemed appropriate by ICP Authority

; ICVIndirect project

= ∑ ICVNon-LC+ ∑ ICVLC

Non-LC

Page 11: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-4

ICP Credit Value (ICV) Calculation

3.1 Impact Coefficient, µ

Impact coefficient derived from:

• Programs that support government’s initiatives in GNI growth;

• Programs that support high value jobs creation and human capital capabilities development;

• Programs that support increase of investment portfolios

• Prioritized economic activities• Prioritized Growth Zones (ETP, NKEA,

Malaysia Plan, Industrial Master Plan etc.)

Page 12: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-5

12 NKEA

1. Oil & Gas2. Palm oil and related

products3. Financial services4. Wholesale & Retail5. Tourism6. Information & Comm

technology7. Education8. Electrical & Electronic9. Business Services10. Private Healthcare11. Agriculture12. Greater K. Lumpur

FOCUSING CORRIDORS

1. Iskandar Malaysia2. Northern Corridor Economic

Region3. East Coast Eco. Region4. Sarawak Corridor Renewable

Energy5. Sabah Development Corridor

ICP OBJECTIVES

1. Foster strategic local and international partnership

2. Maximize the usage of local contents3. Establish a sustainable Malaysian

industrial, economic and technological base, with strategic capabilities development and industrial participation in the global supply chain

4. Technology acquisition, development and diffusion

5. Collaborate in strategic R&D&C projects

6. Facilitate investments and collaborate in strategic Human Resource Development (HRD) initiatives.

ICP Credit Value (ICV) Calculation

3.2 Criteria for µ entitlement

Criteria must contain at least one of the factors. (NKEA ‘OR’ CORRIDOR ‘OR’ OBJECTIVE)

Page 13: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-6

ICP Credit Value (ICV) Calculation

3.3 Example of ICV calculation:

3.3.1 Case 1: Project title: Project Financing for Company A (Investment):

Assuming an investment of RM100 mil to support project located in Sabah Development Corridor which aim to add value to the palm oil industry by fostering strategic local and international partnership.

Solution:

Nominal value = RM 100 mil

Applicable for µ (30% NKEA, 30% Economic Corridor, and 40% Objective)

Multiplier = 5 (cash investment, project financing)

µ = 0.5 × (0.3+0.3+0.4)µ = 0.5 × 1µ = 0.5

[RM 100 mil × 5 × (1+0.5)]

= [ NV × M × (1 + µ)] Category

=

RM 750 mil=

ICVIndirect project

Page 14: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-7

ICP Credit Value (ICV) Calculation

3.3 Example of ICV calculation:3.3.2 Case 2 : Project Title: Localization for Air Insulated Switchgear and Gas Insulated Switchgear

No. Milestone/Activity LC/ Non-LC

Item/Evidence NominalValue (RM)

Multiplier ICV(RM)

1 Technical assistant on design by the Supplier

Non-LC Man-hour 100,000 4 400,000

2 Manufacturing Contract Value: 2,100,000- LC- P.O for oversea supplier

1,600,000500,000

31

4,800,000500,000

3 Provide training for testing and commissioning

Non-LC Man-hour 100,000 2 200,000

4 Perform testing LC Contract Value 500,000 2 1,000,000

5 Reimbursable LC Accommodation, transport, etc

50,000 1 50,000

Total ICV: 8,450,000

ICVDirect project = ∑ ICV

Non-LC+ ∑ ICV

LC

Therefore, ICV RM 8.45 mil=

Page 15: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-8

ICP Credit Value (ICV) Calculation

3.3 Example of ICV calculation:

3.3.3 Case 3 : Project Title: Market Access for Air Insulated Switchgear and Gas Insulated Switchgear

No. Milestone/Activity LC/ Non-LC

Item/Evidence NominalValue (RM)

Multiplier ×(1 + µ)

ICV(RM)

1 Technical assessment on recipient capability and capacity by the Supplier (audit, gap analysis, etc)

Non-LC Man-hour 100,000 2 × (1 + 0.2) 240,000

2 Contract awarded to Recipient

LC

Non-LC

Contract Value

P.O for oversea supplier

21,100,000

5,000,000

4 × (1 + 0.2)

1 × (1 + 0.2)

101,280,000

6,000,000

3 Reimbursable LC Accommodation, transport, etc

50,000 1 × (1 + 0.2) 60,000

Total ICV 107,580,000

ICVIndirect project = ∑ ICV

Non-LC+ ∑ ICV

LC

Applicable for µ (40% Objective). Therefore, µ = 0.2.

Therefore, ICV RM 107.58 mil=

Page 16: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-9

ICP Credit Value (ICV) Calculation

3.3 Example of ICV calculation:3.3.4 Case 4 : Project Title: Transfer of Technology of Air Traffic Management System

No. Milestone/Activity LC/ Non-LC

Item/Evidence NominalValue (RM)

Multiplier ICV(RM)

1 Selection of candidate and logistic arrangement

Non-LC Man-hour 400,000 1 400,000

2 Development of training module

Non-LC Man-hour, modules 800,000 3 2,400,000

3 Training Non-LC Man-hour 750,000 4 3,000,000

4 Performance evaluation andcertification

Non-LC Man-hour 36,000 2 72,000

5 Licensing of local recipient Non-LC IPR transfer and commercialization

66,000,000 4 × (1 + 0.2) 316,800,000

6 Reimbursable Non-LC Accommodation, allowances, transport, etc

4,000,000 1 4,000,000

Total ICV 326,672,000

Therefore, ICV RM 326.672 mil=

Page 17: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-10

ICP Credit Value (ICV) Calculation

4. LOCAL CONTENT (LC)

LC(prg)ICV ="($%&LC Prj (i) ))

*+,

LC(prg)ICV

=

= The total LC ICV of the ICP projects in an ICP Program

where

LC Prj (i)ICV The LC ICV of the ICP projects in an ICP Program

LC(prg)ICV > 30% of ICVBased on the Policy Obligation

Page 18: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

2-11

ICP Credit Value (ICV) Calculation

5. LEASING

Page 19: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

3-1

Category Item Description Direct Indirect

1 Investment

1.1Cash a) Equity/ WorkingCapitalInvestmenttolocalentity 5 5

b)BankGuarantee(forotherBGsthanMainContractandICPrequirements) 4 5

c) Project Financing(ICPProjectrelated)– Principalonly 3 5

d)PrincipalGuaranteeforStandbyLetterofCredit(SBLC) 3 5

1.2Non-

Cash

Equipment,SpecialTools,Infrastructure,AcquisitionofIP,etc.(withproven

ownershiptransfer)

3 4

2 Research,DevelopmentandCommercialization(R&D&C)/TransferofTechnology /Knowledge

2.1 ImplementationanddiffusionofToT Plantolocalindustry

a) IPRtransferandCommercializationthroughJV/Partnershipwithlocalcompany

(TechnologywithTechnologyReadinessLevelTRL7and8)*

b) TechnologyCommercializationandRollOut/Start-UpCompany

(TechnologywithTechnologyReadinessLevelTRL7and8)*

c) Tools/equipment,laboratoryandworkshopset-up

d) TrainingandSkillsDevelopmentCourses (design,engineeringand

development)

e) IPRDevelopmentandSharing

f) Technologyadaptationtolocalenvironmentandconditions

g) TransferorresidentofToT projectteamassignmenttoOEM

h) SubjectMatterExpertstolocalrecipientassignment

i) Drawings,manualsandtrainingdocumentationsforrecipient

j) TrainingandSkillsDevelopmentCourses-general

*RefertoTRLDefinitionbyNASA

4

4

4

4

4

3

3

3

3

2

5

5

4

4

4

3

3

3

3

2

ATTACHMENT 3ICP MULTIPLIERS

Page 20: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

3-2

Category Item Description Direct Indirect

2 Research,DevelopmentandCommercialization(R&D&C)/TransferofTechnology /Knowledge

2.2 Identificationoftechnologyneedsandgapanalysisa) TechnologyExpertsandIndustrialExpertsassignment 3 3

2.3 ImpactAnalysisa) TechnologyExpertsandIndustrialExpertsassignment 3 3

2.4 Development ofNewPolicy,Standard,Blueprint,Roadmapetca) Policyb) Standardc) Blueprint,Roadmap,Studyd) Certification

N/A2

N/A1

4323

3 MarketAssistance

a) CaptiveMarketAccess N/A 4

b) MarketAccess Assistance,OEMSupplyChainAcceptance N/A 2

ICP MULTIPLIERS

Page 21: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

3-3

Category Item Description Direct Indirect

4 Human CapitalDevelopmenta) Technical Transfer,SkillsandCompetencyDevelopmentforProfessional

Services(e.g.ondesign,systemsintegration,platformtechnology,engineering&developmentandProfessionalCertificationetc.)

4 4

b) OnJobTraining(International/LocalPlacement)*AttachmentatOEM.Allcostinvolveincludingflightticket,accommodation,etc

2 3

c) KnowledgeTransferandSkillsDevelopment forProfessionalServices(e.g.classroomactivitiesfordesign,engineeringanddevelopmentetc.)

3 3

d) Non-TechnicalTransferandSkillsDevelopment 2 2

e) TrainingandSkillsDevelopmentCourses-general 2 2

f) HigherLearningPlacementProgramatLocal/InternationalInstitution(masters,PhD)*Tuitionfee,allowances,accommodation,etc

N/A 2

5 Incidental/Others

5.1 Flightticket,accommodation,allowances,etc. 1 1

ICP MULTIPLIERS

Page 22: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

3-4

TRL Description1.Basicprinciplesobservedandreported

Thisisthelowest"level"wherescientificresearchbeginstobetranslatedintoappliedR&D.

2.Technologyconceptand/orapplicationformulated

Nextlevelofmaturation,practicalapplicationsofthosecharacteristicscanbe'invented'oridentified.Atthislevel,theapplicationisstillspeculative:noexperimentalproofordetailedanalysistosupporttheconjecture.

3.Analyticalandexperimentalcriticalfunctionand/orcharacteristicproofofconcept

Atthisstep,active(R&D)isinitiated.Thismustincludebothanalyticalstudiestosetthetechnologyintoanappropriatecontextandlaboratory-basedstudiestophysicallyvalidatethattheanalyticalpredictionsarecorrect.ShouldconstitutePOCvalidationoftheapplications/conceptsformulatedatTRL2.

4.Componentand/orbreadboardvalidationinlaboratoryenvironment

FollowingsuccessfulPOCwork,basictechnologicalelementsmustbeintegratedtoestablishthatthe"pieces"willworktogethertoachieveconcept-enablinglevelsofperformanceforacomponentand/orbreadboard.Thisvalidationmustbedevisedtosupport theconcept thatwasformulatedearlier,andshouldalsobeconsistentwiththerequirementsofpotentialsystemapplications.Thevalidationis"low-fidelity"comparedtotheeventualsystem:itcouldbecomposedofadhocdiscretecomponentsinalaboratory.

5.Componentand/orbreadboardvalidationinrelevantenvironment

Atthislevel,thefidelityofthecomponentand/orbreadboardbeingtestedhastoincreasesignificantly.Thebasictechnologicalelementsmustbeintegratedwithreasonablyrealisticsupportingelementssothatthetotalapplications(component-level,sub-systemlevel,orsystem-level)canbetestedina'simulated'orsomewhatrealisticenvironment.

6.System/subsystemmodelorprototypedemonstrationinarelevantenvironment(groundorspace)

AmajorstepintheleveloffidelityofthetechnologydemonstrationfollowsthecompletionofTRL5.AtTRL6,arepresentativemodelorprototypesystemorsystem- whichwouldgowellbeyondadhoc,'patch-cord'ordiscretecomponent levelbread-boarding- wouldbetestedinarelevantenvironment.Atthislevel,iftheonly'relevantenvironment'istheenvironmentofspace,thenthemodel/prototypemustbedemonstratedinspace.

7.Systemprototypedemonstrationinaspaceenvironment

TRL7isasignificantstepbeyondTRL6,requiringanactualsystemprototypedemonstrationinaspaceenvironment.Theprototypeshouldbenearoratthescaleoftheplannedoperationalsystemandthedemonstrationmusttakeplaceinspace.

8.Actualsystemcompletedand'flightqualified'throughtestanddemonstration(groundorspace)

Inalmostallcases,thislevelistheendoftrue'systemdevelopment'formosttechnologyelements.Thismightincludeintegrationofnewtechnology intoanexistingsystem.

9.Actualsystem'flightproven'throughsuccessfulmissionoperations

Inalmostallcases,theendoflast'bugfixing'aspectsoftrue'systemdevelopment'.Thismightincludeintegrationofnewtechnology intoanexistingsystem.ThisTRLdoesnot includeplannedproductimprovementofongoingor reusablesystems.

Technology Readiness Levels (TRL) – definition by NASA

Page 23: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

3-5

Cat(k) Item Description MultiplierA LocalServices/Sourcing i)Designandsystemsintegrationwork 4

ii)HighSkillWorks*PersonnelthatrequirecertificationsuchasTIGwelding,diving,NDT,etc

3

iii)Installation,Assembly,Testing,CommissioningandProjectManagement 2

iv)GeneralWorks 1

B LocalProduct i)Parts&Component,MainEquipment,TestEquipment

a) CustomMade 3

b) OffThe Shelves 1

C PlantFacility i) Plantequipment and machinery 3

ii) Tools,Jigs andFixtures 4

D Logistics i) Integratedlogisticsupport(ILS) 1

ii)Forwarding,haulageandtransportation,storage&warehouse 1

iii) Local Insurance 1

E Partnership/Consortium WorkscopeawardedtoLocalPartner 1

F Professional andHighTechnicalSkillEmployment

Theminimumskillrequired iscertificate 1

LOCAL CONTENT MULTIPLIERS

Page 24: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

4-1

Penalty Calculation

PENALTY CALCULATION

Penalty (RM) = Unachieved ICV (RM) × Performance Bond (%)

• Penalty will be calculated based on un-achievement of the Mandatory ICV for both LC and Non-LC

Unachieved ICV (RM)

= Unachieved Non-LC ICV (RM) + Unachieved LC ICV (RM)

Program

Where;

Program

ATTACHMENT 4

Page 25: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

4-2

Penalty Calculation

1. Example of penalty calculation for Un-achievement of the Non-LC only

Total Obligation = RM 500milNon-LC Obligation = 70% × RM 500 mil = RM 350 milLC Obligation = 30% × RM 500 mil = RM 150 mil

Upon PIA,Total Non-LC ICV verified = RM 300 milTotal LC ICV verified = RM 150 mil

Total Unachieved Non-LC ICV = RM 350 mil – RM 300 mil = RM 50 milTotal Unachieved LC ICV = RM 150 mil – RM 150 mil = RM 0 mil

(RM 50 mil + RM 0 mil) × 5% =

RM 2.5 mil=

Penalty (RM) = (Unachieved Non-LC ICV (RM)+ Unachieved LC ICV (RM) )× Performance Bond (%)

Therefore, penalty impose:

Page 26: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

4-3

Penalty Calculation

2. Example of penalty calculation for Un-achievement of the LC only

Total Obligation = RM 500milNon-LC Obligation = 70% × RM 500 mil = RM 350 milLC Obligation = 30% × RM 500 mil = RM 150 mil

Upon PIA,Total Non-LC ICV verified = RM 450 milTotal LC ICV verified = RM 100 mil

Total Unachieved Non-LC ICV = RM 450 mil – RM 350 mil = + RM 100 mil (exceed Non-LC Obligation)

Total Unachieved LC ICV = RM 150 mil – RM 100 mil = RM 50 mil

(RM 0 mil + RM 50 mil) × 5% =

RM 2.5 mil=

Penalty (RM) = (Unachieved Non-LC ICV (RM)+ Unachieved LC ICV (RM) ) ×Performance Bond (%)

Therefore, penalty impose:

Page 27: MALAYSIAN ICP MANAGEMENT FRAMEWORKtda.my/wp-content/uploads/2019/04/ICP-Guidelines-Second... · 2019-04-08 · DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN

DASAR DAN GARIS PANDUAN PROGRAM KOLABORASI INDUSTRI (ICP) DI DALAM PEROLEHAN KERAJAAN

4-4

Penalty Calculation

3. Example of penalty calculation for Un-achievement of both Non-LC and LC

Total Obligation = RM 500milNon-LC Obligation = 70% × RM 500 mil = RM 350 milLC Obligation = 30% × RM 500 mil = RM 150 mil

Upon PIA,Total Non-LC ICV verified = RM 300 milTotal LC ICV verified = RM 100 mil

Total Unachieved Non-LC ICV = RM 350 mil – RM 300 mil = RM 50 milTotal Unachieved LC ICV = RM 150 mil – RM 100 mil = RM 50 mil

(RM 50 mil + RM 50 mil) × 5% =

RM 5 mil=

Penalty (RM) = (Unachieved Non-LC ICV (RM)+ Unachieved LC ICV (RM) )× Performance Bond (%)

Therefore, penalty impose: