Upload
aarif-shah
View
223
Download
0
Embed Size (px)
Citation preview
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 1/26
TABLE OF CONTENTS
Sr.
No:Topic’s Name: Page No:
1) Acknowledgment:
2) Executive Summary:
3) Purpose of the Project:
4)Scope Statement; Exclusion &
Deliverables:5) Resources Requirement:
6) Financial Requirement; HR & Technical
7) Feasibility; All types
8) Cost & Time Estimation:
9) Work Down Break Structure (WBS):
10) Network Diagram:
11)Risk Mgt. Process; i.e. Risk Factors &Mitigation:
12) Recommendation:
13) Key Success Factors of the Project:
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 2/26
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 3/26
Project Management
Executive Summary:
The objective of this report /study is primarily to facilitate
potential entrepreneurs to facilitate investment and provide
an overview about construction of New Hostels Intuitions /
University The Feasibility Study is the preliminary study that
determines whether a proposed systems project is technically,
financially, and operationally viable. Generally, a feasibility
study precedes technical development
and project implementation. The capital cost for a
construction project includes the expenses related to the
initial establishment of the facility. The owner is interested in
achieving the lowest possible overall project cost that is
consistent with its investment objectives. In most construction
budgets, there is an allowance for contingencies or
unexpected costs occurring during construction. As
construction projects become larger and more complex, so do
the risks associated with them. The sheer size, scope, and
timing of today's projects pose significant risk management
challenges, including identifying risks, determining the
allocation of risks among the parties involved, developing
mitigation and risk treatment plans and opportunities for cost
savings in single project applications or across an entire
portfolio of projects.
Because of the increasing complexity and size of project risks,
sponsors must view risk on an enterprise-wide project or
portfolio basis to properly and consistently identify risks,
develop optimal risk allocation strategies, and, if necessary.
To mitigate the risk; the Project Manger’s has extensive,
process-driven strategies and tools designed to manage and
monitor risks from a project's earliest stages to the final
delivery and commissioning.
3
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 4/26
Project Management
Purpose of this Project:
The objective of this report /study is primarily to facilitate
potential entrepreneurs to facilitate investment and providean overview about construction of New Hostels Intuitions /
University.
The project may form the basis of an important investment
decision and in order to serve this objective, the document
covers various aspects of Hostel construction concept
development, start-up, and production, marketing, finance
and business management. The document also provides
sectoral information, brief on government policies and
international scenario, which have some bearing on the
project itself. This particular report which comes under
“Construction and Real Estate” sector.
4
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 5/26
Project Management
1. Scope:Negotiation with the owners of land and search of location is
carried out carefully. Planning regarding collection of
materials, labours and other equipments which are required
for the project is completed. Building of hundred meters long,
twenty meters in floor, 8 and 6 feet step wise width and
twelve feet high flood protection wall at nearby City University
of Science & Information Technology (CUIST), Peshawar in 12-
months in this main them to improve the Education level of
the society in the region.
1.1: Goal of the Project:
To construct a well furnished era of the technology
hostel of composed of 100 Rooms for City University of
Science & Information Technology (CUIST), Peshawar.
To construct a high-quality, hostel within 12
months at cost not to exceed Rs. 20,000,000
1.2: Objectives of the Project:
To complete search for the location of area, where
hostel to be constructed within 30-days, after approval
of the project.
To advertise and select the Constructer, within 15-
days after the searching of appropriate area.
To construct the building for hostel within 7-
months after approval from Government agency / body.
To complete the furnishing of hostel within 3-
months after construction of hostel building.
5
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 6/26
Project Management
1.3: Deliverable of the Project:
1.3.1: Intermediary deliverables:
Survey for the selection of suitable/ feasible
place for the construction. Short listing of marked
places.
Result of Law and Investigation.
Selection of delivery.
1.3.2: Final Deliverables
Digging place for the construction.
Collecting of materials for the construction.
Hiring labours for the constructions whosesufficient experienced
6
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 7/26
Project Management
2. Feasibility:
The Feasibility Study is the preliminary study that determines
whether a proposed systems project is technically, financially,and operationally viable. The Alternatives Analysis, usually
included as part of the Feasibility Study, identifies viable
alternatives for the system design and development. Between
them, the documents provide:-
An analysis of the system objectives, functional
requirements, and system design concepts;
A determination of the feasibility of applying
automated systems to effectively, efficiently, and
economically improve program operations;
An evaluation of alternative approaches for
reasonably achieving the objectives and goals; and
Identification of a proposed approach.
A feasibility study is an evaluation of a proposal designed to
determine the difficulty in carrying out a designated task.
Generally, a feasibility study precedes technical development
and project implementation. In other words, a feasibility study
is an evaluation or analysis of the potential impact of a
proposed project. Feasibility, perhaps the most inclusive is to
do the assessment by constraint category. Common constraint
categories include the flowing:-
2.1: Technical Feasibility
Technically this project is feasible; because it may
provide accommodation for the student of City
University of Science & Information Technology (CUIST),
Peshawar. City University uncovered area / spare area is
7
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 8/26
Project Management
suitable place for this purpose and the equipments that
are required for the project are also available and there
is no short coming of any thing. The project can fulfill all
the needs.
2.2: Financial Feasibility
Financial resources that are required for the project are
enough. The operating cost of the project is reasonable
and there is sufficient fund for the project. So financially
this project is feasible.
3.3: Operational Feasibility
Operationally this project is feasible because
operationally the ways for proposals bids are created
and there is no deficiency exists.
3.4: Geographic Feasibility
Geographically this project is feasible because all the
resources and materials that are required for the project
are available at the same place and there is no
disbursement of activities, so it is feasible
geographically.
3.5: Time Feasibility
The most important thing is time feasibility; but as for
as this project is concerned it is timely feasible;although it is lengthy project and it will take up to 12- 14
Months maximum time and if two or three months gape
occurs we can cover that through slack time which is
possible.
8
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 9/26
Project Management
3.6: Resource Feasibility
Resource wise this project is feasible because we have
enough resources which are available easily and there is
no hurdle in it.
3.7: Legal Feasibility
To determine whether the proposed system conflicts
with legal requirements; legally this project is feasible
because this project is approved by the Government of
Pakistan; and other Government Agencies and legally
documented. There is no legal constraint for the project.
8.3: Political Feasibility
As for is the political feasibility is concerned there is not
such thing in the project that can create a political
conflict. So we can say that this project is feasible
politically.
9
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 10/26
Project Management
4. Resources Requirement:
4.1: Financial Requirement:
Project Investment
The total cost of the project is Rs. 20.00 million
Capital Investment: 5.00 million
Working Capital Requirement: 15.00 million
Total Investment: 20.00 million
The proposed pre-feasibility is based on the assumption of 50% debt
and 50% equity. However this composition of debt and equity can
be changed as per the requirement of the investor
Debt: 50%
Equity: 50%
Total Project Investment: 100%
4.2: Human Requirement:
4.2.1: Skilled Labours
4.2.2: Unskilled Labour
4.3: Raw Material Requirement
Following raw materials would be required for thecontraction of the hostel:-
• Bricks
• Crush
• Steel
• Mud
•
Cement
10
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 11/26
Project Management
• Floor Tiles
• Bath Room Fittings
• Cupboards
• Lighting Accessories
• Sewerage and water Supply Pipes
• Dedex Pipe
• Steel Doors and Grill
• Win Bard
• Chipboard
• Glass
• Varnish
• Paints
• Hardware
• Wires
• Misc. Electrifications Equipment
• PVC Pipes
4.4: Machinery Requirement
All the required machinery i.e. Mixer, Lifts etc would be
purchased for this purpose; although they available on too,
but the rental expenses are too much high, therefore, it is
proposed that such sort of machinery should be purchased.
4.5: Material Cost Calculation:
Material Cost:
Sr. No: Material: Rs. Unit:
1. Bricks 3,600 Thousand
2. Sand: 2,200 Truck (350 cbft)
11
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 12/26
Project Management
3. Crush 20 Cubic ft
4. Steel 40 Kg
5. Cement 230 Bag
6. Mud 800 Trolley
7. Title: 4,500 Thousand
8. Grills including labour 250 Sq ft
9. Gate including Labour 250 Sq ft
10. Glass 50 Sq m
11. Tile for Front: 800 Sq m
12. Door: 150 Sq ft
13. Wood 60 Sq Ft
14. Lamination: 2000 Per Sheet
15. Chipboard: 700 Per Sheet
16. Ply: 300 Per Sheet
12
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 13/26
Project Management
6. Estimation Cost & Time of the Project:
The costs of a constructed facility to the owner include
both the initial capital cost and the subsequentoperation and maintenance costs. Each of these major
cost categories consists of a number of cost
components.
The capital cost for a construction project includes the
expenses related to the initial establishment of the
facility:
• Land acquisition, including assembly,
holding and improvement
• Planning and feasibility studies
• Architectural and engineering design
• Construction, including materials,equipment and labor
• Field supervision of construction
• Construction financing
• Insurance and taxes during construction
• Owner's general office overhead
• Equipment and furnishings not included
in construction
• Inspection and testing
The operation and maintenance cost in subsequent years
over the project life cycle includes the following expenses:
• Land rent, if applicable
13
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 14/26
Project Management
• Operating staff
• Labor and material for maintenance and
repairs
• Periodic renovations
• Insurance and taxes
• Financing costs
• Utilities
• Owner's other expenses
The magnitude of each of these cost components
depends on the nature, size and location of the project
as well as the management organization, among many
considerations. The owner is interested in achieving the
lowest possible overall project cost that is consistent
with its investment objectives.
It is important for design professionals and construction
managers to realize that while the construction cost
may be the single largest component of the capital
cost, other cost components are not insignificant. For
example, land acquisition costs are a major
expenditure for building construction in high-density
urban areas, and construction financing costs can
reach the same order of magnitude as the construction
cost in large projects such as the construction of
nuclear power plants.
From the owner's perspective, it is equally important to
estimate the corresponding operation and maintenance
cost of each alternative for a proposed facility in order
14
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 15/26
Project Management
to analyze the life cycle costs. The large expenditures
needed for facility maintenance, especially for publicly
owned infrastructure, are reminders of the neglect in
the past to consider fully the implications of operation
and maintenance cost in the design stage.
In most construction budgets, there is an allowance for
contingencies or unexpected costs occurring during
construction. This contingency amount may be
included within each cost item or be included in a
single category of construction contingency. The
amount of contingency is based on historical
experience and the expected difficulty of a particular
construction project. For example, one construction
firm makes estimates of the expected cost in five
different areas:
• Design development changes,
• Schedule adjustments,
• General administration changes (such
as wage rates),
• Differing site conditions for those
expected, and
• Third party requirements imposed
during construction, such as new permits.
Contingent amounts not spent for construction can be
released near the end of construction to the owner or to add
additional project elements.
15
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 16/26
Project Management
Proje
ctCost:
Rs.20
,000,000
Projec
tCost:
Rs.20,
000,000
Initiation
35%
Rs.7,000,000
Initiation
35%
Rs.7,000,000
Concrete
5%
Rs.1,000,000
Concrete
5%
Rs.1,000,000
Farming
8%
Rs.1,600,000
Farming
8%
Rs.1,600,000
Plumbing
10%
Rs.2,000,000
Plumbing
10%
Rs.2,000,000
Electrical
12%
Rs.2,400,000
Electrical
12%
Rs.2,400,000
Inertial
15%
Rs.3,000,000
Inertial
15%
Rs.3,000,000
Roofing
15%
Rs.3,000,000
Roofing
15%
Rs.3,000,000
Procurementof
Land
70%
Procurementof
Land
70%
Architecture
Design
2%
Architecture
Design
2%
Procurementof
Material
28%
Procurementof
Material
28%
PourFoundation
50%
PourFoundation
50%
InstallTerrace
30%
InstallTerrace
30%
PourStairway
20%
PourStairway
20%
FrameExterior
Wall
25%
FrameExterior
Wall
25%
FrameInterior
Wall
35%
FrameInterior
Wall
35%
InstallRoofing
Tresses
40%
InstallRoofing
Tresses
40%
InstallWater
Lines
30%
InstallWater
Lines
30%
InstallGasLines
30%
InstallGasLines
30%
InstallFixtures
40%
InstallFixtures
40%
InstallWiring
25%
InstallWiring
25%
InstallSwitches
35%
InstallSwitches
35%
InstallFixtures
40%
InstallFixtures
40%
InstallDrywall
20%
InstallDrywall
20%
InstallCarpet
40%
InstallCarpet
40%
InstallPainting
40%
InstallPainting
40%
InstallFelt
50%
InstallFelt
50%
InstallShingles
30%
InstallShingles
30%
InstallGateway
20%
InstallGateway
20%
Appropriation Method of Allocating Project Costs Using the Work down Structure (WBS)
16
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 17/26
Project Management
7. Work Breakdown Structure (WBS):
A key strategy of effective planning is to partition the project
into manageable chunks that can be individually plannedestimated and controlled. The work breakdown structure is a
graphical tool that displays the project's statement of work
making it easier to understand and communicate. It is
employed from the earliest stages of project planning.
The work breakdown structure (WBS) is a powerful tool for
expressing the scope or extent of a project in simple graphic
terms. It represents the project in terms of the hierarchy of
deliverables and services it will produce. The project is
therefore described just as a manufacturer would document
the bill of materials breakdown for a washing machine or
automobile. The WBS starts with a single box at the top which
represents the whole project. The project is then partitioned
into its components with lower level boxes. The WBS supports
the principle of management by deliverables providing a map
of what is to be produced.
7.1 WBS ROLE
The role of the WBS is to:
Partition the major projectdeliverables into smaller components toimprove the accuracy of cost estimates
Provide a mechanism for collectingand organizing actual costs
Provide a mechanism forperformance measurement and control
Note that the WBS provides a simple map of what is to be
produced. It does not deal with schedules and therefore has
17
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 18/26
Project Management
no time dimension. It is however used as entry criteria for
schedule development.
7.2 WBS for Construction of 100 Rooms:
A: INITIATION:
A1: Procurement of Land:
A2: Architecture Design:
A3: Procurement of Materials:
B: CONCRETE:
B1: Pour Foundation:
B2: Install Terrace:B3: Pour Stairway:
C: FORMING:
C1: Frame Exterior Walls:
C2: Frame Interior Wall:
C3: Install Roofing Tresses:
D: PLUMBING:
D1: Selection of Plumber:D2: Plumbing Contract:
D3: Install Water Lines:
D4: Install Gas Lines:
D5: Install Fixture:
E: ELECTRICAL:
E1: Furnishing Plane:
E2: Install Wiring:
E3: Install outlet:
E4: Install Fixtures:
F: INTERIOR:
F1: Install Drywall:
F2: Install Carpet:
F3: Install Painting:
G: Roofing:
G1: Install Felt:
18
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 19/26
Project Management
G2: Install Shingles:
G3: Install Gateway:
19
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 20/26
Project Management
7.3: Activities; Predecessors etc:
SR. NO: ACTIVITY:PREDECESSOR
S:
A: INITIATION:
A1: Procurement of Land: -
A2: Architecture Design: -
A3: Procurement of Materials: -
B: CONCRETE:
B1: Pour Foundation: A1, A2, A3
B2: Install Terrace: B1
B3: Pour Stairway: B1
C: FORMING:
C1: Frame Exterior Walls: B1
C2: Frame Interior Wall: C1
C3: Install Roofing Tresses: C2, D2, D3, D4
D: PLUMBING:
D1: Selection of Plumber: B1
D2: Plumbing Contract: D1
D3: Install Water Lines: D1
D4: Install Gas Lines: D1
D5: Install Fixture: D1
E: ELECTRICAL:
E1: Furnishing Plane: C3
E2: Install Wiring: E1
E3: Install outlet: E2
E4: Install Fixtures: E3
F: INTERIOR:
F1: Install Drywall: E1
F2: Install Carpet: F1F3: Install Painting: F2
G: ROOFING:
G1: Install Felt: E1
G2: Install Shingles: G1
G3: Install Gateway: G2, F3, E4
20
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 21/26
Project Management
7.4: Network Diagram:
Start
A1
A3
A2 B1
B2
B3
D1
C1
D2
D3
D4
D5
C2 C3 E1
E2
E3
E4
G3
G1F1
F2
G2 F3
End
21
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 22/26
Project Management
8. Risk Mgt. Process @ Hostel Construction:
As construction projects become larger and more
complex, so do the risks associated with them. Thesheer size, scope, and timing of today's projects pose
significant risk management challenges, including
identifying risks, determining the allocation of risks
among the parties involved, developing mitigation and
risk treatment plans and opportunities for cost savings
in single project applications or across an entire portfolio
of projects.
Because of the increasing complexity and size of project
risks, sponsors must view risk on an enterprise-wide
project or portfolio basis to properly and consistently
identify risks, develop optimal risk allocation strategies,
and, if necessary.
8.1 Risk Factors in the Project: The following risk factors may be involved in the
Construction of Hostel in the City University of
Science & Information Technology (CUIST),
Peshawar; they are describe in the following
heading:-
Shortage of materials; specialized skilled;
skilled labours & man powers due to
terrorist activities in the region.
Time period for completion of project may
be increased; if the time period is increased
so the cost might be increased too; due to
inflation factor.
22
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 23/26
Project Management
The problem of non-availability of machinery
or experts may arise on the occasion.
Any other, problem regarding contractors;
sub contractor; skill labour etc.
8.2 Risk Mitigation Techniques:
8.2.1: Insurance Design and Placement:
o The project-specific risk transfer and
management programs that include theoptimal blend of insurance, alternative risk
transfer, and retained risk to maximize
protection.
8.2.2: Subcontractor Default :
o Through our proprietary Sub Secure®, the
Project Manager should the skill of that to
identify potential adverse implications of a
subcontractor's financial situation and
provide guidance for managing the risk of
subcontractor default. In addition, Marsh
can provide guidance on the nuances of a
subcontractor default insurance program,
like Sub Guard®, and how to implement it
on a project. Besides; can also help
subcontractors to gain competitive
advantage by presenting their financials to
contractors in the best possible light.
8.2.3: Risk Consulting:
o To mitigate the risk; the Project Manger’s
has extensive, process-driven strategies and
23
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 24/26
Project Management
tools designed to manage and monitor risks
from a project's earliest stages to the final
delivery and commissioning.
8.2.4: Project Governance :
o Projects with tight margins, tight schedules,
high risks, and complex reporting
requirements limit management's ability to
identify and mitigate problems when they
occur.
8.2.5: Project Performance Audits:o Rectifies the challenges brought on by the
increased need for transparency in project
management, common goals in the review
process, and standardization in contractor
payment processes.
8.2.6: Loss Control:
o Site safety is crucial to project performance;
control the same
8.2.7: Supply Chain:
o The Project Managers should have complete
suite of supply chain risk services, from
identifying and mapping risk within the
supply chain to identifying and applying
solutions (alternative risk strategies) to
monitoring threats that affect a client's
supply chain.
24
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 25/26
Project Management
Schematically, the Risk Management Process isDepicted in the following Diagram:
25
8/3/2019 Major Project Project Mgt.
http://slidepdf.com/reader/full/major-project-project-mgt 26/26
Project Management
9. Strategic Recommendations
The Education Industry is only profitable if the
projects are completed in time.
Quality of materials used ensures quality of
Hostels built. Superior quality is the best competitive
advantage these days.
Careful selection of residential area counts
towards selling price and timely sales
The investment in good architectural design is
worth it. A good look is the first thing buyers would
be looking for at the first place.
10. Key Success Factors/Practical Tips for Success:
The key success factors for hostel are careful
selection of construction site and a good
architecture. The investment in good construction
material and efficient use of labour are also very
crucial. In short quality pays in the long run