Maintenance+Cost

Embed Size (px)

Citation preview

  • 8/9/2019 Maintenance+Cost

    1/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Implementing Total Productive Maintenance andComputation the Cost

    MAINTENANCE AND RELIABILITY MANAGEMENT

    2009

    FARID KEYHANI

    E-Mail: [email protected]

    Page1

  • 8/9/2019 Maintenance+Cost

    2/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Table of ContentsChapter 1 Introduction ................................................................................................ 4

    Project Background ................................................................................................... 4Problems of the Current System ................................................................................. 5Aims and Objectives .................................................................................................. 6

    System maintenance (especially in mechanized model) if well designed andimplemented to answer the practical affairs of conditions is to reduce maintenancecosts. In this paper we have introduced different methods, their history and their maintenance - computational methods, chart maintenance costs and the use of methods such as work tables, etc. to reduce the costs. ............................................... 6

    Chapter 2 - Research Work ............................................................................................ 7Types of maintenance- introduction .......................................................................... 7

    Breakdown Maintenance (BM) [9] , [5] ................................................................. 7Preventive maintenance [9] , [5] ............................................................................ 7Predictive maintenance [9], [5] .............................................................................. 8Condition-Based maintenance (CBM) ................................................................... 8

    From PM to TPM ....................................................................................................... 9Total Productive Maintenance (TPM) ..................................................................... 10Different Generation of Maintenance ....................................................................... 11

    Why TPM? [11] .................................................................................................. 11Six losses in the work place / decrease in plant cost: [9] ......................................... 125S The Foundation of TPM ................................................................................... 13Growing Expectations of Maintenance ................................................................... 13

    Firs preventive maintenance ..................................................................................... 13Value of Preventive Maintenance ........................................................................ 13

    Second predictive maintenance ............................................................................... 21React, plan or predict? .......................................................................................... 22Condition prediction ............................................................................................. 23Predict to protect profit ........................................................................................ 24Detect, diagnose, Act ........................................................................................... 24

    Predictive Maintenance - Cost Effect ...................................................................... 25Planning aid to predictive maintenance [2] ....................................................... 25

    How can escape of too much PM and how can release of plant cost? ................... 27The No. 1 Law You Should Know [6] ................................................................. 27Reducing Maintenance Cost in a Tough Economic Climate [8] .......................... 31

    Chapter 3 ...................................................................................................................... 32In Conclusion [3], [1] ............................................................................................... 32

    Chapter 4 ..................................................................................................................... 34References ................................................................................................................ 34

    Page2

  • 8/9/2019 Maintenance+Cost

    3/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Acronyms used in the report

    KLIA An Airport in Malaysia, kuala lampur city

    BM Breakdown Maintenance

    CBM Condition-Based maintenanceTPM Total Productive Maintenance

    5S Shine Straighten Systemize Sustain - Sort

    RCFA Root Cause Failure Analyses

    PLC Programmable Logic Controller

    SCADA SCADA Soft were

    PDM Predictive Maintenance System

    JIT JUST-IN-TIME

    TQM Total Quality Maintenance

    Page3

  • 8/9/2019 Maintenance+Cost

    4/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Chapter 1 Introduction

    Project Background

    .Today, developing countries in particular nations of South East Asia For

    Economic and Industrial Development, and also the technologically developed

    countries throughout the world are faced with the ever increasing costs of production,

    maintenance and management. Therefore, they have the responsibility to ensure thatthey control these costs otherwise runaway costs that are not properly controlled will

    ultimately plunge the firm into failure. Among the items forming the cost of goods

    sold that need proper monitoring and controlling are direct materials; direct labor and

    overhead costs. The area of interest can be about overhead costs of production that

    have to be separately analyzed and solutions to the firms problems to be done

    through appropriate action so that they reduce the costs of production and

    maintenance. The most important items forming production cost of indirect materialsare depreciation; maintenance; repairs; electricity and fuel, etc. In order to promote

    efficiency in the firm to help enhance its productivity, data analysis of all the data is

    also necessary to be implemented and it can also be part of the costs .

    The costs of machines and equipment during recent years have been increasing . And

    most of the time, discussion about maintenance has been one of the most important

    problems managers in industries have been facing and efforts have been made in this

    regard to access ways to enhance profitability and increasing efficiency, safety and

    decreasing the expenses. By implementing effective controlling programs and with

    proper, regular surveillance of the status of equipment and information systems, the

    management can decrease direct costs and indirect costs at the industries. In fact by

    forecasting using an advanced system, they can find out the approximate time of

    breakdown and this can reduce repair costs and reduce interruption-time at the

    operating machinery can encourage effective planning for the desirable performance

    Page4

  • 8/9/2019 Maintenance+Cost

    5/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    of the machines and it can also increase the safety , financial savings and overall, it

    can increase economic performance.

    Problems of the Current System

    Research results in the United States of America shows that between 1979 and 2005,

    the maintenance costs had an average growth of between 10% to 15% . The

    technology development process and changes to technology in machinery

    industries .Predictable growth in maintenance costs and repairs will continue with

    greater acceleration

    But more interesting results of this research are related to cost analysis. A very

    surprising analysis shows that about 35% of the costs are unnecessary costs

    and wasted expenses. It can be seen that the remainder that is 65%, actually

    consists of the costs that are necessary.

    Page5

  • 8/9/2019 Maintenance+Cost

    6/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Aims and Objectives

    System maintenance (especially in mechanized model) if well designed and

    implemented to answer the practical affairs of conditions is to reduce

    maintenance costs. In this paper we have introduced different methods,

    their history and their maintenance - computational methods, chart

    maintenance costs and the use of methods such as work tables, etc. to

    reduce the costs.

    .

    Page6

  • 8/9/2019 Maintenance+Cost

    7/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Chapter 2 - Research Work

    Types of maintenance- introduction

    Breakdown Maintenance (BM) [9] , [5]Breakdown maintenance is also called as run-to-failure maintenance. It may

    be described as a fire-fighting approach to maintenance. Equipment is allowed to run

    until failure. Then the failed equipment is repaired or replaced. In these strategies the

    maintenance activities are not planned. These strategies are mostly used where the

    consequences of failure do not result in significant expenditure. This is the oldest type

    of maintenance. It is suitable for small, non-critical, low price equipments. Corrective

    maintenance involves running systems to breakdown and can only be applied to

    equipment which is inexpensive, largely duplicated and easy to repair or replace and

    where loss of the machine or equipment for a particular process or job will not

    constitute a significant disruption to production

    Preventive maintenance [9] , [5]Preventive maintenance is a schedule of planned maintenance actions aimed at

    the prevention of breakdowns and failures. The primary goal of preventive

    maintenance is to prevent the failure of equipment before it actually occurs. It is

    designed to preserve and enhance equipment reliability by replacing worn

    components before they actually fail. Preventive maintenance activities include

    equipment checks, partial or complete overhauls at specified periods, oil changes,

    Page7

  • 8/9/2019 Maintenance+Cost

    8/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    lubrication and so on. In addition, workers can record equipment deterioration so they

    know to replace or repair worn parts before they cause system failure. Recent

    technological advances in tools for inspection and diagnosis have enabled even more

    accurate and effective equipment maintenance. The ideal preventive maintenance

    program would prevent all equipment failure before it occurs.

    Predictive maintenance [9] , [5]A sound description of predictive maintenance is the application of

    technologies and early detection processes to monitor and detect changes in condition

    to allow more precise intervention. Predictive maintenance can be defined as follows:

    measurements that detect the onset of a degradation mechanism, thereby allowing

    casual stressors to be eliminated or controlled prior to any significant deterioration inthe component physical state Under predictive maintenance, diagnostic equipment is

    used to measure the physical condition of equipment and it may include vibration

    analysis, shock pulse methods, ultrasonic, thermo graphic analysis, oil analysis,

    electrical surge comparisons, coolant analysis, wear particle analysis, and

    performance trending.

    All machines give early warning signs predicting their impending failure.

    When one of these indicators reaches a specified level, work is undertaken to restore

    the equipment to proper condition. This means that equipment is taken out of service

    only when direct evidence exists that deterioration has taken place.

    Condition-Based maintenance (CBM)Condition-based maintenance (CBM) includes scheduled maintenance as well

    as corrective maintenance. CBM is not a technology or a technique, but it depends on

    other technologies to provide this objective evidence. Temperature, pressure and

    vibration are examples of monitoring parameters. BEVIEL Broglie (2000) has alsoexplained the differences between condition-based maintenance and predictive

    maintenance. Unlike the condition-based maintenance policy, predictive maintenance

    involves acquiring controlled parameters data which are analyzed to find a possible

    temporal trend. This makes it possible to predict when the controlled quantity value

    will reach or exceed the threshold values. The maintenance staff will then be able to

    plan, depending on the operating conditions, when the component substitution or

    revision is really unavoidable.

    Page8

  • 8/9/2019 Maintenance+Cost

    9/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    THE OPPORTUNITY [10]

    Condition Based Maintenance (CBM) promises to deliver improved

    maintainability and operational availability of plants while reducing life-cycle

    costs

    THE CHALLENGE [10]

    Prognostics is the Achilles heel of CBM systems - predicting the time to

    failure of critical machines requires new and innovative methodologies that will

    effectively integrate diagnostic results with maintenance scheduling practices

    From PM to TPM

    Almost fifty years have passed since Japan imported preventive maintenance

    (PM) from the United States. Later adoptions include productive maintenance (PM),

    and reliability engineering. What we now refer to as TPM is, in fact, American-style

    productive maintenance, modified and enhanced to fit the Japanese industrial

    environment.

    TPM is now well accepted by the Japanese industrial sector, and is attractingthe attention of Western industrial nations, China and various Southeast Asian

    countries.

    Page9

  • 8/9/2019 Maintenance+Cost

    10/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Total Productive Maintenance (TPM)

    Total Productive Maintenance (TPM) is a maintenance program, which

    involves a newly defined concept for maintaining plants and equipment. The goal of the TPM program is to markedly increase production while, at the same time,

    increasing employee morale and job satisfaction. (TPM) is a well-defined and time-

    tested concept for maintaining plants and equipment. TPM can be considered the

    science of machinery health. TPM brings maintenance into focus as a necessary and

    vitally important part of the business. It is no longer regarded as a non-profit activity.

    Down time for maintenance is scheduled as a part of the manufacturing day and, in

    some cases, as an integral part of the manufacturing process. The goal is to hold

    emergency and unscheduled maintenance to a minimum.

    TPM was introduced to achieve the following objectives:

    Avoid waste in a quickly changing economic environment.

    Produce goods without reducing product quality.

    Reduce costs.

    Produce a low batch quantity at the earliest possible time.

    Send only non-defective parts to the customers.TPM involves all Denso Associates. The major difference between TPM and other

    concepts is that the Production Operators are directly involved in the process of

    maintaining their equipment.

    The old notion of "I operate the equipment, You Maintain it" is NOT followed.

    NIPPOUNDENSOSO was the first company to introduce plant-wide preventive

    maintenance in 1960. By then NIPPOUNDENSOSO had made quality circles,

    involving the employees participation in implementing Productive Maintenance.Based on these developments NIPPOUNDENSOSO was awarded by the Japanese

    Institute of Plant Engineers (JIPE) the distinguished plant prize for developing and

    implementing TPM. NIPPOUNDENSOSO of the Toyota group became the first

    company to obtain the TPM certification

    Page10

  • 8/9/2019 Maintenance+Cost

    11/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Different Generation of Maintenance

    First Ggeneration :-Fix it when it broke

    Second Generation :

    -Scheduled overhauls

    -System for planning and controlling work

    -Longer asset life

    Third Generation :

    -Condition Monitoring

    -Higher availability and reliability

    -Better product quality

    -No damage to the environment

    -Expert systems

    -Multi skills and teamwork

    Why TPM? [11]

    Because of cost! Proper implementation of TPM leads to a organizedand well equipped firm. Some of the features of the industry where TPM has been

    successfully implemented are:

    Avoid wastage in a quickly changing economic environment.

    Producing goods without reducing product quality.

    Reduce cost.

    Produce a low batch quantity at the earliest possible time.

    Goods send to the customers must be non-defective.

    OR

    A Safer Workplace

    Associate Empowerment An Easier Workload

    Increased ProductionPage11

  • 8/9/2019 Maintenance+Cost

    12/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Fewer Defects

    Fewer Breakdowns-Aims for zero equipment breakdown

    Fewer Short Stoppages -Reach zero machine downtime state

    Decreased Costs

    Decreased Waste

    Maintenance goal: more production lower coast

    Six losses in the work place / decrease in plant cost: [9]

    The objective of TPM is maximization of equipment effectiveness. TPM aims

    at maximization of machine utilization and not merely machine availability

    maximization. As one of the pillars of TPM activities, Kaizen pursues efficient

    equipment, operator and material and energy utilization that is extremes of

    productivity and aims at achieving substantial effects. Kaizen activities try to

    thoroughly eliminate losses. Six major losses that were identified. Details of which is

    given below.

    1. Equipment failure causes production downtime. Equipment failure requires

    maintenance assistance and can be prevented with the use of appropriate preventive

    maintenance actions, developed and applied operating procedures, and design

    changes. Most importantly, equipment failure requires an improvement effort that

    should be the result of a successful partnership between production and maintenance.

    Predictive maintenance techniques such as vibration, oil, and thermo graphic analysis

    can be used to anticipate equipment failure. If the failure occurs, it is important to use

    Root Cause Failure Analysis (RCFA) techniques to identify the root cause of the

    problem and effective and applicable solutions that will eliminate or mitigate the

    failure occurrence and impact.

    2. Set-up and adjustments: this refers to loss of productive time between product

    types, and includes the warm-up after the actual changeover. Changeover time should

    be included in this loss opportunity and it should not be part of the planned downtime.

    3. Small stops are typically less than 5-10 minutes and they are typically minor

    adjustments or simple tasks such as cleaning. They should not be caused by logistics.

    4. Speed losses are caused when the equipment runs slower than its optimal or

    designed maximum speed. Examples include machine wear, substandard materials,

    operator inefficiency, equipment design not appropriate to the application, etc.

    Page12

  • 8/9/2019 Maintenance+Cost

    13/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    5. Losses during production include all losses caused by less-than-acceptable quality

    after the warm-up period.

    6. Losses during warm-up include all losses caused by less-than-acceptable quality

    during the warm-up period.

    5S The Foundation of TPM

    TPM starts with 5S. Problems cannot be clearly seen when the work place is

    unorganized. Cleaning and organizing the workplace helps the team to uncover

    problems. Making problems visible is the first step of improvement.

    Growing Expectations of Maintenance

    As maintenance passes through various levels of refinement there is a growing

    expectation from the manufacturing firms for a unified approach despite diverse

    distractions. The technology of maintenance is unending, its marked with finding and

    applying cost effective ways of avoiding performance deterioration. Prior to TPM

    there were several attempts to boost the maintenance by improving the cost

    effectiveness of the machine operations. The changing maintenance techniques can be

    illustrated as a time dependent factor.Predictive and preventive maintenance are on peak of new generation of maintenance(TPM) to decrease our plant cost

    Firs preventive maintenance

    Value of Preventive Maintenance

    There are multiple misconceptions about preventive maintenance. One such

    misconception is that PM is unduly costly. This logic dictates that it would cost morefor regularly scheduled downtime and maintenance than it would normally cost to

    operate equipment until repair is absolutely necessary. This may be true for some

    components; however, one should compare not only the costs but the long-term

    benefits and savings associated with preventive maintenance. Without preventive

    maintenance, for example, costs for lost production time from unscheduled equipment

    breakdown will be incurred. Also, preventive maintenance will result in savings due

    to an increase of effective system service life.

    Long-term benefits of preventive maintenance include:

    Page13

  • 8/9/2019 Maintenance+Cost

    14/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Improved system reliability. Decreased cost of replacement. Decreased system downtime. Better spares inventory management.

    Long-term effects and cost comparisons usually favor preventive maintenance over

    performing maintenance actions only when the system fails.

    WHEN DOES PREVENTIVE MAINTENANCE MAKE SENSE

    Preventive maintenance is a logical choice if, and only if, the following two

    conditions are met:

    Condition #1: The component in question has an increasing failure rate. In

    other words, the failure rate of the component increases with time, thus

    implying wear-out. Preventive maintenance of a component that is assumed to

    have an exponential distribution (which implies a constant failure rate) does

    not make sense! Condition #2: The overall cost of the preventive maintenance action must be

    less than the overall cost of a corrective action. (Note: In the overall cost for a

    corrective action, one should include ancillary tangible and/or intangible costs,

    such as downtime costs, loss of production costs, lawsuits over the failure of a

    safety-critical item, loss of goodwill, etc.)

    If both of these conditions are met, then preventive maintenance makes sense.

    Additionally, based on the costs ratios, an optimum time for such action can be easily

    computed for a single component. This is detailed in later sections .

    THE FALLACY OF "CONSTANT FAILURE RATE" AND "PREVENTIVEREPLACEMENT" [12]

    Even though we alluded to the fact in the last section of this on-line

    reference, Availability, it is important to make it explicitly clear that if a component

    Page14

  • 8/9/2019 Maintenance+Cost

    15/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    has a constant failure rate ( i.e . defined by an exponential distribution), then preventive

    maintenance of the component will have no effect on the component's failure

    occurrences. To illustrate this, consider a component with an MTTF = 100 hours,

    or = 0.01, and with preventive replacement every 50 hours. The reliability vs. time

    graph for this case is illustrated in Figure 1.1. In Figure 1.1, the component is

    replaced every 50 hours, thus the component's reliability is reset to one. At first

    glance, it may seem that the preventive maintenance action is actually maintaining the

    component at a higher reliability.

    Figure 1.1: Reliability vs. time for a single component with an MTTF = 100 hours, or =

    0.01, and with preventive replacement every 50 hours.

    However, consider the following cases for a single component:

    Case 1: The component's reliability from 0 to 60 hours:

    With preventive maintenance, the component was replaced with a new one at

    50 hours so the overall reliability is the reliability based on the reliability of

    the new component for 10 hours, R(t = 10) = 90.48%, times the reliability of

    the previous component, R(t = 50) = 60.65%. The result is R(t = 60) = 54.88%. Without preventive maintenance, the reliability would be the reliability of the

    same component operating to 60 hours, or R(t = 60) = 54.88%.

    Case 2: The component's reliability from 50 to 60 hours:

    With preventive maintenance, the component was replaced at 50 hours so this

    is solely based on the reliability of the new component, for a mission of 10

    hours, or R(t = 10) = 90.48%.

    Page15

  • 8/9/2019 Maintenance+Cost

    16/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Without preventive maintenance, the reliability would be the conditional

    reliability of the same component operating to 60 hours, having already

    survived to 50 hours, or .

    As it can be seen, both cases, with and without preventive maintenance, yield the

    same results.

    DETERMINING PREVENTIVE REPLACEMENT TIME

    As mentioned earlier, if the component has an increasing failure rate, then a carefully

    designed preventive maintenance program is beneficial to system availability.

    Otherwise, the costs of preventive maintenance might actually outweigh the benefits.

    The objective of a good preventive maintenance program is to either minimize the

    overall costs (or downtime, etc.) or meet a reliability objective. In order to achieve

    this, an appropriate interval (time) for scheduled maintenance must be determined.

    One way to do that is to use the optimum age replacement model, as presented next.

    The model adheres to the conditions discussed previously, or:

    The component is exhibiting behavior associated with a wear-out mode. That

    is, the failure rate of the component is increasing with time. The cost for planned replacements is significantly less than the cost for

    unplanned replacements.

    Page16

  • 8/9/2019 Maintenance+Cost

    17/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Figure 1.2: Cost curve for preventive and corrective replacement.

    Figure 1.2 shows the Cost per Unit Time vs. Time plot. In this figure, it can be seen

    that the corrective replacement costs increase as the replacement interval increases. In

    other words, the less often you perform a PM action, the higher your corrective costs

    will be. Obviously, the longer we let a component operate, its failure rate increases to

    a point that it is more likely to fail, thus requiring more corrective actions. The

    opposite is true for the preventive replacement costs. The longer you wait to perform

    a PM, the less the costs; while if you do PM too often, the higher the costs. If we

    combine both costs, we can see that there is an optimum point that minimizes the

    costs. In other words, one must strike a balance between the risk (costs) associated

    with a failure while maximizing the time between PM actions.

    OPTIMUM AGE REPLACEMENT POLICY [12]

    To determine the optimum time for such a preventive maintenance action

    (replacement), we need to mathematically formulate a model that describes the

    associated costs and risks. In developing the model, it is assumed that if the unit fails

    before time t , a corrective action will occur and if it does not fail by time t , a

    Page17

  • 8/9/2019 Maintenance+Cost

    18/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    preventive action will occur. In other words, the unit is replaced upon failure or after a

    time of operation, t , whichever occurs first.

    Thus, the optimum replacement time can be found by minimizing the cost per unit

    time, CPUT (t ). CPUT (t ) is given by:

    (5)

    Where:

    R(t ) = reliability at time t . C P = cost of planned replacement. C U = cost of unplanned replacement.

    The optimum replacement time interval, t , is the time that minimizes CPUT (t ). This

    can be found by solving for t such that:

    (6)

    Or by solving for a t that satisfies Eqn. (7):

    (7)

    Interested readers can refer to Barlow and Hunter [2] for more details on this model.

    INTRODUCTION TO REPAIRABLE SYSTEMS EXAMPLE 2

    The failure distribution of a component is described by a 2-parameter Weibull

    distribution, with = 2.5 and = 1000 hours.

    Page18

  • 8/9/2019 Maintenance+Cost

    19/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    The cost for a corrective replacement is $5. The cost for a preventive replacement is $1.

    Estimate the optimum replacement age in order to minimize these costs.

    SOLUTION TO INTRODUCTION TO REPAIRABLE SYSTEMS EXAMPLE 2

    Prior to obtaining an optimum replacement interval for this component, the

    assumptions of Eqn. (5) must be checked. The component has an increasing failure

    rate, since it follows a We bull distribution with greater than one. Note that if = 1,

    then the component has a constant failure rate and if < 1, it has a decreasing failure

    rate. If either of these cases exist, then preventive replacement is unwise.

    Furthermore, the cost for preventive replacement is less than the correctivereplacement cost. Thus, the conditions for the optimum age replacement policy have

    been met. Using Block Sim, the failure parameters can be entered in the component's

    Block Properties window. Select "Optimum Replacement" from the Block menu,

    enter the costs and compute the optimum time, 493.0470. Figure1.3 illustrates this.

    Figure 1.3: Using BlockSim's Optimum Replacement utility to obtain the results in

    Example 2.

    Figure 1.4 shows a plot illustrating the cost per unit time.

    Page19

  • 8/9/2019 Maintenance+Cost

    20/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Figure 1.4: Graph of cost vs. replacement time for Example 2.

    DISCUSSION ON INTRODUCTION TO REPAIRABLE SYSTEMS EXAMPLE2

    The effect of the corrective/preventive cost ratio on the optimum replacement

    interval is plotted in Figure 7.7. It can be seen that as the cost ratio increases, the

    optimum replacement interval decreases. This is an expected result because the

    corrective replacement costs are much greater than the preventive replacement costs.

    Therefore, it becomes more cost effective to replace the component more frequently

    before it fails.

    Page20

  • 8/9/2019 Maintenance+Cost

    21/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Figure 1.5: Replacement interval as a function of the corrective/preventive cost ratio.

    Second predictive maintenance

    Predictive maintenance programs provide businesses with valuable insight into

    the condition of their in-service process equipment, and are crucial in keepingindustrial processes online, streamlining maintenance schedules, and minimising

    repair expenses. Todays industrial environment can be unforgiving, driven by the

    quest for quality, throughput and arguably most importantly, profit. With many

    businesses operating 24 hours a day seven days a week, it is crucial that their

    industrial processes are kept online, and free from interruption. To achieve this,

    individual process equipment elements and machinery units must perform at an

    optimum level across a range of demanding operating conditions, all while remaining

    fault-free. Here, the expectation from the industrial sector has never been higher. An

    unavoidable by-product of any industrial process is the wear and tear on individual

    pieces of process equipment and their internal components. Breakages, leaks,

    overheating and complete breakdowns can lead to lengthy process shutdowns and lost

    revenue. These worse-case-scenario breakdowns become more prevalent when

    process equipment is neglected or poorly maintained. To ensure process equipment

    and machinery are kept in optimum working order, a systematic maintenance program

    is vital. The ability to accurately predict, and then address, the maintenance

    requirements of individual pieces of equipment goes a long way to maximising

    Page21

  • 8/9/2019 Maintenance+Cost

    22/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    uptime and avoiding costly process shutdowns. Here, predictive maintenance

    strategies lead the way. Offering crystal ball-like insight into the condition of onsite

    process equipment, predictive maintenance programs are fast becoming an essential

    component of modern industrial processes.

    React, plan or predict?The ongoing maintenance of process equipment is a necessary operating

    overhead experienced across nearly every application in the industrial sector.

    Equipment, such as motor gear-units, drive some of industrys most vital processes

    and, as a result, need to be kept in good working order. This is often easier said than

    done. According to SEW-Eurodrive applications engineer, Luke Schmidt, gear-unit

    maintenance has traditionally been carried out three different ways--reactive, plannedor predictive. Reactive maintenance is the least efficient maintenance strategy, he

    says. Addressing system faults and breakdowns after they occur, means processes

    can be offline for long periods while spare parts are procured and repairs made.

    Usually, going offline for any period of time means loss of revenue, which is

    unacceptable. Furthermore, specialist service staff can be expensive, especially at

    short notice or unusual times. Planned maintenance programs go some way to

    ensuring the wellbeing of gear-units, but can be viewed as unnecessary or wasteful,

    depending on the application. Regular planned maintenance can be beneficial, but is

    often not very cost-effective, says Schmidt. It can result in unnecessary

    maintenance being carried out, which wastes time, materials, labour resources and

    money. Unwarranted oil changes and parts replacement, in particular, can have

    significant environmental impact.

    Further difficulties can be encountered, as planned maintenance activities are often

    carried out over summer shutdown periods--busy peak periods for maintenance staff.

    According to SEW-Eurodrive Strategic Marketing and Product Manager, Darren

    Klonowski, more sophisticated maintenance strategies, such as a predictive

    maintenance program offer clear advantages. Predictive maintenance allows

    businesses to monitor their process equipment, determine the condition and schedule

    maintenance accordingly, he says. It ensures equipment life is maximised, and helps

    keep machinery online, preventing unplanned downtime.

    Page22

  • 8/9/2019 Maintenance+Cost

    23/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Condition predictionPredictive maintenance programs are centered around condition monitoring

    processes. Here, field mounted sensors continuously detect and collect an array of

    performance parameters unique to individual machines. The collected data is then

    used to establish the real condition of the machine and its components. This kind of

    insight allows maintenance technicians to take preventative action before a failure

    occurs, therefore avoiding the consequences of that failure. Condition monitoring

    permits the early detection of the initial stages of component wear, which if left

    unaddressed, can lead to catastrophic

    failures, says Klonowski. This level of

    foresight is obviously a real benefit,

    particularly with respect to gear-units,

    which are often subjected to continuous

    operation under extremely demanding

    conditions. Being able to monitor the

    condition of bearings, gears, drive shafts

    and lubricating oil gives technicians a

    detailed understanding of what

    maintenance tasks needs to be carried outin order to extend the gear-unit life and

    keep it online longer. Such field-

    mounted devices monitor a number of

    gear unit parameters, including vibration,

    oil level and temperature, and brake-

    wear. By monitoring these gear-unit

    parameters, on-sitetechnicians can accurately plan maintenance activities, explains Schmidt. It means

    maintenance is carried out only when and where it is required which maximizes

    component life and sees maintenance resources utilized efficiently.

    Page23

  • 8/9/2019 Maintenance+Cost

    24/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Predict to protect profitPredictive maintenance programs effectively address two primary

    considerationsthey protect expensive process equipment, as well as entire critical

    process lines.While there is merit in monitoring individual gear-units for the sole

    purpose of avoiding costly repair bills, often it is the protection of the process as a

    whole that is more important, says Klonowski. The gear-unit being monitored may

    be relatively inexpensive, but it might be responsible for driving a production line

    with a high throughput rate. If this line goes offline, the business can lose money at an

    alarming rate.Its not just the gear-unit that should be looked at, adds Schmidt. Its

    the role of the piece of equipment in the process. The cost, production impact and

    flow-on affects associated with that piece of equipment going offline must be

    considered. A less-expensive gear unit might be responsible for driving a process that

    has a production output rate of $50,000/hr. Predictive maintenance programs go a

    long way to ensuring these process stay online, while saving money According to

    Klonowski, predictive maintenance strategies are more costeffective when compared

    with reactive and planned maintenance schemes . Reactive maintenance results in

    periods of minimal maintenance followed by periods of extreme activity when urgent

    or emergency repairs are carried out--usually at an inflated rate, he says. Planned

    maintenance delivers some cost benefits, but can result in unnecessary and costlymaintenance being performed.

    Detect, diagnose, ActAt the heart of predictive maintenance installations lies a network of field-

    mounted condition monitoring devices or sensors linked via I/O to an on-board

    frequency inverter or central programmable logic controller (PLC). Each inverter or

    PLC can be connected to the plant-wide supervisory control and data acquisition

    (SCADA) system, and internet mail server via an Ethernet link . Such a system

    architecture provides real flexibility, says Schmidt. It allows machine performance

    and condition data to be easily detected, diagnosed and acted on. It can be configured

    to alert key personnel, once a pre-determined alarm-point or milestone has been

    reached. The alarm can be sent to an on-site HMI (Human-Machine Interface),

    SCADA or PC, or alternatively to an off-site control centre, mobile phone or pager.

    Predictive maintenance strategies are especially valuable in remote locations where

    gear-unit breakdown and unplanned downtime can take extended periods of time to

    remedy. By remotely monitoring applications in isolated or unsupervised areas,

    Page24

  • 8/9/2019 Maintenance+Cost

    25/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    technicians can accurately predict maintenance requirements and plan ahead says

    Schmidt. It means maintenance resources can be deployed at a time that permits

    repairs and upkeep to be carried out on multiple pieces of equipment at the same

    location.

    In addition to being integrated into plant-wide communications and control systems,

    many field-mounted sensors are equipped with onboard displays and indicators.

    Visual indicators provide maintenance staff with an immediate indication of the

    gear-unit condition, says Schmidt. Some devices actually show the hours to next

    service of the gear-unit. More sophisticated devices, such as vibration analysis

    sensors, allow the early detection of roller bearing and gearing damage, as well as

    gear-unit unbalance and resonance problems.

    As pressure mounts to keep industrial wheels turning around the clock, predictive

    maintenance is emerging as vital factor in efficient industrial processes. With the

    ability to establish the current and future condition of in-service process equipment,

    predictive maintenance is set to become more than a maintenance option, but rather a

    necessity.

    Predictive Maintenance - Cost Effect

    1-How Can Get The Most Gain of Predictive Maintenance?

    2-How Can Use Predictive Maintenance Useful and careful?

    1-1 In first , I will say that statistics show maintenance is not lost of money ;

    maintenance is the best way to save our equipment and facilities life-time . Predictive

    Maintenance is also a intelligent method to discover fault before shutdown, THEN

    MAINTENANCE IS A INVESTMENT.

    Planning aid to predictive maintenance [2]Three key principles in best practice maintenance planning will be introduced

    within this article those being The Maintenance Planning Framework; The Shut

    Calendar, and; The Planners Plan. These three vital tools should be within any

    Maintenance Planners toolbox. The most demanding call on maintenance resources

    comes when a plant or facility is shutdown for an extended period of time for

    scheduled maintenance. Usually a large complement of work must be scheduled into a

    Page25

  • 8/9/2019 Maintenance+Cost

    26/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    relatively short period of time. Work schedules may have to be modified. Special

    equipment may have to be rented. Contractors may have to be hired to fill additional

    labor requirements and special needs. Scheduled shutdowns provide unique

    opportunities to a maintenance department not normally available during standard

    operation or even during short shutdown periods. Lost capacity can be restored to

    An overtaxed facility during an extended shutdown. Major equipment overhauls can

    be performed to help prevent future unscheduled shutdowns. Government mandated

    inspections and repairs can be accomplished during a shutdown, bringing a plant into

    better state of compliance. In order to achieve the above and ensure that the

    maintenance activities are completed efficiently and effectively, maintenance

    planning needs to be well structured. Based on this, the main objectives and functions

    of maintenance planning should be of cussed on ensuring that:

    Proactive preventative maintenance tasks are adequately planned, scheduled and

    implemented in accordance with Business Centered Maintenance.

    All maintenance activities that improve the reliability and availability of the

    operating equipment are completed on time.

    All maintenance activities are undertaken in a planned and proactive manner which

    increases optimises the productivity of the maintenance personnel.

    All resources are readily available at the right time to allow maintenance to be

    completed in accordance with the maintenance plan.

    All personnel are adequately informed about what maintenance tasks are to be

    completed, when this is to occur and on what equipment.

    Information is appropriately captured and recorded to allow maintenance personnel

    to make informed and accurate decisions about what maintenance needs to be

    performed, and when to perform this so that the operating equipment meets the needs

    of the production department in a timely and cost effective manner. Alternatively,maintenance planning can be referred to as ensuring that the maintenance activities

    are completed at the right time, in the right manner, with the right tools and the right

    skilled resources that is, it is all about ensuring that it is done right the first time.

    This can be further simplified in terms of the role / function that must be provided /

    undertaken by the Maintenance Planner in order to ensure that the maintenance

    Page26

  • 8/9/2019 Maintenance+Cost

    27/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    activity / job is done right the first time

    How can escape of too much PM and how can releaseof plant cost?

    16 Golden Way to save time and money on preventive maintenance:

    1. PM Consumes Too Many Resources: Many maintenance managers believe

    their PM program is simply bigger than it should be. They feel like they dont have

    enough manpower to manage all of their PMs along with the other important

    maintenance work, too.

    2. Lack of Results: Despite all of the time and money being spent on

    preventive maintenance, there are still way too many unexpected equipment failures.

    Case in point: During a recent chemical plant tour, the frustrated maintenance

    manager said, We just PDM that machine, and it failed a short time later anyway. So

    why didnt we catch the problem with the PM? Why indeed. So in a nutshell, the

    problem with preventive maintenance is that it takes too much time and produces too

    little results.

    The No. 1 Law You Should Know [6]The number one law of economics you need to know is based on a principle

    discovered over 200 years ago. Youve probably heard of it its called the Law of

    Diminishing Returns. As any good MBA student can tell you, this law states that as

    one production factor increases while the others remain constant, overall production

    decreases after a certain point. In plain English, it means as you increase preventive

    maintenance, production output eventually decreases. The following chart illustrates

    this. You see, theres a fine line between doing too much, too little and just the right

    amount of preventive maintenance. Clearly, theres a point at which increasing PM

    Page27

  • 8/9/2019 Maintenance+Cost

    28/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    hurts the bottom line. The reason? Simple. Most PM procedures require that the

    equipment is shut down. That means uptime goes down, so production output

    eventually goes down too. Meanwhile, maintenance costs go up. So how much

    preventive maintenance is too much? According to a private study, best practice

    programs generate 15% of their maintenance work from PM inspections. Another

    15% is corrective work identified by those inspections.

    The real truth about PM

    By definition, all PMs are time-based. That means either calendar time or operating

    time dictates when an asset should be inspected, cleaned, adjusted, replaced or

    reconditioned. But is there really a direct relationship between the time equipment

    spends in service and the likelihood it will fail? In short, the answer is no. The truth is,

    most equipment failures are not age related. In fact, for complex systems, the majority

    of failures will occur at random. Consider the facts. The following graphs demonstrate

    failure probabilities relative to the age of the equipment itself: First, its important to

    understand this data comes from the airline industry, where maintenance and

    operations standards are exceptionally high. That gives us a true picture of how

    equipment fails when it is maintained and operated correctly. The reality is, 89% of

    equipment failures are not age-related. Therefore, theres no amount of time-based

    preventive maintenance which can manage these failures effectively. Thats why

    using time as the primary basis for your maintenance strategy is inherently flawed. It

    will have very little impact on overall reliability. From a risk standpoint, its much

    safer to assume that equipment failures can happen at any time.

    Page28

  • 8/9/2019 Maintenance+Cost

    29/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    CONSIDER PDM FIRST

    No matter what kind of industry youre in, predictive maintenance (PdM) is

    almost always more cost-effective than people as your first line of defense against

    equipment failures. Based on studies done in major industries including chemicals,

    paper, metals, automotive and power generation, something interesting happens as

    more equipment is added to the PDM program.

    OVERALL MAINTENANCE COSTS GO DOWN. HERES WHAT THE DATASHOWS: [6]

    As you can see, there is a direct

    correlation between high levels of PdMand low overall maintenance costs

    measured as a percent of the assets

    replacement value. On the other hand,

    the data also shows that increasing the

    size of a PM program directly results in

    higher maintenance costs. The graph

    below illustrates:

    Why is the case? Consider the facts:

    Predictive maintenance inspections can identify problems much earlier on the failure

    curve than preventive maintenance (see chart below). So PDM gives you more time to

    plan, schedule, make the repairs and avoid unscheduled downtime .

    And thats really the secret, that predictive maintenance drives more planned work.

    What that means is:

    Page29

  • 8/9/2019 Maintenance+Cost

    30/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Jobs done faster, safer and at a lower cost.

    Studies show that a well-planned job takes only half as much time to execute as an

    unplanned job.

    Each dollar invested in planning saves three to five dollars during execution

    And dont forget, most predictive maintenance

    inspections require equipment to be up and

    running. That means downtime for maintenance

    is minimized a key issue at plants where the

    value of downtime is $5,000, $10,000, $20,000

    an hour or more.

    CONSIDER THE TIME FACTOR [6]

    Do you struggle to find the time to perform PMs? Is there a significant

    number of PMs not being completed on time? Are PMs frequently deferred? If so,

    thats another red flag. Look, all PMs are time-based, so its important to do them

    on time. What that means is, a PM should be done within a timeframe of plus-or-

    minus 10% of its due date. For example, if a PM is scheduled every thirty days, it

    should be completed within a three-day window of the due date. The following chart

    illustrates:Frankly, one of the hidden problems of preventive maintenance is theres no

    immediate, observable consequence of not doing it. For example, if you dont change

    the oil in your car at 3,000 miles, its probably not going to break down the next day.

    However, you cant defer preventive maintenance if you want to have an effective

    reliability program. PM may not be the most urgent or exciting work you do, but its

    definitely among the most important.

    Page30

  • 8/9/2019 Maintenance+Cost

    31/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Reducing Maintenance Cost in a Tough Economic Climate [8]The current economic climate dictates that cost management is a critical

    activity for many companies and their managers. Maintenance is very often seen as an

    area where cost cutting targets can be easily and quickly achieved. Many maintenance

    managers take the view that this type of philosophy always ends up with increased

    costs in the future. This is not true in many cases.

    The most maintenance departments are more reactive than they should be and

    because of this, they over spend and underperform. Costly, inefficient and ineffective

    Preventive Maintenance (PM) programs result in a vicious cycle of reactive

    maintenance. High levels of reactive maintenance destroy the ability to plan and

    schedule and reduce labor productivity by 50% or more (Palmer 1999). Reactive

    maintenance also results in massive inventories of, or express delivery charges for,

    spare parts. The combination of ineffective PM and high levels of reactive

    maintenance results in a massive overspend on maintenance and provides fertile

    ground for cost reduction.

    It is not uncommon for a company to

    consume twice the maintenance labor it

    needs.

    For example, the Carbon productionfacility in an Aluminums Smelter

    reduced its annual maintenance labor by

    over 4,000 man hours, while, at the same

    time, increasing plant availability. The

    table below shows the detail.

    The company reported that this was done by:

    Reviewing the various options of scheduled discard vs. condition based strategies(especially in lubrication tasks)

    Gaining a clear understanding of the reasons for each PM task and documenting

    them. Eliminating tasks that were not linked to cost effective prevention of failure

    Setting inspection frequencies to match rates of equipment function deterioration

    Avoiding duplication of effort between various trades and operations groups.

    The reduction was not a paper figure the labor reductions were real savings

    computed by comparing one years executed hours to the next.

    Page31

  • 8/9/2019 Maintenance+Cost

    32/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Chapter 3

    In Conclusion [3] , [1]

    Many failures happen suddenly and randomly. Because of this some failures

    will happened regardless of the maintenance program. In such case defect elimination

    or consequence mitigation are the only options to reduce the impact of failure.

    Objective and manufacturing are cost, quality, and delivery.

    Maintenance is a total to achieve these objective

    Maintenance must be integrated into the manufacturing function

    Maintenance strives to eliminate downtown and minimize breakdown

    cost

    Computerized maintenance management software, thats easier to use,

    that it is to say. Formal scheduling answer the question how much

    work should we do next week. Scheduling is a matter of control.

    CBM (condition based maintenance) Also referred as prediction

    maintenance, this is a method where by facility detection is constantly

    or periodically monitored by facility diagnosis and maintenance is

    conducted when an abnormality is found.

    CM (corrective maintenance) is the maintenance wore which improves

    the existing \facility to a state where it is free of breakdown (reliable),

    easy to check and repair (good maintenance), easy to operate and

    operates safety.

    Predictive maintenance at dell includes standardize routes preformed

    by all maintenance technicians. Routes utilize visual inspection,

    ultrasound, vibration, and infrared. Technicians are assigned to an area

    and given short duration, dedicated routes to complete. Scheduling is

    key to assure equipment, tools and technician availability.

    Page32

  • 8/9/2019 Maintenance+Cost

    33/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Result

    For zero failure maintenance of basic condition observe the operating

    condition recover deterioration increase operating and maintenance skill.

    THEN MAINTENANCE IS A INVESTMENT AND ITS NOT LOST

    Page33

  • 8/9/2019 Maintenance+Cost

    34/34

    Farid Keyhani, Master of Engineering, April 2009, E.mail: [email protected]

    Chapter 4

    References

    [1] Mark Burgett, Rich young, (2007), a journey to predictive maintenance, AMMJ,

    [2] Mike Killick, Gary Thomas, (2004)a journey to best practice MaintenancePlanning, AMMJ,

    [3] Doc Palmer, (2006), a journey to Maintenance Scheduling, AMMJ

    [5] Kamran Shahanaghi, Seyed Ahmad Yazdani, (2009), a journey to Analyzing theeffects of implementation of TPM in the manufacturing companies, World journal of Modelling and Simulation

    [6] Andy page, George Karalexis, (2009), a journey to ways to save time and Moneyon preventive Maintenance, AMMJ, vol 22, no 23,page 22

    [7] SEW-Eurodrive,(2009) a journey to the Predictive Maintenance crystal ball,AMMJ

    [8] Steve Turner,(2009), a journey to Peducing Maintenance Costs in a toughEconomic climate, AMMJ

    [9] Dr. j.Venkatesh, (2007) six losses in the work place, types of maintenance, 2-15 pages

    10] Dr. George Vachtsevanos,(2003), Cost and complexity trade-offs in prognostics NDIA Conference on intelligent vehicles in Travers city

    [11] Dr.N.Suren Dwivedi, (2005), Total Product Maintenance in Lean Manufacturing,University OF Louisiana at Lafayette

    [12] Barlow, R. and L. Hunter, Optimum Preventive Maintenance Policies,Operations Research, Vol. 8, pp. 90-100, 1960. [book]