Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Draft Handbook for Maintenance of Distribution
network, under DHBVN
MAINTENANCE PROCEDURES
Proper maintenance of electrical systems helps in minimizing/preventing unwarranted breakdowns
of Equipment / lines improving the reliability and generating revenue. Periodical or preventive
maintenance is normally followed to keep the equipment continuously in service for desired output.
Condition based maintenance is the most accepted and adopted concept in maintenance now a day’s
which helps in providing advance information about the health of the equipment to take corrective
action in advance.
As the system is growing, it is getting more and more complex. Due to stringent regulations the
utility cannot afford to have breakdowns in the system resulting in interruption of power supply to
the consumer. On the other hand equipment are getting older and are more prone to failure.
Equipment overhaul and major maintenance are also expensive and need to be planned based on the
condition of the equipment rather than on a periodic basis as a routine.
SLD OF 33/11KV SUBSTATION
MAJOR EQUIPMENTS INSTALLED AT 33/11 KV SUBSTATION 1. POWER TRANSFORMER
2. CIRCUIT BREAKER
3. CURRENT TRANSFORMER
4. POTENTIAL TRANSFORMER
5. LIGHTNING (SURGE) ARRESTERS
6. 33 KV LINE ISOLATORS & EARTH SWITCHES
7. BATTERY BANK & BATTERY CHARGERS
8. 11 KV VCB PANELS
9. 33 KV C&R PANELS
10. 33 KV OUT DOOR BUS
11. 11 KV INDOOR BUS
12. APFC PANELS
13. ACDB ( AC-DISTRIBUTION BOARD)
14. ISOLATORS
15. POWER AND CONTROL CABLE
16. CAPACITOR BANK
1. POWER TRANSFORMERS
A transformer is an electrical device that transfers electrical energy between two or more circuits
through electromagnetic induction. Electromagnetic induction produces an electromotive force
within a conductor which is exposed to time varying magnetic. It constitutes the single most
expensive item in a substation.
In order to provide long and trouble free service, it is important that a careful and regular
supervision and maintenance of the transformer and its components is carried out. The frequency
and extent of such a supervision and maintenance is dependent on the experience, climatic
conditions, environment, service conditions, loading pattern etc. All work done on transformers
should be recorded in maintenance register / checklist.
POWER TRANSFORMER USED IN DHBVN
S.
No. RATING
PRIMARY
CURRENT SECONDARY
CURRENT
CURRENT
TRANSFORMR
RATIO 33 KV SIDE
CURRENT
TRANSFORMR
RATIO 11 KV SIDE
1 4 MVA 69.98 Amp 209.94 Amp 200-100/1-1-1 Amp 300-150/5-5-5-5 Amp 2 5 MVA 87.48 Amp 262.44 Amp 200-100/1-1-1 Amp 300-150/5-5-5-5 Amp 3 6.3 MVA 110.22 Amp 330.67 Amp 400-200/1-1-1 Amp 600-300/5-5-5-5 Amp 4 8 MVA 139.97 Amp 419.90 Amp 400-200/1-1-1 Amp 600-300/5-5-5-5 Amp 5 10 MVA 174.96 Amp 524.88 Amp 400-200/1-1-1 Amp 600-300/5-5-5-5 Amp 6 12.5 MVA 218.70 Amp 656.10 Amp 400-200/1-1-1 Amp 900-450/5-5-5-5 Amp
Alarms & Trippings provided for Power Transformers being used in Sub Stations under
DHBVN
S. No. Alarm / Tripping Ratings of Power Transformers
4 MVA 5 MVA 6.3 MVA 8 MVA 10 MVA 12.5 MVA
1 Differential relay
2 Pressure Release Valve
(PRV)
3 Oil Temperature Alarm
(OTA)
4 Oil Temperature Trip
(OTT)
5 Winding Temperature
Alarm (WTA)
6 Winding Temperature Trip
(WTA)
7 Low Oil Level Alarm
(LOLA)
8 Buchholz Alarm (BA)
9 Buchholz Trip (BT)
10 Over Current Relay (O/C)
11 Earth Fault Relay (E/F)
General Supervision in 33/11 Power transformer 1. Dirt and Dust: The external transformer surfaces shall be inspected regularly; and when
required cleaned of dust, insects and other air borne dirt etc.
2. Rust and Treatment: A regular inspection is to be done on the external surface of the
transformer tank and radiators.
3. Mechanical Damage: Checks must be carried out for mechanical damage to the fabrications
and associated equipment. Particular attention should be given to vulnerable areas such as
radiators.
4. Check out all Joints for Signs of Leakage: All joints, both welded and gasketted, must be
checked for signs of oil leakage. If there is any doubt of a leak, the area must be cleaned of oil,
using a suitable solvent (methyl alcohol) and sprayed with liquid chalk.
5. Check for Oil Level: All oil levels associated with the equipment including oil conservator
and all oil filled bushings shall be checked. Also the oil in the oil seal should be maintained.
6. After completing all the checks ensure that all materials or tools, used for maintenance work,
have been removed. All clothes and other debris must be disposed of. The transformer
compound should be left in a clean and tidy condition.
7. Silica Gel Breather: In open breathing transformer, the breather plays active role in
maintaining- the transformer dry by admitting dry air when transformer breathes. In
transformers having air cell or diaphragm, the breather ensures dry air inside the air cell or
above the diaphragm. The silica gel inside the breather becomes pink from bottom to top over a
period of time.
TESTS OF POWER TRANSFORMERS Following test should be carried out before the installation of Power transformer
Polarization index (by Digital Meggar) or Insulation resistance (by Analog meggar)
a) Connect the one lead of meggar at HV side of Transformer and Other one at LV
terminal.
b) Take the IR of 60 Sec and 10 minutes. The ratio of both the results should be greater
than 1 and less than 5.
c) Repeat the same procedure between HV terminal to earth and between LV terminals to
earth.
d) If analog meggar available then just measure the IR of all three condition mentioned
above. It should me 5000MOhm or above for new transformer.
Ratio Test.
a) Connect the ratio meter if available.
b) Connect the one terminal of meter at HV side other at LV side to confirm the ratio.
c) If ratio meter is not available then just connect the supply of 440V to HV side and
measure the voltage at LV side with respect to the ratio of PTR (33/11 kv). The
deviation should not be more than 0.5 %.
Magnetic Balance Test.
a) This test preferably conducted on LV side of Transformer.
b) Connect the supply of 250 volt between (r) phase and neutral (N).
c) Measure the voltage between y-N and b-N. The sum should be equal to supply voltage
d) Repeat the same procedure between y-N and b-N and conform the results.
Vector group test ( for Dyn11)
a) Short the R phase of HV side with r phase of LV side
b) Supply the voltage (440 V) at HV side.
c) Measure the voltage between R-N, N-Y, B-b, B-y, Y-b and Y-y
d) Condition for confirming vector group of Dyn11 is
1) RN + NY = RY
2) Bb < By
3) Yy = Yb.
Transformer Oil Analysis
Dissolved gas Analysis (DGA)
IEC gas ratio analysis
Dual Triangle method
GENERAL LIMITS OF TRANSFORMER OIL TEST
2. CIRCUIT BREAKERS: A circuit breaker is an automatically-operated electrical switch designed to protect an electrical
circuit from damage caused by faults. Circuit breaker can be reset (either manually or
automatically) to resume normal operation.
OPERATING PRINCIPLE
Under fault conditions, current intensity increases multiple times the normal current flow. This
current senses by relay and energized tripping coil of breaker to isolate the system. Circuit breaker
also used to isolate the section manually
Type of circuit breakers used in DHBVN
At 33 KV level 1. Oil circuit Breakers
2. Vacuum circuit breaker
At 11 KV level
1. Vacuum circuit breakers
CIRCUIT BREAKER RATING:The breaking capacity of a circuit breaker depends on
(i) Symmetrical breaking capacity
(ii) Asymmetrical breaking capacity
Symmetrical breaking capacity
It is the rms. Value of the ac component of the fault current that the circuit breaker is capable of
breaking under specified conditions of recovery voltage.
Asymmetrical breaking capacity
It is the rms value of the total current comprising of both ac and dc components of the fault current
that the circuit breaker can break under specified conditions of recovery voltage.
Making Capacity of circuit breakers
The rated making current is defined as the peak value of the current (including the dc component) in
the first cycle at which a circuit breaker can be closed onto a short circuit.
Testing of circuit breakers
BREAKER TIMING
CONTACT RESISTANCE MEASUREMENT
Testing Procedure:
De- energize, discharge the equipment which is to be tested as a safety precaution. .
Check whether Timer leads and associated clips that are to be connected to the breaker
poles are good & tight.
Make the test connections on the lines of circuit diagram
Switch on the power supply to the timer and issue Close command from the timer. Note
down the close timing displayed on the timer
After recommended time interval (3 seconds), issue Open command from the timer.
Note down the open timing displayed on the timer.
Now issue Close-Open (CO) command from the timer. Note down the CO timing
displayed on the timer.
Confirmation of Test:
Breaker opening time should be less than the closing time of the breaker, it should
come in the range of 30-45 ms. while closing time should be 40-60 ms.
CO- time breaker should at the middle of the closing and opening time.
Opening time < closing -Opening time < closing time
Please refer GTP Details of the Breaker for confirmation of the Timing Results.
Inference/Recommendation:
If the specimen breaker satisfies the respective condition then the respective breaker is considered
to be satisfactory. If any deviation is observed from above mentioned condition then corrective
action should be taken with the help of the manufacturer /OEM.
3. CURRENT TRANSFORMERS:
A current transformer (CT) is a type of instrument transformer designed to provide a current in
its secondary winding proportional to the alternating current flowing in its primary. They are
commonly used in metering and protection circuits
Principle
The current transformer works on the principle of variable flux. In the "ideal" current transformer,
secondary current would be exactly equal (when multiplied by the turn’s ratio) and opposite of the
primary current
4. POTENTIAL TRANSFORMERS
Voltage transformers (VT) or potential transformers (PT) are another type of instrument
transformer, used for metering and protection in high-voltage circuits. Typically the secondary of a
voltage transformer is rated for 110 V at rated primary voltage, to match the input ratings of
protective relays. Ratio test is a routine test of potential transformer, ratio test is recommended during overhaul and
maintenance to check the expected ratio of potential transformer. Limit level of the tests is +- 3 %.
5. LIGHTNING (SURGE) ARRESTERS:
Lightning is one of the most serious causes of over voltage. A lightning rod provides a cone of
protection, which has a ground radius approximately, equal to its height above the ground. The
typical lightning arrester also known as surge arrester has a high voltage terminal and a ground
terminal.
LA voltage rating Corresponding to the system voltage
RATED SYSTEM VOLTAGE
(KV)
HIGHEST SYSTEM VOLTAGE
(KV)
ARRESTER RATING IN KV
FOR EFFECTIVE EARTHED
SYSTEM
11 12 9
33 36 30
66 72.5 60
132 145 120/132
220 245 198/216
400 420 336
Surge Arrestors installed in the substation are intended to divert surges to earth and thus protect
costly switchyard equipment. Proper insulation coordination is necessary for enhancing life span of
costly substation equipment.
6. ISOLATORS & EARTH SWITCHES
Disconnectors have main current carrying arms and operating mechanism for connection and
disconnection. Being off-line devices, they are normally air break type. Normally horizontal double
break, Horizontal center break, Pantograph, Vertical break Disconnectors are in use in EHV
substations.
The alignment of Disconnectors is very important for smooth operation. The limit switches, the
healthiness of auxiliary contacts needs to be checked periodically. The main contacts are to be
inspected and made smooth if any pitting marks seen. All moving parts are to be lubricated for
smooth operation. The gear mechanism and motor normally do not require any maintenance and
manufacturer's' recommendation should be referred for maintenance of gears.
Earth Switches: The earth switch is a safety device and smooth operation is to be ensured by
proper alignment. The earth blade contacts are to be cleaned properly for proper contact and contact
resistance to be measured to ensure healthiness. The earth connection from blade to earth is to be
carefully checked. All the joints should be tightened. Flexible copper braid connections are
provided and healthiness ensured. All moving parts should be lubricated for smooth operation.
7. BATTERY AND BATTERY CHARGERS:
In substation DC supply has equal importance. All protection & indication circuits enable with DC
supply only. Substations generally use Lead Acid batteries / Nickel-Cadmium batteries for DC
supply. Now a days valve regulated lead acid batteries (maintenance free batteries) are also in use
for substation applications.
Battery Chargers: Battery charger is to be maintained for keeping the battery always charged and
also to supply normal DC load for operation.
Rating of Battery bank along with VA capacity used
BATTERY CHARGER DETAIL USED IN DHBVN
VOLTAGE LEVEL VA CAPACITY OPERATING VOLTAGE
33 KV 150 24 Volt/ 50 Volt
8. 11 KV VCB CONTROL AND RELAY PANELS
A circuit breaker is an automatically-operated electrical switch designed to protect an electrical
circuit from damage caused by faults. Circuit breaker can be reset (either manually or
automatically) to resume normal operation.
9. 33 KV CONTROL & RELAY PANELS
33 KV relay & control panels are used to operate 33 KV outdoor circuit breakers. It also used to get
all the monitoring information like breaker on /off status, spring charge, local remote status, trip
circuit healthy information, DC & AC voltage related information etc.
33 KV control panels also include relays for protection & master trip relays also.
10. 33 KV OUT DOOR BUS
33 KV outdoor bus is used to connect incoming lines, power transformers, and outgoing lines etc.
33 KV outdoor bus works as the most visual architecture of a grid substation to interconnect various
substation equipment.
11. 11 KV INDOOR BUS
11 KV indoor bus system includes circuit for LT side of power transformer to 11 KV bus system.
11 KV bus includes 11 KV incomer as the source of power and outgoing feeders as supply source
of energy to the system.
The size of the bus-bar is important in determining the maximum amount of current that can be
safely carried. The bus-bar should be able to carry the expected maximum load current without
exceeding the temperature limit. The capacity of bus should also be checked for maximum
12. APFC PANELS (AUTOMATIC POWER FACTOR CONTROLLERS)
APFC consists of a number of capacitors that are switched by means of contactors. These
contactors are controlled by a controller that measures power factor in an electrical network.
Depending on the load and power factor of the network, the power factor controller will switch the
necessary blocks of capacitors in steps to make sure the power factor a selected value. Power factor
reduce due to high inductive load in system. Presence of this high inductive load power factor
reduces.
Generally on any supply system power demand is varying, power factor also varies as a function of
load requirement. Hence it is difficult to maintain consistent power factor by using fixed
compensation i.e. fixed capacitors. Thus under light load condition it may cause leading power
factor, which results over voltage, Saturation of transformer, Mal-operation of relays, Penalty by
electrical authority .
13. ACDB (AC-DISTRIBUTION BOARD):-
AC supply is required at grid substation for various purpose. It includes.
Supply to ac motor of breakers.
Charging of battery banks
Switch yard lighting system.
Panel lighting system.
Sources of supply for grid auxiliaries.
Normally a local transformer is used for such type of supply. Also a temporary sources also
available at grid level to supply in case of maintenance of local transformer.
EARTHING SYSTEM AT SUBSTATION An earthing system in a sub-station is to provide under and around the sub-station a surface which
shall be at a uniform potential and near zero or absolute earth potential as possible .This provision
ensures that no human being in sub-station is subjected to a shock or injury on occurrence of a short
circuit or development of other abnormal conditions in the equipment
Installed in the yard.
Ground mat is provided below ground level. Earth electrodes are driven into ground at several
points and are connected to grounding mat to form earth mesh. All the structures, Transformers &
other power equipment are connected to this mesh by galvanized steel strips (40x5 mm).
Earth Electrodes is a metal plate, pipe or a conductor electrically connected to earth. Copper,
Aluminum, mild steel, galvanized iron are generally used for electrodes.Generally 40mm dia, 2.6m
long GI/MS rods are used
EARTH MAT: It is formed by steel 75/8 flats laid horizontally at a depth of 0.5 m below surface of ground to form
a mesh of rectangular formation & are welded together. The spacing of earth rods is determined by
required touch & step potential. In addition to earth mat, earth electrodes are used these are also
connected to the mesh. Solid bar risers are welded to mesh and brought up near the equipment
foundations.
BASIS FOR DESIGN OF GROUNDING SYSTEM
Magnitude of fault current
Transient Over voltage
Lightning Protection
Application of Protective devices for selective ground fault protection
Type of load served viz. Motor, Generator etc.
GENERAL GUIDELINES FOR EARTHING
An effective grounding system must satisfy the following conditions:
Provide a low impedance path to ground for personnel and equipment safety.
Withstand and dissipate repeated faults and surge currents
Provide ample corrosion allowance to various chemicals to ensure continuous service during
life of the equipment being protected.
Provide rugged mechanical properties for easy driving of earth electrodes with minimum
difficulty.
All non-current carrying metal parts associated with installation shall be effectively earthed
to a grounding system or mat which will limit the touch and step potential to tolerable
values.
BASIC REQUIREMENT FOR EARTHING:
The current carrying path of earthing system should have enough capacity to carry
maximum fault current.
The resistance of earth & current path should be low enough so as to prevent voltage rise
between N & E.
Step & Touch potential should be within the safe limits.
Systematic survey of earth resistivity should be carried out.
The earth electrodes should be driven in the ground to a sufficient depth.
To obtain sufficient low earth resistance ,
The area of earth mesh is increased.
The spacing of buried rods is reduced.
Soil is kept wet.
The number of earth electrodes are increased.
Earth resistance is reduced by means of Nacl (Common salt), CaCl2 (Calcium chloride),
Na2CO4 (sodium carbonate), CuSO4 (Copper Sulphate), charcoal, soft coal etc.
Method of improving Grounds:
Increasing number of electrodes, creating parallel path.
Increasing depth of driven rod (2.44 m is economical depth).Volume of soil contact
increases. Moisture contact at depth also increases.
Increasing size of driven rod.
Soil treatment with salts. These are effective up to the soil of resistivity 300 ohm
meters. After that other methods are used. One of the most suitable substance for
chemical treatment of soil of very high resistivity for reducing the earth resistance is
Natural Clay, also called Bentonite. It is non corrosive, stable & has a resistivity of 2
Ohm.m at 300% moisture.
33 KV Transmission lines
In DHBVN, HVPNL is the main source of supply, all 33 KV lines come to substations via rail or
RCC pole structure.
Following conductors have been used
S. NO. CONDUCTOR
TYPE AREA
RATED CURRENT
UNDER NORMAL
CONDITION
MVA LOADING (33 KV
LEVEL)
1 WOLF 150 532 26.6
2 LEOPORD 130 386 19.3
3 DOG 100 368 18.4
4 RACCOON 80 344 17.2
5 RABBIT 50 251 12.55
6 WEASEL 30 186 9.3
ITEMS USED IN 33 KV LINES
PCC Pole 11.0M Long.
ACSR Conductor 150mm2
33 KV Pin insulators with pin
11 KV Disc insulators 45KN B&S type
Disc Fitting B&S type
Single Tension Fittings for 130mm2 ACSR Conductor
Suspension Fittings for 130mm2/ 150 mm2 ACSR conductor
U- Bolt for suspension Fitting
PG Clamps for 130mm2 / 150 mm2 ACSR conductor
33 KV Top Brackets / hamper
MS X Arm (Single Pole) 100x50x6 mm (2200mm)
M.S. Channel (X-Arm) 100x50x6mm 3050mm (for H pole)
M.S.Channel 75x40x6 3350mm (for earth wire)
M.S. Angle 50x50x6mm-2860mm (Bracing H. Pole)
M.S Angle 50x50x6mm-2200mm (Belting for H-pole)
Half Clamps
Full Clamps
Stay Sets 8' long complete with X-Plat 460mm of Angle 65x65x6 Elbow & rod with
Disc
Stay wire 7/8 SWG
G.I. Pipe 40 mm dia 6 mtr. Long for earthing
Earthing with Earth rod as per Drawing
GSL 8 SWG
MS Nuts & Bolts
Danger Plates (Enameled)
Number Plates (Enameled)
Phase plate for each phase set of 3 (on each H-Pole & 4-Pole)
Eye Screw Bolts 9”x5/8"
Barbed Wire
"G.I. Strip 25x6 mm 9 meter. For earthling
Knee Bracing - MS Flat 50x6
Catenary wire 7/14 SWG
CI pipe 250 mm diameter 14 mm thick for highway crossing
S/C 630mm2 33kV XLPE cable
End termination kit for S/C 630 sq. mm Cable
33KV Isolators (630 Amps), with clamps
ACSR Conductor 150mm2 (Leopard)
33 KV AB cable 3 Core 185+240 mm2
End termination kit for AB cable 3 Core 185+240 mm2
Dead end calm p assembly with eye hook
Trench (with angle and MS sheet cover) for laying 33 KV XLPE cable in yard
MAINTENANCE OF 33 KV LINES
Normal ground patrolling of lines should be conducted by lines maintenance crew periodically.
Periodicity will be decided on the basis of importance of the line, terrain condition, and proximity
of the line to habitations, forests, gardens, water borne areas etc. and environmental impact on the
line.
During ground patrolling of the line, the patrolman should check for the following
Location no; type of poles (PCC/Rail pole etc.), location address.
Clearances of the line, both to ground and in air.
Availability of all poles and their condition. Obstructions in the proximity of the line
(within line corridor) like trees, branches, structures etc. location wise should be noted.
Observing the condition of insulators, conductors, earth wire, jumpers, clamps,
dampers, spacers etc., with binoculars, from ground level/nearest possible elevated
level.
Special patrolling of the line should be done after momentary tripping of the line on fault, for any
defects. Defects noticed shall be rectified immediately if this can be attended while the line is live
or at the earliest by availing shutdown, anyway, before the defect develops into a major one causing
breakdown. Proper planning of materials and manpower is required in order to carryout rectification
under shutdown in minimum time to avoid/minimize interruption to loads.
Break down maintenance: When a permanent/semi-permanent fault occurs on the line, the line
may break down causing interruption of longer duration. The faults could be snapping of
conductors, disconnection of jumpers, cross-arms/ pole twisting or pole collapse with or without
damage to foundation. This may be due to various reasons like heavy wind due to storms,
weakening of pole due to aging, accidents, thefts etc.
BEST PRACTICES FOR PERSONNEL SAFETY
Electrical Safety Clearance (Live Metal clearance)
Rated Voltage Safety Clearance (meters)
Up to 33kV 0.8
66kV 1
MINIMUM CLEARANCE (IN M) BETWEEN LINES WHEN CROSSING EACH OTHER
MINIMUM CLEARANCE (IN M) BETWEEN LINES WHEN CROSSING EACH OTHER
11-66 KV 110-132 KV 220 KV 400 KV 800 KV
LOW AND MEDIUM 2.44 3.05 4.58 5.49 7.94
11-66 KV 2.44 3.05 4.58 5.49 7.94
110-132 KV 3.05 3.05 4.58 5.49 7.94
220 KV 4.58 4.58 4.58 5.49 7.94
400 KV 5.49 5.49 5.49 5.49 7.94
800 KV 7.94 7.94 7.94 7.94 7.94
GUARDING SYSTEM Guarding means safe guard. This is below the line. In case of conductor snapping, it will touch the
guarding wire before laying on ground or will lay on guarding. The guarding is always earthed. The
line protection will operate and will switch off the line. Snapped conductor will not remain charged.
In absence of guarding, conductor will fall on ground and as no protection is operated, conductor
will remain charged. This will cause accidents. Hence the guarding is very essential.
Types of Guarding:-
P. V. C. Guarding.
Lecing guarding.
11 KV LEVEL
DISTRIBUTION TRANSFORMER
Scope:
This operational guideline is intended to carry out the fundamental checks on Transformer for its
maintenance and while taking it into service. This requires that the concerned SDO should prepare
the action plan and ensure the availability of necessary tools and tackles to carry out this activity.
Prerequisites:
Ensure that necessary permit has been taken. Feeding Sub-station is responsible for providing
outage and PTW. The working party is responsible for ensuring isolation. Ensure that the
transformer is de-energized, isolated & grounded.
Working party should ensure the availability of proper tools and accessories, safety apparels, spares
and consumables required for carrying out the work.
UNDERGROUND CABLES: the underground cable network of any electricity distribution utility
is a vital component of the LV/HV network of the system. It has a several unique benefits over
overhead networks. In particular, they have:
Lower transmission losses.
Can absorb emergency power loads.
Have lower maintenance costs.
Emit no electric field and can be engineered to emit a lower magnetic field than an overhead
line;
Require a narrower band of land to install.
They are less susceptible to the impacts of severe weather.
The reliability of the underground distribution network directly affects the reliability of the overall
system and ultimately the overall customer satisfaction.
Directives & Checks
Abnormality Causes/ Effect Preventive-Corrective action plan
Electrical Stress
1. Flash over due to Phase to phase & Phase
to earth clearance at cable termination Ensure sufficient clearance
2. Termination failure due to Core crossing
above cut back area at cable termination
Ensure core crossing below cut back area
at cable termination
3. Termination failure due to Contaminated
surface of terminations Ensure cleanliness of terminations
4. Cable failure due to Cable testing at high
voltage(DC)
Ensure Testing at Recommended Voltage
(Refer table2)
Mechanical
Stress
1. Stress develop due to Improper Bending
Radius
Ensure Proper Bending radius
(Refer table1)
2. Stress develop due to Mechanical
vibrations
Ensure proper depth
(Refer table3)
3. Stress develop due to Improper cable
supports Ensure proper span length
Thermal Stress 1. Insulation degradation due to overloading Ensure Recommended Loading
Abnormality Causes/ Effect Preventive-Corrective action plan
(Refer table4)
2. Insulation degradation due to Hot spot at
joints & Terminations
Ensure proper Tightening/crimping of
Lugs & Ferrules
3. Insulation degradation due to Improper
Earthing connections
Ensure Cable earthing connected with
Sub-station earthing
External damage Insulation Damaged by external agency Ensure Patrolling of cable routes
Water ingress
Leakage current through the cable insulation/
cable failure, Corrosion in cable conductor
&Armour due ingress of water
Ensure Lug seal to be intact at outdoor
termination.
Minimum permissible Bending radius (Table1)
PILC XLPE
1C 3C 1C 3C
Upto 1.1 KV 20D 15D 15D 12D
1.1 KV to 11 KV 20D 15D 15D 15D
Above 11 KV 25D 20D 20D 15D
‘D’ Diameter of the cable
Table 2: Tests on Cable during Fault Localization, After Repair or when Network Modification is done.
S. No Test UG Cable
1 Meggar Phase toGround and Phase to Phase to be tested with 2.5/5.0 KV
meggar for one minute or till reading stabilized. Minimum IR value
should be 50 M ohms.
2 Hi pot Each phase to be tested @ 6.5 KV DC for 5 minute with respect to
ground with other two phases grounded. The cable must with stand
the test voltage & leakage current should not exceed 2mA
Depth of the cable (Table-3)
Voltage Level Depth of cable
LT cable (1.1kv) 0.6 m
HV cable (11kv) 0.9 m EHV cable (33kv) 1.2 m
EHV cable (66kv) 1.5 m
Current Rating (Table4)- 11 KV XLPE UG Cable
S. No.
Nominal Size of Cable
(Sqmm)
for 11 kV level
Current Carrying Capacity (Amps)
In Ground at 30˚C In Duct at 30˚C In Air at 30˚C
1 3x95 190 165 230
2 3x120 220 190 260
3 3x150 245 210 295
4 3x185 275 240 335
5 3x240 315 275 395
6 3x300 355 310 450
S. No.
Nominal Size of Cable
(Sqmm)
for 11 kV level
Current Carrying Capacity (Amps)
In Ground at 30˚C In Duct at 30˚C In Air at 30˚C
7 1x630 560 480 840
8 1x1000 680 580 1070
HT OVERHEAD LINES
Introduction:
Overhead lines are the most cost effective and frequently used carriers for electric energy. Exposure
to environment accelerates deterioration; if this not detected and repaired quickly, some of it will
degenerate into serious problems with time. To increase line loading and increase quality of power
supply, frequent inspection programs is required to locate and repair any significant failure at the
earliest possible stage.
Frequent failure in the Overhead lines can cause extensive damage to the insulator and other
electrical & earth joints which not only interrupts electricity supply but also results in large revenue
losses. Poor/inadequate maintenance in the areas of pole, span length, non-tension electrical joints,
conductor spacing, line stay leads to the instability in the electrical and mechanical parameter which
reduce the life of the line. With appropriate on site actions, like proper maintenance procedure, the
useful life of the overhead lines can be extended.
Scope:
This operational guideline is intended to carry out the fundamental Line Survey / Checks for its
maintenance and while taking it into service. This requires that the concerned engineer should
prepare the action plan and ensure the availability of required materials, tools and tackles to carry
out this activity.
Prerequisites:
Ensure that necessary permit has been taken from feeding sub-station officer who is responsible for
providing outage and PTW.
The Operating personnel is responsible for ensuring de-energization, isolation and properly
grounding the network where the activity has to be carried out.
Properly Grounding means
All conductor of the isolated working zones, should be shorted with earth by shorting
links at both ends.
The end of the shorting links which are to be connected with conductor & earth terminal
should be fitted with crocodile clip. (Presently all conductor are shorted with safety
chain without earth.A thin layer of Aluminium oxide form on conductor as it expose in
air which behaves like insulator. Due to small surface contact area by the safety chain
&conductor may cause high resistance at the chain contact point causing unusual
behavior. Shorting links should Better performance than safety chain)
If there be any branch line within the working zones, should be isolated/all conductor to
be shorted in similar manner.
If there be any DT within the working zones, the G.O (Gang Operated Switch) of all
DT’s should be OFF to avoid any back feeding from downstream.
During fixing the crocodile clip of shorting links to the conductor, it should be careful :
Before connection the shorting clip to the conductor, the earthing terminal of
the shorting clip should be earth.
Before connecting the shorting clip to a conductor, it (conductor) should be
earth by earth stick & holding the earth stick on the said conductor, the
crocodile clip of shorting links should be fastened with the conductor by
wearing safety gloves & then the earth stick to be removed. Repetition of the
same process of other too conductors must also be ensured.
The Working personnel should ensure the availability of proper tools and accessories, safety
apparels, spares and consumables required for carrying out the work.
Clearance
LV 11 KV
Minimum clearances from any accessible point
The vertical clearance from the highest point 2.5 m 3.7 m
The horizontal clearance from the nearest point 1.2 m 1.2 m
Minimum Ground Clearance Across the street 5.8 m 6.1 m
Along the street 5.5 m 5.8 m
Line erected elsewhere 4.6m 4.6m
Line with Insulated Conductor 4 m 4m
Line crossing 11 KV & LT line 2.4 m
Current carrying capacity of conductor
Size of conductor Current currying capacity in Amp
Dog (100 sqmm/ 1 SWG) 312
Raccoon (80 sqmm/3 SWG) 297
Rabbit (50 sqmm/ 6SWG) 247
Weasel (30 sqmm/ 8 SWG) 114
Maintenance Activity:
General Maintenance
Check visually, the condition of Pole base & alignment of pole. If the pole tilted, should be
straighten & rammed the pole base with brick bats after digging the earth around the pole base. If
any bend occurred at the mid of the pole, has to be changed & pole to be erected as per drawing
attached.
Check visually the condition of existing stay
Check the Condition & size of GI wire. It should be 7/10 SWG.
Check the Condition of Guy/Egg Insulator, if any damage or missing observed, should
be fix/replace.
Check the Condition of tension screw, if any damage observed , it has to be changed
otherwise to tighten the turn buckle ,if required
Check the condition of anchor hook
Check visually the Line Hardware
Condition of Disc Insulator, if there is any crack, flash mark on the surface of the disc,
disc should to be change.
Condition of strain clamp of disc insulator, If any crack or flash mark on surface, it has
to be change.
Condition of Pin insulator, if there be any flash mark on the insulator surface, it has to
be change otherwise check the tightness with the spindle.
Condition of Pin insulator spindle, if any damage or bend, to be change otherwise check
the tightness of the fixing nuts.
Condition of Top hamper; if any tilt observed at top hamper, it has to be straight or any
damage occurred to the metal part, it is to be change, otherwise check the tightness of
fixing nuts bolts.
Condition of the V-arm. if any damage occurred on V-arm or on the fixing clamp, it is
to be changed otherwise check the tightness of the fixing Nuts, bolts
Condition of channel-arm, if any damage occurred on channel-arm or on the fixing
clamp, it is to be changed otherwise check the tightness of the fixing Nuts, bolts.
All metal part to be painted by Primer &Aluminium paint for increasing the durability of
life span. Further all metal parts on the pole of line should be connected to proper earth.
Visual inspection of bare conductor -if any damage occurred on the conductor, it is to be
replaced the damaged portion by same conductor with sleeve joint & the joint is limited
to maximum 2 nos.per span. If any loose, conductor to be re-sagged from section to
section. Also maintain spacing between the conductors.,
Span length should be maximum 40 meter for urban & rural residential area & 60 meter
for rural field area if the length larger than above so mid pole to be provided.
Line should be sectioned at every 4/5 span apart.
Components of an Overhead 11 KV (H.T.) Line of O/H Lines 1. Reinforced cement concrete poles (R.C.C. Poles)
2. Double pole structure
3. Cross – arms
4. Line conductors
5. Pin-type insulators
6. Strain insulators
7. Earth wires
8. Angle iron for earth wire
9. Hooks for earth wire
10. Top hamper
11. Stay wire
12. Stay insulators
13. Anchor rod
14. Dead end clamps
15. Parallel grooved clamp (P.G. Clamp)
16. Earthing
17. Lightning arrestors
18. Danger plates
19. Anti –climbing device
20. Tie wire
HT AERIAL BUNCHED CABLE
The AB cable network of any electricity distribution utility is a vital component of the HV network
of the system. The reliability of the AB cable distribution network directly affects the reliability of
the overall system and ultimately the overall customer satisfaction.
Scope
The operational guidelines apply to DHBVN& any of Business Associates involved in Testing
& Repairing of Cable faults being carrying out for maintenance of electricity distribution
system.
Prerequisites
Ensure that necessary permit has been taken. Sub-divisions are responsible for ensuring
isolation of the faulty cable for both ends & providing the PTW. Ensure that the cable is
de-energized, isolated & grounded.
Patrolling of AB cable feeder may be conducted to identify & removal of unauthorized
tappings before starting of the work.
Copper Screen of HT ABC must be shorted along with messenger wire at starting & End
points and joints with crocodile clamp shorting’s. So that all conductive paths may be
kept at zero potential/ Earth potential
AB cable joints should be made properly. AB cable should not be jointed temporarily. In
case of emergency, proper joints must be made the next day. For jointing of Messenger
wire, mid span joint sleeve should be used instead of binding wires.
The Business Associates should ensure the availability of proper tools and accessories,
safety apparels, spares and consumables required for carrying out the work.
Laying of AB Cables
It may be ensure that AB cable should not be dragged on roads/ footpaths etc. It must be laid by
use of rollers & pulleys. In case AB cable is laid through trees/ vegetation area, branches may
be trimmed to avoid abrasion on AB cables.
Reason of Failure:
Design Snags-
Induction of high voltage at copper screen.
Under rated fault withstand capacity of Cu screen.
Manufacturing defects
Installation snags -
Improper connection between Cu screen & Messenger
Mechanical damage during installation.
Correctives Measures for Design snags:
HT ABC with revised specs. (AL wire screen)
Current Rating
HT ABC (Standard Sizes of Single core cable)
S. No. HT AB Cable Size (SqMM) Max. Continuous Load (Amps.)
1 35 106
2 50 150
3 70 190
4 95 230
5 120 265
6 150 300
7 185 345
Cable jointing Process
Power cables
Cablesare used for the transmission/distribution of electrical power and consist of three major
components:
Conductors
Insulation
Protective jacket
For cables operating at or above 6,000 volts between conductors, a conductive shield surrounds
each insulated conductor to equalize the electrical stress on the cable insulation. The construction
and requirements are specified in standards such as IS7098 and IEC 60502, IEC6084.
The important steps in the cable jointing of medium voltage XLPE insulated screened
armoured cable
a. Strip the jointing ends of both the cables to be done i.e. stripping of outer sheath, armour, inner
sheath, insulation screen, core insulation and conductor screen. Longer end will be 1050mm and
other end 750mm for 33Kv XLPE 3*400 sq. mm cable. Park the tubes 1000mm and 500mm then
1000mm at the longest side of the cable.
b. All the conductor cores shall be joint with the help of jointing ferrule/mechanical connector and
its crimping by suitable crimping tool.
c. Fill up the space between the ferrule and the core insulation and the crimped portion in ferrule
with semi conducting clay, so that it forms a smooth and round profile with 2 mm.
d. Measure a distance of 20 mm on both sides of the semi-conducting tape. Apply stress grading pad
of 30mm width over the core covering 10mm of the semi conducting tape.
e. Keeping conducting layer of core, wrap the self-amalgamating insulating tape so that the required
insulation thickness is built up. Ensure a tapered profile of the tape towards the semi conducting
layer of the insulation, the self-amalgamating tape should be stretched to 2/3rds of its original width
while applying.
f. Fill up the gap 5mm between self-amalgamating insulating tape and semi conducting layer of core
by stress grading pad of 30mm width.
g. Apply semi conducting tape one layer half over lapped about 10mm on one side of metallic
shielding to the other end in the same manner.
h. Wrap 2 layers of self-amalgamating insulating tape, each half overlapped to cover the semi
conducting tape. Stretch the tape 2/3rds of width while applying as shown in figure given below.
i. Wrap one layer of copper wire mesh on the core to connect the copper tape from end to another
over the tapes.
j. Place the black stress control tube centrally over the joint. Starting at the centre shrink the tube
towards one end and then towards the other end until fully shrunk. Apply heat evenly throughout
the process. When completed adhesive will flow from the ends, wipe off excess.
Role of Earthing in Power DistributionEarthing In Electrical System
Earthing means making an electrical connection to general mass of earth.
Earth forms an intrinsic part of electricity System.
Earthing of electrical installation is primarily concerned with ensuring safety.
Soil conductivity is an important consideration. Lower the resistivity, easier to get good
earth.
The ground is more effective conductor than copper wire used in electrical circuit.
Earth provides the shortest path for fault current to travel.
Short circuits allows electrical current to by-pass its normal route. Under short circuit,
current follows the least resistance fault to ground.
Reason for Poor Earthing Practices:
Inadequate understanding about technical requirement of earthing & Standards.
Earthing has no role to play during normal conditions.
Lack of compatibility between earthing requirement of electronic equipments & power
system.
Lack of motivation & importance to engineers for keeping earthing & connections in
proper state.
Why Earthing Important?
Earthing in a substation is extremely important for the safety of operating personnel as well as for
proper system operation.
It provides safe passage to earth fault current to flow. E/F current flow through the earth
and may readily cause operation of fuse or E/F relay.
It provides low resistance path to fault current to ensure prompt & consistent operation
of protective devices under fault current.
It protects the equipment other than live parts from attaining potential. Under fault
conditions, frames & enclosures etc may attain high potential w.r.t ground. So these
non-current carrying parts should be connected to ground for the safety of the operating
personal & other human beings for discharging electrical energy to earth.
It protects the equipment from over voltages, HV surges resulting from lightning &
other causes.
It ensures safety of life from electric shocks by grounding all metallic structures and also
avoid hazardous voltage gradients by suitably designing the grounding system. The
potential of earthed body does not reach to dangerously high values during fault.
It ensure that ground potential rise does not have any dangerous effect on
communication system.
It plays an important role in increasing the reliability & continuity of supply service and
stabilizing the voltage conditions.
It has means of discharging feeders & equipments to ground before proceeding with
maintenance.
Attributes Of Good Earth Connection
Lowest soil resistivity.
Low electrical resistance to earth.
Good corrosion resistance.
Ability to carry high current repeatedly.
A reliable life of at least 30 years.
Low loop impedance path of earthing.
Limits of Earthing Resistance
Following are values of earth resistance considered appropriate for different electrical
installation
FUSES
A switching device, which by the fusion of one or more of its specially designed and proportioned
components open the circuit, in which it is inserted and breaks the current, when the same exceeds a
a) Large HV and EHV s/stns - 0.5 ohms
b) Industrial and Distribution s/stns - 2.0 ohms
c) Medium voltage systems(415 V) - 5.0 ohms
d) Large HV and EHV s/stns - 0.5 ohms
e) Industrial and Distribution s/stns - 2.0 ohms
f) Medium voltage systems(415 V) - 5.0 ohms
given value for a sufficient time. The term fuse covers all the parts forming the complete switching
device.
Principle of operation
The operation of fuse depends upon the heating effect of an electric current. When the electric
current is increased in a circuit due to short circuits or over loads, it increases the rate of heat
generation, which will increase the temperature of the fuse wire and thereby the rate of heat
dissipation increases from the exposed surface of the fuse wire. The final temperature reaches to
such stage that the heat generation will be equal to the rate dissipation. If this temperature happens to
be above the melting point of the material for fuse wire, fuse must have operated
Selection of fuse wire
To select the proper fuse wire to be inserted in a circuit two factors viz. (a) maximum current rating
of the circuit (b) current rating of the smallest size of wire of accessories is to be seen, the fuse wire
inserted should be of size so that when the current with reference to factors (a) and (b) is increased, it
should blow out. The type of wire to be selected to use as a fuse wire depends upon the type of load
connected to the circuit i.e. steady load and fluctuating loads. The steady load covers the heating
loads and the fluctuating load consists of motor, capacitor and transformer loads, all of which take
transient over current when they are switched into the circuit. In steady load circuits, the fuse forms
only the protection part of the circuit. Therefore, the fuse rating should be equal to or next greater
than the ratings of the smallest cable used in the circuit. But if a number of fuse wires are run in
parallel to augment the rating of fuse, total rating should not be equal to the product of rating of and
strand and number of strands used. In fluctuating load circuits, fuse should allow the short time over
current to flow without blowing. For this, it is necessary to select fuses of rated current greater than
that of the cable of the circuit. The fuse wire should always be inserted in live wires or phase of the
circuit, or otherwise even if the fuse blows out, the faulty circuit will be fade and would cause
considerable damage in case of leakage fault.
LT UNDERGROUND CABLES The underground cable network of any electricity distribution utility is a vital component of the
LV/HV network of the system. The reliability of the underground distribution network directly
affects the reliability of the overall system and ultimately the overall customer satisfaction.
Scope:
The operational guidelines involved in Testing & Repairing of Cable faults being carrying out for
maintenance of electricity distribution system.
Prerequisites:
Ensure that necessary permit should be taken. Site In-charge is responsible for ensuring
isolation of the faulty cable for both ends & providing the PTW. Ensure that the cable is
de-energized, isolated & grounded.
The workman should ensure the availability of proper tools and accessories, safety
apparels, spares and consumables required for carrying out the work.
Minimum permissible Bending radius
PILC PVC XLPE
Type of Core 1C 3C 1C 3C 1C 3C
Upto 1.1 KV 20D 15D 15D 12D 15D 12D
‘D’ Diameter of the cable
Tests on Cables during fault localization, after repairs or when network modification is done
Test 230/440 V
Megger Test Phase to ground and phase to phase to be tested with 1KV Megger
for 1 Minute/or till reading stabilizes. Minimum IR values should be
50M Ohms.
Depth of the cable
LT cable (1.1kv) 0.6 m
LT Cables Current Rating
S No. No. of
Cores
Size
(Sqmm)
Current Rating of AL
PVC cables in Amp
Current Rating of AL XLPE
cables in Amp
AIR Ground AIR Ground
1 2 2.5 19 22 37 37
2 2 10 42 48 64 62
3 2 25 70 78 111 104
4 4 25 63 66 91 82
5 4 50 94 96 135 116
6 4 95 139 144 210 171
7 3.5 95 139 144 210 171
8 3.5 150 184 183 277 217
9 4 150 184 183 277 217
10 3.5 240 252 239 379 284
11 4 240 252 239 379 284
12 4 300 283 265 432 319
LT OVERHEAD LINES
Overhead lines are the most cost effective and frequently used carriers for electric energy. Exposure
to environment accelerates deterioration; if the fault is not detected and repaired quickly, some of it
will degenerate into serious problems with time. To increase line loading and quality of power
supply, frequent inspection program is required, to locate and repair any significant failure at the
earliest possible stage.
Frequent failure in the Overhead lines can cause extensive damage to the insulator and other
electrical & earth joints which not only interrupts electricity supply but also results in large revenue
losses. Poor/inadequate maintenance in the areas of pole, span length, non-tension electrical joints,
conductor spacing, pole stay leads to the instability in the electrical and mechanical parameter
which reduce the life of the line. With appropriate on site actions, like proper maintenance
procedure, the useful life of the overhead lines can be extended.
Scope
This operational guideline is intended to carry out the fundamental Line Survey / Checks for its
maintenance and while taking it into service. This requires that the concerned engineer should
prepare the action plan and ensure the availability of required materials, tools and tackles to carry
out this activity.
Prerequisites:
Ensure that necessary permit has been taken from SDO/JUNIOR ENGINEER who is
responsible for providing outage and PTW.
The PTW has to transfer to Working personnel after ensuring de-energization, isolation
and properly grounding the network where the activity has to carry out.
The Working personnel should ensure the availability of proper tools and accessories,
safety apparels, spares and consumables required for carrying out the work.
Clearance
Minimum clearances from any accessible point
1 The vertical clearance from the highest point 2.5 m
2 The horizontal clearance from the nearest point 1.2 m
Minimum Ground Clearance
1 Across the street 5.8 m
2 Along the street 5.5 m
3 Line erected elsewhere (Bare) 4.6 m
4 Line erected elsewhere (Insulated) 4 m
5 Line crossing 11 KV & LT line 2.4m
Maintenance Activity
General Maintenance
Check visually, the condition of Pole base & alignment of pole. If the pole is tilted,
should be straighten & rammed the pole base with brick bats after digging the earth
around the pole base. If any bend occurred at the mid of the pole, should be changed &
new pole to be erected.
Check visually the condition of existing stay
Check the Condition & size of GI wire. It should be 7/10 SWG.
Check the Condition of Guy/Egg Insulator-if any damage observed or is missing, it
should be fixed/replaced.
Check the Condition of tension screw-if any damage observed, it has to be changed.
Tighten the turn buckle if required.
Check the condition of anchor hook.
Check visually the Line Hardware
Condition of Shackle Insulator-if there is any crack, flash mark on the surface of the
insulator, it should be changed.
Condition of Pin insulator spindle- if any damage or bend happened, it needs to be
changed. Check the tightness of the fixing nuts.
Condition of Top hamper- if any tilt observed at top hamper or any damage occurred to
the metal part, it has to be change. Check the tightness of fixing nuts bolts.
Condition of the Double line X-arm. if any damage occurred on X-arm or on the fixing
clamp, it has to be changed. Check the tightness of the fixing Nuts, bolts
All metal parts to be painted by Primer &Aluminium paint for increasing the durability
& life span of the same.
Visual inspection of bare conductor -if any damage occurred on the conductor, it to be
replaced with the same conductor through sleeve joint & the nos. of joint is limited to
maximum 2 per span.
Use of Line Spacer to avoid fall of snapped conductor to ground & also maintaining
equal conductor spacing.
Span length should be maximum 40 m. If the length longer than it, a mid span pole
should be provided.
Line should be sectioned at every 4/5 span, if more, it should be reduced to 4/5 span.
Visual inspection of Earthing should be carried out. If any damage occurred on GI wire,
it has to be replaced with a new complete earth electrode. If there is any joint observed
at earth wire, either the wire or the complete earth electrode has to be changed. Also,
tighten all joints on earth set. Resistance value of earth shall be measured &It’s value
would be < 1 Ohm.
Visual inspection of Earth wire- if any damage/broken happened, it would be re-drawn
by 4 SWG GI wire.
Inspection of Joints – Jumpering should be done by same conductor & will be jointed by
suitable C-wedge connector. Mid span joint has to be done by Suitable Sleeves & the
joint is limited to 2 no per span.
Cable mounting on OH feeder-The cable should be mounted on pole structure through
GI pipe and must be mounted with clamps/STP. Cable be taken upto top of line and
jumper at cable end be through properly crimped lugs and fitted with C-wedge
connector with line.
Service line should be limited to 8 nos.perpole,if the above exceeds the latest instruction
followed by DHBVNsalescircular.
During connection of service cable with the distribution box, the cable/conductor surface
(after opening the insulation) should be cleaned properly and should apply anti corrosive
grease before termination on distribution box.
Configuration of line
LT ARIAL BUNCHED CABLE (ABC)
The AB cable network of any electricity distribution utility is a vital component of the LV network
of the system. The reliability of the AB cable distribution network directly affects the reliability of
the overall system and ultimately the overall customer satisfaction.
Laying of AB Cables
It may be ensure that AB cable should not be dragged on roads/ footpaths etc. It must be laid by use
of rollers & pulleys. In case the AB cable is laid through trees/ vegetation area, branches may be
trimmed to avoid abrasion on AB cables. OH distribution box (3-Φ /1-Φ) should be mounted on
pole for giving service connection. Incoming cable of suitable size for Distribution box should be
jointed with ABC by Mini wedge connector/IPC.
LT ABC (Values as per IS : 6474 – 71 & IS : 7098(1) 88 )
Clearly checking the phase of cable 1 line for R phase, 2 line for Y phase and 3 for B phase.
S. No LT AB Cable Size Current Rating @ 40 deg C
1 3x150+1x120 Sqmm 273A
2 3x95+1x95 Sqmm 235A
3 3x70 +1x70 Sqmm 190A
4 3x50 +1x35 Sqmm 149A
5 3x25 +1x25 Sqmm 99A
6 3x16 +1x25 Sqmm 60A
LT FUSE BOARD
LT fuse board shall be installed on One Pole for Plinth/Pole Mounted DT/H-Pole of the ratings
required at site. Insulated cable from LV side of DTs shall be connected to one side of fuse board
through proper size lug/thimble.
RECOMMENDATIONS
1. Regular Trainings/Seminars shall be organized for field staffs as a part of policy for
improving the capabilities for maintenance of distribution network.
2. Frequently breakdown of feeders shall be thoroughly checked for analyzing the reason of
fault and action shall be taken for minimizing the breakdown.
3. JE/SDO should maintain the Log Book of breakdowns in his area and all the details of
breakdowns must be recorded.
4. Phase balancing of feeders shall be regularly carried out as the balanced distribution
network have less interruptions, no heating of any one conductor and ageing/breaking of
conductors shall be minimized. A balanced network has less technical losses than an un-
balanced network.
5. Analysis of weak and strong area of every sub-division on the basis of data recorded in Log
Book, shall be carried out. After ascertaining the reason of weak area, action should be
taken to make it a strong area.
6. Reasons should be identified for frequent breakdowns of following equipments and
immediate action should be taken: -
Distribution Transformers
Line conductors
U/G cables
Jumpers
Insulators
Overloading of any feeder
7. Tree trimming shall be done on regular basis and the same should be taken as a preventive
maintenance.
Various Faults / Point of concern with Probable Causes and Remedial Actions
S. No. Fault / Point of Concern Probable Cause of Fault /
Point of Concern Remedial Action
1 Overhead Conductor
Faults
1. Flashed /Punctured or
broken insulators
2. Damaged jumper/Conductor
3. Fault due to Tree Contact
4. Faults due to Birds
5. Fault due to Cracked Pole
6. Improper Earthing
7. Unwanted wire b/w two
phase
1. Plan for Flashed /Punctured
or broken insulators
checking and replacement.
2. Plan for Jumper Repairing,
either of same conductor
size or next higher size of
conductor size.
3. Plan for Tree Pruning /
Trimming by using Tree
pruner instrument.
4. Plan to reduce Faults due to
Birds by installing bird
repellent/ falpper .
5. Proper Earthing should be
S. No. Fault / Point of Concern Probable Cause of Fault /
Point of Concern Remedial Action
done
2 Under Ground Cable
Faults
1. Insulation Degradation
i. Electrical Stress
ii. Mechanical Stress
iii. Thermal Stress
2. External damage
i. Water Ingression
ii. Joint Failures
1. Plan to minimize insulation
failure by using proper
meggering instead of Hi-
pot, By usage of HS tape &
end caps to prevent from
moisture.
2. Plan to reduce joint failures
by not using sub-standard
joints kits, by
qualified/skilled jointers.
3. Plan to reduce external
damage by proper
patrolling.
4. Plan to reduce burning of
cables by proper load
balancing.
3
Distribution
Transformer Trippings /
Interruptions
1. Defective Bushing: HV/LV
& Oil Leakage
2. Condition of Breather &
Conservator
3. High unbalancing current
4. Continuous overloading of
DT
5. Frequent LT cable faults
6. Improper protection of
both HT and LT side
7. Development of hot spots
due to passage of time
8. Poor/defective earthing of
neutral & body of DT and
of LT feeders
9. Birds / Animal
electrocution
10. Poor maintenance of DT
11. High rating fuse used
1. HT and LT connections
should be tight
2. Proactive thermo-scanning
3. Earth value should be
checked during Planned
shutdown & earthing
connections should be
tightened
4. Earthing checked and
provided new earthing
where ever required.
5. Proactive patrolling, Drain
valves should be sealed
Segregate multiple LT
feeders that feed from one
ACB.
6. Top fence covering in
monkey/domestic animal
prone s/s, provision of HT
insulation caps.
7. Overhauling of the
DT/replacement with
new/repaired one.
S. No. Fault / Point of Concern Probable Cause of Fault /
Point of Concern Remedial Action
4 Power transformer
Tripping
Differential Protection
operation
1. Inter-turn fault/ Aging
2. LT joints & HT bushing
failures
3. Short circuit at in-zone of
both sides CTs.
4. IED Failure
5. CTs wiring problem
6. CT Saturation
7. Fault at cable box before
LV
1. Complete visual Inspection
of power transformer.
2. Rectifying the root cause of
breakdown
3. Stability test of power
transformer.
5
Oil temperature
indicator tripping /
alarm
1. High temperature of oil
due to heavy loading.
2. Relay mal-function.
3. Low intensity Inter turn
fault.
1. Checking of OTI meter &
WTI meter for variation.
2. Check loading condition
3. Winding resistance of
power transformer.
6 Winding temperature
indicator tripping /alarm
1. High temperature of
winding due to heavy
loading.
2. Relay mal-function.
3. Low intensity Inter turn
fault.
1. Checking of OTI meter &
WTI meter for variation
2. Check loading
3. Winding resistance of
power transformer.
7 11 KV incomer tripping
1. Due to fault in 11 Bus
system.
2. Fault near to substation or
very high intensity of fault.
3. High breaker timer of
outgoing breaker
1. Checking of tripping of any
outgoing feeder along with
intensity of fault
2. Check breaker timing of
tripped breaker.
8 11 KV outgoing breaker
tripping
1. Due to over loading.
2. Due to phase fault /earth
fault
1. Check Relay’s tripping
parameters for analysis.
2. Line inspection is required
before again charging.
9 Failure of Lighting
arrestor
1. Due to heavy voltage
fluctuation.
2. Aging of lighting arrestors
1. Replace the faulty LA.
2. Check other installed LAs.
10 Low voltage at DC
system
1. Due to charging problem.
2. Battery issues in existing
system.
1. Check charger at location.
2. Impedance test of battery
11 DC leakage at
substation
Earthing of any one of the
terminal with ground it may
occur at yard's equipment of in
VCBs
Isolate DC supply at every
section and check DC leakage
in system and rectified the
same.
12 Poor earthing at grid
substation
Due to aging / Soil condition
& improper installation
1. Check earthing resistance at
every pit of yards & neutral
of transformer.
S. No. Fault / Point of Concern Probable Cause of Fault /
Point of Concern Remedial Action
2. In case of poor earthing go
for parallel earthing concept
and connect it with old
earthing PIT.
Distribution transformer failure analysis & corrective actions.
1. Defective Bushing: HV/LV & Oil Leakage
CORRECTIVE ACTION & PREVENTIVE ACTION: Check bushings for cracks, chippings, over heating marks, flashover marks, replace the effected bushing.
Oil leakages if any then keep an eye on
a. tightness of nuts
b. tightness of oil seal caps/replace oil seal & gasket if required
Don’t apply M-seal or other material on HV/LV bushing to stop oil leakage as this may causing
flashover.
Check the HT/LT rod and replace if required.
OIL LEAKAGE FROM TOP PLATE
Oil leakage from top plate can be attended by tightening nuts & bolts diagonally
Replace gasket if required.
2. Condition of Breather & Conservator
Poor condition of breather like cracks on its body, improper coupling of Cup, absence of oil in
cup cause rust formed due to moisture ingress through breather
CORRECTIVE ACTION & PREVENTIVE ACTION:
BREATHER
Moisturized (Pink) Silica gel should be replaced with new / re activated (blue) Silica Gel.
In case of new Breather, ensure to remove seal from breathing hole of oil cup.
Re-activation of used silica gel to avoid excessive consumptions
After filling silica gel, Breather should be tight properly.
Pour oil in Breather oil cup, if required.
Breather should be tightly fixed to breather pipe.
Due to improper coupling of breather bottle and flange, breathing points may be formed,
thereby creating a passage for moisture, which leads to condensation and rusting of the
conservator tank from inside.
During maintenance , the breather size and type to be checked & non transparent breather
should be replaced by transparent breather of recommended size as below:
< 400 KVA- 0.5 Kg
> 400 -990 KVA- 1 Kg
CONSERVATOR & OIL
Oil sample for BDV test should be taken in proper oil sample bottle. In case of low BDV
value take necessary action.
Check the cap and surface of conservator tank for rusting/holes.
Check oil level from oil gauge.
Oil topping should be done if required.
Check Oil Gauge for leakage.
Explosion Vent Diaphragm
Check the Diaphragm, if it is torn then replace it by a new one
3. High unbalancing current :
Higher unbalance current cause rise in winding temperature. This overheating of winding may
damage the inter-winding insulation level and so as to distribution transformer failure.
CORRECTIVE ACTION & PREVENTIVE ACTION:
Monthly load recording and balancing of DT as well as LT feeders.
Unbalance Current should not exceed 10% of Full Load/ Running Load.
4. Continuous overloading of DT
Distribution Transformers are generally not recommended for continuous overloading. However
overloading for a short duration cannot be avoided. It is one of the prime responsibilities of the
utilities to keep a check on the loading of a transformer and should record the loading Patton on a
history card. In case of overloading the additional loss generates more heat, which effects the
burning of winding insulation, causing ultimate failure of the transformer.
CORRECTIVE ACTION & PREVENTIVE ACTION:
Transfer the load to nearby DT (If possible)
Augment or swap the overloaded DT
Provide additional DT.
5. Frequent LT cable faults
More the cable faults, more the fault current travels towards the transformer.
CORRECTIVE ACTION & PREVENTIVE ACTION:
Replace sick cables and reduce length of LT feeders
Tree trimming should be done to avoid transient faults.
6. Improper protection of both HT and LT side
Improper protection system always invites the risk of damage of equipment. As Distribution
Transformers are one of Costliest & vital part of Distribution System, Special care must be
taken while selecting switching & protecting devices. Preferably at HT Side Ring Main unit
(RMU) / breaker should be used with appropriate Protective Relays in case of small DTs Drop
down Fuses (DD fuses) of appropriate ratings can also be used. At LT Side of Distribution
Transformers Appropriate rating of ACBs / MCCBs can be used.
In case of absence of proper protecting devices or installation of improper Rating / Size of fuses
the risk of DT failure became very high. This could be the due to:
Installation of RMU / Breakers with defective / inappropriate Relay or relay setting
Installation of inappropriate Rating / Size of fuses
Consistent overloading.
Lightning Arrestors (LAs) are not installed.
Inappropriate Earthing of DT / Neutral / Las
CORRECTIVE ACTION & PREVENTIVE ACTION:
Get relay setting checked from M&P department
replace defective LT Fuse Board/ LT ACB
Segregate multiple LT feeders that feed from one LT fuse Board
7. Development of hot spots due to passage of time
Development of Hot spots in the system are mainly due to Loose nut bolt connection at HT/LT side,
Improper Lugs crimping, underrated wires & nut bolts, improper alignment of blades of G.O switch,
loose binding of conductor etc . Prolonged Hot spots causes breakdown the system which further
loss of reliability & revenue. Also it will make the equipment deteriorated day by day.
CORRECTIVE ACTION & PREVENTIVE ACTION:
HT and LT connections should be tight.
Proper size of lugs & nut bolts should be used.
Proactive thermo-scanning and urgent compliance to the observations should be done.
Proper crimping of lugs should be carried out. Minimum 3-4 crimping required for each
lugs
8. Poor/defective earthing of neutral & body of DT and of LT feeders
In electricity supply systems, an earthing system or grounding system is circuitry which connects
parts of the electric circuit with the ground, thus defining the electric potential of the conductors
relative to the Earth's conductive surface.
Poor earthing of neutral will not allowed to pass the fault/ unbalance current though the ground.
CORRECTIVE ACTION & PREVENTIVE ACTION:
Check earthing of DT neutral & body, Fence, LT/HT frames.
Earth resistance values must be below 1Ω. If the test values are greater than 1Ω, then new
earthing must be provided as soon as possible.
Proper earthing of LT feeder should be checked & provided new earthings where ever
required.
Total 5 earthings should exist in pole mount DT.
2 for DT neutral
1 body & fence for DT
2 for LA.
Earth value should be checked during planned shut down and earthing connections should be
tightened.
9. Cat/monkey electrocution
In many case, unnecessary trippings and DT bushings failures noticed due to Cat/ Monkey/ Birds
electrocution.
CORRECTIVE ACTION & PREVENTIVE ACTION:
Top covering of fence of monkey/domestic animal prone substation.
Provision of HT insulation caps
10. Poor maintenance of DT
Transformer failure can also stem from poor O&M practices. For example, in addition to normal full
load, continuous over-heating and higher no-load losses may reduce the life of the transformer due to
reduction in the life of insulating papers, oil, etc. Other improper O&M practices leading to
transformer failure are mentioned below:
Negligence to Low BDV value of oil.
Negligence to Megger process & its results.
Low oil level.
Non-usage of Cleats at HT & LT sides.
Poor handling of LT cables associated with DT LT side.
Negligence to HV/LV connection CORRECTIVE ACTION & PREVENTIVE ACTION:
Pre inspection of scope of work to ensure less down time of PSD and material
requirement.
Proper LT Cable end terminations to be installed in order to prevent it from ingression of
water during to rains which turns in Cable fault.
LV/HV CONNECTION (Palm Connectors)
Nuts, bolts & clamps of H.V. & L.V. connections should be tight.
Proper size of lugs should be used on LV/HV cable as to maintain proper voltage.
Defected palm connectors should be replaced. (Pitting on the surface causes HOT
SPOT)
Check HT & LT cable cleats to avoid mechanical stress on transformer bushing.
LT leads & Neutral earth wire should not touch radiators.
During the maintenance palm & lug contact surface to be cleaned properly and
petroleum jelly to be applied to avoid rusting and hot-spots.
Power Transformers
Best practices at substation level maintenance
Note down the temperature and record the maximum daily ambient temperature.
Check that temp rise is reasonable. In case of any abnormal variation, check the cooling
system of T/F. If the same is not found in order. Shut down the T/F for further
investigation.
Check against transformer oil level/ temperature. Top up with dry oil, if necessary.
Check for any oil leakage.
Check for any abnormal sound or excessive chattering. Shut down the T/F in case of
abnormal noise, for further investigation
Examine relays and alarm contacts and their operation, fuses etc. Check for relays
functioning clean or replace the contacts if required
Measure earth resistance of the (a) T/F body, neutral and other body parts, (b) Keep
proper record of test results. (Earth testing to be done during driest part of the season)
Examine Firefighting equipments and ensure that these are in order.
In case of bushing -Test oil for dielectric strength Dehydrate or replace the oil, if
necessary.
Use LT sleeve on 11 KV side
Earthing of panels
In case of cooler fan & pump bearing all Lubricate bearings, check gear box. Examine
Contacts, Check Manual control and interlocks. Replace burnt or worn out contacts or
other parts.
I.R. values with 2.5KV rating meggar. Convert it at 700 C and compare the values with
the value taken at the time of commissioning.
Earth resistance of the (a) T/F body, neutral and other body parts, Keep proper record of
test results. (Earth testing to be done during driest part of the season)
Avoid leakage/seepage of oil from main tank to OLTC tank.
Continuously monitoring of DGA test to keep close eye on transformer condition.
To reduce eddy current, proper earthing of transformer body top cover with body is
must.
TYPES OF UNDERGROUND CABLE FAULTS
Cables are generally laid directly in the ground or in ducts in the underground distribution system.
For this reason, there are little chances of faults in underground cables. However, if a fault does
occur, it is difficult to locate and repair the fault because conductors are not visible. Nevertheless,
the following are the faults most likely to occur in underground cables:
1. Open-circuit fault
2. Short-circuit fault
3. Earth fault.
Following are the main causes of Under Ground Cable failure.
1. Insulation Degradation
2. Joint Failure
PREVENTIVE & CORRECTIVE ACTION PLAN
1. PLAN TO MINIMIZE INSULATION FAILURE
2. PLAN TO REDUCE JOINT FAILURES
3. PLAN TO REDUCE EXTERNAL DAMAGE
4. PLAN TO REDUCE BURNING OF CABLES
Overhead Circuits (O/H Lines) Fault in Overhead Lines
Overhead lines are the main part of electrical power distribution system. These are used to carry the
electrical power from generating station / Sub-station to load centers/ consumer’s point. There are
several types of faults occurs at lines and there are several causes of fault occurrence at Over head
lines.
There are mainly two types of faults in the electrical power system. Those are symmetrical and
unsymmetrical faults.
Causes of Overhead Line faults 1. Flashed /Punctured or broken insulators
2. Damaged jumper/Conductor
3. Fault due to Tree Contact
4. Faults due to Birds
5. Fault due to Cracked Pole
6. Improper Earthing
Corrective & Preventive Action 7. Action Plan for Flashed /Punctured or broken insulators:
8. Plan for Jumper Repairing
9. Plan for Tree Pruning / Trimming
10. Plan to reduce Faults due to Birds
11. Plan to Replace Cracked Pole
12. Plan for Proper Earthing.
Aerial Bunched Cable (ABC)
Symptoms prior to failure
At initial stage:
In Majority of cases, sparking &Hissing sound is developed between Copper screen & Messenger
wire of HT ABC.
Later stage:
Outer Sheath burnt along the Messenger wire & damage of XLPE insulation due to heat of
sparking.
Cause of Sparking
The design of ABC is such that a substantial voltage induced at copper screen and is capable to
puncture the outer sheath along the messenger wire which is at earth potential resulted in sparking
& discharging sound.
Symptoms prior to failure:
At initial stage: In Majority of cases, sparking & hissing sound is developed between Copper screen
& Messenger wire of HT ABC because of improper connection between copper screen &
Messenger wire.
Later stage: Outer Sheath burnt along the Messenger wire & damage of XLPE insulation due to
heat of sparking.
Reason of Failure:
Design snags- a) Induction of high voltage at copper screen.
b) Under rated fault withstand capacity of Cu screen.
c) Manufacturing defects
Installation snags - Improper connection between Cu screen & Messenger.
Mechanical damage during installation.
Mechanical stress
Stress develop due to Improper Bending Radius
o Ensure Proper Bending radius
Stress/ Abrasion develop due to improper clearance between poles & AB cable
suspended on suspension clamps
o Ensure proper clearance between poles & ABC
Stress develop due to Improper Span length
o Ensure proper span length
o Span Length should be depend on the size of the conductor/ABC cable and
pole height/type to maintain min. Sag & specified ground clearance
o It would be 30-35 m for PCC pole
External damage
Insulation Damaged during installation due to improper Laying practices.
o Ensure use of Rollers/ Pulleys during installations.
SN CHECK LIST DESCRIPTION ANNEXURE
1 CHECK LIST FOR MAINTENANCE OF 33/11KV POWER
TRANSFORMER ANNEXURE-PTR/MAIN/01
2 CHECK LIST FOR MAINTENANCE OF ON-LOAD TAP
CHANGER ANNEXURE-PTR/OLTC/MAIN/01
3 CHECK LIST FOR MAINTENANCE OF 33 & 11KV CIRCUIT
BREAKERS ANNEXURE-CB/MAIN/01
4 CHECK LIST FOR MAINTENANCE OF CURRENT
TRANSFORMERS ANNEXURE-CT/MAIN/-01
5 CHECK LIST FOR MAINTENANCE OF POTENTIAL
TRANSFORMERS ANNEXURE-PT/MAIN/01
6 CHECK LIST FOR MAINTENANCE OF LIGHTNING
(SURGE) ARRESTERS ANNEXURE-LA/MAIN/01
7 CHECK LIST FOR MAINTENANCE OF LINE ISOLATORS
& EARTH SWITCHES ANNEXURE-ISOL/MAIN/01
8 CHECK LIST FOR MAINTENANCE OF BATTERY BANK &
BATTERY CHARGERS ANNEXURE-BAT/MAIN/01
9 CHECK LIST FOR 11 KV VCB CONTROL PANEL ANNEXURE-11KV VCB CONTROL
PANEL/MAIN/01
10 CHECK LIST FOR 33 KV OUT DOOR BUS ANNEXURE-33KV BUS/MAIN/01
11 CHECK LIST FOR 11 KV OUT DOOR BUS ANNEXURE-11 KV BUS/MAIN/01
12 CHECK LIST FOR APFC CONTROLLERS ANNEXURE-11 KV APFC /MAIN/01
13 CHECK LIST FOR AC DISTRIBUTION BOARD ANNEXURE-ACDB /MAIN/01
14 CHECK LIST FOR MAINTENANCE OF EARTHING
SYSTEM AT GRID SUBSTATION ANNEXURE-EARTHING/MAIN/01
15 CHECK LIST FOR MAINTENANCE OF 33 KV LINES ANNEXURE-33 KV LINES /MAIN/01
16 CHECK LIST FOR MAINTENANCE OF 11 KV LINES
17 CHECK LIST FOR MAINTENANCE OF LT LINES
18 Annexure- AR-1 HT Auto-recloser
19 Annexures DT-1 Distribution Transformer
20 Annexures DT-2 Distribution Transformer
21 Annexures DT-3 Distribution Transformer
22 Annexures DT-4 Distribution Transformer
23 Annexures DT-5 Distribution Transformer
24 Annexures DT-6 Distribution Transformer
25 Annexures DT-7 Distribution Transformer
26 Annexures DT-8 Distribution Transformer
27 Annexure RMU-1 Ring Main Unit
28 Annexure RMU-2 Ring Main Unit
29 Annexure UG-1 Under Ground Cable
30 Annexure ABC-1 HT AB Cable
31 Annexure-ERT-1 HT Earthing
32 Annexure- G.O.-1 G.O. Switch
33 Annexure- OH-1 HT O/H Conductor
34 Annexure LT ACB LT ACB
SN CHECK LIST DESCRIPTION ANNEXURE
35 Annexure- LT UG Cable LT UG Cable
36 Annexure LT OH Conductor LT OH Conductor
37 Annexure LT ABC LT ABC
38 Annexure LT Earthing LT Earthing
39 Annexure LT Metering & Service Cable LT Metering & Service Cable
40 Annexure LT Feeder Pillar LT Feeder Pillar
41 Annexure LT Fuse Board LT Fuse Board
ANNEXURE-PTR/MAIN/01
CHECK LIST FOR MAINTENANCE OF 33/11KV POWER TRANSFORMER
Name of Grid: Date &
Time
Season
Pre-requisite for Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Safety Cotton Rag
S.
NO.
ITEM TO BE
INSPECTED BRIEF DESCRIPTION OF WORK
FREQUEN
CY
PERMISSI
BLE
VALUES
STATU
S
ACTIO
N
TAKE
N
1 Ambient Temp
Note down the temperature and record the
maximum daily ambient temperature. Hourly NA
2
Winding/Oil Temp
Check that temp rise is reasonable. In case of
any abnormal variation, check the cooling
system of T/F. If the same is not found in order.
Shut down the T/F for further investigation.
Hourly 100° C
3 Load/Voltage
Check against rated figures. In case of any
variation, check the TPI. Hourly NA
1 Oil level in transformer
Check against transformer oil level/
temperature. Top up with dry oil, if necessary.
Daily each
shift
Above from
Min level
2 Oil level in bushings Check for any oil leakage.
Daily each
shift
Above from
Min level
3 Relief Vent diaphragm
Check for cracked or broken. Replace if
necessary.
Daily each
shift NA
4
For internal abnormal
noise.
Check for any abnormal sound or excessive
chattering. Shut down the T/F in case of
abnormal noise, for further investigation.
Daily each
shift NA
5
Heaters in Junction Box Check for proper working, if provided. Replace,
if found defective/damaged.
Daily each
shift NA
6
External connection
(Leads/Jumpers)
Check visually for tightness and sparking on
jumpers, bushings etc. on complete darkness.
Attend it, if required.
Daily each
shift
NA
7
Bus bar and cable boxes
and cables
Check for any damage and signs of overheating
at their joints. Check for overheating of back
covers and attend, if found excessive heated.
Daily each
shift
NA
1
Dehydrating breather
Check for condition/colour of Silica gel.
Recondition or replace as necessary.
Monthly
NA
2 Monthly
3 Monthly
4 Monthly
5 Monthly
6 Ensure for free air passage Monthly NA
7
Tight, lid of the breather for air tightness to
avoid entry Monthly NA
8
Check oil level in oil cup and make up oil, if
required. Monthly NA
9
Remove oil from dash pot and pour in fresh oil
where required. Monthly NA
10
Bushing and gaskets
Examine for cracks, Paint and dirt deposits and
gap settings. clean or replace it. Check gaskets
for leakage.
Monthly NA
11
Cooler fan and pump
bearings, motors and
operating mechanism
Lubricate bearings, check gear box. Examine
Contacts, Check Manual control and interlocks.
Replace burnt or worn out contacts or other
parts.
Monthly NA
12
On load tap changer
driving mechanism
Lubricate bearings, Check gear box oil level and
examine contacts. Clean/Replace burnt or worn
out contacts
Monthly NA
13
On load tap changer
automatic control
Check all circuits independently. Check step by
step operation including limit switches. Attend
if found faulty.
Monthly NA
14
Insulation resistance
Check the I.R.values with 2.5KV rating meggar.
Convert it at 70 0 C and compare the values
with the value taken at the time of
commissioning.
Monthly > 50 M-
ohm
15
Relays alarms,
temperature alarm and
their circuits
Examine relays and alarm contacts and their
operation, fuses etc. Check for relays
functioning clean or replace the contacts if
required.
Monthly NA
16 Arcing Horns
Set the rods for alignment and for proper gap
adjustment. Monthly NA
17
Measuring/Protection
CT’s
Check for sparking and tightness of connection
and oil level. Monthly NA
18 Remote/Manual Switch Check for proper functioning Monthly
NA
19 Firefighting equipments Examine them and ensure that these are in order. Monthly
NA
20 Bucholtz’s relay
Note the oil level in the inspection glass of
Bucholtz’s relay. Monthly NA
1
Oil in T/F and tap
changer
Check for dielectric strength. Dehydrate the oil,
if necessary. Keep continuous record of test
results.
Quarterly NA
2 Ventilators Check that air passages are free. Quarterly NA
3 Bucholtz’s relay Check proper operation by lowering the oil Quarterly NA
4 Forced cooling system Megger testing of motors(pumps) Quarterly NA
5
Checking transformer ground connections for
tightness. Quarterly NA
6 ThermoSyphen Filters Quarterly NA
7 Earth Resistance Check for tightness of earth connections. Quarterly NA
8
Measure earth resistance of the (a) T/F body,
neutral and other body parts, (b) Keep proper
record of test results. (Earth testing to be done
during driest part of the season)
Quarterly NA
1 On load tap
Inspect all moving parts, contacts, brake shoes,
motor etc. Clean, adjust or replace as required. half yearly NA
2 Oil in T/F
Check acidity, PPM & BDV & compare with
standard results. half yearly NA
1
Oil in T/F
Check Tan delta,,Sp.Resistively , sludge
contents, DGA test, compare it with standard
results.
yearly NA
2 Oil filled bushing
Test oil for dielectric strength Dehydrate or
replace the oil, if necessary. yearly NA
3 Cable box
Check for sealing arrangements for filling holes.
Examine compound for cracks. yearly NA
4 Surge diverter and gaps
Examine for cracks and dirt deposits. Clean or
replace if necessary. yearly NA
5 Gasket joints
Check for tightness of bolts to avoid uneven
pressure. Replace damaged gasket. yearly NA
6 Pipe connections
Check oil pipes valves and plugs for tightness
and proper functioning. yearly NA
7 Foundations Check for cracks, if any and setting. yearly NA
8 Bushings Test the bushings with a Hipet bushing tester yearly NA
and compare with previous figures.
9 Temperature indication
Pockets holding thermo-meter should be
checked. Oil to be replenished, if required. yearly NA
10 Dial type oil gauge
Check pointer for free operation. . Adjust, if
required. yearly NA
11 Paint work Should be inspected yearly NA
12
Conservator tank
Check for proper communication of the
conservator with T/F tank by draining some oil
through drain off valve and watching the oil in
gauge glass to drop.
yearly NA
13
In case, the oil does not drop, investigate and
remove the sludge or other obstructions after
dis-assembling the tank.
yearly NA
14
Check for leakage of oil from glass side. Clean
the inspection glass. yearly NA
1
Diverter switches for
tap changer having non-
arcing selector switch
Check for worn out contacts. Filter oil
irrespective of all test. Replace worn out parts.
Yearly or
after 5,000
operations
NA
2 Oil conservator
Internal inspection Clean the conservator
thoroughly Two years NA
3 Buchholtz relay
Mechanical inspection. Adjust floats, switches
etc. if required. Two years NA
4
Non-arcing selection
switch of on load tap
changer
General inspection. Replace worn out parts and
filter the oil.
3 years or
after 15,000
operations
NA
5
Overall inspection including lifting of core and
coils 7 to 10 years NA
6 Major overhauls (complete) of transformers. 7 to 10 years NA
7
3000KVA and below (once in 7 yrs.) Above
3000KVA (once in 10 yrs.)
Once in 7
years
once in 10
years
NA
NA
NA
Note:Insulation resistance measurement, tan δ of winding/bushings, winding resistance at all taps to
be carried out once before expiry of warranty period and then to be continued as per schedule.
Visual observation of transformers and Reactors by going round, should be made daily to check for
any variations in noise, vibrations and any abnormality/leakages from cooler fans, oil pumps,
radiators, valves etc.
WITNESSED BY:- JE/SDO SIGNATURE
ANNEXURE-PTR/OLTC/MAIN/01
CHECK LIST FOR MAINTENANCE OF ON-LOAD TAP CHANGER
Name of Grid: Date & Time
Season
Pre-requisite for Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Cotton Rag
Sr.
no.
ITEM TO BE
INSPECTED BRIEF DESCRIPTION OF WORK
FREQUENC
Y
Permissibl
e Values
STATU
S
ACTIO
N
TAKEN
1
ON LOAD TAP
CHANGER
ON LOAD TAP
CHANGER
Check leakage/seepage of oil from main tank to
OLTC tank DAILY N/A
2 Oil leakage from OLTC. DAILY N/A
1 Silica gel breather MONTHLY N/A
2 Colour of silica gel crystals MONTHLY N/A
3 Oil in oil cup in silica gel breather MONTHLY N/A
4 Vermin proofing of OSR to avoid moisture ingress MONTHLY N/A
5 All unused wires are insulated MONTHLY N/A
1 Prismatic oil gauge in OLTC conservator tank QUARTERL
Y N/A
2 OSR oil glasses. QUARTERL
Y N/A
3 Drain / filer valves QUARTERL
Y N/A
4 Cracks / any abnormality in barrier board QUARTERL
Y N/A
5 Local electrical operation of OLTC QUARTERL
Y N/A
6 Step by Step operation of OLTC QUARTERL
Y N/A
7 Electrical end limit (both upper and lower) QUARTERL
Y N/A
8 Operation of OLTC QUARTERL
Y N/A
9 Space heater / thermostat/illumination lamp in
drive mechanism
QUARTERL
Y N/A
1 OSR relay HALF
YEARLY N/A
2 Oil BDV for OLTC tank HALF
YEARLY
>40KV at
2.5 mm gap
3 Oil DGA HALF
YEARLY
4 OSR trial operation HALF
YEARLY Positive
5 OLTC operation manual/auto/local/remote HALF
YEARLY Positive
1 Complete OLTC YEARLY N/A
2 OLTC drive mechanism cubicle YEARLY N/A
3 Diverter switch tank and barrier board YEARLY N/A
4 Fixed contacts in diverter switch YEARLY N/A
5 Moving contacts in diverter switch tank YEARLY N/A
6 Transition moving contact YEARLY N/A
7 Tightness of internal connections YEARLY N/A
8 Braided flexible/collector ring/pre selector YEARLY N/A
9 Tap lead connection (for out tank OLTC only) YEARLY N/A
10 OSR connections YEARLY N/A
11 All gasketted joints YEARLY N/A
1 Transformer turn ratio / voltage ratio
5 years or
after
replacement
of any
primary part
of OLTC
As per pre
comm
values
1 Winding resistance of HV winding on all taps
At the time of
OLTC
maintenance
As per pre
comm
values
WITNESSED BY:- JE/SDO SIGNATURE -
ANNEXURE-CB/MAIN/01
CHECK LIST FOR MAINTENANCE OF 33 & 11KV CIRCUIT BREAKERS
Name of Grid: Date &
Time
Season
Pre-requisite for Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Safety Cotton Rag
Sr.
no.
ITEM TO BE
INSPECTED BRIEF DESCRIPTION OF WORK
FREQUEN
CY
Permissi
ble
Values
STATU
S
ACTIO
N
TAKE
N
1 General cleanliness Examine that switchgear premises doors, circuit
breaker etc. for general cleanliness. Daily
N/A
2 Oil Check oil leakage, if so level be also ascertained. Daily
N/A
3 Tank Check for temperature by touch and for any unusual
noise and smell. Daily
N/A
4
Alarms and lamp indication
circuit etc.
Test the alarm circuit for continuity and lighting
circuit and earthing system. Daily
N/A
5 Safety aids Check safety aids for proper operation/condition. Daily N/A
6 Load
Check for load conditions on 3 phases, adjust relay
setting. If necessary. Daily
N/A
7 Indicating and measuring
instruments
Check, indicating and measuring instruments for
correct reading and being in proper working order Daily
N/A
1 Auxiliary fuses Check that auxiliary fuses are intact. Weekly
N/A
2 Oil level and gauges Check oil level in gauges of the tank/poles/oil filled
bushing. Replenish oil if found below normal. Weekly
N/A
3 Bushing or insulators
Check for chipped or broken insulator, excessive
dirt film. Weekly
N/A
4 Closing solenoid of air
cylinder, motor or spring
Visual inspection to see that equipment is in
operating conditions Drain condensation from air
cylinder.
Weekly
N/A
5 Latch and trip mechanism
Visual (or otherwise) inspection to see that
mechanism is in operating condition. Weekly
N/A
6 Tripping solenoid Visual inspection to see that solenoid trip device is
in operating condition. Weekly
N/A
7
Cabinet lights and heaters
Check cabinet heaters and see that they are in
service during cold weather. Replace burnt out
lamps.
Weekly
N/A
8 Power supplies and wiring See that all power control circuit switches are closed Weekly N/A
9 Breathers and vents
Check for external obstructions to breathers and
vents and condition of silica gel. Weekly
N/A
1 Nuts, bolts & Jumpers etc. Check whether nuts and bolts are tight and jumpers
are properly connected. Monthly
N/A
2 Drain plug Check that drain plug is tight. Monthly
N/A
3 Operation counter Observe and record reading of operation counter. Monthly N/A
1 Local remote operation
Check that breaker can be operated locally and in
remote control operation. Quarterly
N/A
2 Exhaust pipes Check and clean the exhaust pipes. Quarterly N/A
3 Dash pot Check the working of dash pot. Quarterly
N/A
4
Shutter mechanism and
trolley alignment for 11KV
breakers
To check for proper working of shutter mechanism
and to verify the alignment of trolley. Quarterly
N/A
5
Manual operating device
Check that manual operating lever or jack is kept on
hand and is in visible condition. See that breaker is
closable with it.
Quarterly
N/A
6 Latch and trip mechanism
Observe mechanism during general tripping
operations to see that everything is in working order.
Check pins, bearings and latch for wear, binding and
misalignment. Clean and lubricate the moving
parts. Check latch carefully to see that it is not
becoming worn so as to unlatch from vibration or
stick or fail to trip. Tighten bolts and screws.
Quarterly
N/A
7
Tripping solenoid
Observe operation during electrical tripping. See
that full energy, snappy action of plunger is
obtained. Check plunger for sticking in guide Check
oil and insulation resistance.
Quarterly
N/A
8
Indicating and measuring
instruments
Check for satisfactory operation, adjust where
necessary Quarterly
N/A
1
IR values
Check IR value in ON and OFF positions between
contacts in off position. Check IR value of control
cable with 500V megger.
Half yearly
N/A
2 Earth resistance Check earth resistance of body. Half yearly
N/A
3
Slow closing test This test may be conducted and also check that all
the three contacts are made simultaneously. Half yearly
N/A
4
Adjustment of gap (for
MOCB)& other type to
check the prescribed items
by the manufacturer
The gap may be checked and adjusted to the
required value. Half yearly
N/A
5
Wiring connections
Check and tighten wiring connection at terminal
points. Inspect wiring for open circuit, short circuit
and damaged insulation.
Half yearly
N/A
6 Aux.Switches
Check condition of contacts and refinish with fine
file if burnt or corroded. Check contact springs,
operating rods and levers. Check closing and
operating position with respect to main contacts
while breaker is slowly closed and opened manually.
Half yearly
N/A
7
Control and protection
chamber of 11KV switch
To check for alignment of front door
opening/closing for loose fitting, loose wiring of
opening in 11KV switchgear.
Half yearly
N/A
8 Insulated, jumpers CT and
PT in 11KV switchgear
To check for tightness of connections, proper
insulation and proper geometry. Half yearly
N/A
9 11KV cable connections
Check for overheating and proper connection and
insulation. Half yearly
N/A
1 Foundation
Check foundation for cracks and settings. Settings of
the breaker tank may break bushings or cause
misalignment of contacts or bindings of operating
mechanism.
Annual
N/A
2
Oil valves and plugs
Check condition of paint. Inspect oil valves and
plugs. Flush out oil and clean the oil
tank/quenching chambers.
Annual
N/A
3 Oil levels and gauges
Clean dirty gauge glasses and connections into tank.
Drain out and replace bushing oil if found dirty or
discoloured.
Annual
N/A
4
Breathers and Vents Check to see that screens and baffles in vents or
breathers are not obstructed or broken. Annual
N/A
5 Panels and cabinets
Check air circuit breaker or other panels of
insulating material for cracks and cleanliness. Check
condition of enclosing cabinets including hinges,
latches, locks door gaskets and paint.
Annual
N/A
6
Bushings or insulators
Clean porcelain with water, chloroethene or other
suitable cleaner. Repair chipped spots by painting
with lacquer such as red clay paint. Inspect gaskets
for leaks, tighten bolts. Check insulation resistance
with contacts closed and (Tan delta for condenser
type). Check oil sample from bottom of bushing for
dielectric strength and moisture. Replace or
replenish oil if necessary. Check and clean interior
at least once every five years.
Annual
N/A
7 Main terminals and ground
connections
Tighten all nuts and ground connections. Refinish
joint mating surface, if they have been overheated.
Inspect ground cable to see that it is not loose or
broken.
Annual
N/A
8
Main contacts
Remove the tanks or drain out oil, so that the
contacts can be inspected, dress contacts, if rough
with a fine file. Check contacts voltage drop with
millivolt meter after inspecting reasonable current.
Frequency of contact maintenance should be based
on numbers and severity of faults interrupted, rather
than a definite period. Check adjustment of gap
when required.
Annual
N/A
9 Contact pressure spring
Check for loss of temperature damage or other
deterioration. Annual
N/A
10 Flexible shunt
Check flexible shunts of contact hinges for
overheating or damages. Tighten connections. Annual
N/A
11 Magnetic, air or oil below
out devices
Check arc-rupturing blow out coils, magnetic circuit
arc chutes, de ion grids, oil blasts or other
interrupters for proper operations.
Annual
N/A
12
Cross heads Check contact cross head for misalignment breaks
bends or looseness on lift rods. Annual
N/A
13 Lift rods and guides
Check contacts for lift rods or brakes, weakening or
wrapping and pulling out at ends. Checks adequacy
of guides.
Annual
N/A
14
Operating rods shafts and
bell cranks
Check for loose locknuts, set screws, keys, bearing
bent rods or twisted shafts etc. clean moving parts of
rust, dirt and accumulated grease and oil, wash out
bearings, pivots and gears with chloromethane or
other suitable cleaner and operate breaker several
times to work out dirt and old lubricant. Lubricate
with new grease or oil.
Annual
N/A
15 Closing solenoid air
cylinder, meter or spring
Observe mechanism during several operations to see
that everything is in proper working order. Check
solenoid plunger for sticking in guides. Check coil
resistance and insulation resistance. Dismantle air
cylinder and clean and lubricate. Check spring for
proper tension and closing energy.
Annual
N/A
16
Solenoid valves
Check for condition of valve, and refit as necessary.
See that moving parts are free to operate. Check
resistance and insulation resistance of solenoid coil.
Annual
N/A
17 Operation counter
Check that the operation counter is properly
registering the breaker operations. Annual
N/A
18 Position indicator
Check that position indicator is properly registering
the breaker operations. Annual
N/A
19 Dashpots Check for proper setting and adjust as necessary.
Clean out and replenish liquid in liquid dashpot. Annual
N/A
20
Mechanism cabinets
Check condition of metal and hardware. Repaint as
necessary. See that door gaskets are tight and
properly dust and vermin proof.
Annual
N/A
21 Power supply and wiring
Inspect fuses of circuit breakers in all power and
control supply circuits, check in insulation
resistance of wiring with devices connected.
Annual
N/A
22
Oil dielectric test and
acidity test dependent on
actual tripping
Check dielectric strength of the insulating oil in the
main tanks and oil filled bushings. Oil should be
filtered or replaced if dielectric strength is found to
below 25 KV, or if there is a noticeable amount of
carbon in suspension on the bottom of the tanks.
Also check ratio and phase angle adjustments, the
acidity of the oil.
Annual
N/A
23 Operation
Some breakers particularly those carrying high
values of current have a tendency to develop contact
heating if left closed for long periods. Operating and
closing the breakers several times at intervals, as
system operation permit, may alleviate the heating
by wiping the oxide from the contact surfaces, as
well as demonstrate that the breaker is in operating
condition.
Annual
N/A
24
Bushing current
transformers and potential
devices
Check tap setting and adjustments at terminal board
to see that they agree with diagrams. Check
insulations resistance of wiring with devices
connected. Check of potential devices if changes
have been made in secondary connection and
burden. Tighten connections, including potential
devices top into bushing.
Annual
N/A
1
Testing of oil in oil filled
bushings
Once in two
years
N/A
2
Cleaning blast tube
internally and checking
clamping down nuts.
Once in two
years
N/A
3
Overhaul and checking
efficiency of main
compressor. Complete
overhaul of the O.C.B.
(The period can be changed
depending upon the lead
cycle of the equipment and
manufactures
recommendations).
Once in two
years
N/A
WITNESSED BY:- JE/SDO SIGNATURE -
ANNEXURE-CT/MAIN/-01
CHECK LIST FOR MAINTENANCE OF CURRENT TRANSFORMERS
Name of Grid: Date & Time
Season
Pre-requisite for Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Earth resistance Tester
Cotton Rag
Sr.
no. ITEM TO BE INSPECTED
BRIEF DESCRIPTION OF
WORK
FREQUENC
Y
Permissible
Values
STATU
S
ACTION
TAKEN
1
CURRENT TRANSFORMER
Visual Damages & Deterioration
if any WEEKLY N/A
2 Oil Leakage if any WEEKLY N/A
3 Oil Level in CT WEEKLY N/A
6 Check condition of the Structure WEEKLY N/A
7 All unused wire are insulated in
CT WEEKLY N/A
8 All cables entry into CT is through
cable gland WEEKLY N/A
9 Check any abnormal sound with
Ultra probe 15000 WEEKLY N/A
1 CT Bushing MONTHLY N/A
2 Secondary Terminals MONTHLY N/A
3 CT Junction Box MONTHLY N/A
4 Oil Inspection Window MONTHLY N/A
6 Primary Connections MONTHLY N/A
7 Secondary Connections MONTHLY N/A
8 Mounting Frames MONTHLY N/A
9 Earthing CT/Frame/JB MONTHLY N/A
10 JB Connections MONTHLY N/A
11 Vermin Proofing of CT Junction
Box/Sec Terminal MONTHLY N/A
1 IR value of Primary to Earth HALF
YEARLY >200M Ohm
2 IR value of Secondary to Earth HALF
YEARLY >200 M Ohm
3 IR Value of Primary to Secondary HALF
YEARLY >200M Ohm
4 Tan Delta HALF
YEARLY <5%
1 CT Analysis YEARLY As per CT
Type
WITNESSED BY:- JE/SDO SIGNATURE -
ANNEXURE-PT/MAIN/01
CHECK LIST FOR MAINTENANCE OF POTENTIAL
TRANSFORMERS
Name of Grid: Date & Time
Season
Pre-requisite for Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Safety Cotton Rag
Sr.
no.
ITEM TO BE
INSPECTED BRIEF DESCRIPTION OF WORK FREQUENCY
Permissible
Values
STAT
US
ACTIO
N
TAKE
N
1
POTENTIAL
TRANSFORMERS
Check any abnormal sound with
ultrasonic detector DAILY N/A
2 Visual damages and deterioration if any DAILY N/A
1 Oil Level sight Glass Weekly N/A
2 Earthing PT/Frame/JB Weekly N/A
3 JB Connections Weekly N/A
4 Oil Leakage if any Weekly N/A
5 Check condition of fuses & that all fuses
are intact Weekly N/A
1 PT Bushing Quartarly N/A
2 PT Junction Box Quartarly N/A
3 Secondary Connections Quartarly N/A
4 IR value of Primary to Earth Quartarly >200M Ohm
5 IR value of Secondary to Earth Quartarly >200 M Ohm
6 Oil Level in PT Quartarly N/A
7 Vermin Proofing of PT Junction Box/Sec
Terminal Quartarly N/A
1 Secondary Terminals Annually N/A
2 Primary Connections Annually N/A
3 Mounting Frames Annually N/A
4 IR Value of Primary to Secondary Annually >200 M Ohm
5 Correct Rating of PT Fuse, up to C&R
Panel Annually N/A
6 Check condition of the Structure Annually N/A
7 Check all unused wires are insulated Annually N/A
1 PT Analysis Once in 3 Yrs. As per pre
common values
WITNESSED BY:- JE/SDO SIGNATURE -
ANNEXURE-LA/MAIN/01
CHECK LIST FOR MAINTENANCE OF LIGHTNING (SURGE)
ARRESTERS
Name of Grid: Date &
Time
Season
Pre-requisite for Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Earth resistance Tester
Cotton Rag
Sr.
no.
ITEM TO BE
INSPECTED BRIEF DESCRIPTION OF WORK
FREQUE
NCY
Permissibl
e Values
STATU
S
ACTIO
N
TAKE
N
1 Surge Counter Note and record operation indicator reading along
with leakage current. DAILY
N/A
2 Base & support Usual inspection to detect cracking setting or shifting
of base of supports.
MONTHL
Y
N/A
3 Surge Monitor Check that surge monitor is properly connected and is
in working order and shows a leakage current.
MONTHL
Y
N/A
1 Jumpers and
clamps Check jumpers and clamps for tightness.
HALF
YEARLY
N/A
2
Porcelain
shells and
insulators
Clean porcelain insulators and arrestor unit shells.
Repair chipped spots on porcelain with lacquer such
as red clay paint.
HALF
YEARLY
N/A
3 Grading rings Check and tighten grading rings on high voltage
arrestors.
HALF
YEARLY
N/A
4 Gaps Check external gaps. Smooth off burnt spots and
readjust spacing.
HALF
YEARLY
N/A
1 Weather sheds
and hooks
See that weather sheds and hooks of oxide film
arrestors are securely fastened in place, repaint if
necessary.
ANNUAL
N/A
2 Line and Ground
connection
Check and tighten line and ground connections.
Check ground lead for corrosion or damage below
ground line. Check ground resistance. See that all leads
are as short and direct as possible.
ANNUAL
N/A
3
Operation tests
(Surge
generating
equipment
under
procurement)
To check the general working of lightening
arrestors by M&P Divisions. ANNUAL
N/A
WITNESSED BY:- JE/SDO SIGNATURE -
ANNEXURE-ISOL/MAIN/01
CHECK LIST FOR MAINTENANCE OF LINE ISOLATORS & EARTH
SWITCHES
Name of Grid: Date &
Time
Season
Pre-requisite for Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Cotton Rag
Sr. no. ITEM TO BE
INSPECTED BRIEF DESCRIPTION OF WORK
FREQUEN
CY
Permissi
ble
Values
STAT
US
ACTION
TAKEN
1 Insulators
Check for cracked or broken porcelain and
excessive dirt film and to undertake repair of
chipped spots by painting with lacquer such as red
clay paint.
WEEKLY
N/A
2
Blades and
contacts
Check that blades are properly seated in the
contacts.. WEEKLY
N/A
3
Blades and
latches and
stops
Check that blade latches where provided are
engaged.
WEEKLY
N/A
4
Locks and inter
locks
Check that switches are properly locked in the open
or closed position as required by padlocks or other
key type locks or interlocks.
WEEKLY
N/A
1 Bolts, Nuts &
Jumpers
Check bolts, nuts and jumpers for tightness. Apply
petroleum jelly on male and female contacts. Quarterly
N/A
1
I.R,value and
earth
resistance
Check IR, value with 2.5KV megger and earth
resistance. Check that double earthing is provided.
HALF
YEARLY
N/A
2 Auxiliary &
limit switches
Check condition of contacts and refinish with fine
file if burnt or corroded. Check contact spring
operating rod and lever. Check closing and opening
position with respect to main switch contacts or
travel or motor mechanism.
HALF
YEARLY
N/A
3
Manual
operating Rod
To check for proper engagement of emergency
operating handle and further its operation is smooth
and satisfactory.
HALF
YEARLY
N/A
4 Line & ground
ANNUALL
Y
N/A
5
Blades and
contacts
ANNUALL
Y
N/A
WITNESSED BY:- JE/SDO SIGNATURE -
ANNEXURE-BAT/MAIN/01
CHECK LIST FOR MAINTENANCE OF BATTERY BANK & BATTERY
CHARGERS Name of
Grid:
Date &
Time
Season
Pre-requisite for Maintenance
Caution
Order/P
TW No.
T&P/mat
erial/PP
Es
Cotton
Rag
Sr. no. ITEM TO BE
INSPECTED BRIEF DESCRIPTION OF WORK
FREQUEN
CY
Permissibl
e Values
STATU
S
ACTIO
N
TAKE
N
1 Battery room
and ventilation
See that battery room entrance doors are kept
closed and that ventilation to outside air are open
and air is circulated by running of the exhaust
fan
DAILY
N/A
2 Operation
Check charging rate hourly. Check and record
pilot cell specific gravity, temperature and
floating
voltage
DAILY
N/A
3
Bulb for dry
rectifier
element
Check for burnt bulb and replace when
necessary.
DAILY
N/A
4 Operations
Checking specific gravity and voltage of each
cell of lead acid cells. (before and after
charging) (weekly when trickle charge exists)
DAILY
N/A
5
Leakage test
Perform leakage test by lamp or
voltmeter method.
DAILY
(EACH
SHIFT)
N/A
1
Cleaning of terminals, applying Vaseline and
topping up with distilled water. (for lead acid
batteries)
WEEKLY
N/A
1 Cell Jars and
covers
Check for cracked or leaking jars or covers and
replace when necessary. Keep jars and covers
clean.
MONTHLY
N/A
2 Plates
Inspect plates(in case of transparent containers
only) carefully for signs of deterioration due to
improper charging. Note quantity, colour
and texture of sediment.
MONTHLY
N/A
3
Separators
See that the separators remain in place and are
keeping the plates properly spaced(in case of
transparent containers only)
MONTHLY
N/A
4 Electrolyte
Check electrolyte level and add distilled
water when required. MONTHLY
N/A
5
Acid and
distilled water
storage
See that enough distilled water and acid are kept
in storage to meet current needs. Check
containers for cleanliness.
MONTHLY
N/A
6 Operation
Check and record specific gravity and voltage of
each cell. MONTHLY
N/A
7 Transformer or
reactor
Check general condition and operating
temperature of transformer or reactor used in
bulb or dry type rectifiers.
MONTHLY
N/A
1 Connections
Checking all connections of charger and battery
for tightness. Quarterly
N/A
1
Discharging
and charging
cycle
This is required to be carried out as prescribed by
the manufacturer in order to prolong the life of
the battery.
Half yearly
N/A
2
Bulb or dry
rectifier
element
See the copper oxide or selenium rectifier
elements are not operating too hot, this will
shorten their life.
Half yearly
N/A
3 Rheostat
Check that sliding mechanism of the rheostat is
in order and clean the sliding contacts, if
required. Check contact heating and spring
pressure.
Half yearly
N/A
1
Battery room
and ventilation
Check metallic structures/parts located in the
room for corrosion and clean and paint
as necessary, check ventilation system fan etc.
for proper operation to make sure that no
explosive gases are being accumulated in the
battery room due to excessive gassing or poor
ventilation.
Annual
N/A
2
Base or rack
Inspect concretes base or wooden racks for
deterioration. Repair and repaint with acid
resistant paint as necessary.
Annual
N/A
3 Case pad
Check base pad of sheet rubber, or other material
for deterioration from acid or other causes. Annual
N/A
4 Inter cell
connectors
and terminals
Clean acid corrosion from connectors and
terminals should be lead coated. Tighten
terminals and apply petroleum jelly for exposed
surface.
Annual
N/A
5
Hydrometer and
thermo
meter
Check condition of hydrometer and
thermometers used for daily and monthly
readings against spare units held in reserve.
Annual
N/A
6 Sink funnel
and filters
See that the sink, funnels, fillers and other
distilled water and acid handling facilities kept
clean and in good useable conditions.
Annual
N/A
7 Water still
Check still for proper operation, adequacy
and purity of distilled water delivered. See
that equipment is kept clean
Annual
N/A
8
Complete overhauling of the battery. (as
recommended by manufacturer) Annual
N/A
N/A
N/A
N/A
N/A
N/A
WITNESSED BY:- JE/SDO SIGNATURE -
ANNEXURE-CONTROL PANEL/MAIN/01
CHECK LIST FOR CONTROL PANEL Name of Grid: Date & Time
Season
Pre-requisite for Maintenance
Caution
Order/PTW No.
T&P/material/PP
Es
Cotton Rag
Maintenance Activities
S.NO. BRIEF DESCRIPTION OF WORK Frequency Permissib
le Values Status
Action
Taken
1 Check all indication lamps for working DAILY N/A
2 Check illumination lamp / power socket for working DAILY N/A
1 Vermin proofing of panel and door interlock switch MONTHLY N/A
2 Check & ensure that L/R switch is at remote position. MONTHLY N/A
3 Check fuse / MCB rating MONTHLY N/A
4 Check rating of fuses/MCB MONTHLY N/A
1 Control Panel Interior. HALF
YEARLY N/A
2 Control Panel external surface. HALF
YEARLY N/A
3 Relay / Contactors with air blower (from distance) HALF
YEARLY N/A
4 All Control Connections. HALF
YEARLY N/A
5 Earthing Connection wherever provided HALF
YEARLY N/A
6 Inter panel Coupling. HALF
YEARLY N/A
7 Multicore Cable Glands. HALF
YEARLY N/A
8 Check cubicle heater / thermostat for correct operation HALF
YEARLY N/A
9 Dressing of wiring. HALF
YEARLY N/A
10 Check door bidding for dust proofing. HALF
YEARLY N/A
11 Check & ensure that all multicore cables are earthed at
switchyard side only.
HALF
YEARLY N/A
12 Check and ensure that relay healthy indication is
glowing.
HALF
YEARLY N/A
13 Check that all unused wires are insulated. HALF
YEARLY N/A
1 All Protection Connections. At the time of
Prot checking N/A
1 All Communication Connections. At the time of
Com checking N/A
1 Insulation resistance of Multicore cables At the time of
commissioning
>50 M
Ohm
WITNESSED BY:- JE/SDO SIGNATURE -
ANNEXURE-EARTHING/MAIN/01
CHECK LIST FOR MAINTENANCE OF EARTHING SYSTEM AT GRID
SUBSTATION Name of
Grid: Date & Time
Season
Pre-requisite for Maintenance
Caution
Order/PTW
No.
T&P/materia
l/PPEs
Maintenance Activities
S.NO. BRIEF DESCRIPTION OF WORK Frequency Permissible
Values
Stat
us
Action
Taken
1 All Earth pits MONTHLY N/A
1 All Earth connections at Earth pits. HALF
YEARLY N/A
2 Check all equipments for double earthing HALF
YEARLY N/A
3 Check all earthing conductors for adequacy & proper tightness. HALF
YEARLY N/A
4 Check proper clamping of earthing pipe and earthing
conductor.
HALF
YEARLY N/A
5 Check numbering of all earth pits. HALF
YEARLY N/A
6 Check availability of Cast Iron lid for each earthing pit. HALF
YEARLY N/A
7 Check exposed portion of earth conductor for Galvanizing or
painting
HALF
YEARLY N/A
8 Check & ensure painting of Earth isolator box with Green
colour for fast identification
HALF
YEARLY N/A
9 Check that each multicore cable is grounded through cable
gland.
HALF
YEARLY N/A
10 Check and ensure that all power cables are earthed at one end
only
HALF
YEARLY N/A
11 Check and ensure all multicore cables are earthed at switchyard
end only or alternatively at one end only.
HALF
YEARLY N/A
12
Check and ensure that Substation building earth is connected to
separate earth pit / pits and then the same is extended to mesh
earthing in switchyard.
HALF
YEARLY N/A
13
Check and ensure that individual Transformer neutral is
connected to separate earth pit and then the same is extended to
mesh earthing in switchyard.
HALF
YEARLY N/A
14 All Earth connections at equipment mounting frames HALF
YEARLY N/A
15 All Earth pits resistance for Power / Distribution Transformer
neutral YEARLY < 5 Ohm
16 All Earth pits resistance for LAs YEARLY < 5 Ohm
17 Resistance of earth mesh YEARLY < 1 Ohm
18 Final Status and Remarks
WITNESSED BY:- JE/SDO SIGNATURE -
ANNEXURE-33 KV LINES /MAIN/01
CHECK LIST FOR MAINTENANCE OF 33 KV LINES
Sr.
no.
ITEM TO
BE
INSPECT
ED
BRIEF DESCRIPTION OF WORK FREQUEN
CY
Permissi
ble
Values
STAT
US
ACTI
ON
TAKE
N
1
Poles-
Steel
Wood
Cement
Damages/broken poles or for ground level erosion and
corrosions where the pole is not capable of safely
supporting its load.
Quarterly NA
2 Bowed or leaning poles due to improper guying or
overloading. Quarterly NA
3 Unauthorized attachments such as fencing, aerial wires
etc. Quarterly NA
4 Poles which are very much exposed to hitting/striking
of animals and bumping and scrapping by vehicles Quarterly NA
5 If the pole Number plate is still distinct Quarterly NA
6 Check the condition of foundation and attend it, if
necessary. Quarterly NA
7 Examine if pole requires painting of in case of
steel/wood poles Quarterly NA
1
Stays
Correct direction and proper angle of the stay Quarterly NA
2 Loose broken or any other damage done to stays Quarterly NA
3 Whether stay insulator is intact/whether stay is properly
earthed Quarterly NA
4 If stay rods are corroded. Attend the same if required. Quarterly NA
1
Cross
arms and
pole top
steel
works
If the cross-arms/clamps/knee has/have slipped. Quarterly NA
2 Bending of cross arms due to uneven tension Quarterly NA
3 Excessive rusting of the cross arms bracings etc. Quarterly NA
4 Cracked or splitting or the wooden cross-arms Quarterly NA
5 Loose or damaged bracings. Attend the same, if
required. Quarterly NA
1
Insulators
Broken or chipped porcelain flashover marks Quarterly NA
2 Tilted insulators Quarterly NA
3 Excessive deposit of dust/salt/coal and other pollution
clean the same. Quarterly NA
4 Excessive rusting of fittings, replace the same, if
required. Quarterly NA
1
Conductor
s and earth
wire
Examine, if securely tied to the insulator/pole/cross-
arms Quarterly NA
2 Proper sag, set right the same, if required. Quarterly NA
3 Proximity of trees and other objects including building
etc. Quarterly NA
4 Sufficient clearance between conductors and earth wire
and also from the ground Quarterly NA
5 Sufficient clearance from other electric/telephone lines
passing along below or above it. Quarterly NA
6 Earth wire is properly supported Quarterly NA
7 All the line guards are intact and installed where
necessary Quarterly NA
Sr.
no.
ITEM TO
BE
INSPECT
ED
BRIEF DESCRIPTION OF WORK FREQUEN
CY
Permissi
ble
Values
STAT
US
ACTI
ON
TAKE
N
8
Conductor
s and earth
wire
If joints in the jumpers and conductors appear all right Quarterly NA
9 Broken conductors strands Quarterly NA
10 Nicking near insulator neck/or near conductor clamps Quarterly NA
11 Bindings wire has not become lose and open Quarterly NA
12 Mid span joints have not cracked. Quarterly NA
13
All joints and jumpers of aluminum conductors have
proper clamps/jointing sleeves. Straight the same, if
required.
Quarterly NA
1
Jumpers
and other
line
accessorie
s
Proper supporting and jointing two ends of the jumpers
with suitable clamps. Quarterly NA
2 Sufficient clearance between jumpers on the 3-phases Quarterly NA
3 Sufficient clearance of jumpers from metal Quarterly NA
4 Provision of proper insulation of jumpers Quarterly NA
5 Signs of over-heating and burnings on jumpers and
other fittings. Quarterly NA
6 Loose/defective clamps jointing sleeves, bolts and nuts,
and other fittings. Quarterly NA
1
Tree
trimming
and bird's
nests etc.
Cut off the trees branches where necessary to maintain
a minimum clearance of 1.8m on each side of the line Half yearly NA
2 Remove all dead wood. Half yearly NA
3
Remove all bird's nests. (once before the monsoons or
earlier, if necessary) Half yearly NA
1
Stays
Tighten the loose stays. Annually NA
2 Replace the broken/damaged stays and stay bows Annually NA
3 Replace the broken stay insulator/recondition the Earth Annually NA
4
Provide sufficient barbed wire/cattle guards on the stay
to avoid rubbing of cattles Annually NA
1
Cross
arms
Replace the broken/splitted/cracked/bent cross arms
by new ones. Annually NA
2
Bring in position the slipped cross
arms/clamps/bracings. Annually NA
3
Paint the steel cross arms and bracings etc. If
excessively rusted. Annually NA
1
Insulators
and
fittings
Clean and check for cracked/chipped and
punctured insulators. Replace, where necessary. Annually NA
2
Examine for the surface contamination and
remove it by wiping with a soft cloth (do not use cotton
waste). If the deposit has set hard, a weak acidic
solution may be used.
The insulators be checked twice a year preferably or
before and after (monsoons) Annually NA
1 Conductor
s and
earth
wires
Tighten loose bindings and replace damaged ones. Annually NA
2
Examine for corrosion at the joints of
conductors and insulators. Clean and renew, where
necessary. Annually NA
Sr.
no.
ITEM TO
BE
INSPECT
ED
BRIEF DESCRIPTION OF WORK FREQUEN
CY
Permissi
ble
Values
STAT
US
ACTI
ON
TAKE
N
3 Examine closely for broken strands
particularly at the clamps and insulators due to
vibration and repair, where necessary. Annually NA
4
Examine general condition of the conductor
and earth wires i.e. for kinks, crushed spots over/under
tensioning, etc., and recondition, where necessary. Annually NA
5
Examine for any loose/cracked joints of
conductors in the mid span and recondition where
necessary. Annually NA
6
Examine for any loose/cracked joints slipping
of conductors from the clamps. Tighten all clamps and
fittings. Annually NA
1
Lightening
arrestor
Clean and examine insulators for cracks or
flashover. Replace, where necessary. Annually NA
2
Perform impulse voltage spark over test and
leakage current test to know the condition of
the arrester; replace in case of unsatisfactory
results. Annually NA
3 Keep records of test results. Annually NA
4
Check and tighten all line connections and
earth leads Annually NA
1 Earthing
System
Replace all broken earth leads and tighten others.
Measure earth resistance of various earths with
earth. Tester. In case of low values, recondition
them. Annually NA
2
Anti-
climbing
devices
and
danger
plates
etc.
Recondition the anti-climbing devices such as barbed
wire, locks, etc., paint and reprint the danger plated if
defaced. Annually NA
WITNESSED BY:- JE/SDO SIGNATURE -
CHECK LIST FOR MAINTENANCE OF 11 KV LINES
Sr.
no.
ITEM TO
BE
INSPECTE
D
BRIEF DESCRIPTION OF WORK FREQUE
NCY
Permiss
ible
Values
STAT
US ACTION TAKEN
1
Poles
Steel
Wood
Cement
Stays
Cross arms
Conductor
Insulator
Earthwire
Lightning
arrestor
Earthing
System
Same as recommended for the items as 33
KV lines in addition to the followings
Quarterly
/
Half
year/
Year
1
G.O.
Switchs
(with fuse
unit)
Check for the following:
A method for field
testing for switch
contacts with live line
consists in using an
insulated rod (for 11
KV) adjustable height
having at its upper end
a tallow candle fixed in
a clip Hold the candle
against the hot contact
for a few seconds &
then examine. If the
grease slightly melts,
mark the contact for
attention. If the grease
runs, the switch
requires early attention
and if it smokes,
dangerous condition is
assumed, the switch
required immediate
attention.
2 For smooth operation Quarterly
3
Evidence of over-heating burning,
corrosion/pitting on the switch contacts.
Quarterly
4 Broken or damaged insulators. Quarterly
5 Proper and tight earth connections. Quarterly
6
Fuse links for continuity, tightness of
connections and correct rating.
Quarterly
7 Proper locking arrangement. Quarterly
8 Proper alignment of switch contracts. Quarterly
9
Proper and complete fitting of male contacts
into the female ones.
Quarterly
10 Arcing horns are intact.
Quarterly
1
11 KV
Cable and
Cable
boxes.
Check for the following:
2 Proper supporting of the cable and the cable
boxes. Quarterly
3 Damaged insulators. Quarterly
4 Oil and compound leaks and that the cable
box is properly tippe up with the compound. Quarterly
5 Tight and intact connections. Quarterly
6 Proper earthing. Quarterly
7 Overall condition of the cable and joint. Quarterly
1 G.O.
Switch
(with fuse
unit)
Cleanliness: Clean all dust and other
deposits with neat and dry cloth.
Half-
yearly
(its
maintena
nce may
be done
even
earlier as
These points should be
particularly checked
when contacts are
replaced.
2
Switch contacts: (1) Check for the aliment,
adequate pressure and smooth operation and
adjust, where necessary. (2) Examine for
burning/over-heating or other damages.
Fixed and moving
contacts may be
dressed by using fine
file/fine sand paper.
Sr.
no.
ITEM TO
BE
INSPECTE
D
BRIEF DESCRIPTION OF WORK FREQUE
NCY
Permiss
ible
Values
STAT
US ACTION TAKEN
Recondition or replace, where necessary. the
functioni
ng of GO
Switches
is
generally
in
disorder
and is
always a
source of
trouble).
Use of rough sand
paper be avoided.
3
Insulators: (1) Check for cracks, chipping
and other defects, replace, where necessary.
(2) Remove dirt, coal and other pollutions
by wiping with soft cloth. Use weak acidic
solution, if the deposit has set hard.
Petroleum jelly/ white
Vaseline or other
suitable contact
lubricant should
applied on contacts
grease should be
applied on all the
moving parts.
4 Arcing Herms : Check if those are intact
and replace, if damaged/burnt.
5
Mechanism: Clean, examine and renew
worn out parts. Re-lubricate and check for
correct operation.
6 Fuse unit: Replace old fuses with new ones
of right type and capacity and proper length.
7
Main connections and Earthing: proceed as
described under separate heading of
‘Jumpers’ and ‘Earthing devices’.
8 General : check all hardware and tighten, if
needed.
1
11 KV
Cable and
cable
boxes
Clean and examine for damaged bushings Annually
2 Check for compound level, if there is
leakage.
Annually
3 Perform insulation resistance test,
recondition or replace, where necessary.
Annually
4 Keep continuous records of insulation
resistance.
Annually
CHECK LIST FOR MAINTENANCE OF LT LINES
Sr.
no.
ITEM TO
BE
INSPECT
ED
BRIEF DESCRIPTION OF WORK FREQUENC
Y
Permiss
ible
Values
STA
TUS ACTION TAKEN
1
Pole
Stay
Cross
arm
Conductor
Insulator
Connectors
Cable
Boxes
etc.
Same as recommended for these items under schedule
for HT Lines (Whether cobwebs, kite strings, etc.,
hanging on the conductor)
Four
Monthly
This becomes
source of heavy
leakage when wet.
1
LT
Switch
Check for the flowing:
2 If the switch with cover is intact. Monthly
3 If the cable/switch running hot. Monthly
4 Broken cut-outs. Monthly
5 Signs of over-heating/burning on contacts. Monthly
6 Proper size of fuse wire. Monthly
7 If the switch is properly earthed. Monthly
8 Safety from rain water etc. Monthly
1
LT
Switch
Check lead on the LT circuit and replace the LT
cable/LT switch by higher capacity one, where
necessary.
Half-Yearly
2 Replace the damaged LT Cable with new one of right
capacity. Half-Yearly
3 Examine the switch for smooth operation. Half-Yearly
4 Replace the burnt/cracked cut-outs. Half-Yearly
5 Recondition the switch contacts Half-Yearly
6 Replace the old fuses with new ones of right capacity. Half-Yearly
7 Tighten all connections. Half-Yearly
8
Ensure that the inlet of the cable into the switch is
plugged with plastic compound to avoid entry of rain
water. Refill, where necessary.
Half-Yearly
9 Clean off the cob-web and other nests etc., from the
inside of the switch. Half-Yearly
1
Poles
Stays
Cross
arm
Conductor
Insulator
Connectors
Cable
boxes etc.
Same as recommended for these items under schedule
for HT Lines.
One to two
yearly
(depending
upon the
volume of
work)
Annexure- AR-1
(To be filled by JUNIOR ENGINEER/Project Engineer)
1 Operational checks Status
i Switchgear ON/OFF through PTCC OK Not OK
ii Switchgear ON/OFF manual (in 'Sectionaliser/ RL series' only) OK Not OK
iii Mechanical Interlocks OK Not OK
iv
Switchgear tripping through Emergency Lever (in U Series
only) OK Not OK
v Position Indicator (Mechanical) OK Not OK
2 Electrical Test
a Local / Remote - ON / OFF OK Not OK
b LED indication on PTCC Breaker Close OK Not OK
c LED indication on PTCC Breaker Open OK Not OK
d
Electrical interlock - Enable / Disable switch OK Not OK OK
Not OK OK Not OK
e Battery voltage ( Aux supply should be turn off ) ( 24VDC ) OK Not OK
f Auxiliary supply Normal Abnormal
g Check/ Download WSOS history logs Yes No
h Current values on PTCC ( After switch ON ) OK Not OK
i
Voltage values on PTCC ( After switch ON ) OK Not OK OK
Not OK OK Not OK
j Pressure reading of SF6 on PTCC ( RL Type only ) OK Not OK
k Check PT fuse intactness and continuity OK Not OK
l ON / OFF operation through Battery OK Not OK
3 Environmental checks
a Visual inspection for missing parts OK Not OK
b Cleaning of PTCC panel, ACR ( dust etc ) OK Not OK
c Connection Check of Plugs and CAPM compartment OK Not OK
d Cable entry point sealed in PTCC OK Not OK
E Stress on bushing due to cable/conductor connection OK Not OK
f Method of Conductor connection on bushing OK Not OK
g Tie / clamp support to umbilical cable (control cable) OK Not OK
h Terminal Connectors OK Not OK
i Visual inspection of any damages OK Not OK
j Presence of Earthing OK Not OK
k Earthing ( Pit ) Resistance test results OK Not OK
l Tightening of Cable clamps / connectors to bushing OK Not OK
m Condition of Male/Female Pins on plugs (PTCC / S/G) OK Not OK
n Clearance of PT with Guard wire OK Not OK
o Presence of PT bushing insulated Caps OK Not OK
4 PTCC panel door intactness (window + Main door) OK Not OK
5 Lock of PTCC panel door OK Not OK
6 Condition of Electronic Module - OK Not OK
a. CAPM / SCEM / CCEM / OCPM OK Not OK
b. MDIM3 / MDIM2 OK Not OK
7 Status of battery cells terminals, links OK Not OK
8 Modem Functionality OK Not OK
Remarks:
Witnessed by:
Junior Engineer: S.D.O
Annexures DT-1
Check List for oil filled Distribution Transformers: Checked
(To be filled by Junior Engineer)
1) Check that the colour of the silica gel in the breather is blue.
2) Check the breather for any cracks, holes, transparency and oil in the oil cup.
3) Check for any signs of No arcing/pitting mark on Bus-bar & palm connector.
4) Ensure that there is no leakage of oil from gaskets, flanges, valves, radiators,
bushings etc. Ensure oil level of conservator & cleaning of glass of conservator.
5) Check that the bushing surface is clean.
6) Check the bushings for any crack or any chipping of porcelain.
7) Check the earthing of the tank cover to tank.
8) Check the condition of neutral & transformer body grounding
9) Ensure that the surface of radiator is clean.
10) Check the earthing of fencing (enclosure) with two separate earths.
Witnessed by:
Junior Engineer: SDO:
Annexures DT-2
Test Results:
(To be filled by Junior Engineer)
Test
Parameters
Limits Date of
Test
Actual value Remarks
IR test.
1. IR value shall be
equal for all three
phases for HT-E,
LT-E, HT-LT.
2. Normally IR value
shall be minimum
100 MΩ for HV &
50 MΩ for LV
windings at the the
temp of 50°C.
BDV
> 30 kV(avg) at 2.5mm
gap
Earth
resistance
Earth resistance shall be
less than 1Ω
Witnessed by:
Junior Engineer: SDO:
Annexures DT-3
Check List for Dry type Distribution Transformer: Checked
(To be filled by Junior Engineer)
1) Check that no dust on enclosure, doors & marshalling box.
2) Check the enclosure & marshalling doors are closed properly.
3) Check for working/setting for thermostat in marshalling.
4) Check for working and physical condition of DT energy meter.
5) Check for working of lamp in marshalling box.
6) Check the no dust deposition over active part.
7) Check the earthing of the enclosure at two places with separate earthing point.
8) Check the earthing of the neutral with two separate earthing points.
9) Check for working of exhaust fan.
10) Check there should not be any open space.
Witnessed by:
Junior Engineer: SDO:
Annexures DT-4
Test Results:
(To be filled by Junior Engineer)
Test
Parameters
Limits Date of
Test
Actual value Remarks
IR test.
1. IR value shall be
equal for all three
phases for HT-E,
LT-E, HT-LT.
2. Normally IR value
shall be minimum
100 MΩ for HV &
50 MΩ for LV
windings at the the
temp of 50°C.
Earth
resistance
Earth resistance shall be
less than 1Ω
Witnessed by:
Junior Engineer: SDO:
Annexures DT-5
Pre commissioning checks for oil filled Distribution Transformers: Checked
(To be filled by Junior Engineer)
1) Check that the colour of the silica gel in the breather is blue.
2) Check the breather for any cracks, holes, transparency and oil in the oil cup.
3) Check for any signs of No arcing/pitting mark on Bus-bar & palm connector.
4) Ensure that there is no leakage of oil from gaskets, flanges, valves, radiators,
bushings etc.
5) Check that the bushing surface is clean.
6) Check the bushings for any crack or any chipping of porcelain.
7) Check the earthing of the tank cover to tank.
8) Check the condition of neutral & transformer body grounding
9) Ensure that the surface of radiator is clean.
10) Check the earthing of fencing (enclosure) with two separate earths.
Witnessed by:
Junior Engineer: SDO:
Annexure DT-6
Test Results:
(To be filled by Junior Engineer)
Test
Parameters
Limits Date of
Test
Actual value Remarks
IR test.
1 IR value shall be
equal for all three
phases for HT-E,
LT-E, HT-LT.
2 Normally IR value
shall be minimum
100 MΩ for HV &
50 MΩ for LV
windings at the the
temp of 50°C.
Ratio Transformer turn
ratio test
MBT Magnetic Balance
test
BDV
> 30 kV(avg) at 2.5mm
gap
Earth
resistance
Earth resistance shall be
less than 1Ω
Witnessed by:
Junior Engineer: SDO:
Annexure DT-7
Pre commissioning checks for Dry type Distribution Transformer: Checked
(To be filled by Junior Engineer)
1) Check that no dust on enclosure, doors & marshalling box.
2) Check the enclosure & marshalling doors are closed properly.
3) Check for working/setting for thermostat in marshalling.
4) Check for working and physical condition of DT energy meter.
5) Check for working of lamp in marshalling box.
6) Check the no dust deposition over active part.
7) Check the earthing of the enclosure at two places with separate earthing point.
8) Check the earthing of the neutral with two separate earthing points.
9) Check for working of exhaust fan.
Witnessed by:
Junior Engineer: SDO:
Annexure DT-8
Test Results:
(To be filled by Junior Engineer)
Test
Parameters
Limits Date of
Test
Actual value Remarks
IR test.
1 IR value shall be
equal for all three
phases for HT-E,
LT-E, HT-LT.
2 Normally IR value
shall be minimum
100 MΩ for HV &
50 MΩ for LV
windings at the the
temp of 50°C.
Ratio Transformer turn
ratio test
MBT Magnetic Balance
test
Earth
resistance
Earth resistance shall be
less than 1Ω
Witnessed by:
Junior Engineer: SDO:
Annexure RMU-1
Check list –RMU
Sub-Division
Item Description Status
A Type of Substation
B 11 kV Switchgear/RMU
1 Make
2 Physical Condition
(a) RMU Covers
(b) Earth Bus Bar Status
3 SF6 Preassure Gauge Indication
4 Voltage Indicating LED's
5 Grounding
6 Rubber Mat
7 Fault Passage Indicator
Witnessed by:
Junior Engineer: SDO:
Annexure RMU-2
Check List:
(To be filled by JUNIOR ENGINEER/Project Engineer
1) Check the manometer for any signs of SF6 gas leakage.
2) Check the functioning of the breaker, isolator & earth switch.
3) Check the functioning of FPI.
4) Check the functioning of VPIS
5) Check the Earth Resistance
6) Check the cable tightness
Witnessed by:
Junior Engineer: SDO:
Annexure UG-1
Check List during Cable Testing Checked
1. Ensure cable is not live by Neon Tester.
2. The cable earthing is properly connected to Panel earth
3. The Panel earthing is properly connected to S/S Earth.
4. Ensure Cable Terminations are cleaned properly
5. Ensure Cable cores are earthed other than testing core
6. Ensure cable testing at Recommended voltage
Check during Rectification
1. Ensure caution tape, warning lights Boards & barricading
Provided at work site
2. Ensure cable laid at recommended depth
3. Ensure docketing done on cable & joints
4. Ensure backfilling done properly
Witnessed by:
JUNIOR ENGINEER/PO: SDO:
Annexure ABC-1
Check List
Check List during Cable Testing Checked
1. Ensure AB cable is not live by use of Neon Tester.
2. Ensure AB cable earthing is properly connected to Messenger
3. Ensure Messenger earthing is properly connected to Pole Earth.
4. Ensure AB Cable Terminations are cleaned properly
5. Ensure Cable cores are earthed other than testing core
6. Ensure cable testing at recommended voltage
Check during Rectification
1. Ensure caution tape, warning lights, barricading
Provided at work site
2. Ensure proper jointing done at fault sites.
3. Ensure Plastic Cable Ties are used to hold the joint
Witnessed by:
JUNIOR ENGINEER/PO: SDO:
Annexure-ERT-1
Check list- Earthing
Pre-requisite for Routine Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Earth resistance Tester
Cotton Rag
Routine Maintenance Activities
NATURE OF WORK Freq Permissible
Values Status
Action
Taken
Check and Clean
All Earth pits Twelve Months N/A
Check and Tight
All Earth connections at equipment
mounting frames Twelve Months N/A
All Earth connections at Earth pits. Twelve Months N/A
Measurement
All Earth pits resistance for HT/LT Feeder
Neutral Twelve Months < 5 Ohm
All Earth pits resistance Twelve Months < 5 Ohm
Resistance of Pole Twelve Months < 1 Ohm
General Checks
Check all equipments for double earthing Twelve Months N/A
Check all earthing conductors for
adequacy & proper tightness. Twelve Months N/A
Check proper clamping of earthing pipe
and earthing conductor. Twelve Months N/A
Check numbering of all earth pits. Twelve Months N/A
Check availability of Cast Iron lid for
each earthing pit. Twelve Months N/A
Check exposed portion of earth conductor
for Galvanizing or painting Twelve Months N/A
Check & ensure painting of Earth isolator
box with Green color for fast
identification
Twelve Months N/A
Check that each multicore cable is
grounded through cable gland. Twelve Months N/A
Final Status and Remarks
Witnessed by:
JUNIOR ENGINEER/PO: SDO:
Annexure- G.O.-1
Check List- G.O Switch
Sr No. Particulars Ok Not OK
1 Alignment of Male Female Contact
2 Condition of Post Insulator
3 Operating Rod
4 Earthing of G.O Switch
5 Condition of Arcing Horn
6 Condition of Operating Handle
7 Locking Arrangement
Witnessed by:
JUNIOR ENGINEER/PO: SDO:
Annexure- OH-1
Check List –OH Lines
Sr
No. Parameters Observations
1 Condition & size of GI wire. It should be 7/10 SWG OK Not OK Remarks
2
Condition of Guy/Egg Insulator, if any damage or
missing observed, should be fix/replace. OK Not OK
3
Condition of tension screw, if any damage observed
, it has to be changed otherwise to tighten the turn
buckle ,if required OK Not OK
4 condition of anchor hook OK Not OK
Visual Inspection
5
Condition of Disc Insulator, if there is any crack,
flash mark on the surface of the disc, disc should to
be change. OK Not OK
6
Condition of strain clamp of disc insulator, If any
crack or flash mark on surface, it has to be change OK Not OK
7
Condition of Pin insulator, if there be any flash
mark on the insulator surface, it has to be change
otherwise check the tightness with the spindle. OK Not OK
8
Condition of Pin insulator spindle, if any damage
or bend, to be change otherwise check the tightness
of the fixing nuts. OK Not OK
9
Condition of Top hamper, if any tilt observed at top
hamper it has to be straight or any damage occurred
to the metal part, it is to be change, otherwise check
the tightness of fixing nuts bolts. OK Not OK
10
Condition of the V-arm. if any damage occurred on
V-arm or on the fixing clamp, it is to be changed
otherwise check the tightness of the fixing Nuts,
bolts OK Not OK
11
Condition of channel-arm, if any damage occurred
on channel-arm or on the fixing clamp, it is to be
changed otherwise check the tightness of the fixing
Nuts, bolts OK Not OK
12
All metal part to be painted by Primer &Aluminium
paint for increasing the durability of life span OK Not OK
13 Visual inspection of bare conductor OK Not OK
14
Span length should be maximum 40m /50 m (Urban
/Rural) if the length larger than it , mid pole to be
provided. OK Not OK
15
Line should be sectioned at every 4/5 span apart, if
more it to be reduced to 4/5 span OK Not OK
16 Visual inspection of Earthing OK Not OK
17
Visual inspection of Guard wire- if any
damage/broken happened, it would be drawn by 4
SWG GI wire. OK Not OK
18
Inspection of Joints – all jumpers should be done by
conductor same as line conductor or higher rating &
joints to be done by suitable C-wedge connector/ PG
Clamp/D-clamp. Mid span joint to be to be done by
Suitable Sleeves & the joint is limited to 2 no per
span. OK Not OK
19 Anti-climbing device OK Not OK
Witnessed by:
JUNIOR ENGINEER/PO: SDO:
Annexure LT ACB
SN Parameter Points to be checked Finding
1 Physical
Condition
a) check ACB have cover and locked.
b) Check for any visual deformity/ flash
mark/ crack/ dust on arc chutes, arcing
contacts and moving contacts.
c)Check the point of entry of busbars into
the enclosure (The busbars should be
properly tapes and the entry should be
sealed with sealants like silicon grease)
d) Check tripping circuit, CTs, release (
if applicable).
e) Status of Enclosure to be checked (
damage/ rusting, etc)
2 Alignment
and Support
Structure
The ACBs placed on level structure and
secured properly to be checked-
3 Dressing and
Crimping of
Main &
Looping
cables
All incoming and out going cables to be
crimped and connected properly to the
incoming and outgoing busbars.
4 ACB
Earthing
Earthing to be checked
5 Safeguarding
of Bare
Terminals
Bakelite/ FRP separator plats used where
clearance are reduced are to be checked
Witnessed by:
JUNIOR ENGINEER SDO:
Annexure- LT UG Cable
Check List during Cable Testing Checked
1. Ensure cable is not live by Neon Tester.
2. The cable earthing is properly connected to Panel earth
3. The Panel earthing is properly connected to S/S Earth.
4. Ensure Cable Terminations are cleaned properly
5. Ensure Cable cores are earthed other than testing core
6. Ensure cable testing at Recommended voltage
Check during Rectification
1. Ensure caution tape, warning lights Boards & barricading
Provided at work site
2. Ensure cable laid at recommended depth
3. Ensure labelling done on cable & joints
4. Ensure backfilling done properly
Witnessed by:
JUNIOR ENGINEER/PO: SDO:
Annexure LT OH Conductor
SN Parameter Points to be checked Finding
1 Physical
Condition
(Visual
Checking for
Stay and
Line support)
a.Check the Condition & size of GI wire
(It should be 7/10 SWG)
b.Check the Condition of Guy/Egg
Insulator-
c. Check the Condition of tension screw
d.Check the condition of anchor hook
e. Check the Condition of Shackle
Insulator
f. Check the Condition of Pin insulator
spindle
g. Check the Condition of Top hamper
h. Check the Condition of the Double
line X-arm
i. Check all metal part to be painted by
Primer &Aluminium paint
2 Conductor
Inspection
j. Check if any damage occurred on the
conductor
k. Check for use of Line Spacer
l. Check for use of cradles
3 Earthing check for proper earth wire & Earthing
4 Joints &
Jumpers
check for proper Joints and Jumpers
5 Pole
Connections
i. Check for Cable mounting on over head
feeder
ii. Check for no of service cable form one
single pole & dressing of service cable
6 Configuratio
n of Line
Check for configuration of Line-
Vertical Configuration
Delta Configuration
Witnessed by:
JUNIOR ENGINEER SDO:
Annexure LT ABC
Check List during Cable Testing Checked
1. Ensure AB cable is not live by use of Neon Tester.
2. Ensure AB cable earthing is properly connected to Messenger
3. Ensure Messenger earthing is properly connected to Pole Earth.
4. Ensure AB Cable Terminations are cleaned properly
5. Ensure Cable cores are earthed other than testing core
6. Ensure cable testing at Recommended voltage
Check during Rectification
7. Ensure caution tape, warning lights, barricading
provided at work site
8. Ensure proper jointing done at fault sites.
9. Ensure Plastic Cable Ties are used to hold the joint
Witnessed by:
JUNIOR ENGINEER SDO:
Annexure LT Earthing
Name of LT Feeder:
Date & Time
Pole No-
Season - Summer/Winter:
Pre-requisite for Routine Maintenance Caution Order/PTW No. T&P/material/PPEs Earth resistance Tester Cotton Rag Routine Maintenance Activities
NATURE OF WORK Freq Permissible
Values Status
Action
Taken Check and Clean All Earth pits Twelve Months N/A Check and Tight All Earth connections at equipment
mounting frames Twelve Months N/A
All Earth connections at Earth pits. Twelve Months N/A Measurement All Earth pits resistance for LT Feeder
Neutral Twelve Months < 5 Ohm
All Earth pits resistance for LT ACB Twelve Months < 5 Ohm Resistance of Pole Twelve Months < 1 Ohm General Checks Check all equipments for double earthing Twelve Months N/A Check all earthing conductors for
adequacy & proper tightness. Twelve Months N/A
Check proper clamping of earthing pipe
and earthing conductor. Twelve Months N/A
Check numbering of all earth pits. Twelve Months N/A Check availability of Cast Iron lid for each
earthing pit. Twelve Months N/A
Check exposed portion of earth conductor
for Galvanizing or painting Twelve Months N/A
Check & ensure painting of Earth isolator
box with Green color for fast identification Twelve Months N/A
Check that each multicore cable is
grounded through cable gland. Twelve Months N/A
Final Status and Remarks
Witnessed by:
JUNIOR ENGINEER SDO:
Annexure LT Metering & Service Cable
Name of Consumer:
Date &
Time
Account No-
Sub-Division -
NATURE OF WORK Frequency Permissible
Values Status
Action
Taken
Any visible Cut mark or Puncture on
service cable 24 Months N/A
Checking all required information
written on meter box and are visible. 24 Months N/A
Whether Meter/MCCB is tightly fixed
or hanging 24 Months N/A
All Seals on MCCB & Terminals are
proper and not tampered 24 Months N/A
Consumer cable is at adequate height
while crossing the street/road (from
ground)
24 Months Min 5.8
Meters
Accuracy of Meter 24 Months ±3%
Witnessed by:
JUNIOR ENGINEER SDO:
Annexure LT Feeder Pillar
Name of Feeder Pillar Date
Type of Feeder Pillar Time
Feeder Name
NATURE OF WORK Frequency Permissible
Values Status
Action
Taken
Cable connection tightness 12 Months N/A
Replacement of sockets 12 Months N/A
Tagging of outgoing & incoming
feeders 12 Months N/A
Earthing of Feedar& Service
Pillar (values to be provided) 12 Months N/A
Proper Cable earthing 12 Months N/A
Locking of doors 12 Months N/A
Replacement of fuse 12 Months N/A
Replacement of fuse base 12 Months N/A
Cleaning of Feeder Pillar 12 Months N/A
Condition of Plinth 12 Months N/A
Danger Plate 12 Months N/A
Witnessed by:
JUNIOR ENGINEER SDO:
Annexure LT Fuse Board
Name of DT Date
DT Rating Time
Feeder Name
NATURE OF WORK Frequency Permissible
Values Status
Action
Taken
LV cable from DT shall be routed
through palm/bi-metallic connector. 12 Months N/A
Insulated cable from DT to fuse board
shall pass through DT meter CTs rings. 12 Months N/A
Only insulated cable shall be used for
connecting LV side of transformer to
fuse board.
12 Months N/A
Laying of cable from LV side of DT to
fuse board shall be separated using cleat
(wooden/PVC).
12 Months N/A
Proper size thimbles/Lugs used at cable
end to join it to fuse board. 12 Months
N/A
Lugs/Thimbles shall be fixed using
proper size crimping tool (hammering of
Lugs/Thimbles must be avoided because
this leads to weakening/breaking of
strands of cable).
12 Months
N/A
Proper color tape being used for taping
at lugs/thimbles. 12 Months N/A
Fuse Board shall be installed on Bakelite
sheet. 12 Months N/A
Height of fuse board 12 Months Min 6 Feet
Check for tightness of fuse wire.
12 Months N/A
Check for any oil & dust from fuse wire
and aluminum parts
12 Months N/A
Only insulated cable shall be used for
connecting fuse board to feeder line. 12 Months N/A
Laying of insulated cable form fuse
board to feeder line shall be properly
routed using clamps to fix it from
hanging.
12 Months N/A
Measurement of load of LT side of DT
(Phase wise) 12 Months
As per rating
of DT
R Phase
Y Phase
B Phase
Fuse wire Detail
Size
Rating (Amp)
Witnessed by:
JUNIOR ENGINEER SDO: