DUM DUM – KAVI SUBHAS(in operation )

5/24/2013

Construction of Dum Dum – Mahanayak Uttam

Kumar (Tollygunge) 16.45 Km was sanctioned on

01.06.1972.

First METRO Service commenced on 24.10.84

between Esplanade - Netaji Bhavan (3.4 Km)

covering 5 stations.

Different sections were opened progressively and

finally the complete stretch DumDum to Tollygunge

(16.45 Km) with 17 stations became operational on

27.9.95.

Mahanayak Uttam Kumar (Tollygunge) – Kavi

Subhas (New Garia) 8.5 Km was sanctioned in 1999.

Tollygunge to Kavi Subhas (9 Km) with 6 stations

was commissioned in two phases in Sept’ 2009 &

Oct’2010. 2

Page 3: M rly presentation_22.5.13

SALIENT DETAILS

OF

METRO RAILWAY

KOLKATA

5/24/2013 3

Page 4: M rly presentation_22.5.13

GAUGE : 1676 mm

LENGTH IN OPERATION : 25.107 Km

o Underground : 15.2 Km

o Viaduct : 10 Km

o Surface : 1.8 Km

MAX. SPEED : 55 Kmph

STATIONS : 23

o Underground : 15

o Elevated : 6

o Surface : 2

DISTANCE BETWEEN STATIONS:

o Average : 1.020 Km

o Maximum : 2.151 Km (Dum Dum – Belgachia)

o Minimum : 0.60 Km (Central – Chandni Chowk)

GENERAL FEATURES

5/24/2013 4

Page 5: M rly presentation_22.5.13

5/24/2013 5VIEW OF PLATFORM AT PARK STREET METRO STATION

Page 6: M rly presentation_22.5.13

PROJECTS BEING EXECUTED BY METRO RLY5/24/2013

Page 7: M rly presentation_22.5.13

5/24/2013

Page 8: M rly presentation_22.5.13

SUMMARY OF SANCTION METRO PROJECTS/SURVEYS

No. of

Projects/

Surveys

StatusLength

(Km)

Anticipat

ed Cost (

Cr.)

Expend.

upto Mar’13

(Cr.)

Throw-

Forward as

on 1.4.13

(Cr.)

Budget

Outlay

2013-14

(Cr.)

1

Section

under

operation

25.10 2809.03 3070.11 - -

5

Projects

under

execution

87.83 12236.22 424.81 11811.41 505.00

13Sanctione

d surveys312.00 - - -

Total 424.93 15045.25 3494.92 505.00

5/24/2013

8

Page 9: M rly presentation_22.5.13

SANCTIONED METRO PROJECTS

ProjectLength

(Km)

Year of

sanction

Anticipated

Cost (Cr.)

Executing

Agency

Dum Dum -

Baranagar4.47 2010-11 411.06

M.Rly: 2.54 Km

RVNL: 1.93 Km

Noapara - Barasat 18.13 2010-11 2582.55 M.Rly

Joka – BBD Bag –

Diamond Park18.73

2010-11 &

2012-132913.51 RVNL

New Garia – Dum

Dum Airport32.00 2010-11 4259.50 RVNL

Baranagar –

Barrackpur /

Dakshineswar

14.50 2010-11 2069.60 RVNL

Total

M.Rly: 20.67 Km

RVNL: 67.16 Km

87.83 12236.22

5/24/2013

9

Page 10: M rly presentation_22.5.13

EXTENSION FROM DUM DUM (0.0 Km) TO NOAPARA (2.54 Km)

AS PART OF DUM DUM – BARANAGAR (4.50 Km) PROJECT

Yr. of

incl. in

Budget

Anti. cost

Expn.

upto

March’13

2013-14Progress

(%age)Budget

Outlay

Expn. upto

30.04.13

2010-11 182.24 Cr 181.22 Cr 12 Cr 0.33 100%

5/24/2013

10

Page 11: M rly presentation_22.5.13

Scope of works

• Metro Rly to construct- DumDum to Noapara (2.54km)

Finishing work in progress & expected to be completed by

April’2013

• RVNL to construct- Noapara to Baranagar (1.9km)

Estimate: Sanctioned

Salient features of work to be executed by Metro Rly.

• Double Line viaduct from DumDum to Noapara

• One elevated station at Noapara (km 2.0)

Status of works

• All works completed.

• CRS has inspected the section for commercial

operation on 19.5.13, the authorization of CRS

expected shortly. 5/24/2013

11

Page 12: M rly presentation_22.5.13

Status of Electrical works

• 33 KV receiving sub station at NOAPARA under

commissioning

• Conductor rail under phase -1 has been commissioned

• Escalators and lifts are under commissioning

• Electrification of NOAPARA station under progress.

5/24/2013

Status of S & T works

• Route setting panel interlocking of NOAPARA goomty

station commissioned for non passenger movement

on 24.03.13.

12

Page 13: M rly presentation_22.5.13

5/24/2013

VIADUCT NEAR NOAPARA STATION PLATFORM

Page 14: M rly presentation_22.5.13

5/24/2013

Girders being placed

NOAPARA STATION BUILDING

Page 15: M rly presentation_22.5.13

METRO EXTN. NOAPARA (0.0 Km) - BARASAT (18.13 Km.)

5/24/2013

Page 16: M rly presentation_22.5.13

Project Yr. of

incl. in

Budget

Anti. cost Expn.

upto

March’13

2013-14 Progress

(%)Outlay Exp. upto

30.04.13

Noapara-

Airport2010-11 184.83 Cr. 102.86 Cr. 13 Cr. 2.39 57%

Noapara-

Barasat2010-11 2397.72 Cr. 40.92 Cr. 170 Cr. 3.73 1.9%

Scope:

The scope of work involves extension of Metro line from Noapara to

Barasat via Airport with 5.83 km underground alignment.

5/24/2013

16

Page 17: M rly presentation_22.5.13

Status of Estimates:

Estimates for both works sanctioned.

Material Modification for

Additional station at Michael Nagar (at km 9.62 u/g ) & underground construction

including stations at Airport, Birati & New Barrackpur is under preparation.

Barasat Depot including cost of private land, 37 lines, carshed & service buildings

at a cost of Rs 631 Cr. has been sent to Rly. Bd. lr. dt. 5.2.13. Observations of

Railway Board dated 06.03.13 have been replied vide letter dt. 26.4.13.

Salient Features:

Elevated viaduct:12.32 Km, Underground: 5.83 Km

Barasat Car Depot: For stabling of 37 rakes

Details of stations

1 Dumdum Cantt. Km 2.80 Elevated

2 Jessore Road Km 5.12 On surface

3 Airport Km 6.23 Underground

4 Birati Km 7.80 Underground

5 New Barrackpur Km 10.36 Underground

6 Madhyamgram Km 12.31 Elevated

7 Hridaypur Km 14.93 Elevated

8 Barasat Km 16.87 Elevated

5/24/2013

17

Page 18: M rly presentation_22.5.13

Notification under Section 10 of Metro Railway (Constr. of Works) Act

1978 for acquisition of 2.72 ha. Private land published in The Gazette

of India on 13.12.12. The notification has been published in local

newspapers on 19.05.13.

Acquisition of private land of 32.46 Ha for Barasat Car depot required

which will be processed after sanction of MM.

Metro Rly. requires Right of Way in 124.119 sqm and permanent

transfer of 1.226 sqm in R.S plot No. 2248, 2251, 2252, 2253 in Mouza

Dum Dum Cantt JL No.13 sheet No 3 of Govt of W.B for constr. of

viaduct & pier.

GM Metro Rly. has requested Chief Secretary Govt. of W.B (letter dated

19.03.13) to intervene to expedite the transfer of land. ADM & District

Land & Land Reforms Officer/Barasat has submitted report for

consideration to Joint Secy., L&LR Deptt., Govt. of W.B. (letter dt.

8.4.13). Jt. Secy, L & LR Deptt has been requested to accord

permission for Right of Way and transfer of land (letter dt 26.4.13).

5/24/2013

LAND ACQUISITION

18

Page 19: M rly presentation_22.5.13

STATUS OF WORKSNoapara Km 0.0 – End of Circular Rly ramp. 3.86 km (3.86 km):

o Noapara – Br. No. 3 (1.70 Km):

Contract for construction of viaduct awarded to M/s Tantia Constr. in Aug.’10

(Cost Rs. 73 Cr.)

Work gets suspended between 15th June to 15th Oct. due to restriction

imposed by Irrigation Deptt. for working in Bagjola Khal during monsoon. Now

work is in full swing.

Two overhead electric lines (440V) of CESC were to be shifted near Motish Roy

Br. (Km 0.66), Rs. 32 lakhs deposited with CESC on 6.11.12 & both lines shifted

during Feb.’13.

o Br. No.3 – End of Circular Rly. ramp (2.16Km):

Contract awarded to M/s Senbo in Jun’11 (Cost Rs. 127Cr.)

Work in progress in available stretch of 300m at DumDum Cantt. yard.

Work between Br. No. 3 to Dum Dum Cantt. was held up since one year due to

800 encroachments. 127 shops & 105 hutments in a length 200m has been

shifted to alternate Rly. land & work started at this location during Jan.’13.

Work between Dum Dum Cantt. & end of ramp will require diversion of Jessop

siding & closure of Circular Rly. line which is held up since Sept.’11 for non-

shifting of 30 nos. encroachers.5/24/2013

19

Page 20: M rly presentation_22.5.13

STATUS OF WORK

o End of Circular Rly Ramp Km.3.86 – Jessore Road

Km 5.12 (1.26 km):

Acquisition of land (400.115 Sqm) in the area of

Jessop siding is in progress for which Gazette

Notification under Section 10 published on 13.12.12

and published in local newspapers on 19.5.13.

Tender for construction from end of ramp to Jessore

Road including Jessore Road station (single line

viaduct upto Jessore Road crossing) is under

preparation.

5/24/2013

20

Page 21: M rly presentation_22.5.13

STATUS OF WORKo Jessore Road Km 5.12 – New Barrackpur Km. 10.36 (5.24 km):

Construction in the stretch from Jessore Road to Belgharia Fly over is to be

done by RVNL alongwith construction in Kavi Subhash - Airport project which

is overlapping with this portion.

NOC from AAI for the stretch from Belgharia Expressway Fly over to New

Barrackpur received on 2.07.12.

Proposal for transfer of land 2.67 Ha, ROW 2.09 Ha & shifting of structures

(G+0: 21 nos & G+1: 2 nos) between km 4.57 to Km 5.22 & km 7.32 to km.

10.575 sent to AAI on 13.8.12. AAI has desired that Rly. should submit

comprehensive proposal including requirement of RVNL also.

Airport Director during meeting on 24.11.12 with Secy/ Transport & Spl

Secy./Transport advised to keep Birati stn. & its approaches also

underground. Accordingly revised alignment submitted to AAI on 28.2.13.

Alignment plan for construction along Jessore road was earlier being dealt by

NHAI, but now being dealt by PWD (NH Div.) & accordingly proposal has been

sent to PWD (NH Div) on 3.10.12 for approval, same has been revised keeping

Birati Stn. underground & incorporating observations of SE/NH (Design &

Planning Circle) & sent to SE/NH (Design & Planning Circle) & Airport Director

on 28.02.13. Approval awaited. Chief Secy. Govt. of WB requested by GM Metro

Rly. to intervene to expedite approval ( letter dated 19.03.13).5/24/2013

21

Page 22: M rly presentation_22.5.13

o New Barrackpur to Madhyamgram (1.51 Km)

Subsequent to meeting with Ch. Secy GoWB on

13.12.12, the construction of ramp/pier inside the design

waterway of Noai Khal (Km 10.75-Km12.12) has been

agreed to in principle by Irrigation Deptt. of Govt. of WB

during the meeting with Hon’ble MIC Irrigation &

waterways Deptt on 14.12.12. Proposal has been

prepared accordingly and sent to Irrigation Deptt on

27.12.12 for its formal approval and observations replied

on 01.03.13. Chief Secy. Govt. of WB requested to

intervene to expedite approval ( letter dated 19.03.13).

Further a meeting was held with CE/Design/Irrigation on

17.4.13 & he advised that proposal is not technically

suitable. However, report would be sent to W.B. Govt. to

take a final decision.5/24/2013

STATUS OF WORK

22

Page 23: M rly presentation_22.5.13

o Madhyamgram Km 12.20 – Barasat Km 17.90 (Km 5.70km): The alignment in this stretch is in E. Rly land along Sealdah-Bongaon suburban

line.

Contract for construction of viaduct (3 km) & 2 Stations at Barasat & Hridaypur

awarded to M/s L&T at a cost of Rs. 153.98 Cr. in Oct.’11.

Shifting of utilities ( S&T cables) completed in 900m length (LC 11 to ROB)

at Barasat, but only 300m length is encroachment free where 24 piles out of

66 done. Further 44 piles done bet. ROB & Goods Shed, work stopped by

L&T since July’12.

Further tender for shifting S&T cables in 800m length (bet. ROB & North cabin)

is under finalization by SDAH Divn. but only 400m length bet. ROB & Goods

Shed encroachment free will be available for work.

Tender for shifting of HT/LT lines is under finalization by Metro Rly.

Contract for constr. of viaduct (2.7Km) & 1 stn. at Madhyamgram was awarded

to M/s L&T at a cost of Rs. 130 Cr. on 19.2.12.

Test pile completed but no work is possible due to encroachments.

As site is not available, contract closed without liability on either side.

Construction is possible in 700m (in two stretches) only between LC 11 &

Barasat Goods Shed as the encroachments (794 shops & 1090 hutments) in the

balance portion are to be shifted. However, construction is not being allowed in

vacant Rly. land also by local encroacher demanding compensation/

rehabilitation.

5/24/2013

STATUS OF WORK

23

Page 24: M rly presentation_22.5.13

PROGRESS OF WORKS (Noapara - End of Circular Rly. Ramp)

Item Total

scope

Prog.

upto

Mar.’12

2012-13 Upto

date

prog

Remarks

Qty.

Planned for

the year

Prog.

upto

(Mar.’13)

Land

acquisition(Ha)Nil

Piles (Nos.) 2509 730 534 500 1230

Contract awarded &

works in progress

along Bagjola khal &

in available 300m

stretch near Dum Dum

Cantt. station. Balance

site is not available

due to encroachments

on Rly. land.

Piles caps

(Nos.)210 55 44 34 89

Piers (Nos.) 210 40 48 26 66

Pier Cap (Nos.) 210 33 54 29 62

Casting of

girders (Nos.)824 163 216 44 207

Launching of

girders (Nos.)824 2 80 20 22

Stn. Bldgs. 1 - - 17% 17%

BLT (Km) 13.3 - - - -5/24/2013

24

Page 25: M rly presentation_22.5.13

PROGRESS OF WORKS (Madhyamgram – Barasat )

ItemTotal

scope

Prog.

upto

Mar.’12

2012-13Upto

date

prog

RemarksQty.

Planned for

the year

Prog.

upto

Mar.’13

Land

acquisition (Ha)2.76

Gaz. Not. under Sec.10

issued.

Piles (Nos.) 1278 20 300 55 75

Contract awarded but

work stopped as site not

available due to

encroachments on Rly.

land.

Piles caps(Nos.) 204 - 50 - -

Piers (Nos.) 204 - 50 - -

Pier Cap (Nos.) 204 - 14 - -

Casting of

girders (Nos.)203 - 14 - -

Launching of

girders (Nos.)203 - - - -

Stn. Bldgs. 3 - - - -

BLT (Km) 11.4 - - - - Tender to be invited.

5/24/2013 25

Page 26: M rly presentation_22.5.13

Location Between Ch. & Length Approx No. of

structures

Municipa

lity

Leg.

Assbly

Const.

Parl.

Constitu

encyHuts Shops

Between Bridge.3 – Dum

Dum Cantt. Stn.

Km 1.70 – 2.65 (0.95km) 800 - South

Dum Dum Dum

Dum

Dum

DumAlong Jessop siding Km 3.30 – 3.80 (0.50km) 30 - Dum Dum

Total for Dum Dum area 1.45 Km 830 -

Madhyamgram (MMG) Stn Km 12.2 – 12.5 (0.3km) 24 202

Madhya

mgram

Madhya

mgram

Barasat

MMG flyover –LC No. 9 Km 12.5 - 13.55 (1.05 Km) 294 22

LC No.9- Rly Br. No.13T Km 13.55 – 14.2 (0.65 Km) 188 49

Rly. Br. No.13T - HHR Km 14.2 – 14.74 (0.54 Km) 189 32

Barasat BarasatHridaypur Station Km 14.74 – 15(0.26 Km) - 163

HHR stn - LC No.11 Km 14.9 - 15.6 (0.700 Km) 181 -

LC No.11 - BT flyover Km 15.6 - 16.5 (0.900 Km) 108 -

BT Flyover - L.C.No.13 Km 16.5 – 19.2(2.7Km) 106 326

Total for Barasat - MMG 7 Km 1090 794

Irrig. Land: Bagjola khal Km 0.73 - 1.7 (0.97 Km) 20

Irrig. Land: Noai khal Km 10.74 - 12.11 (1.37 Km) 120

Total for Irrig. Land: 2.34 km 140

Total 10.79 km 2060 794

5/24/2013

DETAILS OF ENCROACHMENTS

Page 27: M rly presentation_22.5.13

EFFORTS MADE FOR SHIFTING OF ENCROACHMENTS

o 30 encroachments along Jessop siding

The issue is being pursued with Chairman & Vice Chairman Dum Dum Municipality

since Dec 2011

On 20.6.12 Vice Chairman , Dum Dum Municipality has submitted two estimates

costing Rs.49,03,762/- based on PWD SOR for:

Construction of temporary hutments at a cost of Rs.12,92,657.

Construction of permanent structures at original location after construction of

viaduct at a cost of Rs. 36,11,105.

o 800 encroachments from Br. No. 3 to Dum Dum Cantonment (0.7km)

The issue is being constantly pursued with local MP, Municipal authorities, District

authorities etc.

In Jan’12, Chairman/South Dum Dum Municipality stated that Rly land on opposite

side should be developed by Rly by filling and then the encroachers would shift

on their own.

However in July’12 Chairman, South Dum Dum Municipality raised the issue of

monetary compensation/construction of hutments in similar fashion as

demanded for 30 no. hutments along Jessop siding (Rs 1.75 lakhs per hutment).

o 1884 encroachments between Madhyamgram & Barasat upto LC No. 13

The issue is being constantly pursued with Municipal authorities, District

authorities etc. Last meeting with DM/Barasat held on 2.4.13 & 4.4.13.

No positive result has been achieved even after continuous meetings/ discussions.5/24/2013

Page 28: M rly presentation_22.5.13

5/24/2013

ASSISTANCE REQUIRED FROM STATE GOVT.

Home Deptt for removal of encroachments

• 30 encroachments along Jessop siding & 800 on E. Rly. land in Br.No. 3 -

DDC

• Alternate vacant low land of E. Rly. on other side of track identified to

shift 800 hutments, further vacant Rly. land available nearby to shift 30

hutments.

• 1884 encroachments on E.Rly. land in MMG – BT LC-13 (Km 12.2 – 19.3 in 7.1

km)

• Both issues being pursued with local people representatives & DM 24-

Parganas (N). Chief Secy. Govt. of WB requested by GM Metro Rly. to

intervene to resolve the issue ( letter dated 19.03.13).

L & LR Deptt for transfer of 1.226 sqm of land to Metro Rly right of way in

124.119 Sqm. (3 plots) Govt. land.

• Land of Dum Dum Cant. Mouza was earlier transferred to HMV for

industries but nothing was constructed, 1.226 sqm of land is required to

be transferred to Rly. & permission for right of way in 124.119 Sqm. is

required. Chief Secy. Govt. of WB has been requested by GM Metro Rly.

to intervene to expedite the transfer of land ( letter dated 19.03.13). ADM

& District L&LR Officer/Barasat vide letter dt. 8.4.13 has submitted report

for consideration to Joint Secy., L & LR Deptt., Govt. of W.B. 28

Page 29: M rly presentation_22.5.13

5/24/2013

ASSISTANCE REQUIRED FROM STATE GOVT. PWD (NH) for approval of alignment

• Alignment between Belgharia Expressway Flyover to Noai Khal (3.5 km)

is partly on PWD(NH) land along Jessore Road. Alignment plan as per N.O.C.

requirement of AAI was submitted on 3.10.12. Meeting was held with CE/NH

on 12.11.12, but now Airport Director has requested for underground

alignment at Birati on account of proposed taxiway, proposal along Jessore

road revised and sent to SE/NH on 28.02.13.

WBSEDCL for shifting of OH HT/LT lines in Madhyamgram - Barasat

• Shifting of OH lines (11 KV: 3.5 km, 33 KV: 0.25 km, 415 V: 20 km) is to be

executed by Elect. Deptt. of Metro Rly. under supervision of WBSEDCL.

Tender opened on 8.7.12 (cost Rs. 2.1 Cr.) but discharged. Fresh tender

opened on 22.3.13 & under finalization.

Barasat Municipality for shifting of 150mm dia water supply pipe line

• 500m of pipe line between Goods Office to North Cabin Barasat is to be

shifted by Barasat Municipality for which revised estimate of Rs. 1.29 Cr.

submitted by Municipality for acceptance of M.Rly & depositing funds.

Madhyamgram & Barasat Municipality for diversion of storm water drain

• The scheme for diversion of drain (300m at MMG & 200m at BT) finalized

with the Municipalities & AEN/E.Rly./BT. Work would be done by M.Rly. for

which tender finalized but work will start only after shifting of S&T cables.29

Page 30: M rly presentation_22.5.13

5/24/2013

ASSISTANCE REQUIRED FROM DIFFERENT AGENCIES

Jessop for slewing of siding & acquisition of land

• 400.115 Sqm vacant land of Jessop to be acquisitioned for which

proposal for Sec. 10 notification issued. For slewing of Jessop

siding, 30 encroachments on E.R land to be shifted.

AAI for transfer of land & permission for shifting of structures

• Proposal for transfer of AAI land 1.338 Ha, ROW 4.779 Ha and

shifting of structures in between Km 4.57 to 10.583 (excl. Km 5.18 to

7.34 to be executed by RVNL as underground with ramp at both

ends) has been submitted to Airport Director on 13.8.12, but

requested to submit complete proposal including RVNL portion.

RVNL has been requested for the same.

30

Page 31: M rly presentation_22.5.13

Metro Projects being executed by RVNL5/24/2013

Page 32: M rly presentation_22.5.13

METRO PROJECTS BEING EXECUTED BY RVNL

BBD Bag – Joka & upto Rake Maintenance Depot at

Bakrahat (16.72 km) alongwith Joka-IIM-Diamond Park

extension (2 Km) sanctioned as Material Modification

New Garia – Dum Dum Biman Bandar via Rajarhat (32 km)

Baranagar – Dakshineswar – Barrackpore (14.5 km)

Noapara – Baranagar (1.93 km)

5/24/2013

32

Page 33: M rly presentation_22.5.13

JOKA – BBD BAG PROJECT 18.72 Km

Yr. of

sanc.

Anticipated

cost

Expn. upto

3/2013

2013-14Overall

financial

progressOutlay

Expn. Upto

30.04.13

%age fin.

Progress in

year

2010-11 2913.5 Cr 276.25 Cr 45 Cr N.A. - 9%

TDC: Joka –Majherhat : June 2014, Majerhat-BBD Bag: March 2016

5/24/2013 33

Page 34: M rly presentation_22.5.13

ACQUISITION OF PRIVATE LAND FOR MTC. DEPOT AT JOKA

Notification under Section 10 of Metro Rly. (Constr. of Works)

Act 1978 published for acquisition of 22.73 Ha (161plots) on

25.3.12

•30 claim cases (54 plots) being heard by Competent Authority

for finalisation of claims

•Some of the claimants are not attending the hearings. Ad-hoc

court of Competent Authority is being held near Joka/Bakrahat

from16.04.13 to ensure greater participation of the claimants in

the hearings for early finalization of compensation.

Notification under Section 10 of the Act for acquisition of

additional 1.73 Ha. issued on 25.03.13.

5/24/2013

34

Page 35: M rly presentation_22.5.13

JOKA – BBD BAG PROJECT 18.72 KMEstimate:

Three part estimates have been sanctioned

•for viaduct from Joka to Majerhat,

•for 7 stations upto Majerhat and

•for Joka depot.

Scope

The project involves construction of

10.4 km viaduct from Mominpur to Joka to Diamond Park

6.32 km underground constr. from Mominpur to BBD Bag

15 stns. (out of which 5 stns. are underground).

Status of work

Contract for construction of viaduct & 7 Stns. buildings

between Joka & Majerhat awarded and work in progress.

Tender for construction of Mtc. Depot opened on 18.8.12 but

discharged due to non availability of land.5/24/2013

35

Page 36: M rly presentation_22.5.13

PROGRESS OF WORKS

Item UnitTotal

Scope

Prog.

Upto

Mar'13

2013-14Upto

date

prog.

RemarksQty.

Planned

for year

Prog.

Upto

April’13

Land Acqu. Hect 25

Sect. 10 notification issued for 22.73 Ha & Hearings being

conducted for settlement of Claim cases. For another

1.73 Ha notification under Sec 10 notification issued.

Piles No. 1384 1076 287 23 1099

Work in progress

Pile cap No. 294 248 80 5 253

Piers No. 294 248 80 - 248

Pier cap No. 272 230 86 6 236

Erection of

viaduct No. of

span

Nos. 321 85 236 13 98

BLT km 18 Tender yet to be invited.

St. Bldg. Nos 7

279/1024 piles & 38/194

pile caps & 25/194 piers

completed.

Mtc. Depot at

Joka Nos 1

Tender for construction

of depot has been

discharged due to non

availability of land

5/24/2013

Page 37: M rly presentation_22.5.13

5/24/2013 PIERS CONSTRUCTED ALONG D.H.ROAD

Page 38: M rly presentation_22.5.13

5/24/2013

GIRDERS BEING CAST AT CASTING YARD AT PAILAN

Page 39: M rly presentation_22.5.13

5/24/2013GIRDERS BEING ASSEMBLED FOR VIADUCT OVER D.H.ROAD

Page 40: M rly presentation_22.5.13

5/24/2013METRO VIADUCT OVER D.H.ROAD

Page 41: M rly presentation_22.5.13

ISSUES OF CONCERNConstruction in land of KoPT

• Permissive possession of land of KoPT received, but M.Rly. had reservations

regarding conditions for leasing 18000 sqm land (30 yrs with non renewal option) &

KoPT was requested (lr. dt 21.11.12) to process for 99 yrs lease with renewal option.

After series of meetings, KoPT has agreed to process for 99 years lease and has

sent the terms and conditions for acceptance of Metro Rly. (letter dated 3.5.13).

• Permission to be obtained to construct in Govt. Mint premises.

• Alternative land for relocation of Rehabilitation India bldg. (in KoPT area) to be

identified for constr. of Majerhat Stn.

Construction in land of MoD

• No works can be planned between Mominpur-BBD Bag section unless alignment

and land transfer is agreed by Ministry of Defence.

• Meeting held with offg. GOC Bengal HQ Area on 10.9.12 regarding swapping of land

of Min. of Defence (8710 Sqm.) with equal value of land of Rly. and permission for

Metro construction in premises of Army Institute of Management and Maidan area.

• Proposal for transfer of the Defence land has been forwarded from Eastern

Command HQ to Army HQ of MoD at New Delhi (letter dated 17.10.12). The

observations of Defence Authorities (letter dated 21.01.13) have been replied by

RVNL to GOC Bengal HQ area (letter dated 26.03.13). As per meeting at MoD on

15.4.13, Committee of officers of Defence, Railway & RVNL to be formed to resolve

the issue.

Removal of encroachments

• Removal of hutments (about 250) for the purpose of construction of stations.5/24/2013 41

Page 42: M rly presentation_22.5.13

5/24/2013

NEW GARIA (KAVI SUBHAS) – BIMAN BANDAR 32 KM TDC: Mar’2016

Year of sanction 2010-11

Anticipated cost Rs. 4259.5Cr

Expn upto 3/13 Rs. 400.25

Cr.

20

13-1

4

Outlay Rs. 250 Cr.

Expenditure

upto April.’13

N.A.

% fin. Prog in

year

-

financial progress

(%)

9%

42

Page 43: M rly presentation_22.5.13

5/24/2013

Estimate

Part Estimate for Viaduct from New Garia to Chingrighata

and Chingrighata to Biman Bandar sanctioned at the cost

of Rs.497.16 Cr. and 716.10 Cr. respectively.

Part detailed estimate of balance work under preparation.

Scope of work

The project involves construction of

32 km viaduct terminating underground at Airport.

23 elevated stns. & one underground stn. at Airport.

Status of work

Contract for construction of viaduct for 25 km from Kavi

Subhash to Rabindra Tirtha awarded.

Constr.in progress in Km 2-4, 12-13,17-19 & 21-23.

NEW GARIA (KAVI SUBHAS) – BIMAN BANDAR 32 KM

43

Page 44: M rly presentation_22.5.13

5/24/2013

Item UnitTotal

Scope

Prog.

Upto

Mar’13

2013-14

Upto date

prog.Remarks

Planned

for year

Prog.

Upto

April‘13

Land Acqn. Hect. 2.61 NIL 21.40 NIL NIL

Gaz. Notification

under Sec.7

published on 25.03.13

Piles No. 6134 1665 2150 157 1822

Work in progress

Pile cap No. 851 144 260 20 164

Piers No. 851 69 260 33 102

Pier cap No. 851 12 260 17 29

Casting of

Segments No. 8100 289 1600 97 386

Launching

of

Segments

No. 8100 NIL 300 NIL NIL

BLT km 50 Tender to be invited

Stn. Bldg. Nos. 24

Detailed Estimate

under approval.

Tender to be invited

after sanction of

estimate.

PROGRESS OF WORKS

Page 45: M rly presentation_22.5.13

5/24/2013

PIERS UNDER CONSTRUCTION ALONG E.M BYEPASS

Page 46: M rly presentation_22.5.13

5/24/2013

PIERS UNDER CONSTRUCTION NEAR NICCO PARK

Page 47: M rly presentation_22.5.13

5/24/2013GIRDER SEGMENTS BEING CAST IN CASTING YARD AT NEWTOWN

Page 48: M rly presentation_22.5.13

5/24/2013

CASTING YARD AT BARASAT

Page 49: M rly presentation_22.5.13

Permission for construction along E.M. Bypass

Underground utilities to be shifted by KMDA

Permission for construction in Wetlands near New Garia

NOC required from Fisheries Deptt. for construction of viaduct across fish ponds.

The Standing High Power Committee has issued order (dated 26.02.13) that under

no circumstances filling up of water body can be considered and advised to

choose another alignment without disturbing the existing the water bodies and

the ecological balance of the area. RVNL has examined the issue and Member

Convenor of High Power Committee requested for consideration of the proposal

since the proposal of Metro Rly. Is the only feasible alternative (letter dated

3.4.13).

Transfer of land of MoD

Transfer of 4447 sqm of Defence land of Bihar Warriors and Defence Accounts

Establishment by the side of WIPRO flyover is required.

A meeting was held with offg. GOC Bengal HQ Area on 10.9.12 regarding

swapping of land of MoD with equal value of land of Railways.

Proposal for transfer of the land has been forwarded from Eastern Command HQ

to Army HQ of MoD at New Delhi (letter dated 17.10.12).

The observations of Defence Authorities (letter dated 21.01.13) have been replied

by RVNL to GOC Bengal HQ area (letter dated 26.03.13). As per meeting at MoD

on 15.4.13, Committee of officers of Defence, Railway & RVNL to be formed to

resolve the issue.5/24/2013

ISSUES OF CONCERN

49

Page 50: M rly presentation_22.5.13

Year of

sanct.

Anticipated

cost

Exp. Up to

Mar’13

2013-14Overall

Financial

Prog. (%)

Outlay Exp upto

30.04.13

%age fin.

Prog. in

year

2010-11 228.82 Cr. 86.50 Cr. 2 Cr. N.A. - 38%

EXTENSION FROM NOAPARA TO BARANAGAR 1.93 Km

5/24/2013

50

Page 51: M rly presentation_22.5.13

Estimate

Sanctioned for viaduct & stn. building.

Scope of Work

Construction of 1.93 km viaduct & Baranagar station building

Status of work

Contract for constr on of viaduct & Stn. Building awarded. Work in progress

EXTENSION OF METRO RAILWAY FROM NOAPARA–BARANAGAR 1.93 Km

Issue of concern

• 450 nos. of hutments in E. Rly. land to be re-located.

• Revised MoU agreed by Irrigation Deptt. is to be executed shortly. 5/24/2013

Item UnitTotal

Scope

Prog.

Upto

Mar’13

2013-14 Upto

date

prog.

RemarksPlanned

for year

Prog. Upto

April’13

Land Acqn. Hect. NIL NIL NIL NIL NIL

Piles No. 270 50 220 11 61

Work in progress

Pile cap No. 45 2 43 NIL 2

Piers No. 45 2 43 NIL 2

Pier cap No. 45 1 44 NIL 1

Girder span 45 8 37 NIL 8

Deck slab span 45 NIL 45 NIL NIL

BLT km 4 Tender to be invited

Stn. Bldg. Nos. 1 Drg under approval

51

Page 52: M rly presentation_22.5.13

TDC: Mar’2016

5/24/2013

BARANAGAR – DAKSHINESWAR & BARANAGAR-BARRACKPUR 14.5 KM

Year of sanction 2010-11

Anticipated cost Rs.

2069Cr.

Expn upto 3/13 Rs. 62.50

Cr.

20

13-1

4

Outlay Rs 10 Cr

Expenditure

upto Apr.’13

N.A.

% fin. Prog in

year

-

financial progress

(%)

3%

52

Page 53: M rly presentation_22.5.13

5/24/2013

Baranagar – Dakshineswar & Baranagar-Barrackpore 14.5 KMEstimate

Part estimate for Baranagar - Dakshineswar sanctioned at a cost of Rs. 208.14 Cr

Scope of Work

Construction of 14.5 km viaduct & 11 nos. station buildings

Status of work

Contract for constr on of Baranagar- Dakshineswar viaduct (2km) & Dakshineswar

Stn. Building awarded. Work in progress

Contract for identification of underground utilities, felling of tress on alignment &

widening of road etc. in Baranagar – Barrackpur awarded.

Item UnitTotal

Scope

Prog.

Upto

Mar’13

2013-14Upto date

prog.RemarksPlanned

for year

Prog. Upto

April’13

Land Acqn. Hect. NIL NIL NIL NIL NIL

Piles No. 324 135 189 NIL 135

Work in progress

Pile cap No. 54 22 32 NIL 22

Piers No. 54 22 32 NIL 22

Pier cap No. 54 17 37 NIL 17

Girder span 50 13 37 1 14

Deck slab span 50 NIL 50 NIL NIL

BLT km 3.7 Tender to be invited

Stn. Bldg. Nos. 1 123/373 piles cast

53

Page 54: M rly presentation_22.5.13

Closure of 60” and 42” water supply pipe lines under the central verge OF

B.T Road for construction of viaduct:

MOU signed between KMC, Metro & RVNL on 21.10.11

KMC had given the target date of closure of 60” & 42” pipeline as

December, 2012.

KMC has commissioned the new 64” pipeline in Sept. 2012.

The pipeline disconnections are to be done by KMC.

Transfer of land of State Govt. in Governor’s Estate for construction of

Barrackpore Stn.

The matter is being pursued with Home Deptt., Govt. of W.B.

Sanction for additional 4 stations

The proposal of RVNL for providing additional 4 stations at a cost of Rs

250 Cr. has been sent to Rly Bd ( lr. dated 31.7.12) for sanction and the

observations of Rly. Bd have been replied (lr. dt 5.12.12).

5/24/2013

ISSUES OF CONCERN

54

Page 55: M rly presentation_22.5.13

ASSISTANCE REQUIRED

Development of vacant E. Rly land for relocation of encroachers:

Proposal for development of Rly land (Rs 2.55 Cr) & payment of

shifting charges for relocation of 1920 encroachers on Rly land @ Rs

10000 per family along Noapara-Barasat alignment duly approved by

GM/Metro Rly. has been submitted to Rly Bd. at a total cost of Rs 4.47

Cr. for approval. (lr No. MRTS/W-90/48 dt 6.12.12). Observations of

Rly. Bd. (letter dated 01.02.13) have been replied (letter dated

12.03.13).

Sanction for increase in Abstract cost of Maintenance Depot at Joka

by Rs 299.99 Cr

Proposal was sent to Rly Bd (lr. Dt 22.5.12) & the observations of Rly

Bd have also been replied (lr. Dt 22.9.12). Observations of Railway

Board (letter dated 08.03.13) have been replied by RVNL (letter dated

18.03.13 )

5/24/2013

Page 56: M rly presentation_22.5.13

ASSISTANCE REQUIRED

Approval of MoD for swapping of 13,155 sqm of Defence land with land

of E. Rly for Joka-BBD Bag & New Garia- Airport Metro projects under

construction:

Subseqent to meeting with Secretary MoD with CRB on 7.2.12, the

proposal of Railway dated 11.9.12 for swapping of MoD land with equal

value land of E. Rly. at Bagjola and Kanchrapara already under

occupation of MoD was sent to GOC/HQ Bengal Area which has been

forwarded to Eastern Command HQ (letter dated 13.9.12) and to Army

HQ at New Delhi (letter dated 17.10.12) . The observations of Defence

Authorities (letter dated 21.01.13) have been replied by RVNL to GOC

Bengal HQ area (letter dated 26.03.13). As per meeting at MoD on

15.4.13, Committee of officers of Defence, Railway & RVNL to be

formed to resolve the issue.

Sanction for additional 4 stations

The proposal of RVNL for providing additional 4 stations for

Baranagar – Barrackpore at a cost of Rs 250 Cr. has been sent to Rly

Bd ( lr. dated 31.7.12) and the observations of Rly. Bd have been

replied (lr. dt 5.12.12). 5/24/2013about

Page 57: M rly presentation_22.5.13

EXPENDITURE UNDER PH 81 FOR PROJECTS UNDER EXECUTION BY METRO RLY. & RVNL

(FIG IN CR. RS)

5/24/2013

ProjectYear of

sanct.

Anticipated

cost

Exp.

upto 3/12Exp. 12-13

Total Exp.

upto 3/13BG 13-14

DumDum-Tolly.

Ph-11972 1716.95 1804.06 8.77 1812.83 1.00

Tollygunge- Garia

Ph-2

1999-

20001092.08 1214.59 42.69 1257.28 2.00

DumDum-

Noapara09-10 182.24 93.40 87.82 181.22 12.00

Noapara-Airport 09-10 184.83 60.27 42.59 102.86 13.00

Total 3176.10 3172.32 181.87 3354.19 28.00

Noapara-Barasat 10-11 2397.72 21.88 19.04 40.92 170.00

Total (M. Rly.) 5573.82 3194.20 200.91 3395.11 198.00

Circular Railway2000-

2001573.78 165.75 1.09 166.84 24.00

Metro Projects

(RVNL) 10-11,9471.43 275.50 550.00 825.50 307.00

Total for MTP 15619.03 3635.45 752.00 4387.45 529.00

Page 58: M rly presentation_22.5.13

EXPENDITURE UNDER PH 81 FOR PROJECTS UNDER EXECUTION BY RVNL (FIG IN CR. RS)

5/24/2013

PB

No.Project

Year of

sanct.

Anticipated

cost

Expn. upto

3/12

Expn in

12-13

Expn. till

3/13BG 13-14

62BBD Bag - Joka –

Diamond Park

2010-11 &

12-132913.50 106.25 170.00 276.25 45.00

64New Garia – Dum

Dum Airport2010-11 4259.50 100.25 300.00 400.25 250.00

65

Baranagar-

Barrackpore &

Dakshineswar

2010-11 2069.60 32.50 30.00 62.50 10.00

60Noapara-

Baranagar2010-11 228.82 36.50 50.00 86.50 2.00

Total for projects

being executed by

RVNL

9471.42 275.20 550.00 825.20 307.00

Page 59: M rly presentation_22.5.13

5/24/2013

SURVEYS FOR METRO PROJECTS

Page 60: M rly presentation_22.5.13

5/24/2013

Page 61: M rly presentation_22.5.13

Sl.

NoSurvey Yr. of sanct. Present status

1Barrackpore - Kalyani

(32km) 2010-11Report sent to Rly. Bd. in Feb’13 & report

shelved vide Bd’s letter dt. 14.5.13.

2Joka – Mahanayak

Uttam Kumar (10km) 2010-11Report sent to Rly. Bd. in Dec’12 & report

shelved vide Bd’s letter dt. 14.3.13.

3

Joka – Diamond

Harbour (35km) 2010-11

Report sent to Rly. Bd. in Nov’12.

Observations of Board dt. 13.2.13 under

compliance.

4

Barasat to

Barrackpore via State

Highway 2 (12Km) 2010-11

Observation on Final report sent to

RITES for compliance on 10.4.13

5Madhyamgram to

Barrackpore (16km) 2010-11Report sent to Rly. Bd. in Mar’13 & report

shelved vide Bd’s letter dt. 14.5.13.

PET SURVEYS IN PROGRESS FOR METRO CONNECTIVITY

5/24/2013 61

Page 62: M rly presentation_22.5.13

Sl.

NoSurvey

Yr. of

sanct.Present status

6

Santragachi – Shalimar

– Bally Halt –

Chandannagar. (50

Km)

2010-11

Report sent to Rly. Bd. in Feb’13 &

report shelved vide Bd’s letter dt.

14.5.13.

7

Basirhat to Mh. Uttam

Kumar/Kavi Subhash

(70km)

2010-11

Comments on draft report sent to

RITES for incorporation in final report.

8Howrah Maidan – Belur

(8km) 2010-11 Report sent to Rly. Bd. in Feb.’13.

9

Baruipur – Kavi

Subhash (13km) 2011-12

Comments of Metro Rly. on draft report

sent to RITES for incorporation in final

report.

10

Howrah Maidan –

Santragachi –

Dhulagarh (13 km)

2011-12

Comments of Metro Rly. on draft report

sent to RITES for incorporation in final

report.

PET SURVEYS IN PROGRESS FOR METRO CONNECTIVITY

5/24/201362

Page 63: M rly presentation_22.5.13

Sl. No Survey Yr. of Sanct. Present status

11

Budge Budge – Ruby

Hospital via Taratala

Road (24 Km.)

2012-13Draft Report received, under

examination of Metro Railway

12

Kolkata Terminal –

Karunamoyee (Salt Lake)

(7 Kms.)

2012-13Works to be executed by RITES,

Field work commenced.

13Howrah Maidan to

Dankuni (12km)2012-13 Work to be executed by RITES.

14Dankuni to Srirampur via

Singur (18km)2012-13 Work to be executed by RITES.

PET SURVEYS IN PROGRESS FOR METRO CONNECTIVITY

5/24/2013

63

Page 64: M rly presentation_22.5.13

THANK YOU

Page 65: M rly presentation_22.5.13

ENCROACHMENTS IN BETWEEN BR NO- 3 & DDC STN.5/24/2013

Alignment of Noapara – Barasat Line

65

Page 66: M rly presentation_22.5.13

ENCROACHMENTS NEAR WEST SIDE OF DDC STN.5/24/2013

Alignment of Noapara – Barasat Line

66

Page 67: M rly presentation_22.5.13

ENCROACHMENTS NEAR DDC STATION5/24/2013

Alignment of Noapara – Barasat Line

67

Page 68: M rly presentation_22.5.13

ENCROACHMENTS NEAR RAMP OF AIRPORT LINE 5/24/2013

Alignment of Noapara – Barasat Line

68

Page 69: M rly presentation_22.5.13

5/24/2013

Alignment of Noapara – Barasat Line

Hutments

ENCROACHMENTS NEAR HRIDAYPUR STATION69

Page 70: M rly presentation_22.5.13

ENCROACHMENTS NEAR GATE NO 11 NEAR BARASAT5/24/2013

Alignment of Noapara – Barasat Line

70

Page 71: M rly presentation_22.5.13

ENCROACHMENTS OPPOSITE OF BARASAT WHARF 5/24/2013

Alignment of Noapara – Barasat Line

71

Page 72: M rly presentation_22.5.13

ENCROACHMENTS IN BETWEEN BARASAT & L-XING - 11

5/24/2013

Alignment of Noapara – Barasat Line

72

Page 73: M rly presentation_22.5.13

5/24/2013

Alignment of Noapara – Barasat Line

ENCROACHMENTS AT MADHYAMGRAM STATION73

Page 74: M rly presentation_22.5.13

Expenditure for MTP during last 3 years

5/24/2013

0

100

200

300

400

500

600

700

2009-10 2010-11 2011-12

111 122

38933

242

Expenditure in Cr.

Railway RVNL

631

The expenditure by Railway has increased by 218% in 2011-12 over 2010-11

155

74

Page 75: M rly presentation_22.5.13

Expenditure for Passenger Amenities during last 3

years

5/24/2013

0

2

4

6

8

10

12

2009-10 2010-11 2011-12

2.76

6.94

11.24

Expenditure in Cr.

151% increase

62% increase

75

Page 76: M rly presentation_22.5.13

Financial status for MT Projects being executed by Metro Rly.

Sl.

No

Project Yr. of incl. in

PB

Ant. Cost

(Cr.)

Expn. till

31.3.11

(Cr.)

Expn. in

11-12

(Cr.)

Outlay

2012-13

(Cr.)

1.

(a)

Dum Dum –

Tolly-New Garia

1972/

1999

MAC: 2445

Dep.: 364.03

MAC:

2572.09

Dep.:

189.45

257.11 110

(b) Dum Dum –

Baranagar

2010-11 409.77 51.85 64.05 170 (Rly.)

+ 150

(RVNL)

(c) Int. of Airport

line

2010-11 184.83 14.48 45.79 170

Total: 3403.63 2827.87 366.95 600

2. Noapara-Barasat 2010-11 2397.72 0 21.88 1050

Total 5801.35 2827.87 388.83 1650

3. Circular Rly. 1999-00 573.78 165.43 0.33

(M.Rly.)

51.0

(E.Rly)5/24/2013 76

Page 77: M rly presentation_22.5.13

Expected expenditure in 2012-13 for MT Projects by Metro Rly.

Project

Budget outlay (in Cr.) Expected expenditure (in Cr.)

Total Civil Elect S&T Civil Elect. S&T Total

Dum Dum –

Tolly-New

Garia

110 20 55 35 10 15 35 60

Dum Dum –

Baranagar

170+ 150

(RVNL)

130 30 10 85 20 5 110 +

150

(RVNL)

Integration of

Airport line

170 125 40 5 60 18 2 80

Total 450+ 150

(RVNL)

275 125 50 155 53 42 250 +

150

(RVNL)

Noapara -

Barasat

1050 650 350 50 250 30 - 280

Grand Total 1650 1075 475 100 405 83 42 680

5/24/2013 77

Page 78: M rly presentation_22.5.13

Details of expected Civil Engg. expenditure for MTP works in 2012-13

Project Contract/ Item Expected Expn. Status of work

Tolly-Garia Misc. 10 Cr Work in progress

Noapara-

Baranagar

Senbo (Civil/1882 )+ Misc 65 Cr Work in progress

BLT with Rail 600MT 20Cr Tender under finalisation

RVNL works 150Cr

Total 235Cr

Noapara-

Airport

Tantia (Civil/1885) 27Cr Work in progress

Senbo (Civil/1936)+ Misc. 33 Cr Work in progress

Total 60Cr

Noapara-

Barasat

As for NOA-Airport 60Cr Work in progress

L&T (Civil/1935)+Misc 80Cr Work in progress

L&T (Civil/1948) 50Cr Work in progress

Land Acquisition 40Cr.

Shifting of utilities 10Cr

Ramp -Madhyamgram 10Cr Tender to be invited

Total 250Cr

Grand Total 555 Cr

5/24/2013 78

Page 79: M rly presentation_22.5.13

Location

Pvt Area to

be acquired

(Sqm)

Pvt building affected

G+0 G+1 G+2 & above

Bridge no 3 –

Dum-Dum cant

3312 - 3 -

New Barrackpur

to

Madhyamgram 19050 37 15 -

Barasat fly over

to LC-13 5111 38

(21)

30

(24)

18

(17)

Total 27473 75 48 18

5/24/2013

( ) Figure in bracket shows the number to be avoided subject to some condonations.

Details of acquisition of land/properties under process

79

Page 80: M rly presentation_22.5.13

DIS

TAN

CE

Dai

ly t

icke

t Ko

lkat

a

Met

ro

SMA

RT

CA

RD

Rs

50

0KO

LKAT

A M

ETR

O

KOLK

ATA

MIN

I BU

S

WES

T B

ENG

AL

GO

VT

B

US

KOLK

ATA

PR

IVAT

E B

US

DM

RC

SM

AR

T C

AR

D

5 Km 4.00 2.19 6.00 6.00 6.00 10.80

10Km 6.00 3.65 7.00 6.00 6.00 14.40

15Km 8.00 5.12 9.00 7.00 7.00 16.10

20Km 10.00 6.58 10.00 7.00 7.00 18.90

25Km 12.00 8.04 11.00 9.00 9.00 20.70

30Km 14.00 9.50 X 10.00 10.00 22.50

COMPARATIVE FARE CHART in Rs.