Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

Embed Size (px)

DESCRIPTION

Luigi Serio Global tuning And DFBs commissioning Powering Cool-down (Big gain expected) (2-3 wks w.r.t 9 wks)

Citation preview

Page 1: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

Luigi Serio

CRYOGENICS PERFORMANCE AND OPERATION

L. Serio, on behalf of the

LHC Cryogenics Operation andCryogenics Performance Panel

Page 2: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

2Luigi Serio

Contents

• Introduction on cooling down and commissioning time

• Tuning loops adjustment & CV910 puppets – acquired knowledge and expected improvement

• Measured recovery time after quenches vs. theoretical expectations. DFBs filling

• Availability study for cryogenic system - can system components or related services be improved to maximize overall availability

• Improvement of He quality with new compressor. Translation to other sectors

• Vacuum minor leaks' impact on 1.9 K stability - improved strategy for GLPT in 45/81

• Time to repair a fault occurring just before the week-end: is it adequate for running LHC?

• Is recovery time after problems resource dependant? If so, can extra resource be made available when required eg weekends, nights?

• Interlocks: New PIC-Cryo channels

• Is it likely that if multiple sectors are commissioned, a cryo problem in one sector will not affect other sectors – thus allowing effort to be put elsewhere?

Page 3: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

Luigi Serio

Global tuning

And

DFBs commissioning

PoweringCool-down

(Big gain expected)(2-3 wks w.r.t 9 wks)

Page 4: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

4Luigi Serio

LHC Cryogenics: duration of cool-down phases

DesignLHC 7-8Final

9 d21 d

3 d14 d

1 d14 d

1 d21 d

80 K

20 K

4.5 K

1.9 K

Total

DesignLHC 7-8Final

DesignLHC 7-8Final

DesignLHC 7-8Final

DesignLHC 7-8Final

14 d / 2 wks70 d / 10 wksELQA

14 d

4 d

3 d

7 d

28 d / 4 wks

Excluding ELQA or extra-works :

Sketches intended to illustrate achievements and ultimate expectations

S. Claudet - Jul’07

Page 5: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

5Luigi Serio

Data for LHC scheduling purposes

• First time a given cryoplant type is used:4-5 , 8-1 , 3-4 , 7-8: 8 wks + ELQA

• Second time a given cryoplant type is used:5-6 , 6-7: 6 wks + ELQA

• For 2008 onwards:4-5 , 3-4: 4 wks + ELQA

• Warm-up:Complete sector: 4 wks the first time (Design: 2 wks)QRL + some cells: 2 wks

Proposed durations with expected learning effects to be checked autumn 2007

S. Claudet - Jul’07

Page 6: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

6Luigi Serio

Tuning loop adjustments

• June 18: Simultaneous, sawtooth ramping of D2 and Q4

Page 7: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

7Luigi Serio

Tuning loop adjustments

1.85

1.86

1.87

1.88

1.89

1.9

7/07/20070:00

7/07/20076:00

7/07/200712:00

7/07/200718:00

8/07/20070:00

8/07/20076:00

8/07/200712:00

8/07/200718:00

9/07/20070:00

LQTCG_11L8_TT821LBBRP_11L8_TT821LBARA_11L8_TT821LQNCE_10L8_TT821LBBRG_10L8_TT821LBARE_10L8_TT821Regulation Temperature

[K]

inlet magnets cell

outlet magnets cell

Page 8: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

8Luigi Serio

Valves: Flow caracteristics

Installed R ~ 25

New R ~ 100Large sensitivity gain

Page 9: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

9Luigi Serio

Availability: From 7-8 to others

DFBMs

Cryo Maintain LSS: 85% (Since 1st May)

DFBAs

Cryo Maintain ARC: 66% (Since 1st June)

Target LSS: 90%(incl. time lost for quench recovery)

Target ARC: 80%(incl. time lost for quench recovery)

Page 10: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

Luigi Serio

Page 11: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

Luigi Serio

Quench recovery for one quadrupole

Quench 720 A => TTregulation + 20 mK

Quench 2000 A => TTregulation + 200 mK & 5 minutes for Cryostart (2 K)

Quench 6500 A => TTregulation + 1.3 K & ~ 40 minutes for Cryostart (< 2 K)

New : Quench 2 x 6500 A => TTregul + 4 K & 2h30 for Cryostart (< 2 K)

=> No effect on cold compressorsNB : Cryostart recovery time not yet optimised (presence output limit high on JT valve to limit overshoot)

1.8

2.3

2.8

3.3

3.8

4.3

4.8

5.3

5.8

6/27/200712:00

6/27/200712:28

6/27/200712:57

6/27/200713:26

6/27/200713:55

6/27/200714:24

6/27/200714:52

6/27/200715:21

Page 12: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

12Luigi Serio

Recovery Time after Limited Resistive Transitions

• More than 14 cells or full sector recovery up to 48 hours• In case of fast discharge (even w/o quench) 2 h recovery (heating due to eddy currents).

Page 13: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

13Luigi Serio

Interlocks: New PIC-Cryo channels

• For operation reasons a cryo-start signal for 60 Amps will be implemented taking into account beam screen temperature (heat intercept) and eventually the thermal screen temperature

• Details to be discussed with system owner and PIC team

• To be implemented already for sector 4-5

Page 14: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

14Luigi Serio

Helium quality for distribution

• Improvement of He quality with for other refrigerators (sectors)

Problem only for ex-LEP cryoplants from Air Liquide for which the sub-cooler was just made for isothermal refrigeration (LEP) and not for non-isothermal refrigeration (LHC)

Problem identified Autumn’06

Proposal received for modification, but no agreed yet

The change of refrigerator did not show big impact on commissioning. Major gain to be expected in pseudo liquefaction mode when re-filling after a stop

Page 15: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

15Luigi Serio

Vacuum minor leaks

• No major problems for stability /cooling power with the levels accepted in sector 7-8

• Can have (depending on the level) some impact on recovery time

• More problematic is the leak (no connection) of the Y tube in the bayonet heat exchanger– Can still function with adjacent cell but increase in recovery of cryo start

conditions (cooldown)

Page 16: Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

16Luigi Serio

Time to repair a fault outside working hours

• Time to repair a fault occurring just before the week-end: is it adequate for running LHC?

=> We are not running the LHC we are commissioning it and cryogenics is part of the commissioning …

• Is recovery time after problems resource dependant? If so, can extra resource be made available when required eg weekends, nights?

Efforts put on control logic (long term) rather than on manpower (short term) Furthermore resources need to be trained or be expert in the domain for most of

the problems encountered Efforts and intervention are anyway already performed during the weekends and

nights even if you do not realize it

• Is it likely that if multiple sectors are commissioned, a cryo problem in one sector will not affect other sectors – thus allowing effort to be put elsewhere?

=> YES, machines and teams independent