Long Term Construction

Embed Size (px)

Citation preview

  • 8/3/2019 Long Term Construction

    1/6

    Long Term construction

    On January 2, 2008, JGG Builders Corp. of I locos enters into a contract to construct a building for P

    40,000,000. During the construction period many change orders are made to the original contract. All of

    the changes were accepted by both the customer and the contractor. The following schedule

    summarizes the change orders in 2008:

    Cost Incurred Estimated Costs Contract

    In 2008 to Complete Price

    Basic Contract 8,000,000 28,000,000 40,000,000

    Change order # 1 50,000 50,000 125,000

    Change order # 2 - 50,000 -

    Change order # 3 300,000 300,000 600,000

    Change order # 4 125,000 - 100,000

    Under the percentage of completion method, what is the gross profit to be recognized on December 31,

    2008 (Rounded to the nearest peso)?

    a. P 907,828 b. P 888,889 c. P 909,063 d. P 970,830

    In 2006, Builders agreed to construct a commercial building at a price of P 1,000,000. South Builders

    uses the percentage of completion method of recognizing revenue on long term construction projects.

    The data relating to the projects from 2006-2008 are as follows:

    2006 2007 2008

    Cost Incurred each year 280,000 320,000 185,000

    Estimated Cost o complete 520,000 200,000 -

    Billings Date 150,000 400,000 1,000,000

    Collection of billings date 120,000 320,000 940,000

    What is the amount of gross profit to be recognized in 2007?

    a. 80,000 b. 78,500 c. 85,000 d. 90,000

    Using the above information, what is the balance of construction projects net contract billings account

    of south builders December 31, 2007 balance sheet?

    a. 350,000 b. 300,000 c. 550,000 d. 380,000

    Using the above information, assuming the company uses the zero profit method of recognizing revenue

    from the project, what is the balance of the construction in progress account net of contract billings as

    of December 31, 2007?

    a. 200,000 b. 250,000 c. 350,000 d. 300,000

    North Construction Company uses the percentage of completion method of recognition gross profit on

    long term construction contracts. The company started work on the two contracts during 2007. Data

    relating to the two contracts are given below:

    Contracts price Actual cost 12/31/2007 estimated cost to complete

    Contract 1 P 1, 800,000 P 450,000 P 450,000

    Contract 2 1, 350,000 262,500 487,500

  • 8/3/2019 Long Term Construction

    2/6

    In 2008, contrast 3 was started for a contract prize of P 2, 700,000. As of December 31, 2008, the

    following data are available:

    Actual cost 1/1/07-12/31/08 Estimated Cost to Complete

    Contract 1 840,000 210,000

    Contract 2 540,000 360,000

    Contract 3 540,000 960,000

    How much income is to be recognized in 2008?

    a. 1,302,000 b. 432,000 c. 642,000 d. 270,000

    Using the information above, what is the balance of the construction in progress account as of

    December 31, 2008?

    a. 3,222,000 b. 3,942,000 c. 1,920,000 d. 2,562,000

    On July 1, 2006, summer construction Corporation contracted to build an office building for JG Inc., Inc.

    for a total price of 975,000. Data relating to the project from 2006-2008 are as follows:

    2006 2007 2008

    Contract Cost 75,000 600,000 1,050,000

    Estimated Cost to complete 675,000 400,000 -

    Billings to JG Inc. 150,000 550,000 275,000

    Summer construction corp uses the zero profit method.

    What is the balance of the construction in progress account net of billings at December 31, 20007?

    a. P 125,000 due to JG Inc

    b. P 125,000 due from JG Inc

    c. P 25,000 due from JG Inc

    d. P 25,000 due to JG Inc

    Assuming the use of the Percentage of Construction method, how much is the gross profit (loss) to be

    recognized in 2007?

    a. (47,500) b. 47,500 c. (22,500) d. 22,500

    West Construction company recognized gross profit of P 31,500 on its long term project what has

    accumulated costs of P61,250. To finish the project, the company estimates that it has to incur

    additional cost of P122,500. Billings ,made were 40% of the contract price. What is the balance of the

    CIP net of billings?

    a. 18500 liability b. 18,550 asset c. 50,050 asset d. 50,050 liability

    Marlboro Construction company, Inc. entered into a construction contract in 2007 that called for a

    contract price of P 9,600,000. At the beginning of 2008, a change order increased the initial contract

    price by 480,000. The company uses the percentages of completion method. The following data is

    available:

    2007 2008

    Cost incurred to date 4,920,000 8,640,000

    Estimated cost to complete 4,920,000 2,160,000

    What is the gross profit or loss should Marlboro company recognize in 2007 and 2008

  • 8/3/2019 Long Term Construction

    3/6

    2007 2008 2007 2008

    a. (240,000) (720,000) c. 240,000 (960,000)

    b. (240,000) (480,000) d. 240,000 (720,000)

    East Builders works on a 70 million contract in 2008 to construct a shopping mall for SM inc. During

    2008, East Builders uses the percentage of completion method of revenue recognition. At December 31,

    2008, the account balances are

    Construction in progress 24.55 million

    Accounts Receivable 2.4 million

    Contract Billings 12.0 million

    Estimated cost to complete 31.85 million

    How much is the actual cost incurred in 2008?

    a. 24.5 million b. 49 million c. 7.5 million d. 17.150 million

    From BAYSA

    Exercise 7-1

    In 2006, Durabuilt Engineering entered into an agreement to construct an office building at a contract

    price of P 50,000,000. Construction data were as follows:

    2006 2007 2008

    Construction Cost P 7,500,000 P 27,000,000 P 6,300,000

    Estimated Cost to complete 30,000,000 8,625,000 -

    Progress Billings 8,000,000 36,000,000 6,000,000

    Collection from clients 5, 500,000 33,000,000 11,500,000

    Instruction

    1. Determine the revenue, cost of revenue and gross profit to be recognized in 2006,20007,20008

    using the percentage of completion method and the cost to cost method of estimating the percentage

    of work completed.

    2. Prepare necessary journal entries to record construction activities for each year, including the

    recognized revenue, cost of revenue and gross profit.

    3. For 2007, show how the details related to this construction ciontract would be disclosed on the

    balance sheet and in the income statement.

    2006 2007 2008

    Contract price P50,000,000 P50,000,000 P50,000,000

    Cost incurred to date P 7,500,000 P34,500,000 P40,800,000

    Est. cost to complete 30,000,000 8,625,000 -

    __________

    Total estimated cost 37,500,000 P43,125,000 P40,800,000

    Total estimated gross profit P12,500,000 P 6,875,000 P 9,200,000

    Percentage of completion 20% 80% 100%

    To Date Recognized in prior year/s To be recognized this year

    2006 - Recognized revenue P10,000,000 - P10,000,000

    Cost of revenue 7,500,000 - 7,500,000

    Gross profit P 2,500,000 - P 2,500,000

    2007 - Recognized revenue P40,000,000 P10,000,000 P30,000,000

    Cost of revenue 34,500,000 7,500,000 27,000,000

    Gross profit P 5,500,000 P 2,500,000 P 3,000,000

    2008 - Recognized revenue P50,000,000 P40,000,000 P10,000,000

    Cost of revenue 40,800,000 34,500,000 6,300,000

    Gross profit P 9,200,000 P 5,500,000 P 3,700,000

  • 8/3/2019 Long Term Construction

    4/6

    New Dimension Construction Company bagan operations January 1, 2003: During the year

    , the company entered into a contract with centurion Company to construct a manufacturing facility. At

    that time, new dimension estimated that it would take five years to complete the facility at a total cost

    of P 18,000,000. The total contract price for construction of the facility is P 25,000,000. During the year,

    the company incurred P 4,400,000 in construction cost related to the construction project. The

    estimated cost to complete is P 15,600,000. Centurion was billed and paid 30% of the contract price

    subject to a 10% retention fee.

    Determine the amount of gross profit for the year ended December 31, 2003.

    Determine the balance of AR, CIP, Progress Billings on Construction contracts

    ANSWER

    1. Contract price P25,000,000

    Total estimated cost:

    Cost incurred to date P 4,400,000

    Estimated cost to complete 15,600,000 20,000,000

    Total estimated gross profit P 5,000,000

    Percentage of completion ( P 400,000/20,000,000) 22%

    Gross profit to be recognized in 2008 P 1,100,000

    2. Accounts Receivable (P25,000,000 x 30% x 10%) P 750,000

    Construction in Progress (P4,400,000 + P1,100,000) P5,500,000

    Progress Billings on Construction Contracts (P25,000,000 x 30%) P7,500,000

    2006 2007 2008

    a. Construction in progress 7,500,000 27,000,000 6,300,000

    Cash, Materials, etc. 7,500,000 27,000,000 6,300,000

    b. Accounts Receivable 8,000,000 36,000,000 6,000,000

    Progress Billings on Const. Contracts 8,000,000 36,000,000 6,000,000

    c. Cash 5,500,000 33,000,000 11,500,000

    Accounts Receivable 5,500,000 33,000,000 11,500,000

    d. Cost of LTCC 7,500,000 27,000,000 6,300,000

    Construction in Progress 2,500,000 3,000,000 3,700,000

    Revenue from LTCC 10,000,000 30,000,000 10,000,000

    e. Progress Billings on

    Construction Contracts 50,000,000

    Construction In Progress 50,000,000

    Statement of Financial Position

    Current Assets:

    Accounts Receivable P5,500,000

    Current Liabilities:

    Progress Billings on Construction Contracts P44,000,000

    Less Construction in Progress 40,000,000 P4,000,000

  • 8/3/2019 Long Term Construction

    5/6

    You were engaged to AUDIT the books of accounts of MMN contractors which had a 3 year construction

    contract in 2003 for P9,000,000. MMN uses the percentage of completion method for financial

    statement purposes recognized for each year is based on the ration of cost incurred to total estimate

    cost to complete the contract.

    Data on this contract follows:

    Accounts receivable-construction contract billings P 300,000

    Construction in Progress P 937,500

    Less: Account Billed 843,750

    10% retention 93,750

    Net Income recognized in 2003 ( before tax) 150,000

    MMN Contractors maintain a separate bank account for each construction contract. Bank

    deposits to this contract amounted to P 500,000.

    1. How much cash collected on the contract was not yet deposited at December 31, 2003?

    a. 43,750 b. 1,137,500 c. 193,750 d. 287,500

    2. What was the estimated total income before tax on this contract?

    a. 450,000 b. 840,000 c. 1,440,000 d. 287,500

    Answer Key

    Total amount billed P843,750

    Less Balance of accounts receivable 300,000

    Total collections P543,750

    Amount deposited 500,000

    Cash collected not yet deposited P 43,750

    P150,000 937,500/9,000,000 P1,440,000

    On September 14, 2003, NNO Contractors, Inc. won the bid for the construction of a 1,000 room hotel

    for hoteliers, Inc. on the reclamation area for 1.2 billion. On the terms of payment, parties agreed on the

    following:

    One percent mobilization fee (deductible for the final bill) payable within fifteen days after

    signing the contract;

    Retention of 10% on all billings, payable with the final bill after the acceptance of entire

    completed project; and

    Progress billings on construction within seven days from the date of acceptance

    By the end of 2003, the company presented one progress billings for 10% completion by

    hoteliers inc. evaluated and accepted on decmebr 28, 2003 for payment on January. The company used

    percentage of completion method of accounting.

    In the year 2003 NNO contractors Inc. received a fee of

    a. 9.8 million b. 10.8 million c. 12 million d. 1.2 million

    ANSWER:

    C Mobilization fee (P1.2B x 1%) P 1.2M

  • 8/3/2019 Long Term Construction

    6/6

    Collections on billings (1.2B x 10% x 90%) 10.8M

    Total fee received by NNO P12.0M