Upload
dorothy-shelton
View
215
Download
0
Tags:
Embed Size (px)
Citation preview
Long-Baseline Neutrino FacilityLBNF
LBNF/DUNE Logistics WorkshopSummary
Mike Headley
August 19, 2015
LBNF
Overview
• Many, major activities occurring at SURF over next ~15 years- Operations and decommissioning of LUX- Assembly, operations, and decommissioning of MJD- Installation and operations of CASPAR- Installation and operations of the BHSU UG Campus and LBCs- Completion of Ross Shaft refurbishment and continued SURF Ops- Construction, installation, and start of ops for LBNF/DUNE- Installation and operations of LZ
• LBNF / DUNE to commence construction soon (Elaine to cover)- Currently in preliminary design, CD-3A planned for Dec 2015- 2017 - Installation of waste rock handling systems- Late 2017 - Excavation mobilization then outfitting and cryo install- mid-2020s – Commissioning and science operations begin
08.19.15 Mike Headley | Logistics Workshop Summary2
LBNF
Logistics Plan Scope
08.19.15 Mike Headley | Logistics Workshop Summary3
• Arup developing comprehensive logistics plan out to ~2030- Construction and installation plans including utilization of SURF and
surrounding infrastructure, number and timing of deliveries, hours of required operation, parking, and warehouse and lay down space needs.
- Plans for waste storage and removal from SURF.- Traffic management including loading, unloading, parking, planned
access routes, capacity and utilization for transportation of materials, supplies, equipment, and staff.
- Recommendations on facility infrastructure modifications or process changes to improve the efficiency of all activities.
- Summary of risks specifically related to logistics plans.- Projection of personnel involved onsite throughout construction and
installation and recommendations on staff support including housing- Site security and safety considerations.
LBNF
Logistics Plan development schedule
08.19.15 Mike Headley | Logistics Workshop Summary4
• Logistics WorkshopAugust 11-13
• Draft Comprehensive Logistics Report Due September 10• Stakeholder Feedback Due
September 25• Final Comprehensive Logistics Report Due October 9
LBNF
Topics covered
08.19.15 Mike Headley | Logistics Workshop Summary5
• Infrastructure overview
• Surface and underground tours
• Presentations by SURF operations, LUX/LZ, Majorana, CASPAR, BHSU Underground Campus (low background counting)
• LBNF/DUNE presentations by CF, cryostat, cryogenic systems, FD
• Risk identification / analysis of items related to logistics
• Arup led discussion of the topics outlined in the logistics scope
• Presentation of information captured in excel-based toolset to track SURF infrastructure usage over time
LBNF
Key items reviewed in evaluating infrastructure usage
08.19.15 Mike Headley | Logistics Workshop Summary6
• Each group provided a detailed presentation on schedule and infrastructure needs and a resource usage spreadsheet
• Key constraints- Shaft access- Big X- Governor’s Corner
• Shaft options for LBNF+DUNE- Ross only- Ross + Yates “as-is”- Ross + Yates “upgraded” (assume not feasible for now)
• We looked at Ross Shaft for ALL work on LBNF+DUNE only
LBNF
Planning outputs - Assumes Ross Shaft only for LBNF/DUNE (draft)
08.19.15 Mike Headley | Logistics Workshop Summary7
LBNF
Draft schedule and Ross Shaft utilization(Excavation, BSI, and Cryostat phasing needs to be addressed)
08.19.15 Mike Headley | Logistics Workshop Summary8
LBNF
Top 15 risks identified – pre-mitigation scoring
08.19.15 Mike Headley | Logistics Workshop Summary9
ENGR-268
SciencePre-Blast Analysis
If pre-blast analyses are not conducted for experiment structures, then unanticipated damages will result.
Threat
5-Almost Certain->81%
4- $11 -20M 5- >2 years 23
ENGR-265
ScienceYates Shaft Brow Work
If the Yates shaft brow work goes ahead, then there will be delays and impacts to multiple science experiments.
Threat
5-Almost Certain->81%
2- $1M - 3M3- 6 months to
1 year13
ENGR-260
ScienceIntegration Failure
If there are science experiment requirements that are not clearly defined, then there will be integration failures.
Threat
4-Likely-51-80%
2- $1M - 3M3- 6 months to
1 year10
ENGR-296
GlobalSafety Incident
If there is a significant injury or safety incident, then there may be a work stoppage (safety stand-down and/or investigation).
Threat
3-Medium-21-50%
3- $4 -10M3- 6 months to
1 year9
ENGR-286
ShaftShaft Availability
If Ross and Yates Shaft availability were better understood by project team, then the use of the shafts could be better planned more efficiently.
Opportunity
4-Likely-51-80%
2- $1M - 3M2- 1 to 6 months
8
ENGR-278
Shaft Hoist ControlsIf drives and controls and hoists are not modernized, then continued safe and efficient operation cannot be guaranteed.
Threat
3-Medium-21-50%
3- $4 -10M2- 1 to 6 months
8
ENGR-253
SurfaceSurface Laydown
If there is insufficient laydown space at Yates and Ross surface areas, then experiments and contractors will need to seek offsite storage.
Threat
5-Almost Certain->81%
1- Less than $1M
2- 1 to 6 months
8
ENGR-254
SurfaceSurface Facilities
If there is a shortage of surface warehouse space, dry space, and storage capabilities, then this will impact the project.
Threat
5-Almost Certain->81%
1- Less than $1M
2- 1 to 6 months
8
ENGR-256
ShaftShift Schedules
If assumed shift schedules for each portion of project aren't aligned, then there will be confusion and other issues.
Threat
5-Almost Certain->81%
1- Less than $1M
2- 1 to 6 months
8
ENGR-274
ShaftYates Shaft Availability
If current Yates Shaft availability cannot be increased, then all experiments may impose more demand on the Ross Shaft, delaying all operations.
Threat
5-Almost Certain->81%
0 - $03- 6 months to
1 year8
ENGR-277
ShaftAdditional Experiments
If new experiments (e.g. rock-melting or rock-fracturing) are added during project construction, then there will be additional burdens on access, shafts, and other resources.
Threat
5-Almost Certain->81%
1- Less than $1M
2- 1 to 6 months
8
ENGR-289
BSIBlasting Schedule
If blasting takes place while people are underground, then safety issues may arise if QC is not very high..
Threat
5-Almost Certain->81%
0 - $03- 6 months to
1 year8
ENGR-292
BSI Phase 0If pre-phase ventilation tasks are not complete, then there will be delays to Phase 1 construction tasks (e.g. opening up #31 exhaust on 4850L).
Threat
3-Medium-21-50%
1- Less than $1M
3- 6 months to 1 year
6
ENGR-258
SurfaceSurface Compressor Footprint
If surface nitrogen compressors don't require a building (e.g. by using an enclosure or other means to minimize the footprint), then laydown space may be freed up.
Opportunity
3-Medium-21-50%
1- Less than $1M
3- 6 months to 1 year
6
ENGR-267
ScienceExcavation Pressure Impacts
If DUNE excavation causes overpressure surges from blasting, then experiment results will be compromised
Threat
3-Medium-21-50%
2- $1M - 3M2- 1 to 6 months
6
ENGR-269
ScienceManpower Levels
If maximum manpower levels underground are not coordinated during science operation and construction, then priorities will need to be adjusted and delays may be incurred.
Threat
4-Likely-51-80%
0 - $03- 6 months to
1 year6
LBNF
Mitigations to be considered
08.19.15 Mike Headley | Logistics Workshop Summary10
• Install concrete slick line borehole from surface to 4850L to remove concrete/shotcrete transport from the Ross Shaft
• Install boreholes for nitrogen and argon gas delivery to 4850L
• Assuming LBNF/DUNE utilize Ross Shaft for transport of long loads (up to 17m), modify Ross Headframe accordingly and/or evaluate shortening of cryostat steel beams to ease installation
• Utilize Yates Shaft as is – do not modify for long loads and avoid impacts to Davis Campus experiments
• Plan and conduct controlled blasting test program to evaluate impacts for LBNF excavation on other 4850L inhabitants
• Evaluate acceleration of phase 1 excavation to speed cryostat 1 installation and thus FD installation. Adjust EXC, BSI, and cryostat schedules to fix phasing of CF to cryostat installation