10
Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

Embed Size (px)

Citation preview

Page 1: Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

Long-Baseline Neutrino FacilityLBNF

LBNF/DUNE Logistics WorkshopSummary

Mike Headley

August 19, 2015

Page 2: Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

LBNF

Overview

• Many, major activities occurring at SURF over next ~15 years- Operations and decommissioning of LUX- Assembly, operations, and decommissioning of MJD- Installation and operations of CASPAR- Installation and operations of the BHSU UG Campus and LBCs- Completion of Ross Shaft refurbishment and continued SURF Ops- Construction, installation, and start of ops for LBNF/DUNE- Installation and operations of LZ

• LBNF / DUNE to commence construction soon (Elaine to cover)- Currently in preliminary design, CD-3A planned for Dec 2015- 2017 - Installation of waste rock handling systems- Late 2017 - Excavation mobilization then outfitting and cryo install- mid-2020s – Commissioning and science operations begin

08.19.15 Mike Headley | Logistics Workshop Summary2

Page 3: Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

LBNF

Logistics Plan Scope

08.19.15 Mike Headley | Logistics Workshop Summary3

• Arup developing comprehensive logistics plan out to ~2030- Construction and installation plans including utilization of SURF and

surrounding infrastructure, number and timing of deliveries, hours of required operation, parking, and warehouse and lay down space needs.

- Plans for waste storage and removal from SURF.- Traffic management including loading, unloading, parking, planned

access routes, capacity and utilization for transportation of materials, supplies, equipment, and staff.

- Recommendations on facility infrastructure modifications or process changes to improve the efficiency of all activities.

- Summary of risks specifically related to logistics plans.- Projection of personnel involved onsite throughout construction and

installation and recommendations on staff support including housing- Site security and safety considerations.

Page 4: Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

LBNF

Logistics Plan development schedule

08.19.15 Mike Headley | Logistics Workshop Summary4

• Logistics WorkshopAugust 11-13

• Draft Comprehensive Logistics Report Due September 10• Stakeholder Feedback Due

September 25• Final Comprehensive Logistics Report Due October 9

Page 5: Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

LBNF

Topics covered

08.19.15 Mike Headley | Logistics Workshop Summary5

• Infrastructure overview

• Surface and underground tours

• Presentations by SURF operations, LUX/LZ, Majorana, CASPAR, BHSU Underground Campus (low background counting)

• LBNF/DUNE presentations by CF, cryostat, cryogenic systems, FD

• Risk identification / analysis of items related to logistics

• Arup led discussion of the topics outlined in the logistics scope

• Presentation of information captured in excel-based toolset to track SURF infrastructure usage over time

Page 6: Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

LBNF

Key items reviewed in evaluating infrastructure usage

08.19.15 Mike Headley | Logistics Workshop Summary6

• Each group provided a detailed presentation on schedule and infrastructure needs and a resource usage spreadsheet

• Key constraints- Shaft access- Big X- Governor’s Corner

• Shaft options for LBNF+DUNE- Ross only- Ross + Yates “as-is”- Ross + Yates “upgraded” (assume not feasible for now)

• We looked at Ross Shaft for ALL work on LBNF+DUNE only

Page 7: Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

LBNF

Planning outputs - Assumes Ross Shaft only for LBNF/DUNE (draft)

08.19.15 Mike Headley | Logistics Workshop Summary7

Page 8: Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

LBNF

Draft schedule and Ross Shaft utilization(Excavation, BSI, and Cryostat phasing needs to be addressed)

08.19.15 Mike Headley | Logistics Workshop Summary8

Page 9: Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

LBNF

Top 15 risks identified – pre-mitigation scoring

08.19.15 Mike Headley | Logistics Workshop Summary9

ENGR-268

SciencePre-Blast Analysis

If pre-blast analyses are not conducted for experiment structures, then unanticipated damages will result.

Threat

5-Almost Certain->81%

4- $11 -20M 5- >2 years 23

ENGR-265

ScienceYates Shaft Brow Work

If the Yates shaft brow work goes ahead, then there will be delays and impacts to multiple science experiments.

Threat

5-Almost Certain->81%

2- $1M - 3M3- 6 months to

1 year13

ENGR-260

ScienceIntegration Failure

If there are science experiment requirements that are not clearly defined, then there will be integration failures.

Threat

4-Likely-51-80%

2- $1M - 3M3- 6 months to

1 year10

ENGR-296

GlobalSafety Incident

If there is a significant injury or safety incident, then there may be a work stoppage (safety stand-down and/or investigation).

Threat

3-Medium-21-50%

3- $4 -10M3- 6 months to

1 year9

ENGR-286

ShaftShaft Availability

If Ross and Yates Shaft availability were better understood by project team, then the use of the shafts could be better planned more efficiently.

Opportunity

4-Likely-51-80%

2- $1M - 3M2- 1 to 6 months

8

ENGR-278

Shaft Hoist ControlsIf drives and controls and hoists are not modernized, then continued safe and efficient operation cannot be guaranteed.

Threat

3-Medium-21-50%

3- $4 -10M2- 1 to 6 months

8

ENGR-253

SurfaceSurface Laydown

If there is insufficient laydown space at Yates and Ross surface areas, then experiments and contractors will need to seek offsite storage.

Threat

5-Almost Certain->81%

1- Less than $1M

2- 1 to 6 months

8

ENGR-254

SurfaceSurface Facilities

If there is a shortage of surface warehouse space, dry space, and storage capabilities, then this will impact the project.

Threat

5-Almost Certain->81%

1- Less than $1M

2- 1 to 6 months

8

ENGR-256

ShaftShift Schedules

If assumed shift schedules for each portion of project aren't aligned, then there will be confusion and other issues.

Threat

5-Almost Certain->81%

1- Less than $1M

2- 1 to 6 months

8

ENGR-274

ShaftYates Shaft Availability

If current Yates Shaft availability cannot be increased, then all experiments may impose more demand on the Ross Shaft, delaying all operations.

Threat

5-Almost Certain->81%

0 - $03- 6 months to

1 year8

ENGR-277

ShaftAdditional Experiments

If new experiments (e.g. rock-melting or rock-fracturing) are added during project construction, then there will be additional burdens on access, shafts, and other resources.

Threat

5-Almost Certain->81%

1- Less than $1M

2- 1 to 6 months

8

ENGR-289

BSIBlasting Schedule

If blasting takes place while people are underground, then safety issues may arise if QC is not very high..

Threat

5-Almost Certain->81%

0 - $03- 6 months to

1 year8

ENGR-292

BSI Phase 0If pre-phase ventilation tasks are not complete, then there will be delays to Phase 1 construction tasks (e.g. opening up #31 exhaust on 4850L).

Threat

3-Medium-21-50%

1- Less than $1M

3- 6 months to 1 year

6

ENGR-258

SurfaceSurface Compressor Footprint

If surface nitrogen compressors don't require a building (e.g. by using an enclosure or other means to minimize the footprint), then laydown space may be freed up.

Opportunity

3-Medium-21-50%

1- Less than $1M

3- 6 months to 1 year

6

ENGR-267

ScienceExcavation Pressure Impacts

If DUNE excavation causes overpressure surges from blasting, then experiment results will be compromised

Threat

3-Medium-21-50%

2- $1M - 3M2- 1 to 6 months

6

ENGR-269

ScienceManpower Levels

If maximum manpower levels underground are not coordinated during science operation and construction, then priorities will need to be adjusted and delays may be incurred.

Threat

4-Likely-51-80%

0 - $03- 6 months to

1 year6

Page 10: Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015

LBNF

Mitigations to be considered

08.19.15 Mike Headley | Logistics Workshop Summary10

• Install concrete slick line borehole from surface to 4850L to remove concrete/shotcrete transport from the Ross Shaft

• Install boreholes for nitrogen and argon gas delivery to 4850L

• Assuming LBNF/DUNE utilize Ross Shaft for transport of long loads (up to 17m), modify Ross Headframe accordingly and/or evaluate shortening of cryostat steel beams to ease installation

• Utilize Yates Shaft as is – do not modify for long loads and avoid impacts to Davis Campus experiments

• Plan and conduct controlled blasting test program to evaluate impacts for LBNF excavation on other 4850L inhabitants

• Evaluate acceleration of phase 1 excavation to speed cryostat 1 installation and thus FD installation. Adjust EXC, BSI, and cryostat schedules to fix phasing of CF to cryostat installation