LIFTING POCKET CARD
LIFTING CHECKLIST
1. Load
Confirm actual Lift weight including Rigging & accessories Confirm Head height & the crane radius required? Is Centre of Gravity of the load below the Rigging & Crane hook Does load require a lifting beam Is the content of the load secure & the load protected Are Tag lines required
2. Equipment
Is Rigging fit for purpose & recently checked Have all Rigging & Crane Certificates been checked Is the Safe Working Load of Rigging marked available on the equipment Is the SWL of the crane & its mode of operation suitable to complete the lift Does all Lifting accessories eg Chain blocks –come-along shackles meet the
above requirements3. Operators
Has a lifting team been assigned eg Supervisor / Banks man - Rigger /CraneOp – Load Handler
Confirm all members of Lift team are suitably trained & competent toundertake their individual roles
Confirm Crane operators certificate of training is commiserate to the type of crane being used eg Pendant / Remote Control or Cab ( Each require differenttrg courses )
4. Planning
Identify if the lift is Routine or Non Routine Lifting Operation For Non Routine Lifts make sure there is a new or existing Lift plan which
has been completed & reviewed for this operation Make sure Job Risk assessment has been completed and reviewed for this
operations Make sure that Lift team has the Required authority or Permit to Work to
proceed with the lift5. Environment
Confirm ground conditions are free from underground hazard & is strongenough to sustain anticipated loadings
Confirm there are no overhead hang ups or vertical hazards eg OHLE –SteelStructures etc
Check that turntable of mobile cranes are free from any fixed structures whenin normal operation minimum clearance being 750mm
Check there is there adequate light & visibility to complete the lift Check Wind speed is not beyond specific cranes recommendations Ensure suitable physical barriers have been erected to deny unauthorized
access to the lift
6. Communications Has pre lifting meeting being conducted with lift team & all safety
arrangements understood Have primary & secondary means of communication been established and
tested Have Suitable warning signs been erected communicating in an appropriate
language the hazards and exclusion zones7 Lifting Operation
Is the area for lifting load & lifting travel route clear of obstructions &personnel
7/30/2019 lifting checklist.doc
http://slidepdf.com/reader/full/lifting-checklistdoc 2/2
Is the area for landing the load properly prepared clear & strong enough toaccept the load minimizing risk of load becoming unstable following
Ensure Fall arrest arrangements are in place when rigging & de riggingcomponents that are due to size at an elevated position
IMPORTANT;DO NOT START THE LIFT UNTIL THIS CHECKLIST HAS BEEN
REVIEWED