Deliverables for Handover From Network Roll out Project (NRP) to Network Operations
PROJECT Team:Entity Name: Project Name: Project Manager - RAN: Project Manager - CORE: NI Team leader: Transmission Planning:CME Project Mgr: NPO SPOC:SAQ Manager: Contract: Documentation Team Lead: Equipment Vendor: CORE Planning: Vendor Project Manager:
Date of Handover to NOPS: DD-MM-YYYY
Contracts Details and Documentation
CheckedDocuments/ Deliverable
Responsible provider Status Location Remarks
Equipment Supply Agreement (ESA)Services Supply Agreements (SSA)Variation OrdersTraining/Competence transfer RequirementsCorporate GuaranteeLiquidated Damages
RAN Supporting Documentation
CheckedDocuments/ Deliverable
Responsible provider Status Location Remarks
RAN Site DocumentsPISM RFI ChecklistInstallation material’s list Approved DDD with redlineRF antenna alignment reportSite inventory reportCommissioning ReportSite Installation dataIntegration Report Site Stability TestRAN installation checklistPower installation checklist Outdoor DC Power and Alarm testingSite Photo Report Punchlist documentsRadio Station License
Version: 1.1
CheckedDocuments/ Deliverable
Responsible provider Status Location Remarks
Reference Document List and Operating ManualsVendor Product DocumentationVendor BTS/eNb Quick user guideVendor Antenna System User ManualBTS/eNb Implementation Check ListBTS/eNb Implementation Check ListBTS/eNb Work InstructionsThird Party DocumentationSite Specific Document ListSAT Docs PAT DocsUAT Docs Functionality Test Acceptance Manual As Built - ArchitecturalAs Built -Site Location Map/Vicinity MapAs Built -Perspective/Antenna configurationAs Built - Site Layout PlanAs Built - Site ElevationAs Built - Main Panel Board Mounting DetailsAs Built - StructuralAs Built - Antenna Mounting Bracket details/RRH mounting bracket detailsAs Built - Electrical layoutAs Built - Single line diagramAs built - Earthing line diagramSite Integration CertificateProvisional Acceptance CertificateFinal Acceptance Certificate
Version: 1.1
TRS Supporting Documentation
CheckedDocuments/ Deliverable
Responsible provider
Status Location
MW PISM RFI ChecklistSite Installation ChecklistMW Installation Material listApproved DDD Site Installation DrawingMW Inventory ReportMW Installation Checklist (PAT)MW Commissioning Procedure Approved Link Budget Interference Check (PAT)BER Test Result (24 Hr)RFC2544 Test ResultIPRANMW Commissioning SnapshotsMW Installation Photo ReportParameter SettingsRadio Station LicenseMW Punch ListMW Commissioning Acceptance Form PACFACSoft Copy of all docs
Version: 1.1
CORE Supporting Documentation
CheckedDocuments/ Deliverable
Responsible provider
Status Location
Technical Site Survey Report As-built Floor Plan Installation Procedures, Checklist and Certificate of Completion Breaker Allocation and Voltage Test Site Connectivity Plan (port-level) Network Element Parameter data fill Commissioning Procedures, Checklist and Certificate of Completion Network Diagram (high-level) Integration Checklist and Certificate of Completion HW Configuration (Bayface) and Serial Numbers Logs and Test Reports Customer Punchlist and Rectification Site Photos NSN Electronic Documentation Site Connectivity Plan (port-level) SATUATHW Installed Base InventorySW install base inventorySummaryof Minor alarms with recomm connectionNetwork performance reportUser and Profiles ( command matrix list
Version: 1.1
for all NE's)Completed project planCORE Equipment Operations manualStatus of security monitoring systemsCore Network Plan documentCORE Network DocumentNetwork Elements SummarySites & NE's naming ConventionDesign RequirementsNetwork Elements BoM/BoQHW/SW componentsBasic/Optional featuresNetwork TopologySites Interconnect Trans PlanUser Plane topologyMSS/MGW Control RelationshipTraffic EngineeringCapacity AnalysisTrunking/Signalling and RoutingIP Network PlanAs Built - ArchitecturalAs Built -Site Location Map/Vicinity MapAs Built - Site Layout PlanAs Built - Main Panel Board Mounting DetailsAs Built - StructuralAs Built - Electrical layoutAs Built - Single line diagramAs built - Earthing line diagramAdministration, Operation and Maintenance Guide Software Configuration Management PlanArchitectural and Network Diagram
Version: 1.1
Installation/configuration scripts (if applicable)Configuration files (if applicable)Troubleshooting tips (if applicable)Source codeDesign documentsAlarm ManualUser GuideTraining DocumentationSite Integration CertificateProvisional Acceptance CertificateFinal Acceptance Certificate
CME Supporting Documentation
CheckedDocuments/ Deliverable
Responsible provider
Status Location
Site Acquisition Request Form Site Acquisition Request Form (SARF)General Information (SAR & TSSR)Site Acquisition Report (SAR) Technical Site Survey Report (TSSR)Site Design and Variation Soil Investigation Report (for GF sites) Structural Analysis Report (for RT sites) Site Detail Design Package Variation Design Package Approved Variation Order (initial VO's) Approved Variation Order (additional VO's) Notice to Proceed
Version: 1.1
Notice to Proceed (NTP) CME Results and Certificates Site Kick Off Meeting Report Tower Foundation Rebar Inspection Report Rebar Material Certificates (Mill Certificate)Tower Material Certificates (Mill, Welding & Galvanizing Certificate) Tower Foundation Concrete Pouring RequestConcrete Test Certificate Rebar Test Certificate Pole / Tower Verticality and Twist Test Result Pole / Tower Bolt Torque Test Result Earthing System Test Result Field Density / Proctor Density test Results (for GF sites)Anchor Pull-out Test Certificate Non-destructive Test Result (for Schmidt Hammer Test, etc.) AC Power Distribution Test Result Certificate of Compliance - Antenna Support Structures, Foundation Certificate of Compliance -Electrical InstallationsContractor CME Quality Assurance ChecklistAs Built Drawing and PhotographAs Built Drawing Package As Built Photos Site Keys Hand-Over Receipt Site Keys Hand-Over Receipt (3 sets)Acceptance Certificates Provisional Acceptance (PAC) Checklist (signed) Provisional Acceptance (PAC) Checklist (closed ) Provisional Acceptance (PAC) Certificate Final CME Acceptance (CME FAC) CertificateDocumentation Checklist CME Documentation Checklist (signed) Miscellaneous
Version: 1.1
Documents and Correpondence OB Light Warranty Certiicate TVSS Certificate AC-1 Warranty Certificate Transformer Warranty Service Manual for Split Type AirconWarranty Policy for Split Type AirconRemote Control Manual Installation Manual User's Manual
Facilities Supporting Documentation
CheckedDocuments/ Deliverable
Responsible provider
Status Location
Power System InformationList of Power ElementsPACU/ACU system informationList of PACU/ACU ElementsAlarm system configurationAs built PlanInstallation/Users manualProvisional Acceptance (PAC) Checklist (signed) Provisional Acceptance (PAC) Checklist (closed ) Provisional Acceptance (PAC) Certificate Final Acceptance FAC) Certificate
SAQ Supporting Documentation
CheckedDocuments/ Deliverable
Responsible provider
Status Location
Property Documents (Mandatory)Transfer Certificate of Title (of land) Condominium Certificate of Title Tax Declaration (of the land) Tax Declaration (of the building)Tax Declaration (per Unit)Secretary's CertificateBoard Resolution SEC Registration Articles of Incorporation
Version: 1.1
By LawsSpecial Power of Attorney Segregation Plan Tax Clearance Tax ReceiptOther Documentation (Optional)Deed of ConveyanceDeed of SaleDeed of DonationAffidavit of OwnershipAffidavit of disinterested personCertified true copies of Birth Certificate of heirsDeath Certificates and Extra Judicial Settlement Bank ConsentRight of Way AgreementCommercial Terms (CT) For Right of Way Agreement Pre-Construction PermitsNeighbors Consent / Certificate of No NeighborsBarangay Clearance Barangay Resolution DAR Clearance CAAP Clearance DOH Clearance Zoning Certificate Locational Clearance Sangguniang Bayan Resolution Approved Installation Plan HOA (Home Owners Association) Clearance LLDA (Laguna Lake Development Authority) Clearance Philvocs & Receipt Certificate of Non-Coverage HLURB Clearance SUP (Special Use Permit)
Mechanical Permit Building Permit Electrical Permit Fencing Permit Sanitary Permit Permit to operate Genset Post-Construction PermitsCertificate of Electrical Inspection Certificate of Fire Inspection
Version: 1.1
Certificate of Completion Mayors Permit Electronics Permit Occupancy Permit Legal DocumentationCommercial TermsSigned and Notarized Lease Contract AC Power DocumnetationApproved AC Power QuotationAC Power ApplicationAC Power Application ReceiptAC Power Contract (with Power Company)Acceptance CertificatesFinal SAQ Acceptance (SAQ FAC) Certificate Documentation ChecklistSAQ Documentation Checklist (signed)Lease Package Documentation Checklist (Signed) Pre-construction Permitting Documentation Checklist (signed)Post-construction Permitting Documentation Checklist (signed)Permanent AC Power Documents Checklist (signed)Miscellaneous and Correspondence Work Completion Certificate (WCC)Certificate of Conformity to Lease BIR RegistrationCertification of Existing Lease Agreement from Lot Owner Site AgreementExemption Justification Form
Remote System Support and Security
Version: 1.1
CheckedDocuments/ Deliverable
Responsible provider
Status Location
Specific application access granted?SDC setup done(Resolve, RAS, Testbed/Production access as applicable)Set the ticket routing for the products in Resolve and test the ticket routingVerify and test the remote connection to equipment. It should be available for Vendor technical support team, 3rd party (if applicable) Password ListsContact Numbers of the VendorsContact Numbers for 3rd Party VendorsContact Numbers for PLSupport contact for 3rd partiesRemote access to productionRemote access to preproduction
Project Supporting Documentation
CheckedDocuments/ Deliverable
Responsible provider
Status Location
Project SITE Tracker Minutes of Project MeetingsProject Action RegistersProject Completion reportLessons learned and recommended improvementsOpen and closed Resolved tickets, Management escalations.Incident reports and RCA of all cases encountered during the project phaseBugs/issues list closed and still open during project NI to NOPS checklistInsurance Coverage