35
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation 10 th October 2014

LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

Embed Size (px)

Citation preview

Page 1: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

LHCb Upgrade

Optical Fibers from Cavern to the Surface

- what has been done ? - prototypes status and next coming steps - what is missing for final installation

10th October 2014

Page 2: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 2

- LS2 planning tight / many activities in UX foreseen - want links ready to do the commissioning of first electronics as soon as possible

Goal (already decided end of 2012):

~ 15 000 fibers UX85 to Surface ready for beginning of LS2

2013 Study passages through the 2 pits available PM85 pit chosen

Disadvantages Pass thought an LHC side (US85, PM85): - agreement of LHC (space taken, integration in 3D mockup…) documentation provided (ECR), LMC approval. - passage above Cryo equipment during installation additional precautions to take - dependent on machine activities access given by them / LHC planning

Advantages in a ‘technical area’ (no need special derogation/safety exit) no passage through the LHCb shielding wall (difficult before LS2) no space take in the existing ‘LHCb’ cable trays (probably happy to have for LS2)

Laurent Roy

Page 3: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 3Laurent Roy

PZ85 shaft

New LHCb Control Room

End point:New server

Rooms

PM85 shaft

PX85 shaft

Start point: ~3 areas in

UX85

New Power Transformer ?

HV cells

SG8

passage for the

prototypes

Page 4: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 4

Two types of installation possible: blowing (+splicing) or pre-connectorized

- technical Pros and Cons of each solution could not yet help for the choice- Cost relatively similar: also not help to chose already now- Installation of prototypes with both possibilities in our environment to give more information

Laurent Roy

Solution compatible for both types found for the supports:

rails + clamps

bundle of 7 trunk cables (for pre-connectorized) 50mm tube (for blowingin 7 mini tubes)

Page 5: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 5Laurent Roy

- 600mm standard cable trays installed in UX85-C (Cryo part)

Supports installation: has been designed directly for the full quantity

Page 6: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 6Laurent Roy

cable trays installed in UX85-C (Cryo part)

-Try to minimize the curvesbut cannot avoid few of them

However minimum bending radius (76 cm) respected everywhere

Page 7: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 7Laurent Roy

Large scaffoldings mounted-for new cable trays on the wall /US85-for passages through the ‘siporex’ wall

Page 8: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 8Laurent Roy

Scaffolding above Cryo racks

New cable tray

2 holes drilled in UX85-US85 wall-for fibers coming from Bunker+Calo+Muon fibers -for Velo side (Velo, UT, Rich1)

Page 9: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 9Laurent Roy

New cable tray for Muon+Calo

Page 10: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 10

Laurent Roy

closing before LHC powering tests safety / leak of He

2nd holenew supports in US85

Page 11: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 11

Laurent Roy

Difficult passage (between large air duct and the wall)‘en drapeau’

Special support tomove ducts away from power cables (with a safe distance of 25 cm requested)

Page 12: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 12

Laurent Roy

Scaffolding bottom PM85 + Cryo cold box protection

Page 13: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 13

Laurent Roy

2 Cryo exhausts moved away(bottom of the pit)

limited spaceallowed by Cryo and LHC integrationin PM85

Page 14: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

•14

Laurent Roy

Special support for ~85m vertical part in the pit

rails on each sides

mechanical characteristics report provided

Page 15: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 15

Laurent Roy

Mechanical supports studied to occupy the maximum of space available between 2 ‘cryo transfer lines’ 20 tubes ø50mm could be installed x 7 = 140 cables x 144 fibers =20160 fibers is the maximum that should be possible to install

Page 16: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

•16

Laurent Roy

junction between pit and gallery at the surface

Boring ~ 3.5m of concrete + rubble to reduce length: -30m

boring: use the max.diameter possibleØ 40 cm !L: 3.5 m

Page 17: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 17

Laurent Roy

studied for ~ 20 tubes ø50mm (20160 fibers maximum)

gallery side

Page 18: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 18

Laurent Roy

Pit side

Gallery side

very difficult jobforeseen for ~1-2 weekstook ~ 1 month !

Page 19: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

•19

Laurent Roy

New cable trays in the existing gallery(old pictures before install them)

Page 20: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 20

Laurent Roy

Preparation for the passage below the new buildingin SX8

Gallery

done last week

Page 21: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 21

Laurent Roy

Window for Optical fibersTo pass through the underground level to go to a new ‘parking’ gallery Existing ‘caniveau’ where prototype

installedto the SG8

Page 22: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

•22

Laurent Roy

90% of “mechanical supports” already installed for the full quantity

In UX85 Velo-RICH1 region: a small platform will come in ~1 month

to be done for 100%:- new gallery (parking) - cable trays installation (new building+parking)- Calo C side cable tray- Velo side: detail integration for cable tray &

installation

Page 23: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 23

blowing prototype status:

- Tube ø 50mm + 7 microtubes ø12mm installed- Blowing pre-test done with a cheaper cable successful, allowed optimize

machine adjustments (05 Sept 2014)

- Blowing + splicing cable prototype done (29 Sept 2014)

Laurent RoyIn PM85 pit

Page 24: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 24

Laurent Roy

lot of people needed to pull the tube2 full days: 8 people

length 500m

Page 25: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 25

Laurent Roy

End point of the prototype:SG8

Passage between gallery and the pit

Page 26: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 26

blowing machine (test cable)Test the maximum speed possible without damaging the cable (in case it blocks).

Laurent Roy

Pressure adjustment for the rollers speed

Pressure adjustment for the air blown in the tube

Page 27: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 27

blowing machine (prototype cable)-film

Laurent Roy

speed beginning:~ 60 m/min end: ~ 20 m/min Total ~10 min for the 350m (but preparation takes more time)

Page 28: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 28

Splicing preparation

Laurent Roy

Inside the cable 6 ‘mini cables’ x24 fibers (=24 colors)

Splicing cassette finished12 LC (will be 1 MPO in the future)

1,5 days 2 people to do the 144 splicings + measurements15 000 fibers could take 156 day (2 people) more than half a year !!

Page 29: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 29

Laurent Roy

Splicing machine

2 electrical electrodes

-film

Page 30: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 30

Laurent Roy

144 fibers Ready for tests with electronics boards !

Front (in SG8)

Back Start point underground in the M1 bunker rack

Page 31: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 31

preconnectorized prototype status:

- Draka and Fibernet (cheaper) trunk cables each 144 fibers received

should be installed when access possible: CV maintenance (week 48-49-50)

Laurent Roy

End of November

LHC planning

Page 32: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 32

Laurent Roy

Quantities need for LHCb Upgrade (last estimate from Ken):

Final quantity per sub-detector ?Space for patch panels to foresee -> which location ?

Page 33: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

•33

Is it the right configuration for your sub-detector ? (patch panel, type of patch cord…)

What will be the different lengths ?

Laurent Roy

Complete link between the electronic and the patch panels downstairs

Page 34: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 34

Complete link between the DAQ and the patch panels upstairs

Laurent Roy

Which DAQ PCIe40 quantity per sub detector ? Which detector will do a load balancing ?

Page 35: LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation

• 35

Conclusion:

- supports ready for ~ 90 % of the total length (10 % missing to install during Technical Stops)

- Yes it is possible to blow cables in our configuration from down to top

- blowing prototype 144 fibers (UX85-SG8) installed and ready for tests

- 2 trunk version cables received, will be installed in Nov 2 methods will then be compared in details

To progress for the full installation:Need the different lengths of patch cords, quantity of PP on the link, location…- realize ‘worst case’ tests- reserve space (surface & underground)- prepare to order the equipment needed

(optical+PCIe40+’online’+…) - make installation planning information from sub-detectors requested in the next weeks

Laurent Roy