Upload
yeva
View
49
Download
5
Embed Size (px)
DESCRIPTION
Initial Experience with the Machine Protection System for LHC Rüdiger Schmidt R.Assmann, B.Dehning, M.Ferro-Luzzi, B.Goddard, M.Lamont, A.Siemko, J.Uythoven, J.Wenninger, M.Zerlauth. LHC cycle and machine protection Strategy for machine protection Commissioning Operational experience - PowerPoint PPT Presentation
Citation preview
1IPAC May 2010
Initial Experience with the Machine Protection System for LHC
Rüdiger Schmidt R.Assmann, B.Dehning, M.Ferro-Luzzi, B.Goddard, M.Lamont, A.Siemko,
J.Uythoven, J.Wenninger, M.Zerlauth
• LHC cycle and machine protectionLHC cycle and machine protection
• Strategy for machine protectionStrategy for machine protection
• Commissioning Commissioning
• Operational experienceOperational experience
• ConclusionsConclusionsIPAC May 2010 Kyotov1.
1
2IPAC May 2010
3IPAC May 2010
0.0010
0.0100
0.1000
1.0000
10.0000
100.0000
1000.0000
100 1000 10000Momentum [GeV/c]
En
erg
y st
ore
d in
th
e b
eam
[M
J]
LHC injectionnominal
TEVATRON
LHC one nominal bunch at injection
SPSCNGS
SPSmaterial tests
SPSppbar collider
LHC one nominal bunch
at 3.5 TeV
LHC Injection at 450 GeV/c
LHC Physics at 3.5 TeV/c
setup beam flag
LHC 7 TeV/cenergy nominal
beam
Energy stored in one LHC beam
6 cm
A B D C
Today
4IPAC May 2010 IPAC May 2010 Kyotov1.1
5IPAC May 2010
LHC operational cycle and machine protectioin
0
1000
1500
2000
2500
3000
3500
-4000 2000 4000
time from start of injection (s)
Ene
rgy
[GeV
/c]
500
-2000
Injection: 13 bunches from SPS per beam (21010)
energy ramp 10 kJ 100 kJ
circulating beam
coast (100 kJ)
circulating beam
beam dump ~100 kJ
Nominal: 2808 bunches per beam (1.151011)
6IPAC May 2010
0
1000
1500
2000
2500
3000
3500
-4000 2000 4000
time from start of injection (s)
Ene
rgy
[GeV
/c]
500
-2000
Injection: 13 bunches from SPS per beam (21010)
energy ramp 10 kJ 100 kJ
circulating beam
coast (100 kJ)
circulating beam
beam dump ~100 kJ
Injection: Without quenching magnets or causing damage No kick by injection kicker of circulating beam (correct synchronisation)Injection protection absorber in place in case of kicker failure
7IPAC May 2010
0
1000
1500
2000
2500
3000
3500
-4000 2000 4000
time from start of injection (s)
Ene
rgy
[GeV
/c]
500
-2000
Injection: 13 bunches from SPS per beam (21010)
energy ramp 10 kJ 100 kJ
circulating beam
coast (100 kJ)
circulating beam
beam dump ~100 kJ
Circulating beam: In case of failure, detect failure and extract beam into dump block for some failures within a few turns
No accidental firing of a kicker magnet
8IPAC May 2010
0
1000
1500
2000
2500
3000
3500
-4000 2000 4000
time from start of injection (s)
Ene
rgy
[GeV
/c]
500
-2000
Injection: 13 bunches from SPS per beam (21010)
energy ramp 10 kJ 100 kJ
circulating beam
coast (100 kJ)
circulating beam
beam dump ~100 kJ
Extraction: Beams must ALWAYS be extracted into beam dump block Kicker rise must be synchronised with the 3 µs long beam abort gapAbort gap must be clean of particles
9IPAC May 2010
Strategy for machine protection
Early detection of equipment failures triggering beam dump request.– Powering Interlocks: failures in powering system (quench, PC trip,..) – Fast Magnet Current change Monitor
Monitoring of beams to detect abnormal beam conditions and triggering dump request, down to a single machine turn. – Beam Loss Monitors and Beam Position Monitors
Reliable transmission of dump requests to beam dumping system and stop injection + extraction from SPS– Beam Interlock Systems
Reliable operation of beam dumping system, safely extracting beams onto the external dump blocks. – Beam Dumping System
Definition of LHC aperture by collimators, to limit beam losses to (warm) collimator regions.– Beam Cleaning System
Passive protection by absorbers and collimators for specific failure cases.– Beam Absorbers
MOPEB045
WEPEB069
WEPEB073
TUPEB063
TUOAMH01
10IPAC May 2010
Architecture of the Beam and Powering Interlocks
Beam Interlock SystemBeam
Dumping System
Injection Interlockand SPS extraction
PoweringInterlocks
superconducting magnets
PoweringInterlocks
normal conducting magnets
Quench protection system PS
(20000 channels)
Power Converters
~1600
AUG
UPS
Power Converters
Magnets
Fast Magnet Current
Monitors
Cryogenicssome 10000
channels
RFSystem
LHCExperiments
Beam LossMonitors
BCM
CollimationSystem
Jaw PositionTemperature
Screens and Mirrorsbeam
observation
Access System
VacuumSystem
Beam loss monitors
BLM
SpecialBLMs
Monitorsaperture
limits(some 100)
Monitors in arcs
(several 1000)
Timing System (Post Mortem
Trigger)
Operator Buttons
CCC
SafeMachine
Parameter
SoftwareInterlockSystem
Safe Beam Parameter
Distribution
SafeBeamFlag
BPMs
11IPAC May 2010
Steps in commissioning of machine protection
• Before starting beam operation, check interlocks from all system (as far as possible)
• Start with low intensity beam (no risk of damage)
• Commissioning the beam dump system at different energies
• Commissioning the beam cleaning system (80 collimators) at different energies, and for different optics
• Specific tests with beam (Machine Protection tests)
• Analyse operation (for all beam dumps and for beam losses not leading to a beam dump)
• Early commissioning: masking of interlocks– setup beam flag: when energy density is below critical value
• Exceed the stored energy of the setup beam flag (“safe beam”) – masking automatically removed
• Get confidence in machine protection to go to higher intensity
12IPAC May 2010
Commissioning of the beam dump system
• Beam dumps done at different energy, to demonstrate that bunches are correctly extracted via a 700 m long line into the dump block
• To reduce the energy density on the dump block, beam is “painted” by fast deflection of two families of kicker dilution magnets
• A 3 µs abort gap for the switch-on of the extraction kicker field allows loss free extraction under normal operating conditions.
• Some asynchronous beam dumps are expected. Collimators are installed to capture beam that is deflected with a small angle. Tests with de-bunched beam: particles in abort gap are correctly intercepted
Beam dump of 10 bunches, beam spots on screen (measurement and expected centres) in front of beam dump block
13IPAC May 2010
Collimator setup
•
• Cleaning efficiency depends jaw centring on beam, accuracy of gap size and jaw parallelism with respect to beam. The collimators are aligned during the different operational phases (injection, top energy, etc.)
• Excellent performance, no beam induced quench. The efficiency is measured by driving the beam on a resonance.
Betatron cleaningMomentum cleaningAlice CMSATLAS LHCbBeam dumpRF
red line: BLM thresholds
14IPAC May 2010
04/21/23
Early detection of powering failures (FMCM OFF)
• With low intensity beam, the monitor was disabled and a trip of the power converter triggered
• A trip of normal conducting magnets close to the experiments is most critical (fastest beam loss)
• The beam position changed, and beam loss monitors close to collimators recorded the loss and triggered a beam dump
• Redundant protection is required, by measuring voltage drops in the circuit within less than one ms
Position change of ~1.5 mm within 250 turns (25 ms)
Beam position over 1000 turns at one BPM
15IPAC May 2010
Early detection of powering failures (FMCM ON)
• The Fast Magnet Current change Monitor (FMCM) to detect fast powering failures was enabled
• The test was repeated
• The beam was dumped, before any effect on the beam position was visible
• No beam losses were detected
• The redundant protection works. This is an example that we try to use for all possible failures
• Very sensitive in case of problems with the electrical network (a number of beam dumps)
no position change
Beam position over 1000 turns at one BPM
16IPAC May 2010
Software Interlock System
Provides additional protection for complex but less critical conditions (e.g. surveillance of magnet currents and closed orbit)
• Example: triggered on large orbit excursion (> 12 BPMs over 6 mm for beam 2 in the horizontal plane (too large RF frequency change)
MPP - 16th April 2010 16
Threshhold
17IPAC May 2010
“Post Mortem” after beam dump
• Record all state changes from interlock systems • Record transient data for every beam dump for all
systems (beam loss, orbit, beam current, tune, hardware parameters (magnet current, collimator positions, …)
3500280 GeVFMCM RD1 LR1
18IPAC May 2010
Early experience
• Many beam dumps at injection, in general for commissioning purpose
• “False” beam dumps: if a protection system dumps the beam because of an internal failure (e.g. noise spikes, problems in connectors, …)
• About 75 beam dumps after the start of the energy ramp
• All beam dumps are understood (thanks to the interlock systems and post mortem recording)
• Not a single quench with circulating beam– Stored energy of 100 kJ with respect to 10 mJ for quenching a magnet – Cleaning system did an excellent job– Detection of failures worked very well
• Very few beam induced magnet quenches (“quenchinos”), only during injection at 450 GeV – the threshold of a quench detector was exceeded, the quench heaters fired
and quenched the magnet (without firing the magnet would have recovered)– one event: main quadrupole current in one sector 350A instead of 760A – other events: during special aperture studies
19IPAC May 2010
Conclusions
• For many Machine Protection sub-systems: Commissioning finished before LHC beam operation during hardware commissioning (all interlocks related to the magnet powering system)
• Commissioning of LHC with low intensity beams, slowly increasing the intensity, bringing up all machine protection systems
• The beam intensity where interlocks can be masked has been exceeded. LHC operates with all interlock enabled
• LHC can operate with the full machine protection system
• Operational experience and machine protection experiments demonstrated that the machine protection system works as expected, no surprises until today
• These are early days, a huge step in beam intensity is still required
• Next month(s): 1 MJoule, end of this year: >10 MJoule
20IPAC May 2010
Acknowledgements
LHC Machine Protection reflects the complexity of the LHC accelerator.
Many colleagues contributed to LHC Machine Protection. We like to thank them and are very grateful for their contributions.
21IPAC May 2010
Reserve slides
22IPAC May 2010
Beam dumps above injection energy (incl. 3.5TeV)
Reason for beam dump Dumps False dumps
Magnet Protection System 6 6
Cryogenics 6
Feedback / Magnet Protection 6
Experiments 4
Beam dynamics 5
Electrical Network 2
Beam Loss Monitor System 2 2
Beam Position Monitors 5
Beam Dumping System Internal Failure 6
Operational error 2
Dump at the end of the fill 2
Machine Protection Tests 12
Interlock systems 0 0
23IPAC May 2010
Masking interlocks during initial operation
• There are several 10 thousand interlock channels
• Start-up of such a machine is not possible without masking interlock channels– Example: commissioning of the cleaning system with all beam loss monitors
active
• BE PREPARED TO MASK (disable) interlocks!– but in a co-ordinated way
• Setup Beam Flag: interlock can be masked – it is always easy to see what interlocks are masked– when the beam becomes unsafe (stored energy above setup beam limit), the
interlock become automatically enabled
• Masking of interlocks should be considered when designing the system
24IPAC May 2010
Principles for machine protection
• Protect the machine– highest priority is to avoid equipment damage– second priority is to avoid quenching of magnets: with superconducting
magnets it requires few mJoule to quench: no beam losses in the cold part
• Protect the beam: trade-off between protection and operation– complex protection systems reduces the availability of the machine– minimise number of “false” beam dumps (beam dumps due to a failure in the
protection systems)
• Provide the evidence– if the protection systems stops operation (e.g. dumps the beam or inhibits
injection), clear diagnostics provided by the “post mortem” system– if something goes wrong (near miss or even damage), it should be possible to
understand the reason why
25IPAC May 2010
Machine protection during operational cycle
• Injection– injection of beam without quenching magnets or causing damage – no kick by injection kicker of circulating beam (correct synchronisation)
• Circulating beam– in case of failure, detect failure and extract the beam into the beam dump
block, for some failures within a few turns– no accidental firing of a kicker magnet
• The beam must ALWAYS be extracted into the beam dump block (end of fill or in case of a failure)– reliable operation of beam dumping system– kicker rise must be synchronised with the 3 µs long beam abort gap– abort gap must be clean of particles– collimators reduce beam loss in case of failure
26IPAC May 2010
Setup (Safe) Beam Flag - TRUE
• Initial beam commissioning and machine protection tests very difficult with all interlocks active
• Some interlocks can be MASKED when beams stored little energy density
27IPAC May 2010
Setup (Safe) Beam Flag - FALSE
• When stored beam energy exceeds a critical value for the stored beam energy density, all masks are removed
• If an interlock on a masked input is active => beam dump
28IPAC May 2010
Interlocks Systems: ensure time stamping
Beam Interlock SystemBeam
Dumping System
Injection InterlockPowering
Interlockssuperconducting
magnets
PoweringInterlocks
normal conducting magnets
Quench protection system PS
(20000 channels)
Power Converters
~1600
AUG
UPS
Power Converters
Magnets
Fast Magnet Current Monitor
Cryogenicssome 10000
channels
RFSystem
LHCExperiments
Beam LossMonitors
BCM
CollimationSystem
Jaw PositionTemperature
Screens and Mirrorsbeam
observation
Access System
VacuumSystem
Beam loss monitors
BLM
SpecialBLMs
Monitorsaperture
limits(some 100)
Monitors in arcs
(several 1000)
Timing System (Post Mortem
Trigger)
Operator Buttons
CCC
SafeLHC
Parameter
SoftwareInterlockSystem
Safe Beam Parameter
Distribution
SafeBeamFlag
BPMs
The interlock systems allows to identify the origin of any beam dump, and for powering failures to identify the electrical circuit that tripped
• data from several 10000 channels (50k-100k)• all data is time stamped with the same clock (beam interlocks ~
µs, powering interlocks ~ ms)
29IPAC May 2010
Powering System and interlocks
• Hardware commissioning: Ramp all magnets with current functions as during beam operation and commission all interlocks– 1700 high current powering circuits with about 10000 magnets
• Interlocks required for commissioning of the magnet powering system
• Monitors temperatures in superconducting magnet system, voltages, currents, many other parameters, ….
• Failures: quench, power converter failure, cryogenics problem, water cooling failure, UPS failure, failure in the protection systems– firing of quench heaters, extraction of energy in the circuit, stop power
converters, … AND trigger beam dump
• For some magnet circuits: beam dump, for other circuits: no beam dump– can be configured for each circuit– main dipole and quadrupole magnets: always dump beams in case of failure– example: orbit correctors in the arc not (yet) included in the systems that
dump the beam