30
LHC Machine Upgrade Overall Frédérick Bordry Fourth Common ATLAS CMS ElectronicS Workshop for LHC upgrades ACES2014 – 18 th March 2014

LHC Machine Upgrade Overall Frédérick Bordry

  • Upload
    makya

  • View
    31

  • Download
    0

Embed Size (px)

DESCRIPTION

LHC Machine Upgrade Overall Frédérick Bordry Fourth Common ATLAS CMS ElectronicS Workshop for LHC upgrades ACES2014 – 18 th March 2014. Outline. - LS1 status - Run 2 (from LS1 to LS2), LS2 and Run 3 - HL-LHC project (LS3) : 3000 fb -1 - LHC Roadmap up 2035. 2. Long Shutdown 1. - PowerPoint PPT Presentation

Citation preview

Page 1: LHC Machine Upgrade Overall Frédérick Bordry

LHC Machine Upgrade OverallFrédérick Bordry Fourth Common ATLAS CMS ElectronicS Workshop for LHC upgrades ACES2014 – 18th March 2014

Page 2: LHC Machine Upgrade Overall Frédérick Bordry

2LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

- LS1 status

- Run 2 (from LS1 to LS2), LS2 and Run 3

- HL-LHC project (LS3) : 3000 fb-1

- LHC Roadmap up 2035

- LS1 status

- Run 2 (from LS1 to LS2), LS2 and Run 3

- HL-LHC project (LS3) : 3000 fb-1

- LHC Roadmap up 2035

Outline

2

Page 3: LHC Machine Upgrade Overall Frédérick Bordry

3LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

LS1 starts as the shutdown to repair the magnet interconnects to allow nominal current in the dipole and lattice quadrupole circuits of the LHC.

It has now become a major shutdown which, in addition, includes other repairs, maintenance, consolidation, upgrades and cabling across the whole accelerator complex and the associated experimental facilities.

All this in the shadow of the repair of the magnet interconnects.

Long Shutdown 1

Page 4: LHC Machine Upgrade Overall Frédérick Bordry

4LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

PhysicsBeam commissioning

ShutdownPowering tests

F M A M J J A S O N D J F J FM A M J J A S O N D

2013 2014 2015

M A

LHC

SPS

PS

PS Booster

beam to beam

available for works

16th Feb. 18th March

LS 1 from 16th Feb. 2013 to Dec. 2014

Page 5: LHC Machine Upgrade Overall Frédérick Bordry

5LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

3

Done Done

3000

98 % done 85 % doneOpening:100% 75 % done

90 % done65 % done

100 % done 90 % done

80 % done

Closure: 50%

100 % done

Page 6: LHC Machine Upgrade Overall Frédérick Bordry

6LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Page 7: LHC Machine Upgrade Overall Frédérick Bordry

7LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

RB splice R-8 (µΩ) RQ splice R-8 (µΩ)

QBBI.B24R7-M3-Ext-R 77.5 QQBI.20L8-M1-Ext-L 116QQBI.9R4-M3-Ext-L 52.6 QBQI.27R1-M1-Int-L 54.8

QQBI.22L8-M3-Ext-L 52.6 QBBI.B18R2-M1-Int-L 52.5

QBBI.A14L8-M3-Int-R 49.9 QBBI.B25L8-M1-Int-R 51.4

QQBI.16R8-M3-Int-R 47.4 QBBI.B31R1-M1-Int-L 45.9

QQBI.22R7-M3-Int-L 43.3 QQBI.20L4-M2-Int-L 45.6

QQBI.19L1-M3 Ext-L 41.8 QQBI.30L8-M1-Int-L 44.5

QBQI.32R7-M3-Int-L 41.6 QBBI.B17L5-M2-Int-L 44.2

QBQI.31R6-M3-Ext-L 40.6 QEBI.11L1-M1-Ext-L 43.7

QDQI.7R3-M3-Ext-L 39.2 QQBI.15R3-M1-Int-L 42.8

Sector Max R-8excess RB (µΩ) Max R-8excess RQ (µΩ)

56 28.6 21.167 35.0 32.478 71.9 10781 41.8 34.412 29.6 45.523 27.8 43.234 33.6 36.345 48.3 34.9

Highest R-8excess resistance values of RB and RQ splices per sector.

Top ten R-8 outliers

Courtesy of C. Scheuerlein

Excess resistance distribution sorted descending by resistance values. The two highest R-8 excess values of 106 µΩ and 72 µΩ are not shown.

-505

101520253035404550

0 5000 10000 15000 20000

R-8 ex

cess

(μΩ

)

acceptance threshold = 5 µΩ

Page 8: LHC Machine Upgrade Overall Frédérick Bordry

8LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Superconducting Magnets And Circuits Consolidation Dashboards

3 weeks

Page 9: LHC Machine Upgrade Overall Frédérick Bordry

9LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Before After

18 kV & 3.3 kV circuit breakersVacuum UPS-RE82

Pumping station

Cryo plant P7 enclosure

ACS transport

The other activities

Courtesy of Katy Foraz

Helium spill test

Page 10: LHC Machine Upgrade Overall Frédérick Bordry

10LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

LS1: LHC schedule

Courtesy of Katy Foraz

RE

18

RE

22

RE

28

UJ3

2

RE

38

RE

42

RE

48

RE

52

RE

58

RE

62

RE

68

RE

72

RE

78

RE

82

RE

88

RE

12

20

15

MAY

NOV

DEC

JAN

FEB

OCT

20

14

OCT

DEC

JAN

JUNE

JULY

AUG

FEB

2013

MAY

LSS LSS Arc 81 LSSR2E R2E R2E

Pt 7LSS Arc 78 LSS

Pt 8LSSArc 56 LSS Pt 6Arc 23 LSS Pt 3 Arc 34 LSS

Pt 1LSS Arc 12 LSS Pt 2 LSS

R2ELSS Arc 67 LSSPt 4 LSS Arc 45 LSS

Pt 5

2013

FEB

MAR

APR

JUNE

MAR

APR

MAY

JULY

SEPT

AUG

OCT

SEPT

NOVNOV

DEC

20

14

JAN

MAR

FEB

APR

MAY

JUNE

AUG

JULY

SEPT

NOV

OCT

FEB

APR

MAR

JUNE

MAY

JULY

AUG

SEPT

DEC

20

15

JAN

MAR

FEB

APR

MAY

APR

MAR

Powering tests

ELQA

Warm-upLeak tests

ELQA

Leak tests

Preparation

ELQA

Flushing

ELQA

Cool-down

ELQA

Powering tests

Powering testsELQA

Warm-up

Leak tests

ELQALeak tests

Preparation

ELQA

Flushing

ELQACool-down

ELQA

Powering tests

Powering tests

ELQA

Warm-upLeak tests

ELQALeak tests

Preparation

ELQA

Flushing

ELQACool-down

ELQA

Powering tests

Powering testsELQA

Warm-upLeak tests

ELQA

Leak tests

Preparation

ELQA

Flushing

ELQACool-down

ELQA

Powering tests

Powering testsELQA

Warm-upLeak tests

ELQALeak tests

Preparation

ELQA

Flushing

ELQA

Cool-down

ELQA

Powering tests

Powering tests

ELQA

Warm-upLeak tests

ELQA

Leak tests

Preparation

ELQA

Flushing

ELQA

Cool-down

ELQA

Powering tests

Powering tests

ELQA

Warm-upLeak tests

ELQA

Leak tests

Preparation

ELQA

Flushing

ELQA

Cool-down

ELQA

Powering tests

Powering tests

ELQA

Warm-up

ELQALeak tests

Preparation

ELQA

Flushing

ELQACool-down

ELQA

Powering tests

Leak testsCSCM

lockoutlockout

lockout

lockout lockoutlockout lockout

lockout

Beam Commissioning

Physics

Test DSO

IC total

IC total

IC total

IC total

IC total

IC total

IC total

DFB

AJ

DFB

AK

DFB

AL

DFB

AM

DFB

AN

DFB

AO

DFB

AP

DFB

AA

DFB

AB

DFB

AC

DFB

AD

DFB

AE

DFB

AF

DFB

AG

DFB

AH

DFB

AI

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

DYPB

EPC 60A

EPC 60A

EPC 60A

EPC 60A

EPC 60A

EPC 60A

EPC 60A

EPC 60A

EPC 60A

EPC 60A

EPC 60A

EPC 60A

EPC 60A

EP

EP

EP

EP

EP

EP

EP

EP

EE

EE

EE

EE

DFB

XE

DFB

XFIT D

N30

0

IT D

N30

0

Cryo

QRL

ser

v.

mod

ules

DFB

XG

DFB

XHIT D

N30

0

IT D

N30

0

Cryo

DFB

XA

DFB

XB

Cryo

IT D

N30

0

IT D

N30

0

DFB

XC

DFB

XD

IT D

N30

0

IT D

N30

0

Cryo

QRL leak repair

Cryo

B30R

7

B21L

8Q

5L8

C15R

1A2

2R1

C30R

1C3

3R1

C33L

2A2

9L2

B25R

2

C15L

3 A23R

2Q

23R3

A26R

3Q

27R3

B32R

3

C17R

4B3

1R4

Prepa. Works

Dis

man

tling

Pipi

ngCa

blin

g

OF

Cryo

.Et

h.PC

WCC

Pipe

s &

COM

. # E

quip

.

Com

. PC

Shei

ldin

g Ve

rt

SheildingsAccess

Prepa. Works

Prepa. Works

Dis

man

tling

Pipi

ngCa

blin

g

OF

Cryo

Eth.

PCW

CCPi

pes &

CO

M. #

Equ

ip.

Com

. PC

Shei

ldin

gs

SheildingsAccess

Porte

Prepa. Works

Cabl

ing

Dis

man

tling

Civil eng.

Pipi

ng a

nd v

enti

lati

on

Safe

-roo

m (I

)

Cabl

e tr

ays

Shie

ldin

g RR

53Sh

ield

ing

RR57

UPS

Mov

e ra

cks

OF

PC

WCC

Mov

e ra

cks OF

Eth.

Div

erse

wor

ks

Cryo

geni

csU

TA &

C Com

. PC

UTA Ac

cess Sa

fe-r

oom

Al

arm

s

Dis

man

tling

Cabl

ing

Civil eng.

Cabl

e tr

ays

UTAOF

RR

RR

Rack

sRa

cks

Alar

ms

R2E-Test Fire Detection

UPS

EEt

h.

Tabl

eauti

n

Pip

Mov

e ra

cks

Cryo

geni

csVa

cuum

Vacu

um

Acce

ss

PCCo

m. P

C UTA

COM

. # E

quip

.

RR

RR

R2E-Test Evacuation

Disconnect

Eth.

Mo

UPS

Mo

CV a

ctivi

ties

Cryo

geni

csCa

blin

gSh

ield

ing

Shielding

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

Beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

beam

vac

uum

A7L1A4L1

A1L

A1R

A4R

A7R

A7L2

A6L

I5L2

MKIs

A5L

C4L

B4L2

A4L

B1L

A1L

A1R

A4R2

A5R

A7R2

A7L

B5L

A5L

A4L

IP3

A5R

B5R

A7R

A7L

E5L4

D5L

IP4

B5R4

D5R

E5R4

A6R

A7R

A7L

A5L5

B4L

A4L

A1L

A1R

A4R

B4R

A5R

A7R

E5L

A5L

A4L

IP6

A4R

A5R6

C5R

A7L

A6L

B5L7

A5L7

IP7

A4R

A5RB5R

A6R

A7R

A7L

A6L

A5L

A4L

A1L

A4R

B4R8

c4R

A5R

MKIs

I5RA6R

A7R8

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Surv

ey

Cabl

ing

Cabl

ing

Cabl

ing

Cabl

ing

Cabl

ing

Cabl

ing

Cabl

ing

Cabl

ing

Cabling

Cabl

ing

Cabl

ing

Cabling

Cabling

Cabl

ing

Cabl

ing

Cabling

Cabl

ing

Cabl

ing

Cabling

Cabl

ing

Cabl

ing

Cabling

Cabl

ing

Cabl

ing

Cabl

ing

Cabl

ing

Cabl

ing

Cabl

ing

Cabl

ing

Cabl

ing

WCC

WCC

WCC

WCC

WCC

SC te

sts

SC te

sts

SC te

sts

SC te

sts

SC te

sts

UPS

UPS

SF M

aint

enan

ce

UPS

UPS

UPS

SF M

aint

enan

ceU

W M

aint

enan

ceU

W U

pgra

de

SU M

aint

enan

ce

UPS

UPS

UPS

UPS

UPS

SF M

aint

enan

ceN

ew S

F

UW

Mai

nten

ance

UW

Upg

rade

SU M

aint

enan

ce

UPS

UPS

UPS

UPS

UPS

SF M

aint

enan

ceN

ew S

FU

W M

aint

enan

ceU

W U

pgra

deSU

Mai

nten

ance

UPS

UPS

UPS

UPS

UPS

SF M

aint

enan

ceN

ew S

FU

W M

aint

enan

ceU

W U

pgra

deSU

Mai

nten

ance

Electrical Maintenance - No accessElectrical Maintenance - No access

Electrical Maintenance - No access

Electrical Maintenance - No access

Electrical Maintenance - No access

Electrical Maintenance - No access

Electrical Maintenance - No access

Electrical Maintenance - No access

Electrical Maintenance - No access

Acc.

PAD_MADPAD_MAD

PAD_MAD

PAD_MAD PAD_MADPAD_MAD PAD_MAD

PAD_MAD

PAD_MAD PAD_MAD

PAD_MAD

PAD_MADPAD_MAD

PAD_MADPAD_MAD

PAD_MAD

PAD_MAD

PAD_MAD PAD_MAD

Acc.

PAD_MAD

PAD_MAD

PAD_MAD

PAD_MAD

PAD_MAD

PAD_MAD

PAD_MAD

Prepared by Checked by Approved by

M. BarberanM. BernardiniJ. CoupardK. Foraz

Klys

tron

sSi

licon

oil r

econ

ditio

nnin

g

MKD

-MKB

gen

erat

ors

MD

-MKB

test

s

MD

-MKB

test

s

Christmas

MKD

-En

try

boxe

s

MKD

-En

try

boxe

s

R2E-Test Fire Detection

LHCF

LHCF

UW

SF M

.

UW

SF

M.

UW

SF

M.

UW

SF

M.

13 TeV operation

Page 11: LHC Machine Upgrade Overall Frédérick Bordry

11LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

http://cern.ch/ls1dashboard

LHC injectors getting ready for hardware testsLHC: all signals are green for beam on January 2015LS 1

Page 12: LHC Machine Upgrade Overall Frédérick Bordry

12LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

LS1 statusLHC injectors getting ready for hardware tests

LHC: all signals are green for beam on January 2015

Yogi Berra

Page 13: LHC Machine Upgrade Overall Frédérick Bordry

13LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Run 2 Run 3

Run 4

LS 2

LS 3

LS 4 LS 5Run 5

LS2 starting in 2018 (July) => 18 months + 3 months BC LS3 LHC: starting in 2023

LHC schedule: Run2 and Run 3

Beam commissioning

Technical stop

Shutdown

Physics

LHCb b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

Injectorso o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

t

LHCo o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

Injectorso o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

LHCb b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

Injectorsb b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

2015 2016 2017 2018 2019Q4 Q1 Q2

2020 2021Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q3 Q4

2022 2023 2024 2025 2026 2027 2028

Q1 Q2 Q3 Q4 Q1 Q2Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3

Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q1 Q2 Q3 Q4

2029 2030 2031 2032 2033 2034

Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2Q3 Q4

Q2 Q3 Q4 Q1 Q2 Q32035

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q4Q2 Q3 Q4 Q1 Q2 Q3Q4 Q1 Q2 Q3 Q4 Q1

Run 2 Run 3

Run 4

LS 2

LS 3

LS 4 LS 5Run 5

(Extended) Year End Technical Stop: (E)YETS

EYETSYETS YETS YETS

YETS

YETS

300 fb-1

30 fb-1

Page 14: LHC Machine Upgrade Overall Frédérick Bordry

14LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Expectations after Long Shutdown 1 (2015)

• Collisions at least at 13 TeV c.m.• 25 ns bunch spacing

Using new injector beam production scheme (BCMS), resulting in brighter beams.

Number of

bunches

Intensity per bunch

Transverse emittance

Peak luminosity

Pile up

Int. yearlyluminosity

25 ns BCMS 2508 1.15 × 1011 1.9 µm 1.6×1034 cm-2s-1 ~43 ~42 fb-1

• β* ≤ 0.5m (was 0.6 m in 2012)• Other conditions:

– Similar turn around time– Similar machine availability

• Expected maximum luminosity: 1.6 x 1034 cm-2 s-1 ± 20%– Limited by inner triplet heat load limit, due to collisions debris

Courtesy of the LIU-PS project team

Batch Compression and Merging and splitting (BCMS)

Page 15: LHC Machine Upgrade Overall Frédérick Bordry

15LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Number of

bunches

IbLHC

[1e11]

Collimator

scenario

EmitLHC

(SPS)[um]

Peak Lumi[cm-2s-1]

~Pile-up

Int. Lumi[fb-1]

25 ns 2760 1.15 S13.5

(2.8) 9.2e33 21 24

25 nslow emit

2508 1.15 S41.9

(1.4) 1.6e34 43 42

50 ns 1380 1.6 S1 2.3 (1.7)

1.7e34levelling0.9e34

76levelling

40 ~45*

50 nslow emit 1260 1.6 S4

1.6 (1.2) 2.2e34 108 …

• 6.5 TeV• 1.1 ns bunch length• 150 days proton physics, HF = 0.2

All numbers approximate

* different operational model – caveat - unproven

Courtesy Mike Lamont

Potential performance

Page 16: LHC Machine Upgrade Overall Frédérick Bordry

16LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

LINAC4 – PS Booster:– H- injection and increase of PSB injection energy from 50 MeV to 160 MeV, to

increase PSB space charge threshold– New RF cavity system, new main power converters– Increase of extraction energy from 1.4 GeV to 2 GeV

These are only the main modifications and this list is far from exhaustive

Project leadership: R. Garoby and M. Meddahi

LS2 : (2018), LHC Injector Upgrades (LIU)

SPS− Electron Cloud mitigation – strong feedback system, or coating of the vacuum system− Impedance reduction, improved feedbacks− Large-scale modification to the main RF system

PS:− Increase of injection energy from 1.4 GeV to 2 GeV to increase PS

space charge threshold− Transverse resonance compensation− New RF Longitudinal feedback system − New RF beam manipulation scheme to increase beam brightness

Page 17: LHC Machine Upgrade Overall Frédérick Bordry

17LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Run 2 Run 3

Run 4

LS 2

LS 3

LS 4 LS 5Run 5

LS2 starting in 2018 (July) => 18 months + 3 months BC LS3 LHC: starting in 2023 => 30 months + 3 months BC

Injectors: in 2024 => 13 months + 3 months BC

LHC schedule: Run2 and Run 3

Beam commissioning

Technical stop

Shutdown

Physics

LHCb b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

Injectorso o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

t

LHCo o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

Injectorso o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

LHCb b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

Injectorsb b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

2015 2016 2017 2018 2019Q4 Q1 Q2

2020 2021Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q3 Q4

2022 2023 2024 2025 2026 2027 2028

Q1 Q2 Q3 Q4 Q1 Q2Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3

Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q1 Q2 Q3 Q4

2029 2030 2031 2032 2033 2034

Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2Q3 Q4

Q2 Q3 Q4 Q1 Q2 Q32035

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q4Q2 Q3 Q4 Q1 Q2 Q3Q4 Q1 Q2 Q3 Q4 Q1

Run 2 Run 3

Run 4

LS 2

LS 3

LS 4 LS 5Run 5

(Extended) Year End Technical Stop: (E)YETS

EYETSYETS YETS YETS

YETS

YETS

300 fb-1

30 fb-1

LS3 : HL-LHC installation

LHC schedule: LS3

Page 18: LHC Machine Upgrade Overall Frédérick Bordry

18LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Why High-Luminosity LHC ? (LS3)

By continuous performance improvement and consolidation

By implementing HL-LHC

Almost a factor 3

Goal of HL-LHC project:• 250 – 300 fb-1 per year• 3000 fb-1 in about 10 years

Page 19: LHC Machine Upgrade Overall Frédérick Bordry

19LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

c) Europe’s top priority should be the exploitation of the full potential of the LHC, including the high-luminosity upgrade of the machine and detectors with a

view to collecting ten times more data than in the initial design, by around 2030. This upgrade programme will also provide further exciting opportunities for the study of flavour physics and the quark-gluon plasma.

HL-LHC from a study to a PROJECT300 fb-1 → 3000 fb-1

including LHC injectors upgrade LIU (Linac 4, Booster 2GeV, PS and SPS upgrade)

The European Strategy for Particle Physics Update 2013

Page 20: LHC Machine Upgrade Overall Frédérick Bordry

20LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

tod

ay

“…exploitation of the full potential of the LHC, including the high-luminosity upgrade of the machine and detectors…”

=> High Luminosity LHC project

ProjectKick-off meeting: 11th Nov. 2013

(Daresbury)

http://cern.ch/hilumilhc

Page 21: LHC Machine Upgrade Overall Frédérick Bordry

21LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

The HL-LHC Project

• New IR-quads Nb3Sn (inner triplets)

• New 11 T Nb3Sn (short) dipoles

• Collimation upgrade• Cryogenics upgrade• Crab Cavities• Cold powering• Machine protection• …

Major intervention on more than 1.2 km of the LHC Project leadership: L. Rossi and O. Brüning

Page 22: LHC Machine Upgrade Overall Frédérick Bordry

22LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Squeezing the beams: High Field SC Magnets

Courtesy Lucio Rossi

Quads for the inner triplet Decision 2012 for low-β quadsAperture 150 mm – 140 T/m (Bpeak ≈12.3 T)

(LHC: 8 T, 70 mm )

- Dipoles 11 T for LS2

More focus strength, * as low as 15 cm (55 cm in LHC)thanks to ATS (Achromatic Telescopic Squeeze) opticsIn some scheme even * down to 7.5 cm are considered

- Dipoles for beam recombination/separation capable of 6-8 T with 150-180 mm aperture (LHC: 1.8 T, 70 mm)

Page 23: LHC Machine Upgrade Overall Frédérick Bordry

23LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Target:200 T/m gradient at 1.9 K

LQS01a: 202 T/m at 1.9 KLQS01b: 222 T/m at 4.6 K 227 T/m at 1.9 K

LQS02: 198 T/m at 4.6 K 150 A/s 208 T/m at 1.9 K 150 A/s limited by one coil

LQS03: 208 T/m at 4.6 K 210 T/m at 1.9 K1st quench: 86% s.s. limit

3.3 m coils90 mm aperture

LQS of LARPCourtesy: G. Ambrosio FNALand G. Sabbi , LBNL

Page 24: LHC Machine Upgrade Overall Frédérick Bordry

24LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

A GLOBAL PROJECT

20 40 60 80 100 120 140 160 180distance to IP (m)

Q1 Q3Q2a Q2b D1

Q1-3: 140 T/mMCBX: 2.2 T 2.5/4.5 T mD1: 5.6 T 35 T mD2: 3.5 T 35 T mQ4: 120 T/m D2 Q4

Baseline layout of HL-LHC IR region

Setting up International collaboration

but also involving industrial firms with national laboratories

Page 25: LHC Machine Upgrade Overall Frédérick Bordry

25LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Crab Cavities, Increase “Head on”

Aim: reduce the effect of the crossing angle

DQWR prototype17-Jan-2013

RF-Dipole Nb prototype

Without crabbing Without crabbing

• 3 proto types available• Cavity tests are on-going• Test with beam in SPS foreseen in

2015-2016• Beam test in LHC foreseen in 2017

New crossing strategy under study to soften the pile-up density: some new schemas have interesting potential as “crab-kissing”, to be discussed with all experiments

Page 26: LHC Machine Upgrade Overall Frédérick Bordry

26LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

R2E: Removal of Power Converter (200kA-5 kV SC cable, 100 m height)

Φ = 62 mm

7 × 14 kA, 7 × 3 kA and 8 × 0.6 kA cables – Itot120 kA @ 30 K

MgB2

(or other HTS)

Also DFBs (current lead boxes) removed to surface Final solution to R2E problem – in some pointsMake room for shielding un-movable electronicsMake the maintenance and application of ALARA principle much easier and effective

Page 27: LHC Machine Upgrade Overall Frédérick Bordry

27LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Luminosity Levelling, a key to success

• High peak luminosity• Minimize pile-up in

experiments and provide “constant” luminosity

• Obtain about 3 - 4 fb-1/day (40% stable beams)

• About 250 to 300 fb-1/year

Page 28: LHC Machine Upgrade Overall Frédérick Bordry

28LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

25 ns 50 ns

# Bunches 2808 1404

p/bunch [1011] 2.0 (1.01 A) 3.3 (0.83 A)

eL [eV.s] 2.5 2.5

sz [cm] 7.5 7.5

sdp/p [10-3] 0.1 0.1

gex,y [mm] 2.5 3.0

b* [cm] (baseline) 15 15

X-angle [mrad] 590 (12.5 s) 590 (11.4 s)

Loss factor 0.30 0.33

Peak lumi [1034] 6.0 7.4

Virtual lumi [1034] 20.0 22.7

Tleveling [h] @ 5E34 7.8 6.8

#Pile up @5E34 123 247

25 ns is the option However:50 ns should be kept as alive and possible because we DO NOT have enough experience on the actual limit (e-clouds, Ibeam)

Baseline parameters of HL for reaching 250 -300 fb-1/year

Courtesy Oliver Brüning

Continuous global optimisation with LIU

Page 29: LHC Machine Upgrade Overall Frédérick Bordry

29LHC Machine Upgrade OverallFrédérick Bordry ACES2014 – 18th March 2014

Run 2 Run 3

Run 4

LS 2

LS 3

LS 4 LS 5Run 5

LHC schedule approved by CERN management and LHC experiments spokespersons and technical coordinators (December 2013)

LS2 starting in 2018 (July) => 18 months + 3 months BC LS3 LHC: starting in 2023 => 30 months + 3 months BC

Injectors: in 2024 => 13 months + 3 months BC

LHC roadmap: schedule beyond LS1

Beam commissioning

Technical stop

Shutdown

Physics

LHCb b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

Injectorso o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

t

LHCo o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

Injectorso o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

LHCb b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

Injectorsb b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

2015 2016 2017 2018 2019Q4 Q1 Q2

2020 2021Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q3 Q4

2022 2023 2024 2025 2026 2027 2028

Q1 Q2 Q3 Q4 Q1 Q2Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3

Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q1 Q2 Q3 Q4

2029 2030 2031 2032 2033 2034

Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2Q3 Q4

Q2 Q3 Q4 Q1 Q2 Q32035

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q4Q2 Q3 Q4 Q1 Q2 Q3Q4 Q1 Q2 Q3 Q4 Q1

Run 2 Run 3

Run 4

LS 2

LS 3

LS 4 LS 5Run 5

(Extended) Year End Technical Stop: (E)YETS

EYETSYETS YETS YETS

YETS

YETS

300 fb-1

3’000 fb-1

30 fb-1

Page 30: LHC Machine Upgrade Overall Frédérick Bordry