Levels of a programme_schedule.doc Levels of a programme / schedule, number 1 By John Keeton 23 rd May 2005 When producing programmes for a project, I use the following levels of programmes: LEVEL 1 : Project Management overview schedule/programme, by Project Phase.  LEVEL 2 : Area or Process/Utility Unit schedule/pro gramme, by Project Phase by A rea or Unit. LEVEL 3 : Discipline schedule/prog ramme, by Project Phase by Area/Unit by Single or Multi-disciplines.  LEVEL 4 : Main Activities schedule/programme , by P roject Phase by Area/Unit by Single or Multi-disciplines by Main Activities.  LEVEL 5 : Detail Activities schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines by Detail A ctivities.  LEVEL 6 : Micro-detail Activities schedule/pro gramme, by Project Phase by Area/Unit by Single or Multi-disciplines by Micro-detail Activities.  

Levels of Program

Embed Size (px)

Citation preview

 

Levels of a programme_schedule.doc 

Levels of a programme / schedule, number 1By John Keeton23rd May 2005

When producing programmes for a project, I use the following levels of programmes:

LEVEL 1 : Project Management overview schedule/programme, by Project Phase.  

LEVEL 2 : Area or Process/Utility Unit schedule/programme, by Project Phase by Areaor Unit. 

LEVEL 3 : Discipline schedule/programme, by Project Phase by Area/Unit by Single orMulti-disciplines. 

LEVEL 4 : Main Activities schedule/programme, by Project Phase by Area/Unit by Singleor Multi-disciplines by Main Activities.  

LEVEL 5 : Detail Activities schedule/programme, by Project Phase by Area/Unit bySingle or Multi-disciplines by Detail Activities. 

LEVEL 6 : Micro-detail Activities schedule/programme, by Project Phase by Area/Unit bySingle or Multi-disciplines by Micro-detail Activities.