Upload
raoufi-mustapha
View
222
Download
0
Embed Size (px)
Citation preview
8/3/2019 Levelized Cost of Electricity
1/27
T h e D r i v e r s o f T h e
Llzd Ct e ctcty Utlt-SclPtltcs
s u npower CorporaT on
14 August 2008
8/3/2019 Levelized Cost of Electricity
2/27
s un powe r 2
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
eXeCuTive suMMarY
For more than three decades, utilit-scale solar generated electricit has been dismissed as too costl.
But the cost of solar generated electricit is consistentl coming down, while the cost of conventionalelectricit is increasing. Advances in solar cell technolog, conversion efcienc and sstem
installation have allowed utilit-scale photovoltaic (PV) to achieve cost structures that are competitive
with other peaking power sources. The calculation of the levelized cost of electricit (LCOE) provides
a common wa to compare the cost of energ across technologies because it takes into account
the installed sstem price and associated costs such as nancing, land, insurance, transmission,
operation and maintenance, and depreciation, among other epenses. Carbon emission costs and
solar panel efcienc can also be taken into account. The LCOE is a true apples-to-apples comparison.
Around the globe, the solar industr has installed approimatel 10 gigawatts of solar PV sstems.Pacic Gas & Electric Co. has announced more than 2 gigawatts of agreements involving both solar
thermal and PV technologies, including 800 megawatts of photovoltaic power the largest utilit-scale
contracts for PV in the world. SunPowers 250 megawatt central station, high-efcienc, PV power
plant in California Valle will be the rst to deliver utilit-scale PV power to PG&E. These solar power
plants are vivid eamples of how the electricit production landscape is changing rapidl to embrace
a much broader portfolio of renewable resources. The LCOE equation sorts through the relative costs
of such sstems and pinpoints the increasingl positive economics for harvesting the worlds most
abundant energ resource sunshine.
The economies of scale inherent in utilit-scale solar sstems are similar to those found with other
power options, but PV has the benet of being completel modular PV works at a 2 kilowatt
residential scale, at a 2 megawatt commercial scale or at a 250 megawatt utilit scale. PV has the
unique advantage among renewable resources of being able to produce power anwhere: deserts,
cities or suburbs. Smaller scale PV costs more on an LCOE basis, but it can be selectivel deploed on
the grid wherever and whenever needed to reduce distribution capacit constraints and transmission
congestion while producing pollution-free power. All PV can be constructed quickl and even utilit-
scale power plants can begin delivering power within a few quarters of contract signing a major
advantage when compared to conventional power plants. At SunPower, we serve customers across thespectrum, from small-scale to utilit-scale solar, because each application has distinctive advantages
and will contribute to driving solar power to become a major source of carbon-free power.
T LCoe eqt Ky t eltg emgg egy Tclg
The LCOE equation is an evaluation of the life-ccle energ cost and life-ccle energ production. It
allows alternative technologies to be compared when different scales of operation, investment or
operating time periods eist. For eample, the LCOE could be used to compare the cost of energ
8/3/2019 Levelized Cost of Electricity
3/27
s un powe r 3
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
generated b a PV power plant with that of a fossil fuel-generating unit or another renewable
technolog.1 It captures capital costs, ongoing sstem-related costs and fuel costs along with the
amount of electricit produced and converts them into a common metric: $/kWh.
wt d LCoe dct pv?
Both capital costs and operating and maintenance costs are driven b the choice of technolog and
the area of the solar sstem. We outline in this paper how the following ke factors drive the LCOE for
solar PV power plants.
1) Panel Efcienc: SunPowers high-efcienc solar panels generate up to 50 percent more power
than conventional technolog and up to four times as much power as thin lm technologies,
thereb lowering area-related costs.
2) Capacit Factor: SunPowers tracker technolog can increase energ production from solar panels
b up to 30 percent, further reducing area-related costs and contributing more high-value energ
during afternoon hours than ed-tilt sstems.
3) Reliable Sstem Performance and Lifetime: SunPowers established crstalline silicon technolog,
with its histor of consistent, predictable performance, reduces power plant nancing costs
lowering the LCOE.
Sunlight is a diffuse energ resource.
Maimizing energ production per panel area
is critical to achieve the best LCOE in a utilit-
scale PV power plant. As shown in Figure 1, if
a PV power plant with 1 terawatt hour (TWh)
of annual energ production is built with
SunPower high-efcienc PV panels mounted
on solar trackers, up to 75 percent less panel
area is required when compared with thin lm
technolog mounted in a ed tilt conguration.
This energ production densit leverages almost all PV power plant ed plant and operation and
maintenance (O&M) costs, directl reducing the sstem LCOE.
Based on the LCOE, SunPowers high-efcienc power plants generate energ at a price competitive
with other peak power resources. Given our technolog roadmap and LCOE forward cost curve, we
epect our high-efcienc silicon PV technolog to maintain that competitive position.
1 W. Short, D. Packe, T. Holt, A Manual for the Economic Evaluation of Energ E fficienc and Renewable Energ Technologies,National Renewable Energ Laborator March 1995
0.0
0.5
1.0
1.5
2.0
2.5
SunPower T20 Tracker 11% CIGS/CdTe Fixed
Tilt
6% aSi Fixed Tilt
Square M iles of PV Panels per 1 TWh
Sq. Miles of
PV
fg 1 - PV Panel Area Required for 1 TWh Annual Production
8/3/2019 Levelized Cost of Electricity
4/27
s un powe r 4
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
Tbl Cntnts
I. The LCOE Equation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5A. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
B. Major LCOE Inputs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1. Initial Investment . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2. Depreciation Ta Benet . . . . . . . . . . . . . . . . . . . . . . 6
3. Annual Costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4. Sstem Residual Value . . . . . . . . . . . . . . . . . . . . . . . 7
5. Sstem Energ Production . . . . . . . . . . . . . . . . . . . . 7
C. The LCOE Model Sensitivit. . . . . . . . . . . . . . . . . . . . . . . 8
II. LCOE Variables for Utilit-Scale PV . . . . . . . . . . . . . . . . . . . 9
A. PV Power Plant Performance . . . . . . . . . . . . . . . . . . . . . 9
1. Sstem Capacit Factor . . . . . . . . . . . . . . . . . . . . . . . 9
2. PV Panel Performance and Lifetime . . . . . . . . . . . 12
3. Predicting Sstem Performance . . . . . . . . . . . . . . 14
B. Initial PV Power Plant Investment . . . . . . . . . . . . . . . . 15
1. PV Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2. Area-Related Epenses. . . . . . . . . . . . . . . . . . . . . . 173. Land Use and Epense . . . . . . . . . . . . . . . . . . . . . . 19
4. Grid Interconnection Costs . . . . . . . . . . . . . . . . . . . 21
C. PV Power Plant Operating Epenses . . . . . . . . . . . . . . 21
D. Sstem Residual Value . . . . . . . . . . . . . . . . . . . . . . . . . 24
E. SunPowers LCOE Forecasting Tool . . . . . . . . . . . . . . . 24
III. Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
8/3/2019 Levelized Cost of Electricity
5/27
s un powe r 5
-
i. T LCoeequtn
The recent announcements of a wide variet of utilit-scale solar
photovoltaic (PV) power projects provide evidence that utilit-scale
PV is now reaching levels that are price competitive on a levelized
cost of electricit (LCOE) basis with other peak power sources.
Deriving a utilit-scale PV LCOE requires a range of inputs which
this paper discusses in detail. It also will review the LCOE benets
of high-efcienc silicon PV technolog for utilit-scale solar power
plants.
a. i tdctThe LCOE equation is one analtical tool that can be used to compare
alternative technologies when different scales of operation, invest-
ment or operating time periods eist. For eample, the LCOE could
be used to compare the cost of energ generated b a PV power
plant with that of a fossil fuel generating unit or another renewable
technolog.
The calculation for the LCOE is the net present value of total life
ccle costs of the project divided b the quantit of energ produced
over the sstem life.
The above LCOE equation can be disaggregated for solar generation
as follows:
W. Short, D. Packe, T. Holt, A Manual for the Economic Evaluation of Energ Efcienc andenewable Energ Technologies, National Renewable Energ Laborator March 1995
8/3/2019 Levelized Cost of Electricity
6/27
s un powe r 6
-
When evaluating the LCOE and comparing other commonl known
$/kWh benchmarks it is important to remember that the LCOE is an
evaluation of levelized life ccle energ costs. The price of energ
established under Power Purchase Agreements (PPAs) or b feed-
in-tariffs (FITs) ma differ substantiall from the LCOE of a given
PV technolog as the ma represent different contract or incentive
durations, inclusion of incentives such as ta benets or accelerated
depreciation, nancing structures, and in some cases, the value of
time of da production tariffs.
B. Mj LCoe i t
1. INITIAL INVESTMENT
The initial investment in a PV sstem is the total cost of the projectplus the cost of construction nancing. The capital cost is driven b:
a-ltd ct which scale with the phsical size of
the sstem namel the panel, mounting sstem, land, site
preparation, eld wiring and sstem protection.
Gd tcct ct which scale with the peak power
capacit of the sstem including electrical infrastructure such
as inverters, switchgear, transformers, interconnection relas
and transmission upgrades.
pjct-ltd ct such as general overhead, sales and
marketing, and site design which are generall ed for similarl
sized projects.
2. DEPRECIATION TAx BENEFIT
The depreciation ta benet is the present value of the depreciation
ta benet over the nanced life of the project asset. Public policwhich enables accelerated depreciation directl benets the sstem
LCOE because faster depreciation translates to faster recognition of
the depreciation benet.
8/3/2019 Levelized Cost of Electricity
7/27
s un powe r 7
-
3. ANNUAL COSTS
In the LCOE calculation the present value of the annual sstem
operating and maintenance costs is added to the total life ccle
cost. These costs include inverter maintenance, panel cleaning,
site monitoring, insurance, land leases, nancial reporting,
general overhead and eld repairs, among other items.
. SySTEM RESIDUAL VALUE
The present value of the end of life asset value is deducted from
the total life ccle cost in the LCOE calculation. Silicon solar panels
carr performance warranties for 25 ears and have a useful life
that is signicantl longer. Therefore if a project is nanced for a 10-
or 15-ear term the project residual value can be signicant.
5. SySTEM ENERGy PRODUCTION
The value of the electricit produced over the total life ccle of the
sstem is calculated b determining the annual production over the
ife of the production which is then discounted based on a derived
discount rate. The rst-ear energ production of the sstem is
epressed in kilowatt hours generated per rated kilowatt peak ofcapacit per ear (kWh/kWp). The kWh/kWp is a function of:
The amount of sunshine the project site receives in a ear
How the sstem is mounted and oriented (i.e. at, ed tilt,
tracking, etc.)
The spacing between PV panels as epressed in terms of
sstem ground coverage ratio (GCR)
8/3/2019 Levelized Cost of Electricity
8/27
s un powe r 8
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
The energ harvest of the PV panel (i.e. performance sensitivit
to high temperatures, sensitivit to low or diffuse light, etc.)
Sstem losses from soiling, transformers, inverters and wiring
inefciencies
Sstem availabilit largel driven b inverter downtime
To calculate the quantit of energ produced in future ears, a
sstem degradation rate is applied to initial sstem performance
to reect the wear of sstem components. The sstem degradation
(largel a function of PV panel tpe and manufacturing qualit)
and its predictabilit is an important factor in life ccle costs as it
determines the probable level of future cash ows.
Finall, the sstems nancing term will determine the duration ofcash ows and impact the assessment of the sstem residual value.
C. T LCoe Mdl stty
The LCOE is highl sensitive to small changes in input variables
and underpinning assumptions. For this reason, it is important to
carefull assess and validate the assumptions used for different
technologies when comparing the LCOE.
Figure 2 illustrates the models sensitivit to input assumptions. We
provide three scenarios that all start with the same PV sstem price
and predicted energ output using a tracker in a high insolation3
location. We then modif 1) the annual degradation rate, 2) the
forecasted economic life, 3) the annual O&M epense, and 4) the
discount rate. The resulting LCOE for the three scenarios range from
$0.09 / kWh to $0.23 / kWh, illustrating that for the same sstem
capital cost and initial energ output the range of energ prices can
var b a factor of two or more. Comparing LCOE calculations and
power plant energ pricing requires aligning assumptions across
eamples and calibrating against empirical data to generate a moreaccurate LCOE forecast.
3 Insolation is the level of solar radiation received at a given location
8/3/2019 Levelized Cost of Electricity
9/27
s un powe r 9
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
One use for LCOE calculations is to compare costs without
incentives. If incentives such as the U.S. Investment Ta Credit (ITC)
are assumed in an LCOE calculation the should be specicallreferenced to make clear the basis for comparison between
technologies.
Given the high sensitivit of the LCOE to input variables, it is
important to understand the validit of performance output over
a sstems lifetime. Silicon PV sstems have been operating
outdoors for more than 20 ears4 and therefore the performance
and degradation mechanisms are well understood. For silicon-
based PV sstems it is possible to accuratel forecast future output
allowing one to populate the LCOE equation variables with a high
level of condence.
To understand the LCOE outlook for utilit-scale PV it is important to
understand the lifetime sstem performance and cost. The following
sections summarize ke cost and performance drivers for a utilit-
scale PV power plant.
a. pv p plt pmcThe lifetime energ generated from a PV power plant is a product
of the plant location, annual performance for a given capacit,
component degradation and sstem lifetime.
fg 2
Solar PV LCOESensitivit toVariable Changes
C 1 C 2 C 3
Sstem Price 100% 100% 100%
kWh/kWp 100% 100% 100%Annual Degradation 1.0% 0.5% 0.3%
Sstem Life 15 25 40
Annual O&M $/kWh $0.030 $0.010 $0.005
Discount Rate 9% 7% 5%
LCOE $/kWh $0.23 $0.13 $0.09
ii. LCoevbls
Utlt-Scl Pv
4 E. Dunlop, D. Halton, H. Ossenbrink, 20 years of Life and More: Where is the End of Life ofa PV Module? IEEE Proceedings 2005, p.1595
8/3/2019 Levelized Cost of Electricity
10/27
s un powe r 10
-
CapacityFactor(AC)
Sstem Price $ / Wp (DC)
20%
22%
24%
26%
28%
30%
32%
34%
36%
38%
40%
$2.00 $2.50 $3.00 $3.50 $4.00
ssmlml rrg g eeqlt LCqlt LCoeoe vv ll
1. SySTEM CAPACITy FACTOR
The capacit factor is a ke driver of a solar projects economics.
With the majorit of the epense of a PV power plant being ed,
capital cost LCOE is strongl correlated to the power plants
tilization. The annual capacit factor for a PV power plant is
calculated as:
A PV power plants capacit factor is a function of the insolation at
the project location, the performance of the PV panel (primaril as it
relates to high temperature performance), the orientation of the PVpanel to the sun, sstem electrical efciencies and the availabilit of
the power plant to produce power.
7
Annual kilowatt -hours generated for eac h kilowatt AC of peak ca pacity (kWh/kW p)
8760 hours in a year
fg 3
Associated Capacit Factorsand Sstem Prices Producing
an Identical LCOE5
Capacit factor is generall epressed as a function of the AC rating of a plant so the abovekWh/kWp calculation is based on the kWh per AC watt peak as opposed to the DC watt peak
8/3/2019 Levelized Cost of Electricity
11/27
s un powe r 11
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
The economic impact of the capacit factor is substantial. Figure 3
illustrates a range of identical LCOE values, epressed in $/kWh,
for a given PV power plant sstem price as epressed in $/Wp and
the associated capacit factor. As the capacit factor declines, the
required installed sstem price must also substantiall decline to
maintain sstem economics. For eample, a $2.50/Wp sstem with
a 24 percent capacit factor (such as with a ed tilt conguration)
delivers the same LCOE as a $3.50/Wp sstem with a 34 percent
capacit factor (such as with a tracker). The highest capacit factorsare generated with trackers which follow the sun throughout the
da to keep the panel optimall oriented towards the sun. This
tracking also has the benet of generating more energ in the
peak electricit demand periods of the afternoon. SunPower has
developed two patented tracking sstems to optimize the capacit
factor of a PV power plant: the T0 Tracker optimized for space-
constrained sites and the T20 Tracker optimized for maimum
energ production.
fg 4 - SunPws T0 Tck fg 5 - SunPws T20 Tck
8/3/2019 Levelized Cost of Electricity
12/27
s un powe r 12
-
The LCOE model assigns an equal value to electricit generated
throughout the ear. However, electricit generated at peak
periods is more valuable to the utilit. The use of tracking with a
solar sstem can increase the output of a plant after 4 p.m. in the
summer b more than 40 percent, which is often a period of peak
demand on the sstem when energ is highl valued. Figure 6 gives
a comparison for the summer energ output of a ed and tracking
PV power plant as compared with the California ISO load. A tracker
enables higher output during the peak afternoon period for a given
plant capacit.
2. PV PANEL PERFORMANCE AND LIFETIME
Successful prediction of PV panel performance over time is critical
to project investors. Furthermore, demonstrating the historical
performance of a compans panel technolog is critical to
determine nancing parameters which underpin the LCOE
calculation.
Silicon PV has the longest operating histor of an solar cell
technolog. The photograph in Figure 7 shows a monocrstalline
silicon panel after 20 ears of outdoor eposure with no major
visual degradation. Studies on the performance of silicon PV panels
show onl four percent total degradation after 23 ears of outdoor
eposure.6 This eperience provides a high level of condence in
fg 6
Comparison of California SummerLoad Requirements with Fied and
Tracking PV Sstems
Summer CA
Peak Load
!
"
#!
#"
$!
$"
%!
%"
&!
&"
!
$!
&!
'!
(!
#!!
#$!
#&!
#'!
#(!
0
0
0
0
0
0
T20 Tracker
Fixed Tilt
CAISO load
sspp ppdct . Lddct . Ld ppll
SummertimeMWh
perMWpNameplate
C
SO
oad(G
)
8/3/2019 Levelized Cost of Electricity
13/27
s un powe r 13
-
making future performance predictions. Note that most investors
nance a solar sstem based on an assumed panel degradation rate
of 0.5 to 1.0 percent per ear, a faster rate than this historical data
for silicon PV might indicate.
Research on silicon PV historical performance suggests that panel
ife ma etend much further than the 25-ear design life.7 This
demonstrates that long-term performance ma enable longer
nanceable sstem lives in the future. Figure 8 illustrates the LCOE
model sensitivit to nanced sstem life based on a seven percent
discount rate. As indicated in the gure, etending the nanced term
of the project beond todas 20- to 25-ear values could have a
material impact to the LCOE.
fg 7
Monocrstalline Silicon PV Panelafter 20 ears of Outdoor Eposure
fg 8
LCOE Sensitivit toFinanceable Sstem Life
CCoeoe vs.vs. sYsY ssTT MM LifeLife
60%
65%
70%
75%
80%
85%
90%
95%
100%
!"# !!# !$# !%# ! '"# '!# '$# '%# ' $"#
Financeable Sstem Life (years)
6 F. De Lia, S. Castello, L. Abenante, Efcienc Degradation of C-Silicon Photovoltaic Mod-ules After 22-year Continuous Field Eposure, Proc. 3rd World Conf. on PV Energ Conver-sion, Ma 2003, Osaka, Japan.
7 E. Dunlop, D. Halton, H. Ossenbrink, 20 years of Life and More: Where is the End of Life ofPV Module? IEEE Proceedings 2005, p.1595
8/3/2019 Levelized Cost of Electricity
14/27
s un powe r 14
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
13. PREDICTING SySTEM PERFORMANCE
In addition to calculating PV panel output, an estimate of the
sstems overall performance must be made to nance a project.
The ke variables in a PV power plants performance are plant
uptime, weather-based performance (insolation, ambient temperature,
soiling, etc.), inverter and power sstem efcienc, and sstem
component degradation (largel from the panel).
SunPower has developed an analtical model, PV Grid, which
accounts for the above variables and makes future performance
predictions based on SunPowers eperience with more than 450
installed commercial rooftop and power plant sstems. With this
tool SunPower provides project investors with a well-demonstratedmeans of estimating project cash ows.
Figure 9 illustrates the actual versus epected performance for a
10 megawatt SunPower tracking power plant sstem in German,Bavaria Solar I. During the rst three ears of operation, the sstem
performance has eceeded the performance estimates under which
the project was nanced.
fg 9
Epected and ActualEnerg Production for10MW Bavaria Solar8
B slk pmc
8 A. Kimber, Long Term Performance of 60MW of Installed Sstems in the US, Europe, andAsia, Proceedings of the 22nd Annual Photovoltaic Solar Energ Conference, September 2007
8/3/2019 Levelized Cost of Electricity
15/27
s un powe r 15
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
This correlation between empirical data and future predictions is
critical in reducing investor risk and the related cost and terms
of capital investments. An important path to utilit-scale LCOE
reduction is to demonstrate to investors the predictable output,
degradation and sstem life which would support a lower cost of
project capital. As more PV data is generated and investors become
more familiar with the technolog, this ma become possible.
B. itl pv p plt itmt
1. PV Panel
When discussing the potential for photovoltaic solar cost reduction
the focus is understandabl placed on the panel. Over the past
several ears, solar panel prices have represented approimatel
$4/Wp of total PV sstem installed prices of $6-$9/Wp9 dependingon the market and application tpe.
Until 2004, PV cell and panel production costs were steadil
declining following classic learning curve behavior as the solar
fg 10
Representative Eperienceof SunPower PV Power
Plant Technolog
9 Within the PV industr sstem prices and sizes are often referred to in terms of the DC Wp ofthe sstem such as here. In other instances AC Wp prices and sizes are published. AC Wp pricesare higher than DC values because of the losses in transforming power from DC to AC i.e. a1 megawatt DC sstem at $7.00/Wp might be rated as 0.8 megawatts AC and $8.75/AC Wp.
8/3/2019 Levelized Cost of Electricity
16/27
s un powe r 16
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
industr grew. In 2004 and through 2008 however, the rapid growth
in PV demand led to a global shortage of solar-grade polsilicon,
the ke raw material used in conventional silicon solar cells. The
spot market price of polsilicon during this period rose from $25/
kg to greater than $500/kg for some reported transactions. The
cost of polsilicon became the driving cost of a conventional solar
panel, increasing production costs to articiall high levels relative
to the historic learning curve. As a secondar effect, solar cell
manufacturing costs also suffered as the result of underutilized,
silicon-constrained factories.
In 2007, some solar manufacturers entered into new intermediate
and long-term contracts that will continue through the rest of thedecade, lowering feedstock costs for those that have contracted
for that silicon. The polsilicon industr should also benet from
an improved cost structure as compared with pre-shortage
levels due to the scale economies of the new factories being built
and new silicon purication process technolog. In the rst half of
2008, SunPower saw its rst material silicon cost reductions as we
beneted from the deliver of substantial volumes of polsilicon
under suppl contracts from new production facilities.
One benet of the silicon shortage was that the cost and scarcit
of silicon prompted a signicant improvement in silicon utilization
b solar cell manufacturers. In SunPowers case, the grams of
polsilicon consumed to manufacture a watt at the solar cell level
declined from 13 g/W in 2004 to 6.3 g/W in 2008 and is planned to
decline to an estimated 5 g/W with SunPowers Gen 3 technolog
now under development. B 2011 this approimatel 60 percent
reduction in the use of silicon, coupled with an approimatel 50
percent decline in the price of polsilicon, will independentl drive
large cost reductions for PV panels.
8/3/2019 Levelized Cost of Electricity
17/27
s un powe r 17
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
Cell and panel conversion costs are driven b ield, depreciation,
labor, chemical consumption, electricit cost and materials.
Conversion costs can be improved b shorter and more efcient
processes, higher throughput production lines, larger plant sizes
driving scale economies, and greater automation, among other
factors. All of these costs are also leveraged b the efcienc
of the solar cell. SunPowers cost structure and cell efcienc
advantage demonstrate that higher efcienc cells can absorb the
increased manufacturing costs to make each cell due to the higher
watts per cell. Efcienc advantages continue downstream into
panel assembl, sales, marketing and installation. For eample,
holding all other costs constant, an increase in cell efcienc of
one percentage point will equate to approimatel a ve percentdecrease in installed sstem costs. Figure 11 illustrates the solar
conversion of efcienc of SunPowers solar cells relative to
conventional silicon and thin lm PV technologies.
2. AREA-RELATED ExPENSESPV power plant area-related epenses include sstem costs which
directl scale with the area of PV panels used. These ependitures
are the dominant non-panel costs in a PV sstem and include steel,
foundations, mounting hardware, plant installation, shipping and
warehousing, eld wiring, and the electrical components used to
connect the panels. Area-related costs are highl correlated with the
prices of steel, copper and concrete as well as transportation epenses.
fg 11
Relative Solar CellConversion Efciencies
6
8
10
12
14
16
18
20
22
Solar Cell
Efficiency (%)
S u n P o w e r
A - 3 0 0
HITConventionalThin Films Ribbon
= Average produ ction efficiency
S u n P o w e r
G e n 2
rlt sl Cll C ecc
8/3/2019 Levelized Cost of Electricity
18/27
s un powe r 18
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
The structural materials necessar for panel installation are driven
b the wind load requirements of the project. These are a function
of the PV panel surface area that is eposed to the wind whether the
sstem is tracking or ed (similar to how the wind force on a sail is
a function of the sail size). As a result, simplied tracking and ed
tilt congurations share similar cost structures with the eception of
the drive and control components.
There is a common misconception that trackers signicantl add
to the cost of a sstem over ed tilt congurations. SunPower
has developed trackers which can move up to 300kWp of panels
with a simple half-horsepower motor which requires little
maintenance. SunPower has determined that the nancial benetof the increased energ production generated b tracking the sun
signicantl outweighs the incremental sstem costs. B the end
of 2008, SunPower and its partners will have deploed more than
250 megawatts of tracking sstems on three continents. With this
eperience, SunPower has determined that tracking sstems have
delivered superior LCOE economics for its customers than ed
congurations.
Area-related installation costs can var substantiall b site and b
countr. For eample, a fence post-like support foundation might
be easil driven into the ground in Bavaria whereas a South Korea
tphoon zone ma require a thick steel beam placed in a hole
drilled into rock and secured with reinforced concrete at four times
the cost. As a result the range of foundation costs for a ed tilt
sstem or single-access tracker could var from $30 - $200 / m2 of
PV depending on the site. Additionall, differences in government
electrical codes can signicantl impact costs; one jurisdiction ma
require epensive steel wire conduit while others allow the direct
burial of cable into the ground.
Once the area-related costs for a sstem are calculated, a simple
transformation to $/Wp can be accomplished b dividing $/m2 b
the Wp/m2 of the panel. In the case of SunPowers high-efcienc
panels, area-related $/Wp costs are approimatel 50 percent
lower than thin lm PV panels. Figure 12 below demonstrates how
area related costs are leveraged through efcienc for a sample
8/3/2019 Levelized Cost of Electricity
19/27
s un powe r 19
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
central station PV solar power plant with 1 TWh of annual energ
production. Note that although the material costs are higher for
standard efcienc and thin lm panels, the are largel similar to
what the would be with a ed tilt sstem so tracking still makes
economic sense provided there is available land.
3. LAND USE AND ExPENSE
Land used for solar power plants has been readil available and
inepensive in the past, largel because the land had little economic
value other than in some cases low-ielding agricultural activities.
As solar power plant developers began acquiring land in South
Korea, Southern Europe and the southwest U.S., prices for prime
land conducive to a solar power plant rapidl increased in cost and
general land availabilit became an issue. Korea and Southern
Europe have seen solar-suitable land price increases of more than
300 percent and southwest desert land has sold for prices as high
as a reported $23,000 per acre for at land10 with high insolation
located near electrical transmission lines, a roughl 15,000 percentincrease over historical values for the same parcels.
There are two fundamental drivers for the land consumed b a solar
power plant: solar panel efcienc and sstem ground coverage
ratio (GCR). Sstem GCR is the ratio of solar panel area to land area.
fg 12
Area Related CostComponents for a T20
Tracker Power Plantwith 1 TWh of Annual
Production
PV Panel Used for Project SunPower Standard Efcienc Thin Film
PV Panel Efcienc 20.0% 14.0% 11.0%
Sstem Size (DC kWp) 423,191 439,754 430,108
Land Required (Sq Miles) 5.11 7.58 9.44
Truckloads of Concrete Required 12,718 18,218 22,678
Steel Required (Tons) 35,083 50,258 62,561
Cabling Required (Miles) 410 587 730
Trenching Required (Miles) 32 45 57
Modules to Wash (Sq Feet) 14,579,689 21,643,300 26,941,782
Tracker Installation Labor (hours) 365,450 523,516 651,678
Concrete Required (Tons) 254,353 364,367 453,568
a rltd Ct 1 Tw T20 Tck pjct
10 T. Wood, The Southwest Deserts Real Estate Boom, Fortune Magazine, Jul 11, 2008.
8/3/2019 Levelized Cost of Electricity
20/27
s un powe r 20
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
PV panels mounted at use land the most efcientl and have the
maimum GCR but have the lowest capacit factor, meaning lower
utilization of ed plant costs. Conversel a two-ais tracker has
the maimum possible capacit factor but requires up to 10 times
more land than at congurations. To put it simpl, the better the
orientation to the sun (thus capacit factor), the longer the shadows
created and therefore the further apart panels must be placed to
avoid panel to panel shading.
To deliver the best utilit-scale PV LCOE one must balance land use
with the sstem capacit factor. SunPower addresses this optimi-
zation problem b manufacturing the worlds highest efcienc PV
panels along with tracking sstems that efcientl use land whileincreasing energ production. SunPowers tracker offerings include
the T20 Tracker, which maimizes capacit factor in an efcient land
footprint, and the T0 Tracker, which optimizes land use for
constrained sites while still providing a high capacit factor.
Figure 13 illustrates the land consumption versus capacit factor for
a power plant producing 1 TWh / ear in a high insolation location.
One can see in this eample that:
With high-efcienc PV panels, up to 75 percent less land is
required for a given capacit factor conguration.
With high-efcienc PV panels mounted on trackers, up to
30 percent higher capacit factors are attainable while using
a similar or lower amount of land per quantit of energ
produced than low and medium efcienc panels mounted on
ed tilt sstems. This means that lower LCOE congurations
are achievable without prohibitivel increasing the amount of
land required.
8/3/2019 Levelized Cost of Electricity
21/27
s un powe r 21
-
. GRID INTERCONNECTION COSTS
Grid interconnection costs relate to the inverter, transformer,
switchgear, medium voltage substation and electrical interconnect,
the high-current electrical backbone bringing power in from the
arra and ultimatel the transmission back to the central grid in
the case of a power plant requiring a transmission upgrade for gridintegration. These costs are driven b the price of the manufactured
components, the skilled labor used to install and the price of copper,
which drives much of the inverter and electrical wiring costs. Power
transmission costs are driven down through scale economies, more
intelligent sstem design and through improved plant utilization
such as with solar tracking.
C. pv plt otg ex
The operation and maintenance (O&M) of a PV power plant is
relativel straightforward because there are few moving parts and
no cooling sstems. O&M costs generall scale with three factors 1)
sstem peak power dominated b inverter maintenance, 2) sstem
annual energ production densit, and (3) general site related items.
Improving the capacit factor of a sstem directl reduces O&M
fg 13Land use and CapacitFactors11 for 1 TWh
Production Congurations
!"!!
!#!!
!$!!
!%!!
!&!!
!'(!!
!'#!!
!'$!!
!'%!!
!'&!!
'
'
'
' ' '
' ' ' ' ' ' ' ' ' ''
' ' ' ' '
' ''
#()!*+,-!
'$)!.*/!
'')!012*30456!57!
%)!8*/!57!
LdLd rrqmt qmt hhgg iiltlt pvpv pp ppltlt
t 1 Tt 1 Tww aall ppdctdct
34% T20 Tracker 32% T0 Tracker 26% Fied Tilt
a C C a p a C i T Y f a C To r
SquareMilesRequired
11 Note the listed capacit factors are based on the AC rating of the power plant at the point ofgrid interconnection, the DC nameplate capacit of the PV power plant will be approimatel 20percent higher than the AC rating depending on the PV panel tpe and sstem conguration.
8/3/2019 Levelized Cost of Electricity
22/27
s un powe r 22
-
costs through higher utilization rates of ed assets. Figure 14
demonstrates this as it relates to the inverter requirements to
generate 1TWh of annual energ in a PV power plant. In this
eample, 1 TWh of energ would require 335 inverters, each 1 MWp,
with a SunPower T20 Tracker versus 442 inverters with a ed tilt
sstem at the same location. The use of a tracking sstem would
therefore signicantl reduce the inverter O&M cost.
Signicant power related maintenance costs also eist with respect
to transformers, switch gear and grid interconnection, and all
benet from a high capacit factor sstem conguration.
Module cleaning, panel repair or replacement, mounting structure
and wiring maintenance, and vegetation control all scale with
the annual energ production densit of the panels. The annual
energ production densit is a criticall important factor for sstem
economics (both O&M and overall LCOE). The annual energ
production densit is the kWh generation per unit area per ear as
measured as:
The impact of the annual energ production densit can be
substantial. Figure 15 shows the area of PV panels required in a high
insolation solar power plant to generate 1 TWh of annual output.
fg 14
Inverters Required for 1 TWhof Energ Production in the
Southwest U.S. Desert
Capacit Factor 34.1% 25.8%
1 MWp Inverters per annual TWh1 MWp Inverters per annual TWh 335335 442442
Inverter O&M Cost 100% 132%
T20 TckT20 Tck ffxd Tltxd Tlt
8/3/2019 Levelized Cost of Electricity
23/27
s un powe r 23
-
O&M costs which correlate with the area of PV panels used can thus
be reduced using high-efcienc PV panels mounted on tracking
sstems. A simple eample of these O&M savings is with the cost
of cleaning panels. With a high annual energ production densit
panel, washing costs can be reduced b up to 75 percent. This allows
for either a direct reduction of O&M costs or allows for panels to
be washed more frequentl and economicall, increasing sstem
annual energ production. Although often overlooked, washing and
soiling can have a material impact to a PV power plant LCOE.
In a tracking sstem there is the added cost of motor and controller
maintenance. But in SunPowers eperience this cost is relativel
small when compared to the other O&M cost savings the tracker
provides. For eample, the SunPower motor requires onl annual
ubrication and a single motor can control more than 300kWp
of PV. Also, the tracker bearings require no lubrication and are
designed for more than 25 ears of use. The O&M cost of a utilit-
scale tracking sstem would be less than $0.001/kWh over a ed
conguration, which does not include the O&M savings from theincrease in energ production.
Looking to the future, opportunities for O&M cost reduction
include improved inverter reliabilit, scale economies from larger
plant sizes, automated washing and water reccling tools, and
sophisticated remote monitoring.
fg 15
PV Panels Required for 1TWh of Annual Production
!"!#
!"$#
%"!#
%"$#
&"!#
&"$#
SunPower T20 Tracker 11% CIGS/CdTe Fixed Tilt 6% aSi Fixed Tilt
' ' ' ' ' ' ' 'ssq Ml q Ml pvpv pp l 1 Tl 1 Tww
8/3/2019 Levelized Cost of Electricity
24/27
s un powe r 24
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
D. sytm rdl vl
Related to the previous section, solar PV nancial models generall
assign zero residual value to the project. The sstem however,
could have a useful life of 50 ears or more ielding a material
residual value to the sstem after the 20- or 25-ear nanced term.
Additionall, the PV power plant could increase in value if fossil-fuel
based energ prices continue to rise.
Due to the time value of mone, the LCOE impact of a sstems
residual value is diluted but could still materiall reduce a PV power
plants LCOE.
It is conceivable that in the future PV sstems will be treated asassets with an active secondar market. In the wind industr,
secondar turbine sale and refurbishment has begun to occur.12
SunPower has seen some value being placed on the future
reclamation of the structural steel used in its power plants, but
placing a value the residual energ of a PV power plant is still
immature in the market.
e. sp LCoe fctg Tl
SunPower has set a compan goal of reducing the LCOE of its
installed sstem cost b at least 50 percent b 2012 based on 2006
costs. Through its vertical integration, SunPower has a unique
window into the detailed costs of a solar sstem from quartz
mining for metallurgical silicon to the construction and maintenance
of a PV power plant.
To plan and track LCOE reductions b market and application around
the world, SunPower has developed a Web-based database that
aggregates hundreds of cost, performance and nancial inputs from
its projects. The project dovetails with SunPowers research anddevelopment work funded b the U.S. Department of Energs Solar
America Initiative (SAI). The SAI sets forth aggressive solar LCOE
reductions through technological and process innovation.13
12 J. Runon, Finding a Second Life For Retired Wind Turbines,hp://www.renewableenergyworld.com, Jul 1, 2008
13www.eere.energy.gov/solar/solar_america/pdfs/solar_market_evoluon.pd f
8/3/2019 Levelized Cost of Electricity
25/27
s un powe r 25
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
The LCOE for an incremental PV power plant to be built in the future
is inuenced b a variet of eternal factors including echange
rates, labor prices in respective manufacturing and construction
locations, scarcit of critical raw materials, the cost of capital, land
prices, and man other factors. These risks are minimized b the
use of a high-efcienc solar panel technolog like SunPowers
since the efcienc leverages almost all non-PV plant costs. Once
built, the LCOE of energ coming from a silicon PV power plant is
ver predictable since the LCOE is heavil inuenced b capital cost,
location and sstems technolog choice.
Based on etensive LCOE scenario analsis with a range of cost
and performance structures for incumbent and emerging solar
technologies, SunPower believes that utilit-scale, central station
solar power plants built with high-efcienc silicon PV will deliver a
competitive LCOE now and in the future.
fg 16
SunPowers LCOEForecasting Tool
8/3/2019 Levelized Cost of Electricity
26/27
s un powe r 26
-
We conclude that on the man dimensions of cost and performance
that underpin the LCOE for a solar power plant, high-efcienc
tracking PV offers a ver compelling solution. To review, the LCOE is
the net present value of total life ccle costs of the project divided b
the quantit of energ produced over the sstem life.
Ke LCOE benets for high-efcienc PV power plants include:
Lt Ttl L Cycl Ct
High-efcienc panels minimize power plant capital coststhrough the reduction in the number of modules and scale of
the mounting sstem and land required to generate a given
amount of energ.
Higher conversion efciencies, more efcient use of silicon
and larger scale manufacturing operations will drive continued
high-efcienc panel cost reductions.
Life ccle O&M costs are substantiall lower for high-efcienc
tracking PV due to up to four times the energ production per
panel per ear.
A higher sstem residual value for a silicon PV plant drives
total life ccle cost reduction.
hgt Ttl Ltm egy dct
Through optimized solar tracking, SunPower PV power plants
maimize the annual energ production of a sstem leading to
high capacit factors and a lower LCOE.
With a more than 20-ear operating histor, monocrstalline
PV modules provide predictable energ production which
reduces investor investment risk and enables longernanceable sstem lives.
LCOE analsis shows how SunPowers high efcienc silicon PV
power plants generate electricit at a price competitive with other
peak power resources. Based on comparison between published
cost predictions for other technologies and our internal cost
reduction roadmap and resultant LCOE forward cost curve, we
epect to maintain this competitive position into the future.
iii. Cnclusns
8/3/2019 Levelized Cost of Electricity
27/27
The DriverS of The LeveLizeD CoST of eLeCTriCiTy for UTiLiTy-SCaLe PhoTovoLTaiCS
For more information about this paper, please contact:
Bb okk
Senior Director, Investor Relations
SunPower Corp.
(408) 240-5447
Lead Author
Mtt Cmbll
Supporting Teampt acb
Jl Bld
ed sml
st wgt