12
Legal Watch: Personal Injury 29th January 2015 Issue: 049

Legal Watch - Personal Injury - Issue 49

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Legal Watch - Personal Injury - Issue 49

Legal Watch:Personal Injury29th January 2015Issue: 049

Page 2: Legal Watch - Personal Injury - Issue 49

In This Issue:

• Employers’ liability

• Employers’ liability/costs

• Public liability

• Civil procedure/expert evidence

• Part36

• Costs/conditional fee agreements

• From within Greenwoods

Employers’ liability

Events

Plexus and Greenwoods hold a series of events which are open to interested clients. See below for those being held in the next few months:

The Major Bodily Injury Group (MBIG) | Spring

Seminar | 28.04.15 | The Wellcome Collection,

London

The case of Dusek and others v Stormharbour Securities LLP

(2015) EWHC 37 (QB) illustrates how an employer may attract

liability if it fails to enquire adequately about the safety of travel

arrangements made for an employee.

The claimants, who were the wife and children of a deceased

employee, brought a fatal accidents claim against the

defendant employer.

The deceased had been working on a project to secure funding

to develop hydroelectric projects in the Andes Mountains

in Peru, along with a Peruvian investment company. Two

Korean companies were identified as potential investors. It

was decided that it was necessary for the investors to visit

the site and the investment company advised one of the

Korean companies that the site was reachable either by long

overnight jungle walks or by a road trip to an airfield and

then a helicopter ride. The Korean companies requested

that a representative of the defendant was present and so

the defendant sent the deceased on the trip. The Peruvian

company chartered a helicopter from Cusco to Mazuco. One

of the quotations received advised against flying from Cusco

and instead recommended starting from Mazuco to avoid

crossing the Andes because of the remote and inhospitable

terrain. The Peruvian company went with an operator willing

to fly the route it wanted. The first leg of the trip from Cusco

to Mazuco, although completed, was delayed due to poor

weather conditions and the maximum permissible density

altitude and weight were exceeded. The parties then flew

around the project site but returned to Mazuco because of

poor weather conditions. The crew made a flawed decision

to fly back to Cusco the same day and ran into operational

difficulties as a result. They crashed into the Andes Mountains

and everyone on board the flight was killed.

Page 3: Legal Watch - Personal Injury - Issue 49

The issues were (i) whether the scope of the employer’s

duty of care extended to the helicopter charter and flight;

(ii) if there was such a duty, did the employer breach it; (iii)

if the employer breached its duty, did that breach cause the

employee’s death.

Finding in favour of the claimants, the High Court judge

held that the deceased had been on the helicopter for

the purposes of his employment and the defendant owed

him a duty to take reasonable care not to subject him to

unnecessary risk. Irrespective of whether it had organised

the helicopter trip or whether the employee was looking to

it to take reasonable care of his safety, the employer owed

him a duty to take reasonable care to ensure that he was

reasonably safe while travelling to and from work abroad

where he was required to go.

“(The defendant) owed a duty to safeguard the employee from the danger involved by inquiring into the safety of the trip and conducting a risk assessment.”It was clear that there were obvious potential dangers

involved in the trip, namely unsafe operation or performance

of the helicopter. The defendant knew that the deceased

would be going on a chartered helicopter trip to visit a site

in a remote, inhospitable, inaccessible and mountainous

area. It owed a duty to safeguard the employee from the

danger involved by enquiring into the safety of the trip and

conducting a risk assessment. It had no knowledge of

whether the companies that organised the trip had flown

with the helicopter operator previously, had carried out a

risk assessment or had any safety concerns. Its health and

safety officer accepted in evidence that something should

have been done. In doing nothing, the defendant breached

its duty of care.

The defendant should have enquired of the Peruvian

company as to details of the flight operator, the helicopter to

be used, the flight route and how they satisfied themselves

as to the safety of the flight route. The Peruvian company

had been advised to take a coach from Cusco to Mazuco

as it was safer to begin helicopter travel from there because

of the dangers of flying over the Andes. If the employer had

made the safety enquiry required to make an appropriate

risk assessment, it would have instructed its employee

not to take the flight because of safety concerns and he

would have listened. The defendant’s breach caused the

deceased’s death.

Page 4: Legal Watch - Personal Injury - Issue 49

Employers’ liability/costsPrior to 1 April 2013, lower value employers’ liability claims

were subject to a fixed uplift of the claimant’s solicitor’s

base profit costs by way of the success fee under an old

style CFA. The issue in Broni and related claims v Ministry

of Defence (2015) EWHC 66 (QB) was whether that regime

applied to members of the armed forces i.e. were they

‘employees’?

The appellants were three members of the armed forces

who appealed against decisions that the fixed success fee

regime applied to the claims that they had brought against

the respondent defendant in respect of injuries they had

sustained at work.

CPR 45 IV had provided for fixed success fees in certain

employers’ liability claims. CPR 45.20(1)(a) provided that

“this Section applies where... the dispute is between an

employee and his employer”. CPR 45.20(3)(b) stated that

“employee” had the meaning given to it by S2(1) Employers’

Liability (Compulsory Insurance) Act 1969, which defined

an “employee” as “an individual who has entered into or

works under a contract of service or apprenticeship with

an employer”. It was decided that the claimants were

employees and that the fixed success fee regime therefore

applied to their claims.

The defendant, seeking to uphold the decisions below,

argued that the court should adopt a purposive approach to

the construction of the words “contract of service” in S2(1)

of the 1969 Act so that the relationship between a serving

member of the armed forces and the defendant was treated

as one of employer and employee.

Allowing the claimants’ appeals, the High Court judge

held that there was no good reason for giving the words

“contract of service” in S2(1) of the 1969 Act a construction

broader than their usual meaning. There was no ambiguity

in CPR 45.20(1)(a) and 45.20(3)(b). The rule addressed

itself to the question of what the term “employee” meant:

it was a person who fell within S2(1) of the 1969 Act. There

was in those circumstances no scope for giving a broad

or purposive interpretation to CPR 45.20(1)(a) different

from the specific meaning given to the term “employee”

by S2(1). The words “contract of service” in S2(1) had a

single meaning which did not vary. The claimants were not

engaged under a contract of service and the fixed success

fee regime did not apply to their claims.

“The claimants were not engaged under a contract of service and the fixed success fee regime did not apply to their claims.”

Page 5: Legal Watch - Personal Injury - Issue 49

Public liabilityThe case of Baxter v Barnes (2015) EWHC 54 (QB) involved

a claim for personal injury brought primarily in contract.

The claimant, an arborist, had sustained serious injuries

when he fell from a piece of equipment which he had hired

from the defendant in order to prune a tree. The equipment

was a mobile elevated work platform. Access to the site

was limited and the tree was close to a slope. The platform

was specifically designed for such situations. It was

suitable for working on sloping ground, provided that the

feet of the outriggers were properly supported on ground

that was reasonably level, firm and stable. The defendant

delivered the platform to the site and helped to set it up in

the first position from which the claimant was going to use

it. Together with the platform, he supplied the claimant with

hard plastic plates, to support the feet of the outriggers of

the platform. Those plates had not been supplied by the

manufacturer for use with that platform. After using the

platform at the first position within the site, the claimant’s

employees moved the platform to another position. Whilst

the platform was in use, it overbalanced and toppled over.

Subsequent investigations revealed that two outriggers had

lifted up from the ground. The experts agreed that, on the

balance of probabilities, the platform had become unstable

and toppled because one or more of the outrigger feet

slipped off the edge of the plate into the soft ground.

The claimant submitted that the accident had been caused

by defects in the platform and/or instructions which the

defendant had given to him in relation to setting up the

platform. The defendant’s case was that the accident was

solely due to errors by the claimant in setting up or operating

the platform.

Finding in favour of the claimant, the deputy High Court

judge held that the claimant was an experienced arborist

who was generally careful for his own safety and that of

his employees. Whilst he had not previously hired that type

of platform, he was knowledgeable about the principles

behind its operation. Further, on the day of the accident

his employees had set up the machine in essentially the

same way and position as the day before. They had not

set it up in a position which the defendant had advised

was unsuitable and they had followed the defendant’s

instructions in setting it up. It was clear on the evidence

that the position was not unsuitable for the positioning of a

platform of suitable quality. In particular, the manufacturer’s

evidence was that the ground appeared suitable for the

platform and that the movement of the outrigger foot was

as a result of the operation of the platform, not the collapse

of the plate into soft ground. The cause of the accident

was the slippage of the outrigger foot upon its bearing

plate. That slippage occurred because the plate was not

of suitable quality for the type of platform concerned. The

platform was specifically designed for use on rough or soft

terrain and on slopes and narrow or uneven surfaces, where

it was liable to be subjected to lateral forces which could

cause a foot, if unrestrained by its bearing plate, to move

considerably. The platform should have been provided with

bearing plates which were attached to the outrigger feet or

so shaped or recessed that the feet were prevented from

slipping off the plate. For that reason, the platform supplied

by the defendant was not of a satisfactory quality for the

purposes of the implied condition contained in S9(2) Supply

of Goods and Services Act 1982. The platform also toppled

over without any warning device or cut-out operating,

whether because of a particular fault which had developed

on that specific platform, or because the combination of

the particular way the topple was initiated and the design

of the platform resulted in the warning device and cut out

not operating before the topple was initiated. The claim

succeeded in contract, but the defendant did not have a

separate liability to the claimant in negligence.

Page 6: Legal Watch - Personal Injury - Issue 49

Civil procedure/expert evidence The Jackson reforms reasserted the need for judges to

control expert witness evidence. In Rengasamy v Homebase

Ltd [Lawtel 26/01/2015] the judge appears to have been

overzealous. Even so, the appeal court placed restrictions

on the time allowed at the trial for oral expert evidence.

The defendant appealed against the judge’s decision to

refuse permission for the parties’ engineering experts to

give oral evidence at the trial of a personal injury claim

brought by the claimant, and it sought an extension of a trial

estimate from two days to three days.

The claimant had fallen off a ladder which had been

purchased from the defendant. He claimed damages for

personal injuries arising from the defendant’s breach of the

implied term as to satisfactory quality under S14(2) Sale

of Goods Act 1979. Both parties instructed engineers to

assess the ladder and they drafted a joint statement. They

agreed that the claimant’s injuries were consistent with

either the ladder collapsing with him on it, or him falling off

the ladder with the ladder then falling to the ground and

him landing on it, but disagreed as to which scenario was

more likely. If the ladder had collapsed then the issue was

whether the ladder was of a satisfactory quality. The claim

was in the region of £31,000.

The defendant submitted that the judge had erred in refusing

permission to allow the experts to give oral evidence

at trial and argued that a time estimate of three days

was appropriate. The claimant contended that the case

management decision was reasonable in the circumstances

and did not exceed the generous ambit of the judge’s

discretion and that the cost of extending the length of the

trial to three days was disproportionate given the value of

the claim.

‘Without hearing oral evidence the court would not have the opportunity to see which of the experts’ evidence was more reliable.’Allowing the defendant’s appeal in part, the High Court judge

held that the court fully supported the judge’s attempts to

address proportionality in terms of the time and costs of

the trial in the interests of both parties. However, the parties

had already proceeded to an exchange of experts’ reports

to allow the court to assess them and had embarked on a

process that allowed them to adduce expert evidence at

trial. That evidence made a key contribution and the experts

differed. Without hearing oral evidence the court would not

have the opportunity to see which of the experts’ evidence

was more reliable. The court was not satisfied that, on

the face of the judge’s reasoning, the way that the expert

evidence could contribute to the case had been taken into

account. The judge had been correct to attempt to control

the parties’ costs and the court’s time by keeping the trial

to a limit of two days. The only criticism was that she had

sought to achieve that by not allowing the parties to adduce

expert oral evidence. The court agreed with the two-day

estimate but made an order that the parties were required,

within seven days, to agree a trial timetable for two days

of court time, with a recommendation that the expert oral

evidence was kept to a half-day limit.

A second case under this heading is Ellison v University

Hospitals of Morecombe Bay NHS Foundation Trust [Lawtel

28/01/2015], which shows the court applying the post

Mitchell approach to the late service of evidence.

Page 7: Legal Watch - Personal Injury - Issue 49

The claimant had received the defendant’s accommodation

report in January 2015. The trial was due to start in the

first week of February. The claimant applied to debar the

defendant from relying on the report. The claimant’s case

was that she and her family had been reasonable in their

desire to be relocated from Cumbria to an area in South-

West London, around Richmond, close to the father’s work

and a specialist school for the claimant and her siblings.

The defendant’s case was that there was no reason to

relocate and that even if the trial judge found that relocating

to London was reasonable, there were suitable properties

available elsewhere. In its counter-schedule of June 2014,

the defendant contended that the Richmond area was

expensive and that there was cheaper accommodation

elsewhere, and that the claimant had failed to mitigate loss.

It reserved the right to look at alternative proposals. The

defendant’s January expert report summarised a range of

properties in different areas within a one-hour commute

of central London. The claimant objected to the report on

the basis that although the addresses were a reasonable

commute, other factors such as a suitable school had been

ignored.

The claimant submitted that as it was only a week until

the trial start date, the trial would have to be adjourned;

and her expert would have to undertake a lot of work in

examining the suitability of the properties put forward

by the defendant. She further argued that the situation

was analogous to an application to extend time, and that

the court should adopt the approach in Mitchell on relief

from sanctions. The defendant submitted that the report

was simply supplementary evidence and that its purpose

was to provide details of alternative housing in London to

assist the trial judge. It further submitted that its report was

clearly foreshadowed by the counter-schedule and that the

claimant could address the issues within a week and at the

worst, the trial would only have to be adjourned for a short

period.

“It was especially troubling that the trial date would have to be put back”Allowing the claimant’s application, the High Court judge

held that the report was not simply updating the evidence

but had included new matters. The claimant was right to say

that a lot of work would have to be undertaken to address

the points raised. It was especially troubling that the trial

date would have to be put back. Further, the defendant

had not applied for permission to use the report. It was

not appropriate to determine whether it was a relief from

sanctions case, but in any event the approach in Mitchell

was highly material. It was not a trivial matter. The defendant

had the onus of establishing that the claimant had failed to

mitigate losses. It had taken the view for at least six months

that if the claimant was to be relocated to London the search

for accommodation should go beyond the Richmond area,

but it was not until the eleventh hour that it put in concrete

its evidential case. The claimant’s case had always been

to be relocated. There had to be compliance with court

orders, and there was a need to avoid delaying the trial. The

circumstances of the case militated against allowing the

trust to admit the evidence.

CommentThis case highlights that defendants who wish to challenge

a claimant’s move to a new property, in a different area, must

take the initiative and locate and offer what they consider to

be a suitable option.

Page 8: Legal Watch - Personal Injury - Issue 49

Part 36As Uwug Ltd and another v Ball (2015) EWHC 74 (IPEC)

illustrates, arguments continue over the application of Part

36.

In an intellectual property claim the defendant had made a

Part 36 offer, giving no details of how he had arrived at the

sum which he proposed to pay in damages. The claimant

did not accept the offer. The defendant withdrew it and

the relevant period expired, under CPR 36.3(1)(c). The

defendant subsequently made a fresh Part 36 offer, in the

same terms as his first one, giving no further reasoning. The

claimant rejected it. The claimant was ultimately awarded

damages which were substantially less advantageous than

those offered by the defendant.

The defendant argued that the court had a wide discretion

in relation to costs, relying on observations made in Bolton

(1995). The claimant argued that the defendant’s Part 36

offers should be disregarded because they contained no

information to allow him to assess whether to accept them

and the defendant’s status as a litigant in person should not

affect that. He also contended that the defendant’s refusal

to enter into mediation should weigh in the balance against

him.

The judge held that there always had to be sufficient flexibility

of approach in assessing costs, to achieve the overriding

objective of dealing with cases justly. However, the court

also had to observe the guidelines in the CPR, particularly

CPR 36.14. The observations in Bolton warned against the

unreflective application of a familiar approach to assessing

costs without sufficient regard to the justice of the case on

the particular facts, but there was no suggestion that the

court had unshackled freedom in the assessment of costs.

“…it did not follow that the defendant’s offer had to be treated as if it had never happened.”Under CPR 36(14)(6)(a), the usual consequences of a

claimant failing to obtain a judgment more advantageous

than the defendant’s Part 36 offer did not apply where the

offer had been withdrawn. However, it did not follow that

the defendant’s offer had to be treated as if it had never

happened. There was no obligation on a party making a Part

36 offer to spell out his reasons, but if he plucked a figure

from the air that might count against him in relation to costs

if the opposing party was left unreasonably in the dark as to

how the offer was calculated. The extent to which a party’s

position was disadvantaged by ignorance of the rationale

behind a Part 36 offer would depend on the facts of the

case. In the instant case, the claimant had been in a position

to assess how the defendant’s offer matched up with the

damages and interest which he would be likely to receive,

on various alternative views as to the outcome, at trial.

However, the defendant’s first offer should not be treated

if it had never been withdrawn. Litigants in person, like all

litigants, had to live with the consequences of ill-advised

procedural decisions. On the other hand, the claimant

should have accepted the offer. Further, the defendant’s

refusal to enter into mediation should not count against him

as it would have been likely to have been unsuccessful and

to have led to a waste of time and expenditure. The claimant

should have his costs up to the date of expiry of the first

Part 36 offer, but no further. The defendant would have his

costs from the date of the second Part 36 offer.

Page 9: Legal Watch - Personal Injury - Issue 49

Costs/conditional fee agreementsIn Legal Watch: Personal Injury 6 we reported the decision

in the first appeal in Blankley (Protected Party) v Central

Manchester & Manchester Children’s University NHS Trust.

The defendant’s appeal against that decision has now been

refused by the Court of Appeal and is reported at (2015)

EWCA Civ 18.

The claimant had suffered brain damage after undergoing

surgery at the defendant’s hospital. As she did not have

capacity, she had acted through a litigation friend to bring a

clinical negligence action. Liability was agreed with damages

to be assessed. The claimant regained capacity and entered

into a conditional fee agreement to cover the assessment of

quantum. The agreement stated that she was responsible

for giving her solicitors sufficient instruction to enable them

to perform their work, and that, if the agreement ended

early, the solicitors reserved the right to require her to pay

their charges and any counsels’ fees. Two years later, the

claimant lost capacity. Her solicitor was appointed as her

receiver and acted as her litigation friend. The proceedings

were settled three years later. The solicitors submitted their

bill of costs to the defendant. The defendant’s case was that

the conditional fee agreement had automatically terminated

as a result of the claimant’s loss of capacity, leaving her

solicitors without a retainer. A costs judge accepted that

argument. The court below allowed the claimant’s appeal,

finding that her supervening incapacity had not frustrated

or otherwise terminated the conditional fee agreement,

especially as it had been entered into in the knowledge that

she had fluctuating capacity.

The defendant submitted that the decision was contrary to

the principle in Yonge (1910) that supervening incapacity

terminated an agent’s authority. It also asserted that a

solicitors’ retainer was a personal contract in which the duty

to give instructions could only be discharged personally. The

claimant doubted the correctness of Yonge, and maintained

that even if a client had a general duty to provide instructions

personally, that duty could not have been intended in this

case, where the solicitors had foreseen that their client

might lose capacity again.

“(The claimant’s)…supervening incapacity had not rendered the retainer incapable of performance; it had only given rise to a short delay pending appointment of a receiver”The Court of Appeal held that the judge had been right to

decide that the claimant’s incapacity did not terminate the

conditional fee agreement. There was much to be said for

re-examining the Yonge principle and related authorities:

it was potentially unfair and unsatisfactory for a client’s

supervening incapacity automatically to terminate a

solicitor’s authority to act on their behalf, thereby exposing

the solicitors to risk of liability to other parties for breach

of warranty of authority at a time when they were unaware

of their client’s incapacity, and depriving them of authority

to protect their client’s position after they became aware

of it. However, the present appeal was narrowly focused

and did not require such an examination. The issue was

whether the conditional fee agreement had been terminated

by frustration when the claimant became unable to give

instructions, causing the retainer to become incapable

of performance. That question could be resolved on the

assumption that Yonge remained good law. The fact that

a solicitor’s retainer was a personal contract did not mean

that instructions generally had to be given personally. In any

event, whatever the general position, the parties to this case

Page 10: Legal Watch - Personal Injury - Issue 49

must have contemplated that the claimant might become

incapacitated again and that instructions would need to be

given on her behalf. Therefore her supervening incapacity

had not rendered the retainer incapable of performance; it

had only given rise to a short delay pending appointment

of a receiver. A further reason why the frustration allegation

had to fail was that, even if the respondent had been under

a duty to provide personal instructions, the situation was

covered by the terms of the conditional fee agreement,

which entitled the solicitors to end the contract and require

the claimant to pay their basic fees.

A CFA also came under scrutiny in Cox v Woodlands Manor

Care Home Ltd [Lawtel 28/01/2015]

The appellant/claimant had been injured at work and sought

to claim against the respondent/defendant, her employer.

She had been introduced to a firm of solicitors and wanted

them to act for her, but had legal expenses cover as part of

her household insurance. She was advised that the legal

expenses insurer was likely to require her to use a panel

solicitor up to the issue of proceedings. She signed a CFA

but also made a claim on the insurance. A solicitor from

the firm visited the claimant’s home where she signed the

CFA, because her injuries made that more convenient than

visiting the solicitors’ office. The insurer confirmed that she

would have to use a panel solicitor until proceedings were

issued. Before that confirmation the solicitors had sent a

pre-action protocol letter and attended on a witness. The

claim was settled for £100,000 and costs on the standard

basis. The defendant argued that the claimant was not liable

to pay her solicitors since the CFA was unenforceable under

the Cancellation of Contracts made in a Consumer’s Home

or Place of Work etc. Regulations 2008. The CFA was a

contract for the supply of services within Regulation 5 and

the claimant was a consumer and the solicitors a trader.

The defendant contended that the CFA was made “during a

visit by the trader to the [claimant’s] home” because, as was

admitted, no notice of the right to cancel had been served

under Regulation 7. A costs judge held that the CFA had

not been “made” when it was signed because there was no

intention to create legal relations until the position with the

legal expenses insurer had been confirmed. A judge allowed

the defendant’s appeal holding that the fact that the CFA

might have ceased to operate, if the insurer agreed that the

solicitors could act, did not prevent it being legally effective

when signed.

“…the CFA had been “made” for the purposes of the regulations when it had been signed”Dismissing the claimant’s appeal, the Court of Appeal held

that the judge was right that the CFA had been “made” for

the purposes of the regulations when it had been signed. It

was wrong to say that there had been no intention to create

legal relations. It was clear that the claimant was legally

committed. The CFA was subject to a condition dependent

on the possibility of funding from the legal expenses insurer.

It was possible that the condition was that the CFA would

not take effect until the insurance position was clarified,

but it was more likely and more consistent with what had

happened that the condition was that the CFA would

terminate if the insurer gave its consent to the solicitors

acting. The claimant had no control over the fulfilment of

either condition and no further action by her was necessary.

Even if the obligations were not immediate, the agreement

was made when signed. That was correct as a matter

of law and also consistent with the policy behind the

regulations. That was to protect consumers in their homes

from pressure that operated at the moment of decision.

That purpose would be rendered more difficult to achieve

if the contract was found not to be made at that point. The

costs judge’s decision was not one of mixed fact and law

with which the judge should not have interfered on appeal.

There was no dispute as to the primary facts including the

parties’ intentions. The question of when the claimant was

legally committed was one of law to which there could only

be one answer. The judge had been entitled and obliged to

reverse the costs judge’s decision and hold that the CFA

was unenforceable.

Page 11: Legal Watch - Personal Injury - Issue 49

From within GreenwoodsSuccessful defence of a multi party ‘slam on’ claim by employing telematics and accelerometer data.

PB and others v SJ and others (The County Court at

Manchester 16 January 2015).

This claim involved seven claimants: a driver and six

passengers involved in a road traffic accident on 5 January

2013. All claimed damages for personal injury and the first

claimant claimed special damages for credit hire and vehicle

storage.

The claimants’ case was that their stationary or near

stationary motor vehicle was positioned in the right hand

lane on Oldham Road and was attempting to turn right into

Grafton Street when the defendant negligently drove her car

into the rear of the their vehicle.

The claims were defended on the basis that the driver of

the claimants’ vehicle deliberately induced a “slam on” style

collision, in the left hand lane of the road, in order for them

to bring dishonest insurance claims. It was also alleged that

two of the claimants were not present at all (although on this

point the judge found against the defendant).

The key to the success of this defence was the evidence

of an independent witness. The judge found him to be

credible and accepted his evidence that there was no

reason whatsoever why the motor vehicle occupied by the

claimants had to brake suddenly other than to allow the

car behind it to crash into it and thereby allow the vehicle

occupants to pursue personal injury claims. The witness

was a driver and was adamant that both vehicles were in

the left hand lane as opposed to the right-hand side of the

road as suggested by the claimants.

He was also in a prime position to see the claimants vehicle

park up and to see the driver and a passenger swap

positions, although the judge held that he was mistaken that

there were only five people in the vehicle.

This contrasted with the view formed by the judge about

the credibility of the claimants and in particular the second

and seventh claimants. He noted that the second claimant

clearly had a much better grasp of English than he sought

to convey in the witness box and he came to the conclusion

that he was lying to the court about his knowledge and

understanding and abilities to communicate in English. The

seventh claimant spoke English without the benefit of an

interpreter and was the last claimant to give evidence. It

appeared to the judge that in giving evidence last she was

attempting to infill the inconsistencies that had been raised

in cross-examination of previous claimants.

A number of the claimants had indicated they had lost

time from work as a result of the accident but produced

no documentary evidence despite an allegation of fraud

against them.

The claimants’ vehicle had been fitted with a ‘black box’,

which vitally provided accelerometer data. When that had

been interrogated, none of the claimants were able to

explain why the vehicle had been stationary in the road

some 30 minutes or so before the accident. This was also

inconsistent with the claimants’ suggestion that they had set

off from the first and seventh claimants’ home and that they

were going to meet friends at a pub and yet none of them

had obtained details of where to meet or even better the

name of the pub. The data also revealed that the claimants

had travelled up and down Oldham Road on no fewer than

two occasions in order to find what started off as friends

but then became a friend and were passing the accident

scene for a third time when the incident occurred. None

of the claimants mentioned this in their witness statements

and no explanation was given for these omissions which

only became relevant once the black box data from the

claimants’ vehicle had been obtained and its detailed

movements were known.

The judge’s interpretation of the data from the ‘black box’

was that the claimants’ vehicle decelerated from 24 to

Page 12: Legal Watch - Personal Injury - Issue 49

The information and opinions contained in this document are not intended to be a comprehensive study, nor to provide legal advice, and should not be relied on or treated as a substitute for specific advice concerning individual situations. This document speaks as of its date and does not reflect any changes in law or practice after that date. Plexus Law and Greenwoods Solicitors are trading names of Parabis Law LLP, a Limited Liability Partnership incorporated in England & Wales. Reg No: OC315763. Registered office: 12 Dingwall Road, Croydon, CR0 2NA. Parabis Law LLP is authorised and regulated by the SRA.

www.plexuslaw.co.ukwww.greenwoods-solicitors.co.uk

Contact UsFor more information please contact:

Geoff OwenLearning & Development Consultant

T: 01908 298 216

E: [email protected]

Publications

If you would like to receive any of the below, please email indicating which you would like to receive.

Weekly:

• Legal Watch: Personal Injury

Monthly:

• Legal Watch: Property Risks & Coverage

Quarterly:

• Legal Watch: Counter Fraud

• Legal Watch: Disease

• Legal Watch: Health & Safety

• Legal Watch: Marine

• Legal Watch: Professional Indemnity

27 miles an hour to stationary or very nearly stationary in

approximately two seconds. That amounted not to slow or

gradual braking but sudden braking that causes a vehicle

to slow down suddenly albeit not instantaneously. The

claimants’ witness as to the interpretation of the ‘black box’

data was an employee of the Part 20 defendant, which had

settled the defendant’s claim prior to the commencement of

the trial. At paragraph 10 of his witness statement he had

referred to a gradual braking movement but under cross-

examination he stated that what he had meant was that the

brake pad had been applied to the drum of the wheel at a

constant pressure, causing a constant deceleration.

The judge accepted that all seven claimants on the balance

of probabilities suffered some injury but given the various

inconsistencies in their hospital entries and the medical

reports these injuries were relatively minor. He was also

satisfied that on the balance of probabilities this was a

slam-on collision deliberately contrived in order that seven

claimants could pursue a claim for personal injuries arising

out of the accident.

If damages had been awarded to the claimants then an

appropriate award would have been £750 each but he

dismissed all of the claims, including the claim for credit

hire and storage and recovery charges. The miscellaneous

expenses claims were abandoned prior to the trial

commencing.

In the light of those findings an award of indemnity costs was

made against all seven claimants in favour of the defendant

and repayment of the interim payment.

For further details please contact:

Karen Mann

T: 020 7462 3469

E: [email protected]