Upload
plexus-law
View
214
Download
1
Embed Size (px)
DESCRIPTION
Plexus Law / Greenwoods Newsletter
Citation preview
Legal Watch:Personal InjuryApril 2014Issue: 015
Events
Plexus and Greenwoods hold a series of events which are open to interested clients. See below for those being held in the next few months:
Personal Data Training | 12.05.14 | Peninsular House
MBIG Seminar | 22.05.14 | London
Credit Hire Training | 12.06.14 | Milton Keynes
In This Issue:
• Post Jackson/Mitchell Cases
• Product Liability
• Costs
Post Jackson/Mitchell CasesThe case of Canning v Network Rail Infrastructure Ltd [Lawtel
14/04/2014] sees a court looking both at strict compliance
with CPR and the impact that granting relief from sanctions
would have on court resources.
The claimant’s wife had been killed by a train on a level
crossing operated by the defendant. Prior to her death, she
had been an editor of cookery books. The claimant earned a
significant amount as a chartered surveyor, but had fallen sick
shortly after his wife had died. His particulars of claim had
stated that had his wife been alive, she would have become
more actively involved in publishing in order to supplement
his loss of income following that illness. The supplementary
witness statement that the claimant had made claimed that his
wife had been involved in the running of his company.
The defendant argued that following Mitchell, the present
application should be treated as an application for relief from
sanctions and dismissed, having been made five months too
late; further, that it changed the basis of the case and the
way it was pleaded. The claimant submitted that it was not
an application for relief from sanctions because under CPR
32.5(3) he was permitted to amplify his witness statement and
give evidence regarding new matters.
‘The defendant argued that following Mitchell, the present application should be treated as an application for relief from sanctions and dismissed’
Refusing the application, the deputy High Court judge held
that the matter had to be treated as an application for relief
from sanctions under CPR 3.9. It was not a trivial breach and
the application was extremely late. Unless and until relief
from sanctions was obtained, the defendant could not be
expected to prepare to deal with the evidence of witnesses
whose statements had been served out of time. The
case advanced by the claimant’s supplementary witness
statement was very different from his original one. The claim
had originally focused on the extra publishing work that the
claimant’s wife could have undertaken following his illness.
It was difficult to see how she could have done that if she
was working on company affairs. The two positions were
inconsistent. If the court was to accede to the application,
the claim would have to be amended. Even prior to Mitchell
it might not have been appropriate to grant the application.
Now the conclusion could be reached more directly: the new
rules were brought in to ensure that litigation was practised
expeditiously. To allow the claimant to rely on the statement
would mean that the court would have to use valuable time
determining which of the two assertions was valid. That
was disproportionate. It would lengthen the proceedings
unnecessarily and increase costs.
The second case under this heading illustrates the confusion
that still surrounds costs budgeting and the fine line
between ‘taking a point’ in a manner deemed to be sensible
and appropriate, and trying to gain an advantage for a client
in a way that is not viewed favourably by the court.
In Kershaw V Roberts and others (2014) EWHC 1037 (Ch)
the appellant/claimant appealed against a judge’s decision
that a directions hearing in the Part 8 claim which he had
issued against the respondent/defendants was not a case
management conference (CMC), so that they were not
required to serve a costs budget seven days in advance of
it.
Shortly after the claimant had issued his claim in the Taunton
County Court, that court sent to all parties a “Notice of
Directions”, stating that a directions hearing would take
place on 21 November 2013. On 14 November 14, the
claimant served a costs budget by fax. The defendants
served their own costs budget by post on 19 November,
but their letter was not received before the hearing. The
hearing on 21 November took place by telephone. The
claimant’s counsel argued that the hearing was a CMC, that
the defendants had failed to serve their costs budget in time
and that their costs budget should therefore be restricted
to court fees only. The district judge allocated the claim to
the multi-track and transferred it to the Rhyl County Court.
At a “costs case management hearing” in that court, the
judge ruled that the earlier directions hearing in Taunton was
not a CMC, with the result that no obligation to file a costs
budget had then arisen. The claimant appealed against that
decision.
Dismissing the appeal, the High Court judge held that as
a matter of construction, the rules were clear in providing
that, unless and until a Part 8 claim was allocated to the
multi-track by the court, the CMC provisions of the CPR
29 would not apply. CMCs were a creature of CPR 29, and
the express power to fix such a hearing was triggered by
the allocation of a claim to the multi-track by the court.
It was that actual allocation which triggered the various
procedural obligations attached to a CMC. The claimant’s
claim was not allocated to the multi-track until the district
judge specifically allocated it at the telephone hearing.
Consequently, that hearing itself was not and could not
have been, a CMC. The district judge was fully entitled to
hold a directions hearing before he gave directions. He
was fully entitled, at that hearing, to allocate the claim to
the multi-track, transfer the claim to Rhyl and give whatever
directions he could at that stage. He was fully entitled, then,
to direct that there should be a CMC in the allocated claim,
to include a costs management hearing. Not only was he
‘...the judge ruled that the earlier directions hearing… was not a CMC’
entitled to make those orders but most judges would have
made them.
The judge went on to say that because of imminent
amendments to the rules, the issue that had arisen would
soon be of historical interest only as the requirement for
costs budgeting is to be excluded from Part 8 proceedings
unless specifically ordered.
CommentAlthough this case draws a distinction between claims
commenced under Part 8 and those under Part 7 (the
majority of personal injury claims), the judge did make it
clear that if an allocation hearing is ordered under Part 7 that
will not be a CMC. However, it remains the case that most
hearings ordered after the filing of directions questionnaires
will be CMCs and on the multi-track a costs budget will be
required.
The decision in The Matter of Guidezone Ltd v Prakash and
others (2014) EWHC 1165 (Ch) is not surprising but it is
nevertheless comforting. This case is also an example of
how a party may be tempted to use Jackson/Mitchell to gain
a tactical advantage that would not otherwise be available.
The applicant/defendants had been ordered to serve their
defences by 14 February 2014. Citing the commitments
of counsel, on 29 January and again on 5 February their
solicitors asked the claimant’s solicitors for an extension
of time. The claimant’s solicitors did not reply until 10
February; they stated that the claimant would not agree
to an extension. The instant application was issued on 11
February.
The claimant opposed the application arguing, among other
things, that the principles in Mitchell, advocating a “new
more robust approach” to compliance with court orders,
applied to the claimant’s application and that it should be
refused.
Allowing the application, the High Court judge held that
the Mitchell guidelines did not apply directly to “in-time”
applications for an extension such as the one issued by
the defendants. The earlier case of Robert v Momentum
Services Ltd (2003) remained good law and was authority
for the proposition that an in-time application should not be
treated as if it were an application for relief from sanctions;
rather, it should be judged against the overriding objective.
In applying the overriding objective, the court should now
have regard to the fact that it had been reformulated to
add explicit reference to “enforcing compliance with rules,
practice directions and orders”. However, unlike in the case
of relief from sanctions, that consideration was not to be
given paramount status. To apply the Mitchell guidelines to
an in-time application would in effect erode the distinction
between an ordinary order directing a timetable and an
unless order. It would run the risk that ordinary orders setting
out timetables would become “trip wires”, which was not the
intention of the Jackson reforms. As to the practicalities, it
was not difficult to see that if the Mitchell guidelines applied
to in-time applications, there would be a risk in every case
that a request for an extension, however unobjectionable
in itself, might be declined by the other party in the hope
of persuading the court to refuse an extension and thereby
gain a significant advantage.
The consistent message from recent authorities was that a
party who needed more time for a procedural step should
not just ignore the problem but ask the other side for
consent and, if consent was not forthcoming, make an in-
time application for an extension. Conversely, the other side
should respond positively and in a spirit of co-operation to
reasonable requests for consent rather than “cry foul” and
seek to take opportunistic advantage of the other party’s
difficulties. Had the defendants’ request been acceded to,
it would not have cost either side anything and would have
had no practical impact on the orderly progression of the
proceedings. The decision to contest the application had
led to an expensive and time-consuming hearing.
It was appropriate to grant the extension of time sought.
Among other things, the penalty of losing the ability to
defend the claim would be wholly disproportionate. The
order in question set out a timetable but did not specify
any sanction for failing to comply with it. Moreover, granting
an extension would have no adverse consequences of
any substance on the claimant, other court users or the
timetable for the hearing of the preliminary issues.
Product LiabilityCases under this heading are relatively rare and so, although
it is on its own facts, we report Love v Halfords Ltd (2014)
EWHC 1057 (QB).
The claimant cyclist alleged that his injuries had been
caused by a defect in a mountain bike which he had bought
from the defendant supplier.
Nine months after the claimant had bought the bike, he lost
control while riding the bike on a tarmac cycle path. He fell
and suffered very serious head and facial injuries, including
the loss of an eye. The steerer tube which connected the
front wheel forks to the handlebars had fractured.
It was the claimant’s case that, from the moment of supply,
there had been a defect that had materially contributed to
the fracture, which in turn had caused his loss of control.
The defendant maintained that the fracture had not caused
the accident, but had been caused by it, the tube having
previously been weakened when it was bent in a prior
incident and then incompetently re-straightened. The
claimant denied there had been any prior incident or re-
straightening.
Finding in favour of the defendant, the High Court judge
held that on the basis of the scientific evidence, the clear
balance of probability was that there had to have been a
prior event where the tube was damaged by being bent and
further damaged by being subjected to a crude and amateur
attempt at repair by re-straightening. The tube had therefore
been shown by the defendant, on a clear balance of
probability, not to have been defective at the relevant time,
namely on the date of supply. There was nothing defective
about its design, assembly or the steel from which it was
made. The probable cause of the final fracture was the
second accident, involving considerable speed and force. A
collision with one of the row of fixed metal stanchions which
the claimant was riding past was likely to have been the
violent event that caused the fracture of the tube by ductile
overload, which occurred as a result of the accident and
was not the cause of it.
CostsAlthough Franklin v Maddison and another [Lawtel
17/04/2014] is not a personal injury case, it is of wider
relevance in the context of qualified one-way costs shifting
(QOCS).
The appellant/claimant had operated auto-trading
businesses which were searched by the police following
the disappearance, and suspected murder of two men. A
number of vehicles were seized, some of which were later
released to persons claiming ownership of them, including
the defendant/respondent. Three cars were returned to
him after he produced keys for them. The claimant was
subsequently convicted of murdering the two men and
sentenced to life imprisonment. Thereafter, he issued
proceedings against the police, complaining that they had
caused him to lose vehicles under their control, and against
the defendant, who was accused of wrongfully taking the
three cars.
At trial, the claimant sought to amend his claim to cover six
cars, but the judge refused on the basis that the proposed
amendment was not properly particularised. She accepted
the defendant’s evidence and concluded, on the balance
of probabilities that he was to be regarded as owner of the
vehicles he had claimed, having made cash payments to
the claimant for them. She indicated that the defendant was
entitled to recover his costs from the claimant.
The claimant’s claims against the police also failed. At the
hearing when judgment was handed down, the defendant
asked for costs on the indemnity basis. The judge referred
to the defendant’s failure to give proper disclosure and
comply with protocols, but indicated that the claimant’s
claim against the defendant was wholly without merit. She
therefore granted the request. However, since the claimant
was in prison and in no position to pay, the defendant had
made no attempt to enforce the costs order in his favour.
The claimant appealed and contended that:
(1) had the claim been considered on the basis of six cars, as
he had wished, the judge would not have concluded that
it was wholly without merit and consequently awarded
costs against him on the indemnity basis;
(2) the judge had failed to take account of the defendant’s
failure to give proper disclosure or comply with protocols.
Dismissing the appeal, the High Court judge held that the
trial judge had refused the claimant leave to amend his
claim, and that point could not be re-opened, but it was
plain that the judge would have rejected the amended
claim in any event since she had preferred the defendant’s
evidence to that of the claimant.
The judge had referred to the defendant’s procedural failures
and gone on to conclude that the claimant’s claim was
totally without merit. The question of costs was a matter for
the judge’s discretion: she had conducted the trial and seen
the witnesses give their evidence, and the costs order she
made in the defendant’s favour on the indemnity basis was
within the wide range of her discretion. There was no reason
to justify overturning the costs order.
(Obiter) The question whether the claimant was in a position
to pay costs was irrelevant in determining the costs order;
what mattered was whether the defendant was entitled to a
costs order in his favour on the indemnity basis.
CommentThis case is of potential assistance to defendants in personal
injury actions where QOCS applies, but it is found that there
were no reasonable grounds for bringing the claim or it was
an abuse of the court’s process. An award of costs on the
indemnity basis may be appropriate and the judge should
not take into account the claimant’s ability to pay the costs.
The information and opinions contained in this document are not intended to be a comprehensive study, nor to provide legal advice, and should not be relied on or treated as a substitute for specific advice concerning individual situations. This document speaks as of its date and does not reflect any changes in law or practice after that date. Plexus Law and Greenwoods Solicitors are trading names of Parabis Law LLP, a Limited Liability Partnership incorporated in England & Wales. Reg No: OC315763. Registered office: 8 Bedford Park, Croydon, Surrey CR0 2AP. Parabis Law LLP is authorised and regulated by the SRA.
www.plexuslaw.co.ukwww.greenwoods-solicitors.co.uk
Contact UsFor more information please contact:
Geoff OwenLearning & Development Consultant
T: 01908 298 216
To unsubscribe from this newsletter please email:
PublicationsIf you would like to receive any of the below, please
email indicating which you would like to receive.
Weekly:
• Legal Watch: Personal Injury
Monthly:
• Legal Watch: Property Risks & Coverage
Quarterly:
• Legal Watch: Counter Fraud
• Legal Watch: Disease
• Legal Watch: Health & Safety
• Legal Watch: Marine
• Legal Watch: Professional Indemnity