51
CE-363 Lecture 23: Interlocking and Construction of Track Dr . Ankit Gupta, Assistant Professor Department of Civil Engineering National Institute of Technology Hamirpur  

Lecture 23 Final

Embed Size (px)

DESCRIPTION

pdf

Citation preview

  • CE-363

    Lecture 23: Interlocking and

    Construction of Track

    Dr. Ankit Gupta, Assistant Professor

    Department of Civil Engineering

    National Institute of Technology Hamirpur

  • Lecture Outline

    Interlocking

    Principles of Interlocking

    Standards of Interlocking

    Methods of Interlocking

    Interlocking Devices

    Methods of Construction of Track

  • Interlocking

    Definition:

    An arrangement of signals, points and other

    appliances so inter-connected by mechanical

    or electrical locking that their operation takes

    place in a pre-determined sequence to ensure

    that conflicting movement of signals and

    points do not take place and train runs safely

  • Interlocking

    Necessity:

    Increase in number of points and signals

    Increase in speeds (high speeds tracks)

    This makes the arrangement of points and

    signals foolproof. Their locking eliminates the

    possibility of conflicting movements of trains.

    Helps in proper and safe working of the

    system.

  • Interlocking

    Interlocking Principles:

    It must be impossible to take OFF a signal for approaching train unless the route to which

    the train is taking is properly set, locked and

    held. At the same time it must be impossible to

    operate the points while the train is moving on

    it.

    This means that points should be set and each

    facing point is locked

  • Interlocking

    Interlocking Principles:

    It must be impossible to take OFF position at one and same time for two fixed signals which

    would lead to conflicting movements

    Means points and signals are locked against

    such movements

  • Interlocking

    Interlocking Principles:

    It must be impossible for loose wagons to

    interfere with the route for which the points are

    set and signal has taken OFF position.

    Means the levers connecting to points and signals

    should be interconnected and operated in a

    particular sequence (pulling / putting back)

    The route for which the points are set and signal

    taken to OFF position should be clear of any obstruction.

  • Interlocking

    Interlocking Standards:

    Standard I

    Interlocked station has mechanical interlocking.

    These are usually branch line stations.

    The points are worked by point levers situated near the points, and the signals are worked from interlocking frames in the signal cabin.

  • Interlocking

    Interlocking Standards:

    Standard I

    The mechanisms use keys such that a key obtained from the points mechanism after setting the points must be used on the signal post locking mechanism to pull off the corresponding signal (s) and also to operate the block instrument.

    Through running speed for trains is restricted to 50km/h.

  • Interlocking

    Interlocking Standards:

    Standard II

    Interlocked station may be mechanically or

    electrically interlocked (usually the latter).

    These are usually non-trunk main line stations.

    The main running line at such a station can be

    completely isolated from the loops and

    shunting sidings on both sides.

  • Interlocking

    Interlocking Standards:

    Standard II

    In electrically interlocked systems, setting the

    points activates electrical circuitry that enables

    or disables the appropriate signal levers and

    block instruments.

    Through running speed for trains is restricted

    to 75km/h.

  • Interlocking

    Interlocking Standards: Standard III

    Interlocked station has points and signals that are either interconnected mechanically within the same mechanism, or electrically as with route-relay and panel interlocking.

    These are usually stations on trunk routes.

    Usually two signal cabins whose signal and points controls are interconnected are provided.

  • Interlocking

    Interlocking Standards: Standard III

    These stations usually have the full complement of home and starter signals for receiving and dispatching trains.

    Through running speed for such stations is limited only by the speed limit for the section.

    The loop lines at such stations have to be completely isolated from the main running line by means such as sand humps, over-run lines, trap points, or derailing switches, etc.

  • Interlocking

    Interlocking Standards:

    Standard III.I (or III/I)

    This is another designation found for some

    stations, which indicates that the station is rated as

    for Standard III, but the loop lines are not

    physically isolated on one side of the station.

    Similarly, a Standard II.I (or II/I) station is rated as

    in Standard II, but has loop lines or sidings that are

    not completely isolated on one side of the station.

  • Interlocking - Methods

    Methods of Interlocking:

    Based on the functions to be performed

    Key interlocking

    Mechanical or electrical methods of interlocking of

    signals

    For principles 1, 2 and 3.

    Track circuiting

    For principle 4

  • Interlocking Methods

    Key interlocking

    Simplest method of interlocking

    Provided with standard I interlocking with speed limit below 50 km/hr

    For an example of a main line and a branch line, points can be set for either of the two

    The point has two keys Key A: to be taken out when the point is set and

    locked for main line

    Key B: taken out when point is set and locked for loop line

  • Interlocking - Methods

    Key interlocking (Indirect Locking)

    At one time only one key can be taken out (depending upon which route is to be set)

    Lever frame operating the signals has two levers. Lever for main line can be operated by only key A and similarly lever for loop line can be operated by only key B.

    Therefore, if main line points are set and locked then key A is released and used for unlocking main line signal thus bringing it to lower position.

  • Interlocking - Methods

    Mechanical Interlocking

    It works with lever frames connected by wire to the signals and points

    It requires lesser staff and improves safety as compared to key interlocking

    It consists of locking frame (signal levers, point levers, point locks), point fittings, plungers, tappets, lock bars, etc. Plungers have notches and tappets are connected to tie bars.

  • Interlocking - Methods

    Mechanical Interlocking

    The lever, plunger, tappet and tie bar connection works on Wedge Action

    Due to this the tappet moves out of the notch at right angles to the movement of plunger. This movement is transmitted to other tappets.

  • Interlocking - Methods

    Mechanical

    Interlocking

  • Interlocking - Methods

    Mechanical Interlocking

    Principle of interlocking

    Signal 1 for main line is operated by lever 1; signal

    2 for loop line is operated by lever 2; point (3) is set

    for main line by lever 3 (normal position) and for

    loop line by lever 3 (pulled position); and lever 4 in

    pulled position locks point (3) in both positions

    The normal setting of points, signals and levers is

    for the main line.

    The point will set for main line if lever 3 remains in

    normal position and lever 4 is pulled.

  • Interlocking - Methods

    Mechanical Interlocking

    Principle of interlocking In normal position of lever 4, tappet D butts against the

    plunger and thus not allow tappet B or C to get released

    from notch

    Pulling of lever 4 brings notch in front of tappet D, thus releasing tappet B or C as required. Also tappet E will move in notch of plunger connecting lever 3

    Now after setting point for main line, signal for main line is set to OFF position. For this lever 1 is pulled. This will move tappet A out of the notch of plunger connected to lever 1 and it will enter the notch on plunger related to lever 2. Therefore, lever 2 becomes inoperable (i.e. signal for loop line can not be set to OFF)

  • Interlocking - Methods

    Mechanical Interlocking

    Principle of interlocking The movement of tappet A also causes the movement

    of tappet F, which moves into the notch of plunger connected to lever 3 thus locking it in position

    To adjust the track for branch line

    Putting back lever 1 in normal position will allow

    tappet A to enter notch on plunger connected to lever

    1.

  • Interlocking - Methods

    Mechanical Interlocking

    Principle of interlocking

    Now lever 3 is pulled to set points for the loop line.

    This will cause tappet E to move back and lock lever

    4 and tappet F to move out of notch on plunger of

    lever 3. this will lock lever 1 due to moving of tappet A

    in notch on plunger of lever 1.

    Now lever 2 is pulled causing movement of tappet C

    in notch and bringing signal to OFF position.

  • Interlocking - Methods

    Electrically operated interlocking

    In the more advanced electrical or electronic

    interlocking schemes, the points and signals are

    worked from one integrated mechanism in a signal

    cabin which features a display of the entire track

    layout with indications of sections that are occupied,

    free, set for reception or dispatch, etc.

    The interlocking is accomplished not by mechanical

    devices but by electrical circuitry -- relays and

    switches in older electrical or electro-pneumatic

    systems, and computerized circuits in the newer

    electronic systems.

  • Interlocking - Methods

    Panel Interlocking (PI) is the system used in most medium-sized stations on IR. In this, the points and signals are worked by individual switches that control them.

    Route Relay Interlocking (RRI) is the system used in large and busy stations that have to handle high volumes of train movements. In this, an entire route through the station can be selected and all the associated points and signals along the route can be set at once by a switch for receiving, holding, blocking, or dispatching trains.

  • Interlocking - Methods

    In recent years interlocking accomplished by modern integrated electronic circuitry instead of electromechanical relay systems has come into use (Solid State Interlocking ('SSI').

    By year 2001, SSI was in place at 14 stations in India. SSI equipment is manufactured by RDSO. 247 stations now have RRI installations and the number of stations with Panel Interlocking has risen to 2,426. (Year 2003)

  • Interlocking

    Mechanical Devices for Interlocking

    Purposes Ensure that the route is set, proper signal is taken

    OFF and route cannot be changed after the signal is OFF.

    Hold the route properly at a diverging point.

    Ensure that the route cannot be changed while the train is on the point

    Ensure correct routing, setting and avoiding conflicting movements.

  • Interlocking - Devices

    Mechanical Devices for Interlocking

    Detectors

    It at once detect any defect or failure in the

    connection between switches and the lever or an

    obstruction between stock and tongue rail

    The signal remains at danger position and cannot

    be taken to OFF position until the defect is set right.

    Detectors are used on all points over which signal

    controls the train movement.

  • Interlocking - Devices

    Mechanical Devices for Interlocking

    Stretcher Bar The two tongue rail are connected to each other by

    means of two stretchers known as William Patent stretchers

    The front stretcher extends under the stock rail to prevent jumping at switches.

    Point Lock It ensures that each switch is correctly set

    It is placed in the middle of the track, a little in front of the toe of tongue rail.

  • Interlocking - Devices

    Mechanical Devices for Interlocking

    Point Lock

    It consists of two stretcher blades, a plunger, plunger

    casing, and a three way crank

    The different types are

    A bolt and cotter, each individually fitted to switch rail and

    padlock or clamp, and a padlock for locking switch rail to

    stock rail. (If V < 16 km ph)

    Key of approved design for locking each rail independently

    (if V > 16 km ph and < 48 km ph)

    A plunger type of facing lock (if V > 48 km ph)

  • Interlocking - Devices

    Mechanical Devices for Interlocking

    Lock Bar Its purpose is to ensure that the point is not

    operated while the train in on it.

    Therefore, it is little longer that the longest wheel base of any vehicle.

    It is provided near and parallel to the inner side of rail.

    When the point lock is worked from the signal cabin, the lock bar rises slightly above the rail level and then comes down.

  • Interlocking - Devices

    Mechanical Devices for Interlocking

    TEMPERATURE

    COMPENSATOR

  • Interlocking - Devices

    Mechanical Devices for Interlocking

    Tappet Locking

    Slotting of Signals It is an arrangement in which the lever operating a

    signal is in one cabin but the actual taking OFF of the signal requires releasing of a control from another cabin.

    Both of these cabins can unilaterally put back the signal to danger position.

    The arrangement of slotting is done either electrically or mechanically

  • Interlocking

    Mechanical Devices for Interlocking

    Connecting devices Usually consist of 3.8 cm diameter pipe or solid rod

    These move on rollers in frames fixed in concrete at 2m to 3m intervals.

    The distance between a cabin to points or signals should not exceed 275 meters.

    Temperature Compensator Used to neutralize the effect of expansion or contraction

    of rods due to variation in temperature

    It consist of a pair of cranks (one of acute angle and another of obtuse angle) connected by a pipe.

  • Construction of Track

    Three stages:

    Earth Work

    Formation and consolidation

    Plate laying

    Laying of railway track

    Laying of ballast on the track

  • Construction of Track

    Earth Work

    Formation

    Formation up in embankment is always preferred to a

    formation in cutting

    Height of embankment above highest water level in the

    area should be at least 60 cm.

    The economical limit of moving the earth in longitudinal

    direction is decided by Mass Haul curve.

    Cost of earth work is related to three factors

    The type of soil used, Hauling distance, Lift required

  • Construction of Track

    Earth Work

    Consolidation

    Required to pack the track so that larger quantities of

    stone ballast are not lost by sinking into loose earth

    formation

    Addition of admixtures

    Compaction using vibratory or impact methods

    Small earthen walls 15 cm high are built at an interval of

    3 to 4.5 m

    Rain water so collected helps in further consolidation

    Embankment should be left open for two monsoons

    before proceeding to second stage of construction

  • Construction of Track

    Plate Laying

    The operation of laying out sleepers and rails over the

    ready formation is known as plate laying

    Placing of ballast is not included here. It ois placed

    after two-three monsoon of plate laying

    The point from where the laying of the track starts is

    known as the base

    The point up to which the new track is carried out is

    known as the rail head

  • Construction of Track

    Methods of Plate Laying

    Tramline method or side method

    Telescopic method

    American method

  • Construction of Track

    Methods of Plate Laying

    Tramline method or side method

    The name is derived from the temporary tramline laid by

    the side of proposed track for carrying out the material

    Economical where existing single line track is to be

    converted to double line track

    Sometimes a road parallel to the proposed track is

    constructed for transporting the material at site.

    This method is usually adopted in flat terrain

    Progress of work is slow, not more than 1.6 km per day

  • Construction of Track

    Methods of Plate Laying

    Telescopic method

    Extensively used in India

    Material is transported in material trains to the

    farthest point of new track, unloaded and carried to

    rail head

  • Construction of Track

    Methods of Plate Laying

    Telescopic method: Operations

    Collections and preparation of material at depot

    Transportation of material from depot to work site

    Unloading of material at worksite and carrying them

    to the rail head

    Fixing the rails to the sleepers and joining the two

    rails with fish-plates

    Packing of track for correct level and alignment

  • Construction of Track

    Methods of Plate Laying

    Telescopic method: Operations Collections and preparation of material at depot

    If due to distance the material train is unable to make a round trip on the same day then a second depot near rail head is established

    Preparation of materials like adzing of wooden sleepers etc is done at the depot.

    Transporting material to the rail head

    Initially when lead does not exceed 1.6 km, the material is transported in trolleys

  • Construction of Track

    Methods of Plate Laying

    Telescopic method: Operations

    Transporting material to the rail head

    When lead exceeds 1.6 km, the material is

    transported by trains

    Minimum two sets of wagons and one locomotive is

    used for quick and efficient transportation

    Unloading of material at the site

    Labour known as Material Gang is used for this purpose.

    They unload the material and supplies it to rail head.

  • Construction of Track

    Methods of Plate Laying

    Telescopic method: Operations Unloading of material at the site

    Linking Gang fixes the rails to the sleepers and joins the rails with fish-plates

    16 labourers are required to carry one rail

    Use of Anderson rail carrier saves this labour and time

    Depot should be as near as possible to the rail head, supply should be regular, on-site transportation should be quick

    Around 37.5 percent of total labour force should be for material gang

  • Construction of Track

    Methods of Plate Laying

    Telescopic method: Operations Fixing and joining of rails

    Center line of track is marked by pegs and a string is stretched along that

    Sleepers are then placed below string at appropriate spacing

    Rail is either marked with chalk or marked rod for sleeper spacing is used

    Suitable chairs or bearing plates are provided below rails to attain specified cant

  • Construction of Track

    Methods of Plate Laying

    Telescopic method: Operations

    Fixing and joining of rails

    Rails on both the sides of the sleeper are fixed one after

    the other to maintain gauge. Rail gauge is used to check it

    Fixing of rails to the sleepers is continuous

    Liners or shims (pieces of metal plates, 1 mm to 4 mm

    thick) are used to provide expansion joint between the two

    rails. Thickness is controlled by day temperature.

    Fish-plates are then placed in position and tightened

    Labour force of 37.5% to total labour should be employed

    as linking gang

  • Construction of Track

    Methods of Plate Laying

    Telescopic method: Operations

    Packing of ballast

    Packing gang is employed for this.

    They first straighten the newly laid track

    Track is brought to required gradient by packing or

    removing earth or ballast under each newly laid

    sleeper

    If there are chances of consolidation, then level of

    track is kept higher by a few millimeters than the

    actual track level desired

  • Construction of Track

    Methods of Plate Laying

    American method: Operations

    Machines are used for track laying

    Truck mounted, projecting arm or jib

    Used for laying the material received at rail head

    Wagon mounted, cantilevered arm or jib

    Assembled panels of two rails and sleepers required

    are prepared in workshop; delivered to rail head;

    unloaded by special machine; linked with rail head, till

    the required length of track is laid

  • Construction of Track

    Methods of Plate Laying

    American method: Operations Laying of ballast on track

    Ballast is transported by ballast train and unloaded into a number of heaps at suitable intervals

    Packing of ballast to get firm foundation is done using shovels

    It can also be done directly by ballast train using a brake van. When train moves slowly the ballast is spread uniformly through openings of wagon floors

    Plough is used to spread the ballast uniformly