Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
LCOE reduction potential of parabolic trough
and solar tower CSP technology until 2025
S. Dieckmann, J. Dersch, S. Giuliano, M. Puppe, E. Lüpfert, K. Hennecke, R. Pitz-Paal
(German Aerospace Center, DLR)
M. Taylor, P. Ralon
(International Renewable Energy Agency, IRENA)
SolarPACES Conference
Abu Dhabi
October 11-14, 2016
Content
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 2
1. Introduction
2. System Overview 2015 vs. 2025
3. Cost Analysis
1. Parabolic Trough Field
2. Solar Tower System
3. Thermal Energy Storage
4. Power Block
4. Results
5. Conclusion
Source: noorouarzazate.com
1. Introduction – Contributing Cost Factors for LCOE
Example based on annuity
loan over 25 years at 7.5%
Main Impact factors:
Investment cost (CAPEX)
Financing conditions
LCOE estimation is mainly
CAPEX estimation
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 3
Loan repayment
37%
Interest 47%
Insurance 5%
O&M 11%
Electricity from grid
0.5%
1. Introduction – Methodology and Boundary Conditions
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 4
Technology-based bottom-up approach relying on inhouse
expertise as well as external data sources
Contrasted with published Power Purchase Agreements
(NOOR II + III)
Ouarzazate, Morocco, DNI: 2017 / 2558 / 2935 kWh/(m²∙a)
Currency: US-$2015
CSP capacity growth to about 20GW in 2025
Parabolic Trough Solar Tower
Nominal Electric Net Output 160 MW 150 MW
Thermal Storage Capacity 7.5 h 9 h
2. System Overview – Parabolic Trough 2015 2025
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 5
Solar Field Thermal Storage Power Block HTF System
Aperture width: 7.5m 10m
Molten salt as HTF
Tout = 393°C 530°C Thot = 385°C 530°C
Storage volume halved!
η = 37.4% 42.7%
Constant optical
efficiency (79.1%)
2. System Overview – Solar Tower 2015 2025
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 6
Heliostat Field Tower & Receiver Thermal Storage Power Block
Thot = 565°C 600°C η = 42.8% 43.9%
ρmirror = 89.3% 91.2%
Closed loop control
Optimized heliostat and field design
ηreceiver = 87.6% 90.5%
Higher acceptable flux
Enhanced thermo-hydraulic design
3.1 Cost and Performance – Parabolic Trough Field
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 7
Total cost reduction: 23%
Cost reduction equally distributed
over sub-components
25% less collectors, foundations,
pylons, drives and receivers
Collector structure: -14 $/m²
(Sub-)supplier standards and
standardized designs
Automatization in manufacturing
HTF cost: -18$/m²
2015 2025
Collector UltimateTrough™ Future Trough
Turnkey Cost* 231 $/m² 177 $/m²
*: includes site preparation, collectors, piping, cabling, HTF, HTF system, assembly & construction
Source: sbp.de
3.2 Cost and Performance – Solar Tower System
Total heliostat cost reduction: -28%
Mirrors: -9 $/m²
Reach parabolic trough mirror cost
Drives: -11 $/m²
Replace costly slewing drives
Closed loop control
Structure & foundations: - 10 $/m²
Bigger market volume, standardized designs
Idustrialized assembly procedures
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 8
Total receiver cost reduction: -20%
Improved material concepts
Optimized absorber surface utilization
Higher average solar flux
2015 2025
Heliostat Stellio™ Future Heliostat
Heliostat Field Cost* 143 $/m² 103 $/m²
Tower Cost 90,000 $/m 72,000 $/m
Receiver Cost 125 $/kWth 100 $/kWth
*: includes site preparation, heliostat field, cabling, assembly & construction
Source: sbp.de
3.3 Cost and Performance – Thermal Storage
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 9
Both technologies:
Adapted storage materials
Innovative storage concepts (e.g. Single-tank thermocline storage)
Tower Storage Costs: -4 $/kWh (-17%)
Trough Storage Costs: -16 $/kWh (-38%)
-12.5 $/kWh for storage medium
halved storage fluid mass thanks to higher temperature
-3 $/kWh for HXs and pumps
Source: www.renewableenergyfocus.com
Parabolic Trough Solar Tower
2015 2025 2015 2025
Cost 42 26 26 22 $/kWh
Hot tank temperature 385 530 565 600 °C
3.4 Cost and Performance – Power Block
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 10
Minor cost reduction potential
Dry cooling predominant
Efficiency gain thanks to
increased live steam
temperatures
Source: The Energy Blog – energy.org.za
Parabolic Trough Solar Tower
2015 2025 2015 2025
Cost 1220 1100 1270 1100 $/kW
Live Steam Temperature 383 520 555 590 °C
Thermal Efficiency 38.4 42.7 42.8 43.9 %
3. Cost and Performance – Overview and Indirect Cost
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 11
Unit 2015 Cost variation [%]
2025
Trough Tower Trough Tower Trough Tower
Direct EPC costs Mio. $ 675 598 -24 -23 508 459
Engineering, management, add. EPC services
% on direct EPC 5 2
Profit margin and contingencies
% on direct EPC 10 19 6
Indirect EPC cost Mio. $ 101 144 -60 -74 41 37
Project development % on dir.+indir. EPC 10 4
Land cost $ / m² land 1 1
Infrastructure Mio. $ 6 6
Additional owner's cost % on dir.+indir. EPC 3 2
Owner’s cost Mio. $ 112 113 -61 -60 44 46
CAPEX Mio. $ 888 854 -33 -37 593 541
OPEX % of CAPEX 2.2 2.3 2.1 1.9
4. Results – Plant Output and LCOE
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 12
Until 2025 LCOEs decrease to
10 $-ct/kWh for medium DNI levels
7 $-ct/kWh for high DNI levels and favourable financing conditions
PPAs ≈ LCOE + 1…1.5 $-ct/kWh
Assuming 4% WACC, LCOE values match well to published PPAs from NOOR
Parabolic Trough 2015 2025
Annual el. output 576 GWh 625 GWh
Overall efficiency 15.1% 17.0%
Solar Tower 2015 2025
Annual el. output 598 GWh 644 GWh
Overall efficiency 15.5% 18.3%
WACC = 7.5%, DNI 2000-2900
PPA NOOR
WACC = 4% DNI 2550
( DNI values in [kWh / (m²∙a)] )
5. Conclusion
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 13
CAPEX: 5600 3600 $/kW (-35%) for both technologies (7.5/9h storage)
LCOEs can reach 7 $-ct/kWh (high DNI, favourable financing)
Major cost drivers Trough:
Molten salt as HTF
Trough collector CAPEX
Major cost drivers Tower
Steep learning curve, reduction of contingencies, overcoming of teething troubles
Heliostat field CAPEX
Financing conditions are a massive cost driver:
For each 1%-point WACC reduction LCOEs decrease by 1.1 $-ct/kWh
IRENA publication (2016): „The power to change – Solar and Wind Cost Reduction Potential to 2025”
> SolarPACES Conference > Oct 11-14, 2016 > Abu Dhabi > LCOE reduction of CSP until 2025 > Simon Dieckmann DLR.de • Chart 14
THANK YOU
for your attention!
Simon Dieckmann
DLR – Line Focus Systems
Contact:
MANY THANKS
to all contributing
partners, co-authors
and colleagues!