LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

Embed Size (px)

Citation preview

  • 7/25/2019 LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

    1/10

    LAUNCHING

    OF THE

    NEW SAN

    CRISTOBAL

    BRIDGE

    MARWAN NADER

    RAFAEL MANZANAREZ

    JACK LOPEZ-JARA

    CARLOS DE LA MORA

    BIOGRAPHY

    Marwan Nader is an Associate

    Vice President at T.Y. Lin

    International in San Francisco,

    CA. Born in 1962, he receivedhis Ph.D. from the University

    of California at Berkeley. He

    has worked on the design and

    construction of bridges for

    over 18 years.

    Rafael Manzanarez is a Vice

    President and Project Manager

    at T.Y. Lin International inSan Francisco, CA. Mr.

    Manzanarez has more than 25

    years of experience in bridge

    design and retrofit.

    Jack Lopez-Jara is a Senior

    Project Engineer at T.Y. Lin

    International in San Francisco,

    CA. Mr. Lopez-Jara has been

    involved in the design and

    construction of several

    suspension and cable-stayed

    bridges, with a special

    emphasis on seismic analysis

    and design.

    Carlos de la Mora is Director

    of Construction at ICA,

    Mexicos largest construction

    company. Mr. De la Mora has

    more than 15 years of

    experience managing the

    construction of complex

    infrastructure projects.

    SUMMARY

    The San Cristobal Bridge in

    Chiapas, Mexico is a 3-span

    (235'591'235') curved steel

    composite and orthotropic boxgirder erected by incremental

    launching. The following

    paper discusses the lessons

    learned from the collapse

    during launching of this

    bridge, as well as the re-design

    and re-launching of the new

    bridge. T.Y. Lin International

    was hired to investigate the

    cause of the collapse of the

    original bridge, check the

    redesign of the bridge and

    perform the erection

    engineering of the bridge.

  • 7/25/2019 LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

    2/10

    LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE

    Marwan NaderRafael Manzanarez

    Jack Lopez-Jara

    Carlos de la Mora

    Description of The San Cristobal Bridge

    The San Cristobal Bridge is part of a new highway connecting the cities of Tuxtla-Gutierrez and San

    Cristobal in the State of Chiapas, Mexico. The bridge crosses a deep canyon with a 3-span, continuous curved

    box girder supported on two intermediate piers and two end abutments. The total length of the bridge is

    1,060 ft (591 ft main span and two 235 ft side spans).

    Figures 1 and 2 show elevation and plan

    views of the San Cristobal Bridge.

    Due to the steep topography of the site, the

    designer considered the incrementallaunching of segments from both abutments

    to reach first the piers, and then to connect

    both ends at midspan.

    The superstructure is an unconventional mix

    of post-tensioned composite (steel/concrete)

    and orthotropic-steel deck sections. The

    central portion of the main span (Segments

    0105) is formed by orthotropic segments,

    whereas the rest of the main span and the

    side spans (Segments 0614) are comprised

    of composite sections. Figures 3 and 4 show

    a typical composite segment, and a typicalorthotropic-steel segment, respectively.

    The Designers selection of light steel o

    Fi ure 1 San Cristobal Brid e - Elevation

    rthotropic segments for the central segments of the main span, and

    heavier steel-concrete composite segments for the back segments was intended to reduce the weight of the

    launched cantilevers and to provide heavier back segments that would prevent the overturning of the bridge

    during launching.

    Figure 2 San Cristobal Bridge Plan View

    Page 1 of 9

  • 7/25/2019 LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

    3/10

    Figure 3 Typical Composite Section

    This solution induces large negative moments at composite segments 07, 08 and 09 in the zones adjacent to

    the piers. Deck post-tensioning was provided to resist those negative moments and to prevent tensile stresses

    in the concrete slab.

    Collapse of the Tuxtla Gutierrez Structure

    The construction of the San Cristobal Bridge started in early 2003. On October 26, 2004, soon after all

    segments had been launched, but before the closure of the bridge, the original structure on the Tuxtla-

    Gutierrez side collapsed, (See Figure 5).

    The Secretaria de Comunicaciones y Transportes de Mexico (SCT) hired a new contractor (Ingenieros Civiles

    Asociados ICA) to rebuild the structure. Their work involved the fabrication and launching of the entire

    bridge and rebuilding of Pier-2 on the Tuxtla Side, and the retracting, retrofitting, and relaunching of the

    bridge on the San Cristobal Side.

    ICA hired T.Y. Lin International (TYLI) to

    perform the following tasks:

    Investigate the Collapse of the

    Original Structure

    Check the Re-Design of the Bridge

    Figure 4 Typical Orthotropic Section

    Figure 5 Collapsed Structure on the Tuxtla-Gutierrez

    Perform the Erection Engineering of

    the New Structure

    The principal cause of the collapse was later

    identified as failure of the shear connectors in

    the concrete slab. This failure induced the loss

    of composite action and the collapse of the

    structure due to the lack of redundancy of thecantilever system. The shear failure of the

    shear studs was caused by their insufficient

    number and due to poor workmanship of the

    welds connecting them to the top flanges of

    the steel box girder, (See Figure 6).

    A site evaluation of the collapsed structure

    found several additional problems:

    Page 2 of 9

  • 7/25/2019 LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

    4/10

    Significant delamination of concrete slab in Tuxtla-

    Gutierrez side.

    Figure 6 TOP: Failed shear studs onTuxtla side of bridge, BOTTOM:

    Existing shear studs on San Cristobal

    Significant cracking of the concrete slabs on both the

    Tuxtla-Gutierrez and San Cristobal sides.

    Signs of local buckling during launching in the lower

    web panels, especially on Segments 6 and 11.

    Significant damage on Pier 2 due to impact of the

    collapsed superstructure onto the pier.

    Further evaluation of the design found the following:

    Overstress in the bottom flanges of the box girders

    due to inadequate spacing and sizing of longitudinal

    stiffeners.

    Insufficient post-tensioning in the concrete slab to

    prevent cracking and tension during launching.

    Insufficient concrete slab strength.

    Changes To The Original Design And

    Construction Sequence

    For the construction of the Tuxtla-Gutierrez side of the bridge and the retrofit of the superstructure on the San

    Cristobal Side, the Designer implemented several changes in the details and in the construction sequence.

    Changes to the Top Concrete Slab: Addition of Shear Studs and PT Tendons, Increase

    in Concrete Slab Strength

    The new details provided additional shear studs (almost double the original number) and required a higher

    level of quality control for the welds connecting the studs to the top flange.

    The original design had the deficiency ofplacing many of the shear studs required

    to provide composite action of the main

    girders on top of a small I-Beam located in

    the middle of the concrete slab instead of

    placing them directly on top of the top

    flange of the girders where they would

    have be more effective.

    Figure 7 Existing and Additional Shear Studs

    Additional shear studs (See Figure 7) were

    welded over the girder top flanges to

    guarantee full composite action during

    launching. Also, additional PT Tendonswere added to reduce the tensile stresses

    in the concrete slab and prevent cracking

    during launching.

    Cracking of the concrete slab during launching of a composite cantilever has negative consequences since it

    causes a change in the section properties, moves down the centroid of the section and causes redistribution in

    the state of stresses and deformations in the structure.

    Page 3 of 9

  • 7/25/2019 LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

    5/10

    Changes to the Bottom Flange: Additional Plate Stiffeners

    An evaluation of the details of the original design found deficiencies in the dimensioning of the longitudinal

    and transverse stiffeners on the steel bottom flange.

    Additional plates and angles were added to

    prevent local buckling and to ensure adequate

    capacity of the bottom flange in compressionzones. Figure 8 shows a typical stiffened

    compression panel with the various forms of local

    and global buckling.

    The AASHTO Specifications (3) provide

    guidelines for the dimensioning of compression

    flanges in Composite Box Girders with both

    longitudinal and transverse stiffeners (AASHTO

    10.39.4.4). The intention of the Specifications is to

    prevent local buckling of the flange plates or local

    stiffener buckling, and to allow the panels to

    develop their capacity without buckling inbetween stiffeners.

    Several changes had to be implemented in the

    design of the compression flanges to satisfy the

    AASHTO Specifications and to limit the

    compressive stresses to the allowable limits

    permitted by the code.

    In many situations, it was not possible (or

    practical) to fully implement the provisions of the

    AASHTO specifications, especially on segments that had already been fabricated and in zones in the deck

    where accessibility was an issue. For those situations, it was necessary to perform detailed finite element

    analyses to more accurately calculate the capacity of the panels and evaluate the possibility of local or global

    buckling. Figure 9 shows a FEM model of a bottom panel with its corresponding buckling mode shape.

    Figure 8 Buckling of Box Girder Compression

    Changes to the Web Plates:

    Reinforcement and Stiffening of Web

    Panels

    Figure 9 Buckling Analysis of Bottom Flange

    Several Failure modes control the design of the

    webs on steel- plate girder bridges that are

    constructed using incremental launching.

    Figure 10 show some of the predominant

    failure modes.

    An evaluation of the web panels of the San

    Cristobal Bridge found that the stiffeners

    provided in the original design were not

    adequate to resist the bearing forces during the

    launching of the segments. Signs of local

    yielding were already observed during the

    launching of the original structures. This

    prompted the designer to add triangular web

    stiffeners on the lower web panels. A potential

    Page 4 of 9

  • 7/25/2019 LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

    6/10

    stability problem due to web panel

    buckling was also identified. This problem

    becomes more evident on Segments 10

    and 11 where the web panels used

    relatively thin 13mm plates.

    Figure 10 Local Failure Modes above Launching Bearings

    (2)

    Finite Element Models of entire webpanels were developed to study these

    problems. Figures 11 and 12 show FEM

    models of Segment 11 with and without

    the addition of longer triangular web

    stiffeners. The study shows that the

    inclusion of those stiffeners limits the

    extent of local yielding and reduces the

    potential of web instability by increasing

    the bearing reaction required for panel

    buckling and shifting the stability problem

    to the upper web area at much higher

    loads.

    Figure 11 Web Panel Buckling Mode Segment

    11 Original Design

    Figure 12 Web Panel Buckling Mode Segment

    11 Re-Design

    Changes to the Original Construction Sequence

    Tuxtla-Gutierrez Side

    A completely new structure was fabricated and launched incorporating all the recommended changes to the

    shear studs, slab post-tensioning and additional stiffeners to the bottom flange and web plates.

    The construction sequence resembled the original design with some changes made in the sequence of

    application of post-tensioning forces.

    The new structure was fabricated and assembled behind Abutment-01 and then launched towards the pier and

    mid-span. Given the space limitations in the launching platform, the assembly and launching operations had

    to be performed simultaneously.

    As the launching progressed and more space was available in the launching platform, more segments were

    assembled behind the abutments and prepared for launching.

    Page 5 of 9

  • 7/25/2019 LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

    7/10

    The PT force and sequence were modified to provide for a larger compression force in the concrete slab

    before the full cantilever is launched and the deck reaches the position of maximum negative moment over the

    pier.

    San Cristobal Side

    After the collapse of the original structure on the Tuxtla-Gutierrez side, the structure on the San Cristobal side

    was pulled back with Segment 01 resting on top of Pier-03.

    Due to restrictions and space limitations at the job site, it was impractical to completely pull back all 14

    segments to perform the retrofit/strengthening work. The original design considered a maximum of 6

    segments behind the abutment during launching, with additional segments to be assembled as the launching

    pushed forward.

    With the superstructure supported on the pier, abutment, and temporary supports behind the abutment, the

    concrete slab (with all PT tendons de-stressed) was completely removed and replaced including additional

    shear studs. The steel box was also reinforced with additional stiffeners in the bottom flange and lower web

    panels.

    The change in the slab casting sequence on the San Cristobal side caused a different stress distribution

    compared to the structure on the Tuxtla side. The new construction sequence caused the weight of the

    concrete slab on Segments 04, 05 and 06 to be carried by the steel girder only instead of the entire composite

    section as in the case of the Tuxtla-Gutierrez Structure.

    A reduction in the post-tensioning was necessary to prevent generating large compressive stresses in the

    concrete slab in the back span where positive bending moments were expected during the service load of the

    structure.

    Figures 13 and 14 show the new construction sequences for the Tuxtla-Gutierrez and San Cristobal structures.

    Fi ure 13 New Construction Se uence Phases I - VIII

    Page 6 of 9

  • 7/25/2019 LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

    8/10

    Stage Construction Analysis

    Figure 14 New Construction Sequence Phases IX - XVI

    A SAP2000 computer model was created to calculate the forces and deflections in the structure during the

    launching of the bridge. Three-dimensional frame elements were used to model the composite and orthotropic

    deck segments as a spine consistent with the actual geometry and alignment of the bridge. Tendon elements

    were used to model the post-tensioning effects in the deck.

    The actual modeling of the launching of the segments was accomplished with the use of non-linear springs to

    simulate the support of the structure on temporary bearings behind the abutments and on top of the piers.

    Since no vertical restraints were provided on those bearings, the non-linear springs had to allow uplift of the

    structure under certain construction stages.

    To simulate the movement of the superstructure on the launching platform, the non-linear springs were added

    or removed accordingly to reflect the boundary conditions at each launching stage.

    The force demands from the construction stage analysis were used to do a stress check of the structure at eachconstruction stage according to the Project Design Criteria.

    Analytical Studies and Field Measurements

    The AASHTO Specifications (3) indicate the use of the moment of inertia of the gross cross-sectional area to

    compute the deflections of composite beams and girders (AASHTO 10.6.5), and the use of effective slab

    widths for the calculation forces and stresses in the section (AASHTO 10.38.3).

    Recent studies (4) also suggest the use of the full effective width for the calculation of both deflections and

    stresses in the cross section.

    Nevertheless some divergence was observed between the analytical results and the field measurements.

    Therefore there was a need to calibrate the effective inertia and effective slab width of the section in order to

    match the observed deflections with the analytical results.

    The difference can be attributed in the particular case of the San Cristobal Bridge to the more predominant

    effect of shear lag and differences in the assumed full-effective-width and actual-effective-slab-width on the

    composite segments with a pre-stressed concrete slab.

    After the initial launching of the structures a reduction factor to the gross inertia of about 20% was used to

    calibrate the results. This reduction factor is consistent with the ratio of the gross inertia to the inertia of the

    section considering an effective slab width equal to 12x the slab thickness. With this adjustment it was

    Page 7 of 9

  • 7/25/2019 LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

    9/10

    possible to achieve a good match between

    the analytical results and the field

    measurements deflections during the

    remainder of the launching operations.

    Figure 15 Comparison of Calculated and Field

    Deflections during Launching

    A comparison of the deflections calculated

    using the SAP2000 model, and the fieldmeasurement was also performed. Figure

    15 shows a plot of the tip cantilever

    deflections during launching for both the

    Tuxtla and San Cristobal ends.

    A discrepancy on the deflections of the

    of the

    the canyon is an economical

    San Cristobal side was observed when the

    full cantilever was launched (Full

    launching of the superstructure but before

    jacking of tendons C and D Stage 22 in

    Figure 15). This discrepancy may be

    explained by the occurrence of some

    minor cracking on the concrete slab,which has the potential of causing a

    reduction on the effective inertia

    introducing larger deflections than the

    ones estimated with the computer model.

    The difference in the elevation of the

    cantilever ends before closure was

    corrected by raising the abutment supportsand introducing a rigid body motion of the

    Tuxtla-Gutierrez structure. The advantage

    of this adjustment procedure is that no

    permanent or residual forces were induced

    in the structure and the behavior and stressdistribution in the bridges was not

    affected. Figure 16 shows a picture

    completed structure after closure.

    Summary And Conclusions

    Due to the restrictions imposed by the

    steep topography of the site, erecting the

    San Cristobal Bridge using incremental

    launching of the superstructure from both

    sides of

    solution.The selected structural system of the deck

    is an unconventional mix of orthotropic

    steel segments and composite

    (steel/concrete) post-tensioned box girder

    segments. The ratio of the main span

    length of 591 ft to the back span length of

    235 ft is larger than 2.5. Overturning and

    uplift at the abutments were expected. The

    Figure 16 Completed Structure of the New San Cristobal

    Bridge July 2006

    Page 8 of 9

  • 7/25/2019 LAUNCHING OF THE NEW SAN CRISTOBAL BRIDGE.pdf

    10/10

    use of lighter steel orthotropic segments for midspan and heavier composite segments on the back span was

    intended to prevent the overturning and uplift at the abutments, and to provide stability during launching.

    This solution involved the launching of composite segments with the concrete deck already cast in place.

    Therefore the composite segments adjacent to the pier were subjected to large negative moments.

    Longitudinal slab post-tensioning had to be provided to overcome the negative moment and to prevent tension

    and cracking of the concrete slab.The collapse of the original structure was primarily caused by inadequate design of the shear connectors

    combined with poor workmanship of the welds connecting the shear studs to the top flange. The failure of the

    shear connectors caused the loss of composite action and led to a catastrophic failure due to non-redundancy

    of the cantilevered box girder.

    For the new design with additional shear studs, additional PT tendons and higher strength of the concrete slab,

    a difference was noted between the predicted deflections (from computer models) and the values measured in

    the field. These differences are attributed to shear lag effects and a discrepancy with the assumptions made for

    the effective slab width of the concrete slab.

    Corrections had to be made to calibrate the effective stiffness of the segments to the actual effective slab

    width after the initial launching. With this calibration it was possible to achieve a good match of the analytical

    and field deflections for the remainder of the launching operations.

    Nevertheless additional discrepancies were still observed on the San Cristobal side when the full cantilever

    was fully launched. Minor cracking in the concrete slab caused a change in the effective inertia of thesegments and resulted in an increase in the cantilever deflections.

    It is concluded that the launching of a composite section with slab post-tensioning is not a practical solution

    due to the complexities and uncertainties in the actual stress distribution and effective width of the slab. Even

    with a careful analysis and control of the loads some cracking in the slab was experienced, inducing larger

    deflections than the ones predicted by the structural analyses.

    Due to the configuration of the bridge, it was possible to correct the discrepancy in the deflections on the

    Tuxtla-Gutierrez and San Cristobal sides by raising the abutment supports at the Tuxtla side, inducing rigid

    body rotations of the deck to match the tip elevations at both ends.

    The behavior of longitudinally post-tensioned composite decks needs to be further investigated in order to

    better understand the behavior of such deck segments under negative moments and the extents of the effective

    slab width.

    References

    1. Galambos, T.V. Guide to Stability Design Criteria for Metal Structures.John Wiley and Sons, Inc., New

    York, 1998.

    2. Rosignoli, M.Bridge Launching. Thomas Telford Ltd., London, 2002.

    3. AASHTO, Standard Specifications for Highway Bridges, Washington DC, 2002.

    4. Chen, S.S. et al. NCHRP Report 543 Effective Slab Width for Composite Steel Bridge Members,

    Transportation Research Board, Washington D.C. 2005.

    Page 9 of 9