LAS VEGAS AQUIFER STORAGE AND RECOVERY PROGRAM

LAS VEGAS AQUIFER STORAGE AND RECOVERY PROGRAM

Texas Innovative Water 2010 Seminar

San AntonioTexas

Tom Morris

Las Vegas

Nevada

Physiographic SettingPhysiographic Setting

• HYDRO-GEO SETTING

– Geology Limits

– GW Water Quality

– Production Yield

• OTHER CONCERNS

– Water Level Declines

– Planned Growth

– Existing Dist System

• APPROACH

– Basins VS Wells

– Old VS New Wells

– Recovery Location

Feasibility EvaluationFeasibility Evaluation

• HYDRO-GEO SETTING

– Geology Limits

– GW Water Quality

– Production Yield

• OTHER CONCERNS

– Water Level Declines

– Planned Growth

– Existing Dist System

• APPROACH

– Basins VS Wells

– Old VS New Wells

– Recovery Location

Feasibility EvaluationFeasibility Evaluation

• HYDRO-GEO SETTING

– Geology Limits

– GW Water Quality

– Production Yield

• OTHER CONCERNS

– Water Level Declines

– Planned Growth

– Existing Dist System

• APPROACH

– Basins VS Wells

– Old VS New Wells

– Recovery Location

Feasibility EvaluationFeasibility Evaluation

• HYDRO-GEO SETTING

– Geology Limits

– GW Water Quality

– Production Yield

• OTHER CONCERNS

– Water Level Declines

– Planned Growth

– Existing Dist System

• APPROACH

– Basins VS Wells

– Old VS New Wells

– Recovery Location

Feasibility EvaluationFeasibility Evaluation

Demonstration OperationsDemonstration Operations

RECHARGE PREP• Flush Well• Drop Laterals• Flip Flow Meter• Prop Check Open

EXISTING WELL CONVERSION• Demo with 2 Wells• Convert 33 wells to ASR• Apparent Well Clogging

• WELL USE TYPE

– Unused Well Conversion

– New Dedicated Injection

– New ASR Wells

• ASR WELL DESIGN

– Various Drill Methods

– Engineered Fluid Control

– Injection Development

• WELLHEAD EQUIPPING

– Bi-Directional Flow Meter

– Check Valve By-Pass

– Automated On-Off Control

– Motor Ratchet

Demonstration OperationsDemonstration Operations

Expanded OperationsExpanded Operations

• WELL USE TYPE

– Unused Well Conversion

– New Dedicated Injection

– New ASR Wells

• ASR WELL DESIGN

– Various Drill Methods

– Engineered Fluid Control

– Injection Development

• WELLHEAD EQUIPPING

– Bi-Directional Flow Meter

– Check Valve By-Pass

– Automated On-Off Control

– Motor Ratchet

Expanded OperationsExpanded Operations

• WELL USE TYPE

– Unused Well Conversion

– New Dedicated Injection

– New ASR Wells

• ASR WELL DESIGN

– Various Drill Methods

– Engineered Fluid Control

– Injection Development

• WELLHEAD EQUIPPING

– Motor Ratchet

– Bi-Directional Flow Meter

– Check Valve By-Pass

– Automated On-Off Control

Expanded OperationsExpanded Operations

• WELL USE TYPE

– Unused Well Conversion

– New Dedicated Injection

– New ASR Wells

• ASR WELL DESIGN

– Various Drill Methods

– Engineered Fluid Control

– Injection Development

• WELLHEAD EQUIPPING

– Motor Ratchet

– Bi-Directional Flow Meter

– Check Valve By-Pass

– Automated On-Off Control

Pump Check

Valve

Recharge Start/Stop

Auto Valve

Isolation

Gate Valves

• HYDRO-GEO EFFICIENCY

– Geology Zones

– Water Level Impact

– Recharge Migration

• WELL OPTIMIZATION

– Maximize Recharge Rates

– Piping Efficiency

– Scheduled O & M

• SYSTEM RELIEF

– Peak Demand Supply

– Commercial P&T

Managed OperationsManaged Operations

• HYDRO-GEO EFFICIENCY

– Geology Zones

– Water Level Impact

– Recharge Migration

• WELL OPTIMIZATION

– Maximize Recharge Rates

– Piping Efficiency

– Scheduled O & M

• SYSTEM RELIEF

– Peak Demand Supply

– Commercial P&T

Managed OperationsManaged Operations

• HYDRO-GEO EFFICIENCY

– Geology Zones

– Water Level Impact

– Recharge Migration

• WELL OPTIMIZATION

– Maximize Recharge Rates

– Piping Efficiency

– Scheduled O & M

• SYSTEM RELIEF

– Peak Demand Supply

– Commercial P&T

Managed OperationsManaged Operations

Lessens LearnedLessens Learned

Alluvial

Course Gravels

Pediment

Sands and Gravels Playa Lake Bed

Sands and Silts

PRE-DEVELOPMENT CONDITIONS

80 Years of Basin Overdraft

Lowered Water Table 100 to 300 Feet

Lessens LearnedLessens Learned

Perched Water System Development

Surface to 35-Feet

HYDRO-SYSTEM CHANGES

Development and Irrigation

Created Un-Natural Shallow Aquifer

Lessens LearnedLessens Learned

RECHARGE AQUIFER RECOVERY

16 Years of Recharge

320,000 AF Banked

Perched Water System Development

Surface to 35-Feet

Lessens LearnedLessens Learned

OTHER RECHARGE PROGRAM RELATED ISSUES

• Disinfection By-Products

• Water Quality Plume

• Pump Wear and Sanding

• Dissolved Air

Questions?Questions?

Visions of HopeVisions of Hope