LABOUR ESTIMATE FOR VARIOUS ITEMS OF WORKS

SN.ITEM DESCRIPTIONQUANTITYLABOUR ( 8 hours per day)

1.Concrete in Foundation.10 m3Head Mason 1/4, Mason 2, Labour 20

2.R.C.C. M - 15 grade.10 m3Head Mason 1/2, Mason 3, Labour 23

Note: For each additional storey, the strength should be increased by 6 nos. for volume of 10 cu.m to lift the materials.

3.Supplying, fitting, fixing and removing shuttering & staging.7 m2Carpenter 1, Labour 2

4.Reinforcement for R.C.C. work including cutting, bending and placing in position.100 kg.Bar binder (Black- smith/fitter) 1, Labour 1

5.Damp proof course.100 m2Head Mason 1/2, Mason 5, Labour 6

6.First class brickwork in 1:6 in super structure.10 m3Head Mason 1/2, Mason 9, Labour 18, Bhisti 2

7.Brick on edge flooring with cement Mortar (1:3).100 m2Head Mason 1/2, Mason 10, Labour 14, Bhisti 1

8.Ironite flooring (40mm thk).100 m2Head Mason 1, Mason 24, Labour 27, Labour for Scrubbing 3

9.C.G.I sheeting on roof10 m2Carpenter 1, Fitter (Blacksmith) 1/2, Labour 2

10.C.I. rain water pipe fixing.9 mMason 1/2, Labour 2.5

11.12mm thk cement plaster on brickwork in 1:6.100 m2Head Mason 1, Mason 10, Labour 14, Bhisti 1

12.Ruled pointing (1:3).100 m2Head mason 1/2, Mason 10, Labour 9, Bhisti 1

13.White washing primer coat and 2 finished coats to new plaster.100 m2Painter 1/2, Labour 2

14.Dry Distemper100 m2Painter 8.5, Labour 5.5

15.Plastic Emulsion paint on new work.100 m2Painter 5.5, Labour (Helper) 5.5

16.Primer coat on wood work/ steel work.100 m2Painter 2.5, Labour (Helper) 2.5

17.Panting two coats over priming coat for new wood work/steel work.100 m2Painter 5.5, Labour (Helper) 5.5

18.Demolishing cement concrete (1:2:4/1:3:6) including lead upto 50m.10 m3Labour23

19.Demolishing R.C.C. work including lead upto 50m.10 m3Labour33.5

20.Demolishing Brickwork in cement mortar including stacking of serviceable material and disposal of unserviceable materials within a lead of 50m.10 m3Labour19.5

21.Removing mortar and cleaning bricks and stacking cleaned bricks.10 m3Mason 6, Labour 25

22.Dismantling doors & windows including framing, stacking of material.1 no.Mason 1, Labour 0.20

23.Supplying and fixing 12mn/15mm dia G.I. pipe with G.I. fittings and M.S. clamps including cutting holes in walls and making good the same100 r.m.Fitter 7, Labour (Beldar) 6

24.Supplying, fitting and laying 25mm G.I pipes with G.I. fittings including trenching and refilling of external work100 r.m.Fitter 1, Labour 8

25.Laying, fitting and fixing 100 mm dia G.I. pipes including testing of joint, trench cutting for pipe laying upto a depth of 90 cm. and refilling, dressing etc.20 r.m.Fitter 1.5, Labour 13

26.Supplying, laying, joining 100 dia stoneware pipes with cement mortar 1:1 (excluding earthwork etc.).15 r.m..Mason 1, Labour 2

27.Wash Basin with C.I. brackets, brass taps, brass plug with brass chain, waste pipe Including cutting walls and making good the same.1 no.Plumber 1, Mason 1/2, Labour 1

28.Sink.1 no.Plumber 1/2, Mason 1/2, Labour 1

29.9" thick brick flat soling filled with local sand.10 m2Labour1

30.Earth work for roads including cutting, loading, unloading, carrying & dressing.10 m2Labour4

31.Stone soling for roads including packing with smaller stones manually.10 m3Labour7

32.Stone soling for roads including packing with smaller stones With steam roller.20 m3Labour7

33.Surface dressing/Bituminous carpeting on roads100 m2Labour(for one layer) 10, Labour (for two layers) 15