Upload
basit-anwar
View
37
Download
10
Embed Size (px)
DESCRIPTION
Labor Productivity and Analysis
Citation preview
Lecture 2-1
© Dr. Farrukh Arif, Assistant Professor, NED UET
CE-591- Cost Engineering and Control
Lecture 2Labor Productivity and
Analysis_______________________
Dr. Farrukh Arif, Assistant Professor, NED UET
Lecture 2-2
© Dr. Farrukh Arif, Assistant Professor, NED UET
Overview
� Labor and Labor Costs−Determining Costs−Labor Hour−Productivity
� Time Study� Work Sampling� Wages and Fringe Benefits
−Incentive Pay
Lecture 2-3
© Dr. Farrukh Arif, Assistant Professor, NED UET
Labor Classification (1/2)
� Major Classification includes−Direct Labor
� “Touches” the Product� Changes – Adds Value to the Product
−Indirect Labor� Supports Direct Labor Efforts
� Labor Pro. & Analysis is concerned with direct labor
Lecture 2-4
© Dr. Farrukh Arif, Assistant Professor, NED UET
Labor Classification (2/2)
� Other Classifications−Recurring-nonrecurring−Designated-non designated−Wage-salary−Management-blue collar−Union-nonunion−Social, political and other factors based classification
Lecture 2-5
© Dr. Farrukh Arif, Assistant Professor, NED UET
Determining Labor Costs (1/2)
� Labor Cost = Time x Wage−Time
� For individuals or for crew work� Expressed relative to unit of measure such
as stud, piece, bundle, container, 100 units, 1000 board feet etc.
� Units: minute, hour, day, month or year.
Lecture 2-6
© Dr. Farrukh Arif, Assistant Professor, NED UET
Determining Labor Costs (2/2)
� Labor Cost = Time x Wage−Worker Pay includes
� Basic Wages� Fringe Benefits
−Worker Pay based on � Type of Labor/Work� Attendance � Performance
Lecture 2-7
© Dr. Farrukh Arif, Assistant Professor, NED UET
� In early estimate, −Building design may be known only by total square feet and type −Large quantities of time are used.
� Guesstimate− Unrelated to any measures, referenced or analyzed data− Based on observational or rough experience
Lecture 2-8
© Dr. Farrukh Arif, Assistant Professor, NED UET
Labor Productivity and Analysis
� Concerned with the analysis of direct labor only � Direct labor
− Carpenter
− Mason
− Electrical wireman
− Roofer
− Engineers (in some cases)
� Indirect Labor − Time Keeper
− Superintendent
Lecture 2-9
© Dr. Farrukh Arif, Assistant Professor, NED UET
Labor Hour (1/4)(The Mythical Man Hour)
� Man-hour = One Worker Working for One Hour− Number of welder man hours per inch of field welding− Number of carpenter man hours to erect 100 ft2 of wooden framework− Number of road crew and equipment hours per mile of 28-ft wide asphalt road construction
� Labor Year (man year)52 Weeks x 40 Hours = 2080 Hours
� Labor Month (man month)2080 / 12 = 173.3 Hours
� Should Be “Time Working NOT Time at Work”
Lecture 2-10
© Dr. Farrukh Arif, Assistant Professor, NED UET
Labor Hour (2/4)(The Mythical Man Hour)
� Misconceptions in Estimating Labor hour− (1) Confusing effort with progress
� Example: 20 man-hrs proposed for a task or one worker will consume 20 hours.
� We assume crew of 2 will consume 10 hours.� Accepted but “Unproved hypothesis”� Cost varies as product of no. of labor and man
hours, progress may not.
Lecture 2-11
© Dr. Farrukh Arif, Assistant Professor, NED UET
Labor Hour (3/4)(The Mythical Man Hour)
� Misconceptions in Estimating Labor hour
− (2) Not considering interface dependencies.
� Philosophy that “Sum of the individual man-hour estimates will equal a total for the jobwithout any slippage of the man-hourconstants.”
Lecture 2-12
© Dr. Farrukh Arif, Assistant Professor, NED UET
Labor Hour (4/4)(The Mythical Man Hour)
� Misconceptions in Estimating Labor hour
− (3) Relying only on experience.� Using estimating information based on non-
quantitative measurement, supported by little data and more experience.
� Incompleteness and inconsistencies show up in implementation stage that is too late.
Lecture 2-13
© Dr. Farrukh Arif, Assistant Professor, NED UET
Productivity Measurement (1/2)
� “time is the measure of productivity.” � Historical records provide
−Cost of labor
−Supervision
−Methods
−But have significant errors
� Four methods for measurement of construction time−Job-ticket reports
−Non repetitive one-cycle time study
−Multiple cycle time study
−Work sampling
Lecture 2-14
© Dr. Farrukh Arif, Assistant Professor, NED UET
ProductivityMeasurement (2/2)
Productivity Analysis Definitions
Lecture 2-15
© Dr. Farrukh Arif, Assistant Professor, NED UET
Job-Ticket Reports and Man-Hour Analysis (1/9)
� Job-ticket is just a time card with additional information.
� Workers may complete their own job ticket.� Job ticket verification can be done through
computer-terminal, or foreman’s report.
Lecture 2-16
© Dr. Farrukh Arif, Assistant Professor, NED UET
Job-Ticket Reports and Man-Hour Analysis (2/9)
Lecture 2-17
© Dr. Farrukh Arif, Assistant Professor, NED UET
Job-Ticket Reports and Man-Hour Analysis (3/9)
� Several job tickets can be collected for variety of jobs.
� The engineer will examine the collected data for consistency, completeness and accuracy using
−Other instructional sheets−Construction codes−Engineering drawings
Lecture 2-18
© Dr. Farrukh Arif, Assistant Professor, NED UET
Job-Ticket Reports and Man-Hour Analysis (4/9)
� After that, a spreadsheet can be devised for the collected job tickets.
� A spreadsheet brings together the facts and prepares data for subsequent mathematical analysis.
Lecture 2-19
© Dr. Farrukh Arif, Assistant Professor, NED UET
Job-Ticket Reports and Man-Hour Analysis (5/9)
Lecture 2-20
© Dr. Farrukh Arif, Assistant Professor, NED UET
Job-Ticket Reports and Man-Hour Analysis (6/9)
� Job-ticket reports and man-hour analysis will vary with different construction trades.
� Example 1−Following is a foreman’s report of rough framing of a residence.−The foreman is non-working and spends only 15% of his time on the job.
Lecture 2-21
© Dr. Farrukh Arif, Assistant Professor, NED UET
Job-Ticket Reports and Man-Hour Analysis (7/9)
Lecture 2-22
© Dr. Farrukh Arif, Assistant Professor, NED UET
Job-Ticket Reports and Man-Hour Analysis (8/9)
−After searching the spreadsheet the work is matched against code 06111.10 “rough framing of partitions.” see the following spreadsheet.
Lecture 2-23
© Dr. Farrukh Arif, Assistant Professor, NED UET
Job-Ticket Reports and Man-Hour Analysis (9/9)
� The elapsed time in the spreadsheet is −8 hours X 2 crew = 16 hours−Total hours are reduced by 80% for cold weather.−Allowed total hours = 12.8 hours−Reduction for cold weather applied to each activity for the whole item of work.
Lecture 2-24
© Dr. Farrukh Arif, Assistant Professor, NED UET
Non-repetitive One-Cycle Time Study (1/7)
� Also called all-day time study� Useful for direct/indirect labor, long cycles type of
work� Non-repetitive because difficult to pre-plan in fine
detail. � Tight statistical reliability of the results is unlikely� Superior to guesstimating and job-ticket analysis� Requires continuous timing with an electronic stop
watch or video camera
Lecture 2-25
© Dr. Farrukh Arif, Assistant Professor, NED UET
Non-repetitive One-Cycle Time Study (2/7)
� Field and Office Procedure:−Recording Information
� Inform the labor that is to be time studied� Record job, equipment, worker(s), environmental conditions and other
circumstances before and during the work
−Time Information and Rating� Time the work and write down the job elements� Record any job change� Record the time consumed by each element� Rate the pace and tempo of each element
−Calculations� Calculate the normal time� Adopt pre-approved allowances, calculate allowance multiplier and extend
normal time to standard time� Express the standard in common units of productivity
Lecture 2-26
© Dr. Farrukh Arif, Assistant Professor, NED UET
Non-repetitive One-Cycle Time Study (3/7)
� Recording Information−Short as Possible (but Time-able)−Have Identifiable Start & End Points−Separate Operator & Machine Elements−Separate Constant & Variable Elements
Lecture 2-27
© Dr. Farrukh Arif, Assistant Professor, NED UET
Non-repetitive One-Cycle Time Study (4/7)
� Time Information and Rating−Stopwatch−Continuous Methods−Performance Rating
� Trained Observer� Subjective Comparison � Observed Operator to Typical Operator
Working at Normal Circumstances
Lecture 2-28
© Dr. Farrukh Arif, Assistant Professor, NED UET
Non-repetitive One-Cycle Time Study (5/7)
� Calculations−Normal time
� Where, Tn = normal time, hours, days etc
� To = observed time, hours days
� RF = rating factor, arbitrarily set, number
Tn = To X RF
Lecture 2-29
© Dr. Farrukh Arif, Assistant Professor, NED UET
Non-repetitive One-Cycle Time Study (6/7)
� Calculations for allowances−Personal−Fatigue−Delay−Together PF&D (in Percent)−Convert to Factor
� Where, Fa = allowance multiplier for PF&D
� PF&D = personal, fatigue and delay allowance, percentage
PF&D%
%Fa −
=100
100
Lecture 2-30
© Dr. Farrukh Arif, Assistant Professor, NED UET
Non-repetitive One-Cycle Time Study (7/7)
� Calculations for standard productivity
� Where Hs = standard time for construction job per unit of effort, hour, day etc.
Hs = Tn X Fa
Lecture 2-31
© Dr. Farrukh Arif, Assistant Professor, NED UET
Example 2
Lecture 2-32
© Dr. Farrukh Arif, Assistant Professor, NED UET
Multiple-Cycle Time Study
� Observing several cycles of a work on same or different locations/occasions
� For improving statistical reliability of the collected data
� Procedure is same as done for non-repetitive cycle time study
� Observations can be “Snap-Back” i.e. stopping and starting stop watch fro each element of the work/activity
Lecture 2-33
© Dr. Farrukh Arif, Assistant Professor, NED UET
Example table 3
Lecture 2-34
© Dr. Farrukh Arif, Assistant Professor, NED UET
Work Sampling (1/6)
� Used for General Purposes:−Estimating Costs−Scheduling−Labor Requirements−Monitoring and Managing Performance
� Statistical Technique
Lecture 2-35
© Dr. Farrukh Arif, Assistant Professor, NED UET
Work Sampling (2/6)
� Compared to Time Study−Multiple Workers / Machines−Study Large Area−Can Handle Long Cycle Times−Less Study Time Required (Lower Cost)−Less Disruptive of Work−Reduces Performance Issues
Lecture 2-36
© Dr. Farrukh Arif, Assistant Professor, NED UET
Work Sampling (3/6)
� Determines Proportion of Time Spent on Predetermined Activities
� Based on Probability & Statistics−Random, Discrete Observations−Sufficient Number of Observations−Representative of Distribution of Population
Lecture 2-37
© Dr. Farrukh Arif, Assistant Professor, NED UET
Work Sampling (4/6)Preliminary Sampling
� Uncovers Potential Problems� Refines Activity Definitions� Helps “Sell” the Sampling Study� Provides an Estimate for P’ i
Lecture 2-38
© Dr. Farrukh Arif, Assistant Professor, NED UET
Work Sampling (5/6)Standard Time
� Compute the Standard Time−Do Not Include Idle Activities
� Hs = standard time for construction job per unit of effort, hour, day etc� Ni = observations of event i, number � H = total man-hours worked during work sampling study� R = rating factor, decimal� PF&D = personal, fatigue and delay allowances, decimal� Np = construction units accomplished during period of observing this event, number
( ) ( )p
is N
DPFHRNNH
&1/ +=
Lecture 2-39
© Dr. Farrukh Arif, Assistant Professor, NED UET
Work Sampling (6/6)Considerations for Sampling
� Explain and Sell Prior to Starting� Appropriately Isolate Studies� Use as Large a Sample Size as Practical� Observe at Random Times� Conduct the Study Over a Long Period
Lecture 2-40
© Dr. Farrukh Arif, Assistant Professor, NED UET
Example 4
Lecture 2-41
© Dr. Farrukh Arif, Assistant Professor, NED UET
Wages
� Wage –−Money Paid for an Amount of Work−Usually for Direct Labor−Sometimes for Indirect Labor
� Salary –−Money Paid for a Given Period of Time
Lecture 2-42
© Dr. Farrukh Arif, Assistant Professor, NED UET
Fringe Benefits
� Additional Costs to Company� For Employees� Required by Law, Contract, Agreement� Can Be Included in Hourly Rates
Or � Covered in Overhead
Lecture 2-43
© Dr. Farrukh Arif, Assistant Professor, NED UET
Determining Wages
� Wage Only � Gross Hourly Cost
−Wages and Fringe Benefits Costs
� Wage Only Calculation−Based on Time in Attendance
Cdl = Ha x Rh
Lecture 2-44
© Dr. Farrukh Arif, Assistant Professor, NED UET
Incentive Wages
� Pure Incentive−(e.g. Working on Commission)
Cdl = NpRp
� Guaranteed Wage Plus IncentiveCdl = HaRh + Rh(HsNp – Ha)
� Minimum Cdl = HaRh
Lecture 2-45
© Dr. Farrukh Arif, Assistant Professor, NED UET
Efficiency
� Ratio of Standard Hours Produced to Actual Hours Worked
� Measure of Labor Efficiency or Productivity
100×=a
sp H
HNE
Lecture 2-46
© Dr. Farrukh Arif, Assistant Professor, NED UET
Gross Hourly Cost� Wages Plus Fringe Benefits Costs� Detailed Calculations Required
−By Engineering −Or (Preferably) Accounting
� Fringe Costs Include:−Legally Required Employee Costs−Contractual Costs−Voluntary Program Costs−Costs for Time Paid but Not Worked
Lecture 2-47
© Dr. Farrukh Arif, Assistant Professor, NED UET
Legally Required Costs
� Social Security −Employer’s Contribution7.65% of First $87,000 (as of 2003)
� Medicare−Employer’s Contribution1.45% of All Wages Paid
Lecture 2-48
© Dr. Farrukh Arif, Assistant Professor, NED UET
More Legal Requirements� Worker’s Compensation
−Income for Worker Who Cannot Work Due to Injury on the Job
� Unemployment Insurance−Pays Workers Laid Off Through No Fault of Their Own
� Non-Exempt Time-and-a-Half Pay−Over 8 Hours/Day and/or 40 Hours/Week
Lecture 2-49
© Dr. Farrukh Arif, Assistant Professor, NED UET
Other Fringe Costs
� Supplemental Medical Insurance−All or a Portion of the Premiums−Can Be Around $500/Month ($2.89/Hr)
� Life Insurance Premiums� Disability Insurance Premiums� Supplemental Pension
Lecture 2-50
© Dr. Farrukh Arif, Assistant Professor, NED UET
Pay for Time Not Worked
� Vacation, Holidays, Sick Pay−Amount of Pay for this Time Is Apportioned Over Total Hours in the Work Year−Added to Wage Rate
Lecture 2-51
© Dr. Farrukh Arif, Assistant Professor, NED UET
Joint Labor Costs
� More Than One Product Produced By Common Labor
� Common Production Up to a Split Point
� Common Labor Costs Need to Be Apportioned to the Different Products
Lecture 2-52
© Dr. Farrukh Arif, Assistant Professor, NED UET
(De)Jointing Labor Costs
� Determine a Common Metric� Find a Proportional Relationship for the
Products� Apply the Same Proportions to the Costs� Market Effects/Strategy Can Distort
−Some Products Subsidize Others−Price Is Not Proportional to Cost
Lecture 2-53
© Dr. Farrukh Arif, Assistant Professor, NED UET
Lecture Summary� Definitions Relative to Labor Costs� How to Determine Time for the Job
−Job-ticket analysis−Time Study (non-repetitive, multiple)−Work Sampling−Other
� Finding the Labor Cost Rate−Wages, Fringe Benefits, Gross Hourly Cost
Lecture 2-54
© Dr. Farrukh Arif, Assistant Professor, NED UET
End of Lecture