Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
www.elkjournals.com
………………………………………………………………………………………………
TRANSMISSION AND DISTRIBUTION LOSSES (POWER)
KVR Doraisamy Nisha Pai
INTRODUCTION
The official figures indicated for average
Transmission and Development (T&D)
losses with reference to the Indian
scenario is an enormous 23 percent of the
total electricity generated. On the other
hand, referring to model studies of some
states undertaken by independent
agencies like TERI, these T&D losses
amount to almost 50 percent of the
generated electricity. The T&D losses
are amounting to a huge number of 58%
has been estimated by SBI Capital
Markets in their latest study carried out
for DVB which contradicts the DVB
claims of 40- 50 % of total generated
power as T&D losses. The figures of
T&D losses directly impact the sales and
the purchase demands of power thus
influencing the electricity tariff rates
which is fixed by the utility and
moderated by the State Regulatory
Commissions.
COMPONENTS OF T&D LOSSES
Various commercial aspects and
technical factors in process of electricity
delivery are responsible for the loss of
energy. The inherent inefficiencies in the
conductors and the equipment which are
used in transmission, transformation,
sub-transmission and distribution of
power contribute to the dissipation of
energy and amount to the technical
losses in the T&D power loss. These
technical losses are intrinsic in any
system and cannot be reduced beyond a
certain level of optimism. These
technical losses can be further classified
according to the power transformation
and transmission System stages. This
classification yields Transmission
Losses (400kV/220kV/132kV/66kV),
Sub transmission losses (33kV /11kV)
and Distribution losses (11kV/0.4kv).
Apart from the technical losses, the
commercial losses amounted in the T&D
losses are a result of pilferage, meter
defects, human mistakes like meter
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
reading errors and the estimation of
unmetered supply of energy.
LEVEL OF T& D LOSSES
Considering the officially declared
figures of T&D losses in India, a gradual
rise is seen starting from about 15
percent recorded up to the year 1966-67
to about 23 percent which is documented
in 1998-99. This uninterrupted
escalating trend in the T&D losses is
concerning and efforts should be aligned
to control it. The Electric Power
Research Institute (EPRI) based in the
USA has documented the order of the
losses in several elements of the T&D
system: (Refer Table 1) the loss figures
indicated above are not fixed and
contextually changing with pattern of
using electrical energy, load density,
intensity of load demand. Also it must be
noted that efficiency and configuration
of the transmission and distribution
system which is subjective to the
elements also tampers the loss figures
indicated above.
The prescription for total energy losses
in the range between 10-15% in the
Indian states is given by the study
‘Guidelines for Reduction of
Transmission and Distribution Losses’
published by CEA (July, 1991). The
enclosed Annexure-A having T&D
losses for various countries should be
compared with the Annexure-B which
indicates the former T&D losses of
Indian states. It is noted from a glimpse
of Annexure-A that the T&D losses are
contained in the 10% mark for most of
the developed countries.
REASONS FOR HIGH T&D
LOSSES
Studies all over the world establishes the
fact that the power losses can be
contained in a reasonably short period of
time and the internal rate of return on
investment in measures taken for loss
reduction is extraordinary. To curb these
technical and commercial T&D losses
first step is to have a clear idea about
their magnitude which can be amounted
by installing accurate energy accounting
system. This system is fundamentally an
energy management tool which
functions to distinguish various
components in the total energy
consumption. That means an account of
energy generation and energy
consumption at various levels like
technical consumption by system
elements as well as by consumers; is
maintained by this tool. Moreover, a
sense of accountability and efficiency in
the working of utilities is brought about
by such methods.
REASONS FOR ESCALATED
TECHNICAL LOSSES
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
Major reasons yielding high technical
losses are amounted below:
Inadequacy in the budgetary investments
arranged in the field of transmission and
distribution systems, chiefly in the sub-
transmission and distribution categories.
The proposed and optimally desirable
investment ratio of generation and T&D
is ideally 1:1. But a practices in power
systems during the time period ranging
from 1956 -97 left it skewed to 1:0.45.
Thus, 65% low investment in the T&D
has led the distribution system to be
devoid of proportionate establishment
and growth resulting in the overloading
of the same. Unplanned growths of sub-
transmission and distribution system
with short sighted aims to extend the
power supply to new areas.
Large scale rural electrification through
long 11kV and LT lines.
Unnecessary multi stage transformations
of voltage.
Inappropriate load management yielding
excess or deficit in power.
Insufficient reactive compensation
reducing the efficiency of power
transmission.
Poor quality of equipment used by the
customers reducing the power factor and
overall efficiency of the power system.
REASONS FOR COMMERCIAL
LOSSES
In India; theft and pilferage are a
significant component in the high
transmission and distribution losses.
Theft / pilferage of energy is majorly
committed by non-consumers and
genuine consumers. The illegal or
unrecorded supply of power is used by
certain antisocial elements by attaching
conductors or tapping the bare
conductors of L.T. feeder or tampered
service wires. Whereas the bonfire
consumers deliberately bind to pilferage
tampering the meter boxes installed for
accounting their power consumption.
Following are some of the common
means for theft and pilferage.
Illegal tapings and extensions of loads.
Mechanical Meter Tampering to change
the meter readings
Terminating the meter recording by
remote control
Deliberate burning of meters causing
loss of property to the utility.
Altering the sequence of terminal wiring
to tamper the reading of the meters.
Power Connection Bypassing the meter
to manipulate the reading.
Altering the C.T. ratio and to
proportionately reduce the recording.
Human Errors in meter reading and
recording.
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
Instrument errors including Faulty
calibration of meters resulting in wrong
readings
T&D LOSSES IN RESTRUCTURED
SEBS
Various states have undertaken power
sector reforms to restructure their SEBs
(State Electricity Boards). As a result,
the reforming states have suddenly
testified higher T&D losses after
carrying out system restructuring and
studying it in detail. For example, Orissa
once reported 23 percent loss which after
restructuring amounted to 51 percent.
AP reported its T&D to be about 25
percent before restructuring its power
sector, estimates it to be around 45
percent as a result of restructuring.
Similarly with Haryana and Rajasthan
the newer estimate is at 40 percent at 43
percent contrary to former account of 32
percent and 26 percent in that order.
REGULATORY CONCERNS
In the situations when there is deficit of
an actual estimate of the T&D losses, the
regulatory commissions cannot estimate
the revenue requirements appropriately
consumers may be forced to pay for the
utility inadequacies.
The determination of the justified cost
incurred by an entity is fundamental in
deciding and regulating tariff because
incurred cost directly indicates the
deficit revenue which is the basis of any
tariff design. Thus, it is the regulator’s
responsibility to ensure fair accounting
of the losses.
The regulator is a moderating agency
that reassure the utility efforts to reduce
losses simultaneously ensuring to curb
the factors hindering the utility’s
performance.
BARRIERS IN PRIVATE SECTOR
PARTICIPATION
The absence of genuine estimates of T&
D losses discourages private sector
participation in power distribution. This
is because a private company would not
indulge in a sector whose revenue
potential is unknown.
UNMETERED SUPPLY
Commercial losses are a function of
unmetered supply of power to
agricultural entities and floating
connections to small and domestic
consumers belonging to weaker sections
of the society.
In most Indian states, as a part of
politically motivated move, the
agricultural tariff is based on the unit
horsepower (H.P.) of the motors used by
the farmers in scheduled farms. Such
power loads are applied and sanctioned
for low load declarations and after the
commissioning of the connections, the
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
consumers illegally keep on increasing
the connected loads thereby imposing
losses on the utilities.
The truthful approximation of unmetered
consumption in the agricultural sector is
a function of cropping pattern, ground
water level, seasonal variation, hours of
operation etc. The State Governments
(of almost all stares) in order to increase
the agricultural output, subsidize the
electric power supply for irrigation to the
farmers also in some States, deprived of
any charges. Thus, to benefit from this
schemes, most Electricity Boards supply
electrical energy to agriculture sector
and ask for entitlement to subsidy from
the State Govt. based on the energy
consumption. Also the energy meters
have been eliminated for agriculture
sector services by the electricity boards
and this nonexistence of energy meters
gives the free will to SEBs for falsifying
the values of average consumption in
Agricultural sector. In the absence of
energy meters, most of the SEBs resort
to fudging consumption figures to
include not only the under estimated
T&D Losses but also energy theft from
their system
The estimation of unmetered supply
affects the estimation of T&D losses
greatly, because estimation in the second
stage has amplification of the inherent
errors. Thus, an overestimated
unmetered agricultural consumption
yields a higher percentage of T&D loss
estimate. This tactic is deliberately used
by majority of the utilities to acquire a
higher amount of money as subsidy from
the State Govt. and they can also project
their system to be more efficient. Thus
the estimates of the unmetered
consumption and T&D loss figures are
implicitly related in both the ways.
Further the boards gets a chance to
ignore the incompetence of the T&D
systems by attributing all ills to the
agricultural supply and consequently
raising the tariff of all other non-
agricultural consumers. Most of the
methods being employed by SEBs for
estimating the unmetered energy
consumption are as follows
LOAD FACTOR BASED
ESTIMATION.
Feeder wise theoretical calculation of
losses based estimation.
Readings of meters installed at all the
Distribution Transformers located on a
feeder based estimation.
However, the accuracy of all the above
methods employed for estimation; is
questionable.
Measures for reducing technical losses
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
SHORT TERM MEASURES
Optimizing the resource and usage
equation by strengthening the weak links
in the distribution system.
Checking the tapings and illegal
connections by reducing the length of LT
lines. This can be achieved by relocation
of distribution sub stations and/ or
installations of additional distribution
transformers (DTs)
Lowering the no load losses such as iron
or core transformers losses facilitated by
installation of lower capacity
distribution transformers at each
consumer premises instead of cluster
formation and substitution by more
efficient DTs.
Installation of shunt capacitors for
reactive compensation thereby
improvement of power factor and the
overall efficiency of power distribution.
LONG TERM MEASURES
Technical parameters like the conductor
size, line lengths etc. in the complete
primary and secondary distribution
system should be optimized. The
parameters like existing loads, operating
conditions, future load forecast etc.
should be holistically comprehended.
And detailed distribution system studies
should be executed considering with a
foresighted and futuristic approach.
The strengthening and improvement of
the distribution systems along with
associated transmission system in
various phases should be planned with
blackouts and shut downs practically
calculated. Also the budget should be
pragmatically allocated for the
implementation requirements of each
phase. The complete system
improvement schemes and plan along
with detailed investment program should
be formulated with an objective to meet
system requirements for first 5 years
period.
MEASURES FOR REDUCING
NON-TECHNICAL LOSSES
The idea, that service quality, customer
relationships, and overall service
satisfaction can minimize revenue
losses; was verified for utilities all
around the world by the studies
undertaken by International Utilities
Revenue Protection Association
(IURPA).
Pakistan also confirmed the same theory
in the case of WAPDA (Water & Power
Development Authority).The
widespread theft of electrical power has
in Pakistan contributed financial crisis
for WAPDA (Water & Power
Development Authority). The World
Bank and Asian Development Bank
which had supplied the bulk of
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
WAPDA’s development loans wanted
WAPDA to act on power theft and T&D
Losses to recover its unpaid dues. But
WAPDA raised the power tariffs
burdening the customers which instead
of improving the financial circumstances
worsened them. There were increased
occurrence of theft and unpaid bills;
consequences of which were extreme
measures to limit power larceny. 35,000
troops were deployed by the Chairman
of the authority (a serving army officer)
to recognize and seize the culprits. The
result of it was commotion and distress
with more than 36 military courts trying
the cases and sentencing the culprits. The
exercise was fatiguing and futile.
Instead of the WAPDA approach the
following should be considered for
mitigating power thefts. These are
widely accepted throughout the world
for the same. Arrangement of vigilance
teams to check and prevent theft of
energy. Extreme penalties for the
culprits of meter seals tampering.
Energy auditing for district offices and
accountability of executive engineers
should be insisted upon. Installation of
tamper-proof meter boxes and numbered
seals. Testing, maintenance and
replacement for existing meters.
INITIATIVES REQUIRED
Keeping the above in view it becomes
essential to quickly assess the realistic T
&D losses in each of the states and take
speedy measures to cut the losses in an
organized manner by all the players in
power sector. The central or the state
governments should strategize periodic
budgets for financial aid to the utilities
for installations of meters on at least all
the distribution transformers. Energy
audits for the systems of all the big
industries as well as the utilities should
be mandatory and after the identification
of high loss its mitigation should be
planned. Schemes for incentive awards
and encouragement to utilities who are
able to reduce T&D losses beyond a set
mark. An arrangement of easy loans
from the banks for the utilities taking
remedial measures to reduce the T&D
losses. Awareness building among
consumers about high penalties on the
unauthorized use of electricity. A long
term (almost 15 years), realistic and
foresighted plan should be developed by
the utilities to meet the growing
electricity demands of the different
sectors of the state’s economy.
ISSUES FOR DISCUSSION
1. Status of metering and steps
required for early installation of the
same
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
The proposed installation of meters
under the financial assistance provided
by the Central government for
installation should be surveyed and the
practicality and implement ability of the
same should be critically thought about.
2. Mitigating power theft
Electrical power theft is a nuisance and
it affects all the utilities in varying
degrees. This theft has impact on not
only the loss of revenue to the utility but
the power quality is compromised which
results in low voltage and/ or voltage
dips.
The amended Sections 39 and 39A of the
Indian Electricity Act 1910 pronounces
the theft of electrical energy and its
abetment as a cognizable offence with
the deterrent punishment of up to 3 years
of imprisonment. The application of this
law and its impact on theft is an
important issue to be discussed.
3. Implementation of energy audits
schemes
Energy Audits of the systems in big
industries and utilities should be
mandatory. Realistic assessment and
time bound action for discrepancies in
figures of total T&D Losses into
technical and non-technical losses
should be taken by utilities. The areas
incurring high revenue loss should be
determined and remedial measures to
reduce them should be initiated.
The chosen sample size impacts
significantly the genuine assessment of
T&D Loss of a utility which further
affects the tolerance limit of variation in
results. Thus, it is essential to determine
and limit the sample size for genuine and
quick approximations of losses.
4. Setting of bench marks for yearly
reduction of T&D losses (technical
and non-technical)
REFERENCES
Power Ministers Conference
February 2000. – Agenda Notes
Electric Power International – fall,
1999.
Guidelines for Energy Audit in
Power Systems, CEA, and New
Delhi May 1992
P. N Khare MSEB, Power Theft – A
Root Cause of T& D Losses
5. Mr. M.H.P. Rao ‘Power Sector
bogged down by T&D Losses’ in
Financial Ex-press, dated July 9 ,1999
(Refer Table 2, 3)
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
LIST OF TABLES:
Table: 1
System element Power Losses (%)
Minimum Maximum
Step-up transformers & EHV transmission system 0.5 1.0
Transformation to intermediate voltage level,
transmission system & step down
to sub-transmission voltage level 1.5 3.0
Sub-transmission system & step-down to distribution
voltage level 2.0 4.5
Distribution lines and service connections 3.0 7.0
Total Losses 7.0 15.5
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
Table 2
Transmission and Distribution Losses (Power) 9
Annexure A: Transmission and distribution loss
Country T&D losses Country T&D losses
percent percent
Japan 4.0 Switzerland 6.0
Denmark 4.0 Sweden 6.4
Germany 4.0 United States 7.0
Ghana 4.0 United Kingdom 7.0
Singapore 4.0 Taiwan 7.0
Guam 4.50a Italy 7.4
Macau 4.81a London 8.3
Korea 5.4 Malaysia 10.0
France 5.9 Thailand 10.3
Australia 6.0 Fiji 10.52a
Canada 6.0 Indonesia 12.0
China 6.0 Mexico 14.0
South Africa 6.0 Hong Kong 15.0
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
Table 3
Transmission and Distribution Losses (Power) 10
State 1991/92 1992/93 1993/94 1994/95 1995/96 1996/97 1997/98a 1998/99b 1999/00c
Andhra Pradesh 20.3 19.2 19.1 18.9 18.9 33.1 32.5 31.9 31.1
Arunachal
Pradesh 28.2 34.9 31.6 31.0 36.0 32.6 31.0 31.1 31.5
Assam 22.7 21.0 20.8 24.9 26.2 26.0 30.1 23.0 30.0
Bihar 18.3 20.5 19.0 24.0 25.9 25.3 25.4 39.5 36.0
Daman and Diu 15.9 0 0 0 0 0 0 0 0
Goa 23.8 20.8 21.8 26.2 28.5 23.5 23.4 29.1 23.0
Gujarat 23.6 21.1 21.3 20.0 18.3 21.4 21.7 20.1 18.0
Haryana 26.8 25.4 25.5 28.5 31.4 32.8 33.4 29.6 29.5
Himachal
Pradesh 19.2 18.5 17.3 17.4 17.5 18.4 19.2 18.5 18.1
Jammu and
Kashmir 50.1 45.3 47.7 46.9 48.6 50.0 47.5 43.8 46.5
Karnataka 19.3 18.7 18.6 18.9 18.5 18.9 18.6 17 18.3
Kerala 22.5 21.0 20.2 20.1 20.1 21.4 17.9 17.5 17.0
Lakshadweep 17.4 0 0 0 0 0 0 0 0
Madhya Pradesh 25.8 22.2 20.2 20.1 19.5 20.6 19.7 17.8 18.6
Maharashtra 18.6 16.4 15.8 15.3 15.4 17.7 17.1 17.3 17.0
Manipur 24.4 22.5 22.5 22.0 21.5 23.0 21.8 19.7 20.0
Meghalaya 11.7 12.2 10.7 18.7 17.8 19.5 17.9 18.9 19.0
Mizoram 34.9 28.1 28.0 28.0 27.0 34.4 25.7 42.0 43.0
Nagaland 23.1 32.4 31.6 30.8 30.0 26.8 29.5 29.0 28.5
Orissa 25.3 23.5 23.4 23.8 46.9 50.4 46.0 42.0 36.0
ELK ASIA PACIFIC JOURNAL OF ELECTRONICS AND COMMUNICATION TECHNOLOGY
ISSN 2394-935X (Online); DOI: 10.16962/EAPJECT/issn. 2394-935X/2016; Volume 2 Issue 1 (2016)
………………………………………………………………………………………………
Punjab 21.8 18.7 18.5 18.3 18.2 18.9 17.8 17.1 17.7
Rajasthan 23.1 24.5 25.2 25.0 28.5 25.9 26.5 29.5 22.0
Sikkima 25.9 21.8 21.5 21.2 21.0 29.2 20.1 20.0 19.8
Tamil Nadu 18.4 17.5 17.3 16.9 17.0 17.2 16.8 16.6 16.5
Tripura 32.0 30.5 30.0 30.0 30.0 30.1 29.3 28.5 28.0
Uttar Pradesh 26.1 24.1 23.2 22.6 22.8 25.1 25.5 26.3 22.9
West Bengal 19.7 23.7 22.4 21.1 20.7 20.1 20.0 19.5 19.0
All-India
(utilities) 22.8 19.8 20.2 20.3 22.2 24.5 23.9 23.2 22.0
a provisional; b
revised ; c estimate