Page 1: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Kuali Research Administration (KRA)Kuali Financial System (KFS)

Kuali Student (KS)Project Management

Andy SlusarKRA Project Manager

Cornell University

Jim ThomasKFS Project Manager

Indiana University

Cath FairlieKS Program Director

The University of British Columbia

Page 2: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Effective PM?

Page 3: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

What is effective PM?

According to Project Management Institute:

• Initiation and Planning

• Execution and Monitoring

• Closing – transition to Sustainment

Page 4: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Agenda

• Initiation and Planning

• Execution and Monitoring

• Sustainment

• Open Source Misconceptions

Page 5: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

KRA/KFS/KS Project Differences

• Project differences– KFS started with IU FIS– KRA and the Coeus relationship– KS started with a vision– Team size/project scope– User community differences– Rice Evolution/Extraction

• Effective project management essential to all

Page 6: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

KFS & KRA Initiation

Guiding Principles• KFS based on Indiana’s FIS• KRA based on MIT’s Coeus• Scope Statement is the developments team’s

“contract” with functional stakeholders• Functional Changes are approved by the

respective Functional Council• Technical Standards are governed by the Kuali

Technical Council (KTC)

Page 7: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

KFS & KRA Initiation

Guiding Principles (cont.)• Maximize commonality of business practices• Make configurable as much as possible given

time and resource constraints• Burden of proof falls on advocates for change to

show benefits exceed costs• All changes subject to “The Reality Triangle”

Page 8: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

KS Initiation

• Development of a detailed Project charter– Contract between the partners– Mission, objectives & vision– Technical Architecture guiding principles– Functional Scope– Development approach (SOAD)– Governance & organization– Project management methodology -

Agile methodology

Page 9: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Technical StreamFunctional Stream

Aug 2007

Oct 2008Nov 2008

May 2009July 2009Aug 2009

Application Architecture- Process models- ER models- High Level Service Models- Domain Definitions

Technical Architecture-Technology proofs-SOA standards

Ser

vice

Mo

del

ing

R1

(Inf

rast

ruct

ure

& C

urric

ulum

Dev

elop

men

t)

Development Infrastructure- Developers workbench - Procedures- Standards

Co

ntr

act

Des

ign

R1

(Inf

rast

ruct

ure

& C

urric

ulum

Dev

elop

men

t)

Service Modeling R2(Domain 2) Software Design &

Development R1(Infrastructure & Domain 1)

Adjust plans and repeat forReleases 2/3/4

Pro

gram

Man

agem

ent

& C

omm

unic

atio

ns

Contract Design R2(Domain 2) Release 1 & Implement Test

Re-plan / Re-Architect / Implement & Transition to Support

Develop Configuration Application- Configuration Infrastructure-Proof of concept Pilot

Phased Modular Approach

Page 10: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring -The Reality Triangle

Scope(FunctionalCouncil)

Schedule (Time)

(Project Mgr)

Resources (Capacity)

(Board)

Page 11: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring -The Other Realities

COST RISK

Page 12: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Tools

Tools in a distributed environment– Confluence from Atlassian (wiki pages for

documentation, collaboration, etc)– Sakai (document sharing, email archive, etc)– Omniplan, MS Excel and Project for project

plans and Gantt charts– JIRA from Atlassian (task tracking)– Resource planning sheets (KFS/KRA)

Page 13: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Tools

Page 14: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Tools

Page 15: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Tools

Page 16: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Tools

Page 17: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Tools

Page 18: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Tools

Page 19: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Tools

Page 20: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Building Capacity

Project Resources • Clear role definitions

• Developer resources

• Functional resources

• Training

Page 21: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Managing Costs

• Monthly cost reporting by institution, by cost category by program year to Board– Detailed– Executive Summary

• Budget/ actual/ forecast reports $$ and FTE counts

• Variance analysis

Page 22: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Managing Costs

FTE Months

Resource Cost

FTEMonths

Resource Cost

FTEMonths

Resource Cost

JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUNInstitutional Contribution

Employee NameDoris Yen 0.3 0.7 0.8 0.9 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 $2,349 $5,482 $6,265 $7,048 $7,832 $7,832 $7,832 $7,832 $7,832 $7,832 $7,832 $7,832 10.7 $83,799Heather Johnson 0.3 0.8 0.6 0.8 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 $2,737 $7,300 $5,475 $7,300 $9,125 $9,125 $9,125 $9,125 $9,125 $9,125 $9,125 $9,125 10.5 $95,810Cindy Nahm 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 $8,181 $8,181 $8,181 $8,181 $8,181 $8,181 $8,181 $8,181 $8,181 $8,181 $8,181 $8,181 12.0 $98,176Audrey Lindsay 0.7 0.7 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 $8,636 $8,636 $7,402 $7,402 $7,402 $7,402 $7,402 $7,402 $7,402 $7,402 $7,402 $7,402 7.4 $91,291Len Carlsen 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 $4,199 $8,399 $8,399 $8,399 $8,399 $8,399 $8,399 $8,399 $8,399 $8,399 $8,399 $8,399 11.5 $96,585Zdenek Zraley 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 $3,489 $6,978 $6,978 $6,978 $6,978 $6,978 $6,978 $6,978 $6,978 $6,978 $6,978 $6,978 11.5 $80,252Joe Yin 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 $3,476 $6,953 $6,953 $6,953 $6,953 $6,953 $6,953 $6,953 $6,953 $6,953 $6,953 $6,953 11.5 $79,959George Lindholm 0.0 0.0 0.0 0.2 0.2 0.2 1.0 1.0 1.0 1.0 1.0 1.0 $0 $0 $0 $1,606 $1,606 $1,606 $8,032 $8,032 $8,032 $8,032 $8,032 $8,032 6.6 $53,012Leo Fernig 3.0 $33,504 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 3.0 $33,504Gord Uyeda 1.5 $16,029 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 1.5 $16,029Chiu, Hanson 0.4 0.4 0.4 0.4 0.4 $0 $0 $0 $0 $0 $0 $0 $2,647 $2,647 $2,647 $2,647 $2,647 2.0 $13,233Doug Loewen 0.2 0.2 0.2 0.2 0.2 $0 $0 $0 $0 $0 $0 $0 $1,808 $1,808 $1,808 $1,808 $1,808 1.0 $9,041Jing Cui 1.0 1.0 1.0 1.0 1.0 $0 $0 $0 $0 $0 $0 $0 $6,632 $6,632 $6,632 $6,632 $6,632 5.0 $33,158Contractor NameCath Fairlie 3.0 $79,988 3.0 $79,988Richard Spencer 3.0 $22,687 3.0 $22,687

0.0 $0Total Personnel Cost 14.3 6.2 6.0 6.5 6.8 6.8 7.6 9.2 9.2 9.2 9.2 9.2 $185,277 $51,929 $49,654 $53,868 $56,476 $56,476 $62,902 $73,988 $73,988 $73,988 $73,988 $73,988 100.2 $886,524 96.0 $872,400 -4.2 -$14,124

Other Program CostsTravel & Accommodation $6,702 $8,548 $572 $6,839 $7,418 $0 $2,257 $0 $6,503 $8,000 $12,500 $8,000 $67,339 $125,000 $57,661Other (Hosted Meetings, Meals, Misc.) $5,154 $370 $0 $486 $1,406 $0 $4,195 $0 $4,434 $0 $0 $6,000 $22,045 $10,000 -$12,045Hardware - Development Environment $0 $0 $0 $0 $4,675 $0 $0 $0 $22,182 $0 $0 $0 $26,857 -$26,857Software Licenses $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0Project Team Training $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0Training and Communication Materials $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0Consulting Expertise $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0Total Other Costs $11,856 $8,918 $572 $7,325 $13,499 $0 $6,452 $0 $33,120 $8,000 $12,500 $14,000 $116,241 $135,000 $18,759

Total Institutional Contribution $197,133 $60,847 $50,225 $61,193 $69,976 $56,476 $69,354 $73,988 $107,108 $81,988 $86,488 $87,988 100.2 $1,002,765 96.0 $1,007,400 -4.2 $4,635

Program Level ExpenseEmployee NameLeo Fernig 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 $11,168 $11,168 $11,168 $11,168 $11,168 $11,168 $11,168 $11,168 $11,168 $11,168 $11,168 $11,168 12.0 $134,016Gord Uyeda 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 $10,686 $10,686 $10,686 $10,686 $10,686 $10,686 $10,686 $10,686 $10,686 $10,686 $10,686 $10,686 12.0 $128,234Kristina Batiste 0.4 0.4 0.4 1.0 1.0 $6,000 $4,500 $4,500 3.2 $15,000

$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0.0 $0$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0.0 $0

Contractor NameCath Fairlie 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 $10,116 $23,496 $25,337 $31,924 $30,236 $20,886 $23,420 $28,625 $10,409 $25,600 $25,600 $25,600 12.0 $281,249Valerie Johnson 0.4 0.4 0.2 0.6 0.7 0.6 0.6 $8,750 $11,156 $3,197 $9,141 $13,669 $7,715 $9,000 3.5 $62,629

0.0 $0Total Personnel Cost 3.0 3.0 3.0 3.4 3.4 3.2 3.6 4.1 4.0 4.0 4.0 4.0 $31,970 $45,350 $47,191 $62,528 $63,247 $45,937 $54,415 $64,148 $39,978 $62,454 $51,954 $51,954 42.7 $621,128 0.0 $0 -42.7 -$621,128

Other Program CostsTravel & Accommodation $3,762 $1,352 $0 $1,303 $5,174 $0 $0 $0 $2,618 $0 $5,000 $5,000 $24,209 -$24,209Other (Hosted Meetings, Meals, Misc.) $0 $2,390 $0 $1,766 $3,794 $0 $0 $0 $0 $0 $4,000 $0 $11,950 -$11,950Hardware - Development Environment $0 $0 $0 $0 $0 $0 $43,151 $0 $0 $0 $0 $0 $43,151 -$43,151Software Licenses $2,796 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,796 -$2,796Project Team Training $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0Training and Communication Materials $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0Consulting Expertise $0 $3,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,000 -$3,000Total Other Costs $6,558 $6,742 $0 $3,069 $8,968 $0 $43,151 $0 $2,618 $0 $9,000 $5,000 $85,106 $0 -$85,106

Total Program Level Expense $38,529 $52,093 $47,191 $65,597 $72,215 $45,937 $97,566 $64,148 $42,596 $62,454 $60,954 $56,954 42.7 $706,234 0.0 $0 -42.7 -$706,234

2007 2008

Actual/Forecast to Complete ($$) Y1 VarianceY1 BudgetY1 Forecast

Cost Category

Actual/Forecast to Complete (FTE Count)

2007 2008

Page 23: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Managing Costs

FTE Months Resource CostFTE

Months Resource Cost FTE Months Resource Cost

Program CostsStaff/Resource Costs (Labour) 506.3 $5,148,128 531.2 $4,952,116 24.9 -$196,012Travel & Accommodation $392,992 $577,500 $184,508Other (Hosted Meetings, Meals, Misc.) $101,912 $53,000 -$48,912Hardware - Development Environment $113,532 $80,000 -$33,532Software Licenses $46,308 $40,000 -$6,308Project Team Training $40,000 $40,000 $0Training and Communication Materials $34,000 $80,000 $46,000Consulting Expertise $101,000 $128,000 $27,000Contingency $250,000 $600,000 $350,000Total Program Costs 506.3 $6,227,871 531.2 $6,550,616 24.9 $322,745

Program ContributionsUniversity of XXXX 100.2 $1,016,549 96.0 $1,007,400 4.2 $9,149University of XXXX 117.5 $1,254,456 100.0 $1,001,417 17.5 $253,039University of XXXX 90.1 $1,171,226 102.0 $992,333 -12.0 $178,893University of XXXX 96.7 $931,024 100.0 $983,500 -3.3 -$52,476University of XXXX 26.4 $538,101 28.0 $496,000 -1.6 $42,101University of XXXX 19.5 $328,099 30.0 $304,300 -10.5 $23,799University of XXXX 4.4 $38,867 18.0 $174,000 -13.6 -$135,133Total Founder & Partner Contributions 454.7 $5,278,322 474.0 $4,958,950 -19.3 $319,372

Cash ContributionsAndrew W. Mellon Foundation Request $500,000 $500,000 $0CANARIE Funding Proposal $0 $250,000 -$250,000

Total Program Contributions $5,778,322 $5,708,950 $69,372Funding Shortfall -$449,549 -$841,666 $392,117

Y1 Forecast Y1 VarianceY1 Budget

Page 24: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Execution & Monitoring - Managing Risk

• Identifying, analyzing, and responding to project risk. • minimize the consequences of adverse events, which

may prevent the project from meeting its objectives. • identify the highest-priority risks –focus on them as

the project evolves• a dynamic and proactive process that requires

continuous vigilance.

• Risk Assessment:• Risk Index = Impact X Probability

• Risk Mitigation:• Activities to lower the probability of the risk• Activities to lower the impact of the risk

Page 25: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Ref. #

Risk Item Description And

Potential Consequence or Impact

Impact on Project

1=Low 2=Med 3=High

Prob. Of Occurring

1=Low 2=Med. 3=High

Risk Index

(Risk x Prob.)

Impact Horizon

Resolution Required

Date

Risk Plan

Mitigate Accept Avoid

Planned Mitigation Activities

Forecast Risk / Expected Outcome

After Actions Completed

Current Status / Actions Taken To-Date

1. Technology Risk: A Service Oriented Architecture implemented using Web Services is a relatively new technology set. Lack of experience within the founding institutions and within the industry for these technologies.

Design mistakes leading to significant problems at the development stage

Design and development take longer than expected as problems are worked out

May be system performance issues with the new technology

Costs increase

3 3 9 Near Mitigate Develop a QA strategy and plan

Conduct architectural reviews with industry experts at critical project milestones

RISK: 3 X 3 = 9 Conducted architectural reviews at end of planning phase by IBM and Sosnoski

Arrangements made with IBM and SUN to conduct a second external review at end of Architecture (Feb 2008)

2. Business Analysis Risk: Project team members are inexperienced with the concepts and guidelines of Service Orientation. Service modeling and service design skills not available. Methodology is new and not well understood.

Results in services that are too tightly coupled and a reduction in flexibility in the system

Don’t realize the expected benefits of service composition or development agility

3 3 9 Near Mitigate Ensure all parties are fully familiar with the concepts of Service-Orientation. This includes business stakeholders as well as applications managers and developers

Formal project team training Contract experienced

resources

RISK: 3 X 2 = 6 Project kick-off meeting to overview SOA approach

IBM presentations on SOMA IBM experts participating in

workshops Business Analysts contracted by

institutions who lack that skill set Continue to develop and document

the methodology to be used. Mentoring provided from skilled resources to less skilled resources during the application architecture phase.

IBM contacted to work with the team to review and comment on the methodology.

Additional resources will be contracted to increase the SOA expertise on the team. Resources being sought from IBM and other sources.

Execution & Monitoring - Managing Risk

Page 26: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Communications

• Good project management requires effective communications & collaboration

• Good communications requires:– A strategy and a plan– Communication/collaboration tools– Effective meetings

Page 27: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Collaboration in a Distributed Environment!

Page 28: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Collaboration in a Distributed Environment!

Page 29: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

• Collaboration is hard work. It requires:– Governance– Excellent communications– Relationship building – Respect & Trust– Commitment– Team Goals vs. Institutional Wants– Complementary competencies – everyone

brings something different to the table

• Result - more creative solutions• KIT – cross project collaboration and

integration

Collaboration

Page 30: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Collaboration Tools

• Blending Collaboration Tools - the right tool at the right time– Face to face meetings or workshops– Video Conference/Skype video– Breeze (Adobe Connect)– Telephone / Skype audio conference– Chat/IM– Email

Page 31: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Meetings/Status Reporting

• In person meetings are a good communication vehicle for reporting status and resolving issues

• Board• Functional Council• Technical Council• Project Leadership meetings• Developer meetings• Code Reviews• One on ones• Face to Face meetings• Focus groups• Informal

Page 32: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Effective Meetings

• Have an agenda• Record Action Items• Track and follow up • Formation of ad hoc subgroups

Page 33: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Sustainment

• Closing the project involves transitioning to sustainment

• Kuali projects are rapidly approaching completion and full transition into sustainment model– several implementation projects in the works

• Kuali Foundation Board working aggressively to define a detailed Sustainment model– Team structure, resources, capacity– Funding model– Support processes

Page 34: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Open Source Misconceptions

• Part time developers• Not industrial strength• Not well tested• Hap-hazard governance• No documentation

Page 35: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Kuali Community Source

Page 36: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Kuali Community Source

• Full Time Dedicated Development Teams • Dedicated Functional Resources• Built for reliability and scalability • Intensive QA/Testing process• Structured and well documented governance

process• Extensive functional and technical documentation• Partner Institutions dedicated to the success of

Kuali!• Commercial Affiliates available to provide

expertise

Page 37: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

How are we doing?

• KFS

• KRA

• KS

Page 38: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Working togetherWe can do it!!

Page 39: Kuali Research Administration (KRA) Kuali Financial System (KFS) Kuali Student (KS) Project Management Andy Slusar KRA Project Manager Cornell University

Kuali Project Management

Questions?

http://www.kuali.org