17
Kingdom of Morocco Ministry of Land-Use Management, Water and the Environment The First Carbon Exhibition in North Africa and Middle East Region Djerba, 22-24 September 2004 Moroccan CDM projects Moroccan CDM projects Energy Efficiency projects Energy Efficiency projects faouzi senhaji GERERE [email protected] CD4CDM Project

Kingdom of Morocco Ministry of Land-Use Management, Water and the Environment

  • Upload
    nhung

  • View
    33

  • Download
    0

Embed Size (px)

DESCRIPTION

Kingdom of Morocco Ministry of Land-Use Management, Water and the Environment. Moroccan CDM projects Energy Efficiency projects. The First Carbon Exhibition in North Africa and Middle East Region Djerba, 22-24 September 2004. faouzi senhaji GERERE [email protected]. CD4CDM Project. - PowerPoint PPT Presentation

Citation preview

  • Kingdom of Morocco

    Ministry of Land-Use Management, Water and the EnvironmentThe First Carbon Exhibition in North Africa and Middle East Region Djerba, 22-24 September 2004 Moroccan CDM projects

    Energy Efficiency projectsfaouzi [email protected] Project

  • Moroccan CDM ProjectsEnergy Efficiency Projects

    Current 7 EE projects (/25) 1 PDDPortfolio 1 EE SS project (/9) 1 PIN

    OCP-Heat Recovery System (HRS) Project 85,000 CER/yrONE- Street lighting project (15,000 LCB & PM program) 2,600 CER/yr

  • OCP-HRS Project Office Chrifien des Phosphateshttp://www.ocpgroup.ma 85,000 CER/yr Contact p.: Ms. Naima BELKOUCH E-mail:[email protected]

  • The Project title: Heat Recovery enhancement at the Jorf Lasfar phosphoric acid production plant Introduction of two Heat Recovery Systems in the process of sulfuric acid production The heat recovered allows for increased power generation This will result in a reduction of the global primary energy consumption

  • Inclusion of a HRS in the process Full name : Heat recovery enhancement at Jorf Lasfar PA plantLocation : Jorf Lasfar, 25 km south of El JadidaCategory : Energy EfficiencyProject proponent : Office chrifien des Phosphates (OCP)PDD : EcoSecurities CleanTech / ApDate of operation : end of 2005First year of CER delivery : 2006Crediting period : 2006-2015Expected CER : 850,000Project summary

  • The Jorf Lasfar plant (OCP) Technical description of the project activity

    The phosphoric acid process uses phosphates to produce phosphoric acid and fertilizers

    The sulphuric acid processing facility uses a MONSANTO process, an exothermic process

  • The Jorf Lasfar plant (OCP) Technical description of the project activity Current use of the heat released from this process:

    to produce steam / process70% recovered& to generate power

    28% in the cooling water (Atlantic ocean) - 2% lost by radiation

  • Inclusion of a HRS in the process Technical features :Components to be installed : two heat recovery systems (HRS)Expected production : 50 t/hr additional sat. steam at 9.5 bars Additional power capacity : 8 MWFinancial issues :Total cost of the project : US $ 18.2 million (MAD 200 million) 15.9 installation cost, 2.3 development costTiming :Starting of works : 2005 (1st & 2nd HRS)Full operation of the two HRS : 2006.Project description

  • OCP-HRS Project

    Methodology :Baseline methodology for power generation from enhanced heat recovery following the retrofit of existing industrial processes (Ecosecurities)ACM 0002 (revised PDD)Approach : option 48 (a) of the Marrakech Accords Demonstrate that the project is not BAUDetermine the most likely scenario in absence of the projectDetermine the avoided emissions by calculating the Projected Operating Margin: Weighted CEF of the national power plantsCalculations :Through the crediting period, the CEF moves down from 0.803 (2006) to 0.682 (2009) and then increases to 0.724 (2015)Over the crediting period, the expected CER are about 850,000Baseline methodology

  • OCP-HRS Project

    Environmental benefits :GHG emission free power generationReduction of atmospheric pollutants SO2, NOx, COSocio-economic benefits :Improvement of the competitivenessNet benefits for the countrys economySustainable development

  • 2. ONE-Street lighting project (15,000 LCB program)

    2,600 CER/yr Contacts : Mr. KHATAMI & Mr. TAHIRI E-mail : [email protected]@one.org.ma

  • ONE-Street lighting SS projectFull name : Street lighting with LCB & power modulatorsLocation : different locationsCategory : 2-C , EE at the end userProject promoter : ONE State Utility agencyPIN approved PDD not developed yetDate of operation : 2005First year of CER delivery : 2006Crediting period : 2006-2015Expected CER : 26,000Project summary

  • ONE-Street lighting projectTechnical features :Installed capacity : 3 MW (15,000 x 200 W)Expected saving : 3 GWh / yr (200 W bulbs to replace 250 W bulbs)Components : 15,000 LCB of 200 W & PMFinancial issues :Total cost of the project : US $ 0.5 million (Cost per bulb: US $ 27.3)Timing :Starting date : 2005 Crediting period : 2006-2015Project description

  • ONE-Street lighting projectMethodology :Described in paragraph 49 of Appendix B of the simplified M&P.Approach : Displacing Electricity : BAU emissions project emissionsEmissions: Number of devices * power of device * average annual operating hours * emission coefficient (as for 1.D.) / grid loss Calculations :Over the crediting period, the expected CER are about 150,000Baseline methodology

  • ONE-Street lighting projectEnvironmental benefits : GHG emission reductionSocio-economic benefits :Fossil fuel used in power generation reducedPromotion of socio-economic activities Sustainable development

  • For more informations :

    Permanent Secretariat of CDM National Council

    Climate Change Unit

    Directorate of Partnership, Communication and Cooperation

    Ministry of Land-Use Management, Water and the Environment

    36 Avenue Al Abtal Rabat Morocco

    Tel/Fax : +212 37 68 17 59 Tel/Fax: +212 37 77 47 88 [email protected] [email protected]

    www.mdpmaroc.com