Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
FEASIBILITY STUDIES AND DETAILED
ENGINEERING DESIGN OF THE MULTINATIONAL
ARUSHA – HOLILI/TAVETA – VOI ROAD
RESETTLEMENT ACTION PLAN (RAP)
FINAL REPORT
October 2012
Submitted to:
Kenya National Highways Authority
Bluesheild Towers, Hospital Road, Upper Hill.
P.O. Box 49712 - 00100 Nairobi. Kenya.
Tel: +254 020 8013842
Email: [email protected]
Website: www.kenha.co.ke
Prepared by:
Timau Plaza, Argwings Kodhek Road, 4th Floor
P.o Box 76672-00508
Nairobi, Kenya
Tel: +254 (020) 3867715/3867716
Email: [email protected]
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
Proponent:
KENYA NATIONAL HIGHWAYS AUTHORITY
Assignment:
RESETTLEMENT ACTION PLAN FOR TAVETA – MWATATE ROAD
Name and Address of the Consultant:
Timau Plaza, Mbagathi Rd, Hurlingham
P.O. Box 76672-00508
Nairobi, Kenya
Tel: +254 20 3867715/3867716
Email: [email protected]
Signed:________________ Date: __________
For: Egis International
Name and Address of the Proponent:
Kenya National Highways Authority
Bluesheild Towers, Hospital Road, Upper Hill.
P.O. Box 49712 – 00100
Nairobi. Kenya.
Tel: +254 020 8013842
Email: [email protected]
Website: www.kenha.co.ke
Signed: ____________________ Date: ________
For: Kenya National Highways Authority
Disclaimer:
This Resettlement Action Plan is strictly confidential to, Kenya National Highways Authority and any use of the materials thereof should
strictly in accordance with the agreement between Kenya National Highways Authority and Egis International (the Consultant).
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
i
TABLE OF CONTENTS
EXECUTIVE SUMMARY.................................................................................................................... 1
1. INTRODUCTION ....................................................................................................................... 1
1.1 Background .................................................................................................................................. 1
1.2 The Project Location ..................................................................................................................... 1
1.3 Summary Description ................................................................................................................... 2
1.4 Objectives and scope of the RAP ................................................................................................... 2 1.4.1 Objectives ........................................................................................................................................................... 2 1.4.2 Scope of the Resettlement Plan .......................................................................................................................... 3
2. METHODOLOGY ...................................................................................................................... 4
2.1 The RAP Process ........................................................................................................................... 4 2.1.1 Literature review................................................................................................................................................. 4 2.1.2 Field activities ..................................................................................................................................................... 4 2.1.3 Data analysis and reporting ................................................................................................................................ 5
2.2 Timeframe ................................................................................................................................... 5
2.3 Structure of the Resettlement Action Plan report .......................................................................... 5
3. PROJECT DESCRIPTION ............................................................................................................. 6
3.1 Current status .............................................................................................................................. 6
3.2 Proposed road project .................................................................................................................. 6
3.3 Project activities/Works ............................................................................................................... 8
4. LEGAL FRAMEWORK .............................................................................................................. 10
4.1 Kenya Country policies on resettlement ...................................................................................... 10
4.2 The land tenure system .............................................................................................................. 10
4.3 Acts Relevant to resettlement .................................................................................................... 11 4.3.1 Land Acquisition in Kenya ................................................................................................................................. 11 4.3.2 Acts related to RAP in Kenya ............................................................................................................................. 12
4.4 African Development Bank’s Policy on Involuntary resettlement ................................................. 14
4.5 Commonalities between GoK and AfDB guidelines ...................................................................... 16
5. SOCIO - ECONOMIC PROFILE OF THE PAPS .............................................................................. 18
5.1 Sources of data .......................................................................................................................... 18
5.2 Education ................................................................................................................................... 18
5.3 Livelihoods and income levels ..................................................................................................... 19
5.4 Land tenure systems ................................................................................................................... 19
5.5 Household structures ................................................................................................................. 20 5.5.1 Damage to assets .............................................................................................................................................. 20 5.5.2 Displacement of communal assets/special interest assets............................................................................... 21
5.6 Other Surveys ............................................................................................................................ 21
6. PUBLIC CONSULTATION AND COMMUNICATION .................................................................... 24
6.1 Consultation and community participation ................................................................................. 24
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
ii
6.2 Stakeholder consultation ............................................................................................................ 24
6.3 Future Consultations and RAP Disclosure .................................................................................... 27
7. IMPACTS OF THE PROJECT ..................................................................................................... 28
7.1 Impact Activities ......................................................................................................................... 28
7.2 Impact Areas .............................................................................................................................. 28
7.3 The Project Affected Persons ...................................................................................................... 29
7.4 Impacted properties ................................................................................................................... 30 7.4.1 Impacts on Land and farmland ......................................................................................................................... 31 7.4.2 Impacts on structures ....................................................................................................................................... 31 7.4.3 Impacts on Loss of Trees and Crops .................................................................................................................. 32 7.4.4 Impacts of relocation on public facilities and services ..................................................................................... 32 7.4.5 Impacts on Loss of Incomes .............................................................................................................................. 33 7.4.6 Impacts on Socio-cultural network and support systems ................................................................................. 33
7.5 Impacts on Vulnerable Groups .................................................................................................... 33
7.6 Minimising resettlement and losses ............................................................................................ 34
7.7 Preliminary evaluation of compensation preferences .................................................................. 34
7.8 Impact mitigation measures in the construction stage ................................................................. 35
8. INSTITUTIONAL FRAMEWORK ................................................................................................ 36
8.1 Overview ................................................................................................................................... 36
8.2 Agencies for the RAP implementation ......................................................................................... 36 8.2.1 Ministry of Roads .............................................................................................................................................. 36 8.2.2 The Kenya National Highways Authority (KeNHA) ............................................................................................ 36 8.2.3 Ministry of Lands .............................................................................................................................................. 36 8.2.4 Ministry of Agriculture and Ministry of Forestry .............................................................................................. 36
8.3 The process of Resettlement and compensation .......................................................................... 36
8.4 Organisational Structure for RAP Implementation and compensation .......................................... 37
9. GRIEVANCE REDRESS MECHANISM ........................................................................................ 39
9.1 Sources of Grievances /Disputes ................................................................................................. 39
9.2 Proposed procedure for grievance redress and management ....................................................... 39
10. ELIGIBILITY ......................................................................................................................... 42
10.1 Introduction ............................................................................................................................... 42
10.2 Eligibility criteria ........................................................................................................................ 42
10.3 Cut-Off Date for Eligibility of Compensation ................................................................................ 42
10.4 PAPs’ Entitlements ..................................................................................................................... 42
11. VALUATION OF AND COMPENSATION FOR LOSSES ............................................................. 44
11.1 Valuation Methodology .............................................................................................................. 44
11.2 Data Collection ........................................................................................................................... 44
11.3 Analysis of Field Data ................................................................................................................. 44 11.3.1 Buildings and Houses .................................................................................................................................... 44 11.3.2 Boundary Fences .......................................................................................................................................... 45 11.3.3 Trees and Crops ............................................................................................................................................ 45 11.3.4 Forests and Bushes ....................................................................................................................................... 45
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
iii
12. RESETTLEMENT SITE ........................................................................................................... 46
12.1 Resettlement alternatives and choices ........................................................................................ 46
12.2 Measures to prevent influx of ineligible persons at the selected sites; ......................................... 46
12.3 Integration with host communities ............................................................................................. 46
12.4 Resettlement Options................................................................................................................. 46
12.5 Environmental protection ........................................................................................................... 46
13. LIVELIHOOD RESTORATION ................................................................................................ 48
13.1 Livelihood disturbance and dislocation ....................................................................................... 48
13.2 Strategies for livelihoods restoration .......................................................................................... 48
14. IMPLEMENTATION ARRANGEMENTS AND SCHEDULE ......................................................... 50
14.1 Overview ................................................................................................................................... 50
14.2 Implementation Schedule ........................................................................................................... 50
15. COSTS AND BUDGET ........................................................................................................... 51
15.1 The RAP Compensation Budget ................................................................................................... 51
15.2 The RAP Implementation Budget ................................................................................................ 52
16. MONITORING AND EVALUATION ........................................................................................ 53
16.1 RAP Monitoring Framework ....................................................................................................... 53
16.2 Internal monitoring .................................................................................................................... 53
16.3 External monitoring .................................................................................................................... 53
16.4 Monitoring indicators ................................................................................................................. 54
16.5 Agency responsibilities ............................................................................................................... 55
REFERENCES ................................................................................................................................. 56
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
iv
List of Tables
Table 1: Provisions available for resolution of observed gaps ................................................................................ 16
Table 2: Assets likely to be displaced by the road project ........................................................................................ 20
Table 3: House Building Materials for the affected structures ................................................................................ 20
Table 4: Detailed PAP participation in consultative forums ..................................................................................... 25
Table 5: PAPs Issues raised and the Responses to the Issues raised ................................................................... 26
Table 6: Administrative areas affected by the project road ...................................................................................... 28
Table 7: Project affected households and persons by administrative locations .............................................. 29
Table 8: List of affected institutions .................................................................................................................................... 29
Table 9: Affected properties ................................................................................................................................................... 30
Table 10: Public structures/institutions affected ............................................................................................................ 32
Table 11: Vulnerable PAP members ...................................................................................................................................... 34
Table 12: Entitlement Matrix ................................................................................................................................................... 43
Table 13: RAP implementation schedule............................................................................................................................. 50
Table 14: Cost estimates for compensation and RAP implementation ................................................................... 51
Table 15: Costs for implementation of the RAP ................................................................................................................ 52
Table 16: Monitoring Indicators ............................................................................................................................................ 54
List of Figures
Figure 1: Location of the Project Road ................................................................................................................................... 1
Figure 2: Project Location Route: Mwatate Taveta + Taveta bypass ......................................................................... 2
Figure 3: Alignment for Mwatate and Taveta Road........................................................................................................... 6
Figure 4: Satellite view of the proposed re-alignment at km 14+000 to km 25+000 ......................................... 7
Figure 5: Satellite view of the proposed re-alignment at km 51+700 to km 57+000 ......................................... 7
Figure 6: Satellite view of the proposed improvements around ................................................................................. 8
Figure 7: Sex distribution for the PAPs ............................................................................................................................... 18
Figure 8: Highest education levels attained by PAPs ..................................................................................................... 19
Figure 9: Livelihood sources .................................................................................................................................................... 19
Figure 10: Main PAP clans ...................................................................................................................................................... 21
Figure 11: PAPs membership in organisations .............................................................................................................. 22
Figure 12: Institutional Arrangement for RAP Implementation............................................................................. 37
Figure 14: Grievance Redress Procedure ......................................................................................................................... 41
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
v
ABBREVIATIONS
A.C.K Anglican Church of Kenya
A.I.C African Inland Church
AIDS Acquired Immune Deficiency Syndrome
CBD Central Business District
CBOs Community Based Organizations
CRC County Resettlement Committee
DC District Commissioner
DRC Dispute Resolution Centre
EMCA Environmental Management Co-ordination Act
ESIA Environmental and Social Impact Assessment
FOSA Front Office Service Associations
GRC Grievance Redress Committee
HBP High Blood Pressure
HIV Human Immunodeficiency Virus
ICT Information Communication Technology
KeNHA Kenya National Highways Authority
km2 Kilometer Squared
Kshs Kenya Shilling
KWFT Kenya Women Finance Trust
M2 Meter Squared
Ms-Excel Microsoft Excel
NEMA National Environmental Management Authority
NGO Non Governmental Organization
NLP National Land Policy
no Number
PAPCs Project Affected Persons Committees
PAPs Project Affected Persons
PIC Public Information Centre
PIU Project Implementation Unit
RAP Resettlement Action Plan
RAPAS Resettlement Action Plan Activity Schedule
ROW Right of Way
SACCO Savings and Credit Cooperative Society
SMEP Small & Micro Enterprise Programme
STI Sexually Transmitted Infections
TB Tuberculosis
VIP Ventilated Improved Pit (Latrine)
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
1
EXECUTIVE SUMMARY
Introduction
The Governments of the United Republic of Tanzania (GOT) and the Republic of Kenya (GOK), within the
development framework of East African Community (EAC), wish to improve the transport infrastructure,
through rehabilitation and upgrading of the road network. This will improve and support economic development
programmes, deepen economic co-operation, and foster regional integration within the EAC. Arusha –
Holili/Taveta – Mwatate Road is one of those roads earmarked for construction with financing from the AfDB.
The Taveta – Mwatate road project section, in Kenya, is the subject of this RAP report.
Taveta – Mwatate road is located in the Coast province in the County of Taita Taveta and within the two
districts of Taveta and Mwatate. The road starts in Mwatate market and traverses through the Tsavo West
National Park and terminates at Taveta town/Holili boarder. The entire road is currently a gravel surface
carriageway with a width of 7.0 m wide with 2.0m shoulders on either side. The proposed upgraded Road will
have a Reserve (right of way) of 60m along its total length including the Taveta bypass. This reserve will
however be reduced to 35m in the urban town of Taveta to reduce on the impact on people. Upgrading of the
road will involve realignment at certain sections of the road, but only up to 1.5 km from the current alignment.
RAP Objectives and scope
This Resettlement Action Plan (RAP) is developed in compliance with the AfDB Policy on involuntary
resettlement, which requires a RAP to be prepared in cases where more than 200 persons are affected negatively
by any project under its funding. Upgrading of Taveta – Mwatate road triggers this policy where a total of 2,365
persons are to be affected and therefore the need to develop a RAP to provide guiding principles to be followed
when involuntary land acquisition is undertaken. The RAP provides a clear definition of the PAPs by socio-
economic and gender category; the cut-off dates for eligibility for compensation and; the assets to be
compensated at replacement cost. It also establishes the land acquisition and compensation processes and;
applies the Kenyan law and AfDB policies on resettlement.
The RAP was developed through a comprehensive process including documentary review, field visits and
observation; census survey of the Project Affected Persons (PAPs); consultative meetings with PAPs and in-
depth discussions with other stakeholders. The PAPs consultative meetings were undertaken between 12th and
28th April 2012.
Impacts of the Project
Upgrading of the Taveta – Mwatate road will require land acquisition hence physical displacement of people,
loss of shelter, assets, income sources and livelihoods, and restriction of access to economic resources. The
project impacts will occur in the 17 sub-locations of Mwatate and Taveta districts but will mainly be
concentrated in Taveta town. The total number of project affected persons (PAPs) as determined from the
census surveys is 2,365 PAPs. The road will affect 842 structures buildings, fences, pit latrines, boreholes,
hotels/restaurants, pubs, residential houses and cattle sheds in addition to 34 institutions (churches, schools,
churches, offices, health facilities and cattle dips, among others. In addition, the road will affect 85 fences and
34 graves.
Various measures have been proposed to minimize the project impacts due to land acquisition and disturbances.
These include reducing the road reserve, redesigning the project route at certain points, facilitating consultations
and participation with the PAPs, and putting appropriate impact limitation and mitigation measures in the
construction and design stages
Socio-Economic Profile of the PAPS
A total of 397 households were enumerated including 11 government offices and 19 institutions. The socio-
economic profile of the 397 households revealed that the total affected population is 2,365 where 50.95% were
females and 49.05% were males. (The total number of people in government offices and institutions was not
established hence they are treated as one entity).
Literacy levels among the PAPs stood at 55%. In terms of livelihood sources, 25% of the PAPs are farmers,
29% traders, 14% civil servants and the rest are either in school or engaged in other economic activities
including charcoal burning, employed in the private sector and the retired
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
2
The average land size for individual PAP households is 1.3 acres. PAPs indicated to have acquired the land they
live in through inheritance (48%), purchase (21%) and through others means (31%). 56% of the PAPs indicated
to own the land they were residing on while 15% of the PAPs resided on the land on lease basis and 29%
indicated to be squatters. 16% indicated to have Title deeds to their land while 14% had Allotment letters The
rest did not have documents of ownership to the land. The average number of structures per household is four
with some having as many as 18. 30% of the structures owned by enumerated household(s) translating to two
units per household will be affected
The project area is inhabited by a number of tribes including Taita, Taveta and Kamba among others. These are
divided into tens of clans. 91% of the PAPs are Christians and 9% are Muslims. Three main shrines exist in this
region: Voilole (Mwatate district) Challa Kendong and Kichongoji (Taveta district) which are however over 10
Kms from the project road.
Legal and Institutional Framework
The Kenya constitution acts and African Development Bank’s resettlement policies on involuntary resettlement
policy have been used to develop this RAP. The same will be followed during implementation of the plan. Thus
while the process and procedures of land acquisition will be governed by Compulsory Acquisition Act Cap 295
and other related laws in the country, internationally policies that will be incorporated in determining the PAPs
entitlement will include the AfDB policies and guidelines as outlined in the AfDB involuntary resettlement
policy, 2003 where development of public transport facilities like roads is covered. Both the Kenyan laws and
AfDB policies recommend prompt and fair compensation that would restore or improve the livelihood of the
PAP to the level before the resettlement. In the Kenyan constitution, the relevant acts are: CAP 295 on
compulsory land acquisition, Government Lands Act Cap 280, Land Titles Act Cap 282, Registration of Titles
Act Cap 281, Land (Group Representatives) Act Cap 287, Trust Land Act Cap 285, Registered Land Act Cap
300, Land control Act 302, Mining Act 306, Agriculture Act 318 and Environmental Management and Co-
ordination Act among others.
Implementation of this RAP and compensation necessitated by upgrading of the Taveta - Mwatate road will
involve the proponent (KeNHA), Ministries of Lands, Agriculture, Forestry and Public Works, and the
contractor. Each of these will play key roles to ensure smooth implementation of the RAP whose process of
implementation include clearance by the GOK and AfDB, verification of property ownership and valuation,
relocation of the PAPs and implementation of programmes aimed at restoration of livelihoods.
Public Consultation and Communication
The RAP development and its implementation is primarily a PAPs affair and they were involved and should
fully participate to ensure its successful implementation. The involvement of the PAPs was both individually
and through a number of consultative forums. During both of these encounters, the PAPs were made aware of
the project design, legal aspects of land acquisition, compensation arrangements and grievance redress systems.
In such meetings, the PAPs requested and had clarifications made on property inheritance for compensation
issues of properties whose ownership is in court and grave inundation. This RAP takes into account extensive
future consultations and disclosures. In general, stakeholders and the community are aware of the importance
and do appreciate the project road.
Grievance redress
Grievances redress mechanisms and procedures which are simple, transparent, accessible to all the PAPs,
flexible and speedy/just/fair are available. The main conflicts and grievances are likely to arise from mistakes on
inventory of the affected properties, disagreements over land parcel ownership and boundaries, pending court
cases, disagreements on plot /asset valuation and delays in compensation payment. These grievances will be
settled through a step by step process from the PAPC through the CRC, the Public Compliant Committee/Land
Compensation as well as seeking legal redress from the courts.
Eligibility
Eligible individual(s) are those who are directly affected socially and economically as a result of improvements
of the project road arising from compulsory acquisition of land and other assets. Properties that are eligible for
compensation will include buildings, land, assets on the land such as crops, trees and crops, graves and affected
public social utilities such as power supply, water pipelines. The categories of PAPs eligible for compensation
will include owners of structures and land that are affected; people who have leased land for cultivation and
their crops or trees are to be removed/damaged; people residing in the areas surveyed during the census and
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
3
asset inventory survey and any other persons or group of persons, who though not mentioned, are entitled to
compensation according to Kenya laws and African Development Bank/Donor policies. The cut-off date for
compensation eligibility of persons and their assets is 30th April 2012
Asset Valuation
Valuation methodology involved field survey to collect data on the PAPs, land to be acquired, structures, trees,
public services and crops affected. The value of the property is affected by the rights of enjoyment or
compensation when such benefit may be alienated. In Kenya, compensation value in case of compulsory
acquisition requires that the value paid to include all the other miscellaneous expenses as well as the injurious
affection due to the disturbance to them. The disturbance allowance is normally 15% of the value of the
property acquired.
Resettlement Site
The method for site selection was based on alternatives proposed by community members during PAPs
interviews and public participation. Generally, the affected community members were not ready to move out of
their communities. Majority opted to resettle within their remaining land parcels. There was therefore no host
communities considered under this RAP as PAPs will fizzle into their existing communities.
86% of the PAP households interviewed were willing to cede land for construction of the project. 87% of the
PAPs preferred assistance in terms of cash grant equivalent to their loss, 12% preferred to be assisted through
provision of a new agricultural/commercial plot and 1% opted to be assisted through Training for self
employment.
Implementation Arrangements and Schedule
The Taveta – Mwatate road is owned by the Government of Kenya through the Kenya National Highways
Authority (KeNHA) who will be responsible for its operation and maintenance. KeNHA, through the PIU, will
therefore lead other institutional units/agencies including the County Resettlement Committee (CRC) and
Project Affected Persons Committee (PAPC) in implementation and management of the RAP.
The RAP anticipates that the project implementation schedule will consist of three phases namely preparation,
implementation and operation. The Resettlement Action Plan Activity Schedule is spread over twelve months
including approval of the RAP and includes:
i. Valuation of affected properties and inventory of assets
ii. Socio-economic survey census for all PAPs and establishment of cut-off date for eligibility
iii. Mobilisation and consultation with PAPs
iv. Verification of property/asset ownership and valuation for compensation including offering of awards
v. Bank account opening and/or revival for those that are dormant
vi. Payment of compensation and delivery of other entitlements within 6 months after serving notices;
vii. Issue a vacate communiqué for removal of all movable structures and assets, six months for complete
remove of all affected structures and assets ;
viii. Dispute /grievances resolution;
ix. Complete removal of all affected structures and assets, six months after issuing of the vacate
communiqué
x. Monitoring, evaluation and final audit
Costs and Budget
The total cost for compensation summed to approximately Kenya shilling three hundred and sixty four million,
seven hundred and thirty six thousands, six hundred and seventy three and seventy cents (Ksh. 364,736,673.70).
The breakdown is as follows, acquired land value estimated to Kenya Shilling ninety four million, five hundred
thousand (Ksh. 94,500,000.00); affected buildings and other structures: one hundred and ninety four million,
four hundred and eighteen thousand, nine hundred and nineteen and ninety cents (Ksh. 194,418,919.90); Fences:
Four million, six hundred and sixty eight thousand four hundred and five. (Ksh. 4,668,405.00); Electricity lines:
Seventeen million, two hundred and fifty thousand (Ksh. 17,250,000.00); Trees and perennial crops: Twenty six
million, four hundred and two thousand, four hundred and forty five (Ksh. 26,402,445) and miscellaneous
(graves and other cultural sentimental allowances) approximately two million, two hundred thousand (Ksh.
2,200,000). 15% disturbance allowance is legally added to the declared value as stated by Compulsory
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
4
Acquisition Act totalling to approximately forty seven million, five hundred and seventy four thousand, three
hundred and forty eight and seventy shilling (Ksh. 47,574,348.70).
The cost for implementation of this RAP is Kenya shilling Thirty three million, and seventy five thousands
(Ksh. 33,075,000.00) including the costs of professional services, project management, capacity building of
PAPs and monitoring services as in the table below:
Expense Description Unit Total Cost (Ksh.)
Professional Services Verification of assets 5 3,000,000.00
Livelihood restoration
Resettlement assistance to the
vulnerable groups
Lump sum 9,000,000.00
Stakeholder participation Future consultations, awareness creation
and communication
42 meetings 2,100,000.00
RAP implementation RAP documentation and implementation Lump Sum 7,500,000.00
Resettlement Committees
costs
Allowances for RAP districts steering
committee and agents (CRCs)
9 Members 1,900,000.00
Allowances for RAP steering committee
and community agents Local
RAP/PAPCs
42 Members 1,500,000.00
Monitoring and evaluation Cost of monitoring and evaluation of the
process
Lump Sum 6,500,000.00
Subtotal - - 31,500,000.00
Administration cost based
at 5% of Total RAP Cost
Administration cost for managing the
RAP process
Percentage of
cost
1,575,000.00
TOTAL 33,075,000.00
Monitoring, Evaluation and Audit
The RAP occupies a central place in upgrading of Taveta – Mwatate road and therefore necessitates both
internal and external monitoring and evaluation. The monitoring plan covers performance monitoring, impact
monitoring and completion audit. Monitoring, evaluation and final audit of the resettlement implementation will
be founded on the baseline survey generated in the RAP and ESIA reports for Taveta – Mwatate road. The
overall objective of the EMA will be to carry out the following:
i. Review the results of the internal monitoring and overall compliance with the RAP;
ii. Assess whether relocation objectives have been met especially with regard to housing, living standards,
compensation levels, etc;
iii. Assess general efficiency of relocation and formulate lessons for future guidance; and
iv. Determine overall adequacy of entitlements to meet the objectives.
The subjects for monitoring and evaluation will include acquisition of land, buildings/structures and
Trees/Crops; compensation, Re-establishment and Rehabilitation; Hazards and Disturbances; Social/
Demographic; Consultation; Training and; Management.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
1
1. INTRODUCTION
1.1 Background
The Governments of the United Republic of Tanzania (GOT) and the Republic of Kenya (GOK), within the
development framework of East African Community (EAC), wish to improve the transport infrastructure,
through rehabilitation and upgrading of the road network. Improvement of the transport infrastructure will
support economic development programmes within the two countries. This will also deepen economic co-
operation, and foster regional integration within the EAC.
Arusha – Holili/Taveta – Mwatate Road is among the transport infrastructure roads earmarked for
construction. The principal stakeholders for this project, besides the East African Community Secretariat, are
the Tanzania National Road Agency (TANROADS) and the Kenya National Highways Authority (KeNHA).
As the development of the regional road network has been hampered, mainly by insufficient financial
resources, the EAC, in collaboration with Partner States has initiated a strategy of coordinated project funding
with development partners in order to mobilize funds for the development of the corridors. In accordance with
these aims and objectives, AfDB has provided a grant to the EAC for studies and designs for three regional
road projects between Kenya and Tanzania. One of the three regional road projects is the Arusha –
Holili/Taveta – Mwatate road that connects the port of Mombasa in Kenya to the Tanzanian town of Arusha,
the East African Community headquarters. The Taveta – Mwatate road project section, in Kenya, is the
subject of this report.
1.2 The Project Location
Taveta – Mwatate road is located in the Coast province in the County of Taita Taveta and traverses the two
districts of Taveta and Mwatate. The road starts in Mwatate market, the district headquarters of Mwatate
district and terminates at Taveta town/Holili boarder, the headquarters of Taveta district. Specifically, the
project road traverses Bomeni and Jipe divisions in Taveta district and Mwatate division in Mwatate district.
A 40 km section of this road traverses the Tsavo West National Park. Politically, the road traverses the two
constituencies of Taveta and Mwatate. A general location plan of the project area is shown in Figure 1 plus
route maps showing towns and villages the project roads traverse:
Figure 1: Location of the Project Road
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
2
1.3 Summary Description
The Taveta – Mwatate road joins the Northern Corridor route at Voi, some 160 kms north of Mombasa. The
project road is approximately 85 km and starts at Mwatate town. The road takes a north westerly direction up
to Maktau and then a westerly direction to Taveta town. At Cess point in Taveta, a 10km road is planned to
bypass the Taveta urban area. Figure 2 below presents the project road route:
Figure 2: Project Location Route: Mwatate Taveta + Taveta bypass
The entire road is currently a gravel surface carriageway. Being an international Trunk Road (Road class A)
its cross-section is type II with a carriageway width of 7.0m wide and 2.0m shoulders on either side. In some
sections, some realignment will be undertaken, but only up to 1.5 km from the current alignment between
Mwatate and Taveta/Holili.
1.4 Objectives and scope of the RAP
1.4.1 Objectives
The main objective of this assignment is to develop a Resettlement Action Plan (RAP) in compliance with the
AfDB Policy on involuntary resettlement, that requires a RAP to be prepared if more than 200 persons are
impacted negatively by any intervention under its funding. This AfDB policy is triggered by the need for land
acquisition for construction of Taveta – Mwatate road where a total of 2,365 PAPs are to be affected. The
purpose for this RAP is therefore to:
i. Provide a clear definition of the PAPs by socio-economic and gender category, household or family;
the cut-off dates for eligibility for compensation and; the assets to be compensated at replacement
cost;
ii. Provide a detailed socio-economic survey in order to identify entitlements, key issues faced in terms
of land acquisition and compensation, as well as options and strategies for minimising impacts on
current land use activities or cultural heritage;
iii. Provide specific rates for compensation or loss of assets at fair market and equitable value and the
methodology of how these values are derived;
iv. Establish the land acquisition and compensation processes, options available, eligibility and
entitlement, PAPs consultation and Communication, grievance redress mechanism and;
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
3
v. Take into account the requirements of the applicable laws of Kenya as well as requirements of the
African Development Bank (AFDB) and the policies and procedures of KeNHA.
1.4.2 Scope of the Resettlement Plan
To achieve the above stated objectives, the RAP activities delved into undertaking the following tasks:
i. Identification of persons and/or groups of Project Affected Persons (PAPs) who will be affected by
the project through loss of assets including loss of structures, shelter and/or loss of crops, trees, land
and incomes;
ii. PAPs and stakeholder consultations on upgrading of the project road and its impacts on the general
public and specifically those directly affected by it;
iii. Review of the AfDB and Kenya national policies, legislation and guidelines related to Resettlement
Action Plan and;
iv. Preparation of a Resettlement and Land Acquisition Plan, detailing the mitigation measures for
resettlement and related costs for the RAP implementation.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
4
2. METHODOLOGY
2.1 The RAP Process
The Resettlement Action Plan for Taveta – Mwatate road was developed within a method consistent with the
AfDB policy regulation and the Government of Kenya legal framework. The process included Literature
review, field visits, public consultation, questionnaires, data analysis and compilation of the RAP document.
Specifically, the various activities undertaken to prepare the RAP were as follows:-
2.1.1 Literature review
Literature review was undertaken to complement and cross-check the field data. It involved reviewing the
existing literatures related to involuntary resettlement and the road designs. Among the documents reviewed
were the roads engineering design, AfDB policies on Involuntary Resettlement and Kenyan laws on land
acquisition and compensation. Other documents reviewed were the District Development Plans, Project area
Topographical and Cadastral maps, the Draft Design Layout and ESIA of Taveta – Mwatate road. Literature
review was aimed at:
i. Understanding the socio-economics of the project area;
ii. Harmonizing differences in resettlement and compensation guidelines between the Kenya government
policy and the AfDB Guidelines and;
iii. Establishing land tenure systems in the project area.
2.1.2 Field activities
Field visit activities included observation; identification and census survey of the Project Affected Persons
(PAPs) heads of households and institutions; conducting discussions with stakeholders and; holding
consultative PAPs locational/sub-locational meetings as part of public disclosure. The field visits were
undertaken to identify the properties to be affected by the project. During the field visits the following tasks
were performed:
i. Observation
This included observation of social and physical setting of the area as well as economic activities
ii. Identification of affected properties
Confirmation of the properties within the Right of Way (ROW) and their distance from the proposed road
centerline;
iii. Interviews and discussions
Interviews were held with the following:
a. PAPs household census
A census household interview for all the affected was conducted using pre-designed semi-
structured questionnaires. The questionnaires were administered to household heads/proxies.
During the household interviews, the following aspects were covered:
Identification of household head, sex and marital status,
Demographic information – household population and sex composition as well as age of
members,
Social data – highest education levels attained, common diseases, culture and social
networks as well as access to services and resources,
Livelihoods and income sources,
Land tenure/ownership, structures in the homestead, perceptions of and willingness to
surrender land for the project road and,
Anticipated impacts of resettlement and compensation.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
5
b. Consultations with other stakeholders
Consultations were undertaken in the form of interviews and discussions held with officials within
the project region. The officials included government officers, group ranches and the provincial
administration. The aim of these consultations was to gather their perspectives on the proposed
project and specifically resettlement and compensation. Stakeholders consulted included:-
Taveta Town council,
The provincial administration,
Land planning department (Wundanyi) and,
Opinion leaders
Discussions with these stakeholders were mainly focused on impacts of the proposed project in
relation to loss of property and resultant resettlement and compensation consequences. In
addition, other issues discussed were existing physical plans, availability of alternative land for
resettlement, gender and the vulnerable population, income restoration and replacement cost for
lost property and possible roles and responsibilities during resettlement process.
iv. Consultative meetings with PAPs
Consultative meetings with PAPs were conducted with the support of the provincial administration. These
PAPs consultative meetings were aimed at creating a common understanding of the project and its impacts
as well as according them an opportunity to contribute to all aspects of the RAP especially its
implementation structure, grievance redress mechanisms and systems for monitoring and evaluation of the
resettlement issues.
2.1.3 Data analysis and reporting
This included analysis of data collected for the socio-economic survey, using MS-EXCEL and presenting the
analysis results into the RAP report for Taveta – Mwatate road.
2.2 Timeframe
The Resettlement Action Plan census survey and PAPs consultation were undertaken between 12th April 2012
and 28th April 2012.
2.3 Structure of the Resettlement Action Plan report
The Resettlement Action Plan report provides basic information of the project, approach and methodology of
the resettlement audit, findings and recommendations. This RAP report is presented in sixteen chapters. The
contents and main aspects contained in the various chapters and appendices are highlighted below;
Chapter 1 Introduction
Chapter 2 Methodology
Chapter 3 Project Description
Chapter 4 Legal Framework
Chapter 5 Socio-Economic Profile of The Paps
Chapter 6 Public Consultation and Communication
Chapter 7 Impacts of the Project
Chapter 8 Institutional Framework
Chapter 9 Grievance Redress Mechanism
Chapter 10 Eligibility
Chapter 11 Valuation of and Compensation For Losses
Chapter 12 Resettlement Site
Chapter 13 Livelihood restoration
Chapter 14 Implementation Arrangements and Schedule
Chapter 15 Costs and Budget
Chapter 16 Monitoring and Evaluation
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
6
3. PROJECT DESCRIPTION
3.1 Current status
The Taveta – Mwatate road is approximately 85 km and starts at Mwatate town. The entire road is currently a
gravel surface carriageway and has a 60m road reserve which has however been encroached mainly in the
urban centres of Mwatate, Bura, Maktau and Taveta. Most of the encroachments are semi-permanent informal
businesses (that were allocated on temporally basis), recreation sites and strips of farmlands concentrated in
the high potential areas of Bura wetlands and Taveta areas. The main features of this project road are as
follows:
i. It is in poor condition that has forced vehicles to use diversions, the main one being the 12km
Mkamenyi/Maktau road which runs approximately 3.5kms parallel to the existing road alignment.
ii. Sharp curves that cannot allow for high speeds.
iii. The current total land area occupied by the road reserve is 5,100km2.
3.2 Proposed road project
The proposed upgraded Road will have a Reserve (right of way) of 60m along its total length including the
Taveta bypass. This reserve will however be reduced to 35m in the urban town of Taveta. The road’s cross-
section is type II that is the carriageway width is 7.0 m wide with 2.0m shoulders on either side, the road
being international Trunk Road (Road class A). However some realignment will be undertaken, but only up to
1.5 km from the current alignment between Mwatate and Taveta/Holili as shown in the figure below:
Figure 3: Alignment for Mwatate and Taveta Road
The existing road from Mwatate to Holili through Taveta town is earth/gravel. The geometry of the
gravel/earth section is 60-70% satisfactory with some sections requiring re-alignments mainly to;
i. Avoid the many railway crossings
ii. Improve the horizontal geometry
iii. Improve approach to major structures.
The existing alignment crosses the railway line 10 times two of which cannot be avoided and the Consultant
has re-aligned the road to avoid 8 other crossings. Presented below is a summary of the major aspects of the
study adopted for the road:-
i. A number of alignment improvements have been proposed for the project road to ensure the designed
road meets the design standards. These improvements have mainly been carried out by increasing curve
radii or elimination of other substandard curves altogether.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
7
ii. Just after Mwatate at km 3+500, the first re-alignment to avoid railway crossing 1 and 2 has been
proposed rejoining the road just before Bura town (km 6+800). This re-alignment, apart from avoiding
the two railway crossings, also improves the geometry of the designed road.
iii. From km 14+000 to km 25+000, re-alignment has been proposed to avoid railway crossing 3, 4, 5 and 6
has been proposed. Though the geometry of the road through this section is acceptable, the need to
avoid the 4 railway crossings necessitated the re-alignment. Below is a satellite view of the proposed re-
alignment to avoid the 4 railway crossings between km 14+000 to km 25+000:
Figure 4: Satellite view of the proposed re-alignment at km 14+000 to km 25+000
iv. From km 51+700 to km 57+000, re-alignment has been proposed to avoid railway crossing 7 and 8 has
been proposed. Though the geometry of the road through this section is acceptable, the need to avoid
the 2 railway crossings necessitated the re-alignment. Below is a satellite view of the proposed re-
alignment to avoid the 2 railway crossings between km 51+700 to km 57+000.
Figure 5: Satellite view of the proposed re-alignment at km 51+700 to km 57+000
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
8
v. From km 64+900 to km 66+600, re-alignment has been proposed to improve the approaches to the road
over Rail Bridge and ensure the railway line is not crossed at an oblique angle. This is the 9th railway
crossing and is the only one on the main alignment where a road over Rail Bridge has been proposed.
This re-alignment also improves the geometry of the road which is currently bendy on the approaches to
the existing level crossing.
vi. The section around Timbilia market just before Taveta town has been re-aligned to pass downstream of
the existing structures to improve the approaches to the existing rivers and enhance safety.
vii. In Taveta town, the existing road passes through a densely built up area with hardly any room for even
a 40m road reserve as the existing road reserve is approximately only 10-15m in some sections of the
town. The Consultant has therefore proposed a bypass on the northern side of the town branching off
the existing alignment just before Timbila market and rejoining the existing alignment west of Taveta
town just before Holili border. In Taveta town, the road has been narrowed to a width of 35m.
viii. The existing level crossing (10th railway crossing) within Taveta town has been maintained as
crossing is within the town centre and as such it would be very expensive to construct road over Rail
Bridge as it would necessitate use of reinforced earth embankments to minimize the number of
properties that would be affected. Further, access to any remaining properties would be greatly
affected because of the level difference. On the Taveta bypass, a second road over Rail Bridge has
been proposed. Below is a satellite view of the proposed improvements around Timbilia Market and
the proposed Taveta bypass.
Figure 6: Satellite view of the proposed improvements around
Timbilia Market and the proposed Taveta bypass
3.3 Project activities/Works
The main project activity will consist of construction of Mwatate – Taveta road and associated works.
Specifically, the construction will consist of, among others, the following activities:
i. Establishment of construction camps;
ii. Construction of temporary/permanent accommodation;
iii. Provision of sewage disposal facilities;
iv. Water abstraction;
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
9
v. Construction of workshops;
vi. Transportation of construction materials and equipment;
vii. Recruitment of the labor force;
viii. Earthworks;
ix. Construction of detours and access routes;
x. Quarries, borrow pits and materials extraction;
xi. Crushing and screening of materials;
xii. Screening, mixing, and stockpiling of aggregates;
xiii. Heating of bitumen and aggregates separately and then mixing in asphalt plant;
xiv. Transportation of asphaltic concrete mixes to the road for laying using paver;
xv. Construction of drainage structures, e.g. culverts, bridges;
xvi. Excavation of side drains, meter drains, and cut-off drains;
xvii. Pavement Construction and;
xviii. Construction of erosion protection works.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
10
4. LEGAL FRAMEWORK
This chapter presents details of the existing laws, policies and institutions relating to land acquisition,
allocation and compensation in Kenya. The chapter also provides an overview of the AfDB policies and
regulations on resettlement and compensation.
4.1 Kenya Country policies on resettlement
Kenya has several statutes that handle the issues of land acquisition and development of infrastructure. The
several statutes that handle the issues of land and infrastructure development in Kenya are:
i. Land Acquisition Act CAP 295
ii. Way leaves act (Cap. 292)
iii. Registration of Titles Act Chapter 281
iv. Government Lands Act Cap 280
v. Trust Land Act Cap 288
vi. Physical Planning Act
vii. Valuation Act Cap 532
viii. Land Control Act 302
ix. Environmental Management Co-ordination Act (EMCA), 1999.
The Kenya constitution statutes that govern land and compensation issues in relation to this RAP are
discussed in the following sub-sections;
4.2 The land tenure system
Following enactment of National Land Policy (2009) and the Kenya Constitution (2010), the Kenyan land
tenure system comprises of three tenure regimes namely, Public Land, Community land and Private land
ownership, (Constitution (2010) article 61(2). The tenure entails;
i. Public Land
According to the constitution and NLP, public land refers to un-alienated government land at the effective
date of the enactment of the constitution, land lawfully held, used or occupied by any State organ, except
any such land that is occupied by the State organ as lessee under a private lease; land transferred to the State
by way of sale, reversion or surrender; land in respect of which no individual or community ownership can
be established by any legal process; land in respect of which no heir can be identified by any legal process;
all minerals and mineral oils as defined by law; government forests, government game reserves, water
catchment areas, national parks, government animal sanctuaries, and specially protected areas; all roads and
thoroughfares provided for by an Act of Parliament; all rivers, lakes and other water bodies as defined by an
Act of Parliament; the territorial sea, the exclusive economic zone and the sea bed; the continental shelf; all
land between the high and low water marks; any land not classified as private or community land under the
Constitution; and any other land declared to be public land by an Act of Parliament.
Public land is to be vested in and be held by a County Government in trust for the people resident in the
County, and shall be administered on their behalf by the National Land Commission. Public land shall not be
disposed of or otherwise used except in terms of an Act of Parliament specifying the nature and terms of that
disposal or use. However according to the constitution article 66(1) the state may regulate the use of any
land, or any interest in or right over any land, in the interest of defense, public safety, public order, public
morality, public health, or land use planning.
In such a case like construction of the road, public land would have been the most appropriate because there
would be no need of acquisition. This is the case for most sections of the road as it will remain within the
current alignment which is public land.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
11
ii. Community land
According to Constitution article 63. (2) Community land consists of land lawfully registered in the name of
group representatives under the provisions of any law; land lawfully transferred to a specific community by
any process of law; any other land declared to be community land by an Act of Parliament. It will also
include land that is lawfully held, managed or used by specific communities as community forests, grazing
areas or shrines; ancestral lands and lands traditionally occupied by hunter-gatherer communities; or
lawfully held as trust land by the county governments, but not including any public land held in trust by the
county. Community land shall vest in and be held by communities identified on the basis of ethnicity,
culture or similar community of interest. Any unregistered community land shall be held in trust by county
governments on behalf of the communities for which it is held. Community land shall not be disposed of or
otherwise used except in terms of legislation specifying the nature and extent of the rights of members of
each community individually and collectively.
Thus use of community land for construction of the road as is case with the Taveta town bypass section and
in areas where there realignments and provision for climbing lanes are the road would revoke acquisition of
land.
iii. Private land
According to the constitution article 64, private tenure consists of registered land held by any person under
freehold tenure; leasehold tenure; and any other land declared private land under an Act of Parliament.
Private land can be held as freehold or leasehold. The proposed road will lead to expropriation of private
land to provide for the Taveta bypass road, realignments and climbing lanes the Constitution article 63 (1) as
land will be transferred from private for public purpose.
4.3 Acts Relevant to resettlement
4.3.1 Land Acquisition in Kenya
Land acquisition in Kenya is governed by the protection of right to property sections:-
(I) (3) which states that “The State shall not deprive a person of property of any description, or of any
interest in, or right over, property of any description, unless the deprivation:-
(a) results from an acquisition of land or an interest in land or a conversion of an interest
in land, or title to land, in accordance with Chapter Five; or
(b) Is for a public purpose or in the public interest and is carried out in accordance with this
Constitution and any Act of Parliament that:-
(i) requires prompt payment in full, of just compensation to the person; and
(ii) allows any person who has an interest in, or right over, that property a right of
access to a court of law and;
(II)(4) Provision may be made for compensation to be paid to occupants in good faith of land acquired
under clause (3) who may not hold title to the land.
This is a critical Act when dealing with the acquisition of land along the road corridor because in some
sections, it will traverse through private land which has to be acquired under the Act.
The National Land Policy 2009 article 211(c) recognize the need to have an appropriate eviction guideline by
indicating that government should “establish appropriate mechanisms for the removal of squatters from
unsuitable land and their resettlement” the Constitution (2010) Article 66 of the constitution further shows the
regulatory conditions that can lead to acquisition of privately owned land by explaining that “the State may
regulate the use of any land, or any interest in or right over any land, in the interest of defence, public safety,
public order, public morality, public health, or land use planning”. It however recommends for prompt
payment of the compensation. Draft Eviction and Resettlement Guidelines 2012, on the other hand
recommends for a development of a policies to guide the evictions and resettlement of the evicted. It states
that “the State should develop transparent policies and procedures for dealing with evictions and ensure that
evictions from settlements do not occur unless those affected have been consulted and appropriate
resettlement arrangements have been made”.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
12
4.3.2 Acts related to RAP in Kenya
There are a number of Acts related to Resettlement Action Planning in Kenya. These include those that touch
on land and assets that may be acquired and compensated for under a RAP namely the Way Leaves Act. Each
of these acts and whether they will be triggered under the RAP for Taveta – Mwatate road are discussed in the
following paragraphs:
i. Way leaves act (Cap. 292)
Way Leaves Act (Cap. 292) Section 3 of the Act states that the Government may carry any works through,
over or under any land whatsoever provided it shall not interfere with any existing building or structures of
an ongoing activity. Notice, however, will be given one month before carrying out any such works (section
4) with full description of the intended works and targeted place for inspection. Any damages caused by the
works would then be compensated to the owner as per the section. Finally section 8 states that any person
without consent causes any building to be newly erected on a way leave, or cause hindrance along the way
leave shall be guilty of an offence and any alterations will be done at his/her costs. The Act further explains
the process of resolving conflicts that arise in determining the compensation value. This act will be triggered
as the road will lead to demolition of some structures and conflicts arising from valuation and compensation
will need arbitration prior or during the road construction.
ii. Registration of Titles Act Chapter 281
The Registration of Titles Act is an act of Parliament that provides for the transfer of land by registration of
titles. When the Commissioner of land issues a letter of allotment to any person in respect of any land, one
of the laws under which the title to that land is issued is the Registration of Titles Act. A freehold title issued
under this act confers absolute control upon individuals or other legal entities upon a given parcel of land. It
also confers upon them power to determine the use to which such land can be put. A leasehold title contains
conditions such as the term of the lease, commencement date thereof, the user of the land etc. Private
ownership of land is embodied in this Act. This Act is triggered as after acquisition the PAPs with title
deeds will have to amend them or surrender them if the entire land is acquired.
iii. Government Lands Act Cap 280
This is An Act of Parliament to control and regulate the leasing and use of Government lands. Under this act
the president through the commissioner of lands, allocates any un-alienated land to any person he so wishes
"unalienated Government land" means Government land which is not for the time being leased to any other
person. Such land can be used for public purposes without any compensation, but once allocated, it is held
as a grant from the government on payment of rents to the government. Acquisition of such land triggers
compulsory acquisition.
iv. Trust Land Act Cap 288
All land, which is not registered under any Act of parliament, is vested in local authorities as Trust. In these
Trust Lands a person may acquire leasehold interest for a specific number of years. The local authorities
retain the powers to repossess such land for their own use should the need arise. The government can also
reserve land for public purpose through “setting apart”.
v. Physical Planning Act Cap 286
The Act provides for the preparation and implementation of physical development plans and for related
purposes. It gives provisions for the development of local physical development plan for guiding and
coordinating development of infrastructure facilities and services within the area of authority of County,
municipal and town council and for specific control of the use and development of land. The proposed road
already exists but this act is triggered by the rampant encroachment on the reserves especially in the urban
areas and trading centres.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
13
vi. The Arbitration Act Cap 49
The provisions of this Act apply to domestic and international arbitration. Article 3 (6)Where a provision of
this Act refers to the fact that the parties have agreed or that they may agree or in any other way refer to an
agreement of the parties, such agreement includes any arbitration rules referred to in that agreement. In this
case, the owner and the tenant may have an arbitration understanding in case of compensation for the
property.
vii. Valuation Act Cap 532
The valuation practice in Kenya is governed by the Valuers Act Cap 532, which provides for a Valuers
Registration Board that regulates the activities and conduct of registered valuers. The Act governs the
formation and composition of valuation practices including the qualification of partners and directors in
charge of valuation. The Board also deals with discipline and complaints in respect to valuation practice.
Other statutes that govern valuation are the Government Lands Act Cap 280 that regulates the valuation for
land rent while valuation for rating is governed by the Rating Act Cap 267. Land Acquisition Act Cap 295
governs valuations for compulsory acquisition purposes.
viii. Land Control Act 302
This act restricts transfer of land and as such has some bearing on the flexibility with which affected farmers
can acquire replacement land. The most pertinent section of this act is Section (9) that states the economic
size for agriculture. It controls the subdivisions of the agricultural land.
ix. Occupiers Liability Act (Cap 34)
This is an Act of Parliament to amend the law as to the liability of occupiers and others for injury or damage
resulting to persons or goods lawfully on any land or other property from dangers due to the state of the
property or to things done or omitted to be done there. Article 2(b) states the obligations of a person
occupying or having control over any premises or structure in respect of damage to property Arbitration Act.
This Act can be revoked where the occupier is the tenant.
x. The Agriculture Act 318
This act provides for the maintenance of stable agriculture and the conservation of soil and its fertility. The
act is triggered as there will be change in some acres of land from crop farming to road use that will however
have minimal impacts on food production. This may affect food security especially for the PAPs who are
depended on crop growing. The PAPs will be allowed to harvest their crops otherwise compensation for any
loss including support for livelihood restoration will be considered in the resettlement and compensation.
xi. Public Roads and Roads of Access Act (Cap. 399)
Section 8 and 9 of the Act provides for the dedication, conservation or alignment of public travel lines
including construction of access roads adjacent to lands from the nearest part of a public road. Section 10
and 11 allows for notices to be served on the adjacent land owners seeking permission to construct the
respective roads. Already public and PAPs meetings have been held during public consultations and
notifications to effect this given. However, the KeNHA/contractor will adhere to this act by providing access
roads during construction; give notices to and for all the affected land and property openers before and
during and immediately after completion.
xii. The Kenya Roads Act, 2007
The Act established the Kenya National Highways Authority in addition to other Authorities with clear and
separated mandates. The Kenya National Highways Authority has the responsibility for the management,
development, rehabilitation and maintenance of all public roads of class C and above. For the purposes of
discharging its responsibility, the Authority shall have the powers and duties to construct, upgrade,
rehabilitate and maintain roads under its control. This act is triggered as KeNHA implements construction of
the Taveta – Mwatate road.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
14
xiii. Local Government Act, Chapter 265
The Act contains provisions empowering local authorities to control discharges. Under Section 163, a local
authority may control or prohibit activities, both industrial and domestic, which constitutes ‘a source of
danger, discomfort or annoyance to the neighborhood’, is an offensive trade or has not been gazetted by the
Minister.
xiv. Dispute Resolution and Arbitration of Disputes
The Dispute Resolution and Arbitration of Disputes is stipulated in the 1995 Arbitration Act. Kenya's
Dispute Resolution Centre (DRC) is an independent, not-for-profit organization that promotes the prompt,
effective and economic resolution of disputes through arbitration, predominantly mediation, expert
determination and early neutral evaluation. This is a resource that could be called upon by the KeNHA to
arbitrate particularly in disputes around the compensation and resettlement process.
In addition, there are a series of clan based local customary structures that could be used to settle disputes
especially on land ownership where majority of the PAPs have no legal document and/are squatters.
xv. Traffic Act, Chapter 403
This Act consolidates the laws relating to traffic on all public roads. It also prohibits the encroachment on
and damage of roads including land reserved for roads. Construction of the proposed road will trigger this
act as there are a number of structures on the road reserve.
xvi. Forest Act, Cap 385
The Act guides for the establishment, development and sustainable management, including conservation and
rational utilization of forest resources for the socio-economic development of the country. The Act also
provides guidelines for management and, registration of forests and is supported by the Forests Act, No. 7 of
2005. The will need to be enforce to deter the contractor against firewood collection, use and trade by
workmen on the road corridor.
xvii. The Wildlife Conservation and Management Act, Cap 376
This Act provides for the protection, conservation and management of wildlife in Kenya. The Act deals with
areas declared as National Parks, under the Act. The Act controls activities within the park, which may lead
to the disturbance of animals. This Act will be triggered as the project road crosses the Tsavo West National
Park and a registered wildlife sanctuary. It should be enforced to deter wildlife hunting for food and trade in
wildlife products. In addition speed control strategies, mainly during the night, in including road signs and
bumps wildlife areas will be provided.
xviii. Environmental Management Co-ordination Act (EMCA)
The Act provides for the establishment of appropriate legal and institutional framework for the management
of the environment and related matters. Part II of the Environment Management & Coordination Act, 1999
states that every person in Kenya is entitled to a clean and healthy environment and has the duty to safeguard
and enhance the environment. Part VI of the Act directs that any new programme, activity or operation
should undergo environmental impact assessment (EIA) and a report prepared for submission to the National
Environmental Management Authority (NEMA). EIA is normally a prerequisite of RAP. An environmental
Impact Assessment was conducted for Taveta-Mwatate road has been prepared and a licence is being sought
from the National Environmental Management Authority for construction of the project.
4.4 African Development Bank’s Policy on Involuntary resettlement
The African Development Bank’s resettlement issues are outlined in the AfDB involuntary resettlement
policy, 2003 where development of public transport facilities like roads is covered. The overall goal under this
policy is to ensure that when people must be displaced they are treated equitably, and that they share in the
benefits of the project that involves their resettlement.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
15
The objectives of this policy are stated as follows:
i. To avoid involuntary resettlement where feasible, or minimize resettlement impacts where population
displacement is unavoidable, exploring all viable project designs.
ii. To ensure that displaced people receive resettlement assistance, preferably under the project, so that
their standards of living, income earning capacity, and production levels are improved;
iii. To provide explicit guidance to Bank staff and to the borrowers on the conditions that need to be met
regarding involuntary resettlement issues in Bank operations in order to mitigate the negative impacts
of displacement and resettlement and establish sustainable economy and society; and
iv. To set up a mechanism for monitoring the performance of involuntary resettlement programs in Bank
operations and remedying problems as they arise so as to safeguard against ill-prepared and poorly
implemented resettlement plans.
The Taveta-Mwatate road projects falls under the AfDB’s transport sector, and will require involuntary
resettlement, due to public safety and security considerations, involving the establishment of a right-of-way
corridor or a buffer zone requiring resettlement. Thus, the following principles as outlined in the banks
policies will be adhered to:
Principle 1: Resettlement should take place where physical displacement and loss of other economic assets
are unavoidable;
Action: To comply with this policy, KeNHA has demonstrated that the proposed resettlement is both
necessary and viable, and that its scope and extent cannot be lessened. Further, KeNHA has shown that they
have designed the proposed project so as to cause the least possible displacement and/or disruption.
Principles 2: Displaced persons and host communities should be meaningfully consulted;
Action: The primary concern is to take seriously the rights and interests of the PAPs. For this to take place,
their voices need to be made clear, via the formation of local level consultative forum. This has been
undertaken through nine public consultative meetings as part of the Environmental and Social Impact
Assessment and the five PAPs meetings held after the census survey. In addition, grassroots institutional co-
ordinating structures, inform of Locational Resettlement Committees, have been integrated as part of the
resettlement implementation structure.
Principle 3: Vulnerable social groups must be appropriately assisted;
Action: In case of the Taveta - Mwatate road, vulnerable social groups include households living below the
poverty line, the landless/squatters, the elderly, the sick and women and children. These members are often
physically weaker, and may need special help in the relocation/disturbance phase. In particular, the
landless/squatters as well as female/child headed households may lose out to more powerful members of their
households or society. KeNHA in association with the RAP implementing agencies must ensure that the
vulnerable are given necessary protection to ensure that they receive equitable access to replacement resources
and this should be closely monitored.
Principles 4: Resettlers should be integrated socially and economically into host communities;
Action: Except in urban centres where land is on plot basis, there are no major cases where a household’s
complete land will be taken. Majority of the PAPs will therefore remain with economic land pieces where
they can rebuild their houses. However, where land is completely acquired, PAPs will be paid a full
compensation to purchase another piece, preferably in their communities. Integration will be undertaken
through appropriate social engineering strategies including expansion of social facilities.
Principles 5: Displaced persons should be compensated for their losses at “full replacement” cost;
Action: KeNHA will guarantee the provision of any necessary compensation for people whose property will
be disturbed to make way for the roads project, or any other disturbances of livelihood associated with the
project in proportion to their loss. In addition, 15% disturbance fee will be paid for.
Principles 6: The total cost of the project should include the full cost of all resettlement activities;
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
16
Action: Compensation will be paid for structures, land and trees that are disturbed according to set rates
derived from market value comparables. According to the compulsory acquisition act Cap 295, the agreed
compensation should be paid in full and promptly before the project starts. In addition, KeNHA will ensure
that compensation costs, as well as those resettlement costs that fall within their scope of commitment, are
built into the overall project budget as upfront costs.
4.5 Commonalities between GoK and AfDB guidelines
From the analysis undertaken above, the GoK and AfDB requirements are found to converge on the following
points:-
Avoidance of involuntary resettlement wherever feasible, and minimising of resettlement where
population displacement is unavoidable by exploring all viable project options;
Compensation at replacement cost (replacement cost of an affected asset is equivalent to the amount
required to replace the asset in its existing condition;
Assistance to the affected people for relocation;
Assistance to the affected people to improve their living standards, capacity for income generation, and
production levels, or at least to restore to their former levels;
Participation of all stakeholders;
Consultations with project affected persons at every stage and;
Grievance redress mechanisms for project affected persons
Where gaps are identified between GoK and AfDB Guidelines, more provisions will be explored. Table 1
below explores provisions available for resolution of observed gaps:-
Table 1: Provisions available for resolution of observed gaps
Types of affected
persons/lost
assets
Kenyan Law AFDB Guidelines Comparison/gaps Recommendations to
bridge the gap
Land owners Recommends
compensation on
monetary terms based
on market value of
the real property and
disturbance allowance
Recommends
land-for-land
compensation.
Other
compensation is
at replacement
cost.
Compensation in cash
versus compensation
in Kind
Where land for
resettlement is not
available,
compensation in
capital and cash will
be the alternative
Land
Tenants/informal
settlers
Payment entitled only
to title holders as
bonafide property
owners
Entitled to some
form of
compensation
whatever the
legal recognition
of their
occupancy
The AfDB policy
goes beyond legal
land ownership
Informal settlrs
should be entitled to
some form of
compensation
Land users Entitled to
compensation for
crops
Entitled to
compensation for
crops and labour,
may be entitled to
replacement land
and as a
minimum
No compensation for
labour or replacement
of incomes to pre-
resettlement level
under the GoK
Land users should
be provided with
compensation for
losses incurred and
transitional
allowance, say for
three months to
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
17
Types of affected
persons/lost
assets
Kenyan Law AFDB Guidelines Comparison/gaps Recommendations to
bridge the gap
standard,
incomes must be
replaced to pre-
project levels.
sustainably continue
their livelihoods
Owners of non
permanent
buidlings
Entitled to cash
compensation at
market value
Entitled to in-
kind
compensation or
cash
compensation at
full replacement
cost including
labour and
relocation
expenses, prior to
displacement.
AfDB policies
extends beyond
inkind compensation
of lost structures to
compensation for
labour and relocation
expenses
Entitlements should
be offered both in
kind and cash based
on PAPs preference
Owners of
permanent
buidlings
Entitled to
replacement at market
value
Entitled to in-
kind
compensation or
cash
compensation at
full replacement
cost including
labour and
relocation
expenses, prior to
displacement.
AfDB policies
extends beyond
inkind compensation
of lost structures to
compensation for
labour and relocation
expenses
Entitlements should
be offered both in
kind and cash based
on PAPs preference
Livelihood
restoration and
assistance
Provision for fair
compensation for any
losses and
improvements
including 15%
disturbance allowance
Provision for full
compensation
including
transport for
relocation and
transition
assistance (such
as moving
allowances)
during relocation
No transitional
assistance after 15%
disturbance
allowance under the
GoK
In cases where in-
kind replacement is
not the preferred
option of the PAPs,
then the cash
compensation
should be based on
the replacement
cost.
Consultation and
disclosure
PAP should be
informed prior
information on
relocation allowed
PAPs should be
meaningfully
consulted
The PAP is informed
under GoK while
under AfDB, he is
involved in making
specific decisions
Consultation and
disclosure should be
fully and
appropriately
provided
Grievance
mechanism and
dispute
resolution
Not documented Fully
documented and
procedures set
out
No detailed
guidelines under the
GoK
Grievance redress
should be
documented and
communicated to
PAPs
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
18
5. SOCIO - ECONOMIC PROFILE OF THE PAPS
This chapter highlights the socio economic profile of the Project Affected Persons (PAPs). The findings are
based on the census survey carried out during the process of preparation of this RAP.
5.1 Sources of data
The socio-economic profile of the PAPs was generated from primary as well as secondary data sources.
Primary data was collected by conducting 100% census house-to-house survey interviews of 397 households.
In addition, data was collected through observation of PAPs homesteads during interviews and, still
photography. Other methods used to collect primary data included (No. 6) PAPs consultative
meetings/discussions and in-depth interviews with the provincial administration, government heads of
departments, County Councils and other stakeholders. Secondary data of the local socio-economic conditions
was collected through literature review of ESIA Study Report, Constituency and District Development Plans.
According to the 2009 population census, the project districts had a population of 284,657 consisting of
145,334 males and 139,323 females. The districts’ annual population growth rate is 1.74% and the average
household size in the project districts is 5 members. The sex distribution for the PAPs is diagrammatically
presented in the following figure 7:-
Figure 7: Sex distribution for the PAPs
The survey data also revealed that the male headed households were 84% while the female headed households
totalled formed 16% of the total number of households. Fifteen of the PAP households had male members
only and mainly composed of either unmarried men or those who had divorced. Their population ranged from
one to four members. 85% of the PAPs households owned and gave their mobile phone numbers. The rest did
not have mobile numbers while some refused to give the information.
5.2 Education
40% of the PAPs population had attained primary level of education. 10% of the PAPs had no education, 23%
were secondary school leavers and the rest (12%) had attained college/technical school and University level of
education. The education scenarios for the PAPs are presented in the figure below:
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
19
Figure 8: Highest education levels attained by PAPs
None
10%
nursery
15%
Primary
40%
Secondary
23%
Tertiary
12%
5.3 Livelihoods and income levels
In the project area, residents earn their livelihoods from diverse economic activities including farming,
employment (civil servant, teacher), trading and doing other jobs including electrical, bodaboda and security.
25% of the PAPs are farmers, 29% traders, 14% civil servants and the rest are either in school or engaged in
other economic activities including charcoal burning, employed in the private sector and the retired. The
various engagements of PAPs are illustrated in figure 9:
Figure 9: Livelihood sources
Farmer
25%
Civil servan
t14%
Trader29%
Other32%
The average household monthly income is Kshs. 30,000 with some households earning as low as Kshs. 1,500
per month and others over Kshs. 150,000. The highest expenditure is on food where households spent Kshs.
8,000 per month followed by education (6,000), health (2,000) and rent (150) among others.
5.4 Land tenure systems
The land tenure systems in the project area is mixed and include individual, commercial for large sisal
growing estates and, government. Generally land ownership is inadequate and majority of the PAPs have no
land documents. 56% of the PAPs indicated to own the land they were residing on while 15% indicated to
have leased the land and 29% indicated to be squatting on the land.
PAPs indicated to have acquired the land they live in through inheritance (48%), purchase (21%) and through
others means (31%).16% indicated to have Title deeds to their land while 14% had Allotment letters. The rest
did not have documents of ownership to the land. The average land size for individual PAP households is 1.3
acres. 28% of the PAPs owned other pieces of land elsewhere beyond where they resided.
Two of the institutions objected to resettlement as they feared that they may lose members while others did
not see appropriate alternative land. 86% of the PAP households interviewed were willing to cede land for
construction of the project. The rest objected to resettlement on the following premises:
i. No any other land for resettlement
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
20
ii. The road will have social disturbances especially the by pass
iii. In Bura trading centre, some community members insisted that there is a road that was already
demarcated in 1970 and the government should use it for constructed the new road
iv. Some indicated that they were too old to move from one place to another
v. Many objected to resettlement on fear that they will not be adequately compensated
87% of the PAPs preferred assistance interms of cash grant equivalent to their loss, 12% preferred to be
assisted through provision of a new agricultural/commercial plot and 1% opted to be assisted through Training
for self employment.
5.5 Household structures
The socio-economic survey of PAPs established that the average number of structures per household is 4. 30%
of the structures owned by enumerated household(s) translating to two units per household will be affected.
35% of the affected properties are owned by the household head, 8% by the spouse (wife) and 5% by the son.
Daughters own only 1% and the rest is owned by other relatives in the household. From the inventories
undertaken as part of this RAP study, it has been determined that the proposed road project will affect 2365
PAPs who own land and buildings within designated traverse. A comprehensive inventory of PAPs and their
assets is provided in appendix six.
5.5.1 Damage to assets
Upgrading of the Taveta – Mwatate road will require land acquisition hence physical displacement of people,
loss of shelter, assets, income sources and livelihoods, and restriction of access to economic resources. The
project impacts will occur in the 17 sub-locations of Mwatate and Taveta districts but will mainly be
concentrated in Taveta town. A total of 842 structures will be affected by the upgrading of the project road.
These will include buildings, fences, pit latrines, boreholes, hotels/restaurants, pubs, residential houses, cattle
sheds, churches, cattle dips, schools, offices and petrol stations among others. The affected structures are as
presented in the table below:
Table 2: Assets likely to be displaced by the road project Affected property items Number of the affected properties
Abandoned structures/Ruins 2
Bathroom, Bathrooms Ceptic Tank and Latrines 85
Business premises 138
Conservancy tank 5
Dip 1
Floor Slabs and foundations 10
Granary and stores 12
Kiosk 129
Kitchen 50
Offices 9
Religious institutions 8
Residential 240
School Classrooms 5
Shallow well, water points, water stand pipes and water tanks 27
Varandah 2
Graves 34
Fences 85 Total 842
The structures within the traverse are built with various materials including mud, iron sheets, stones, cement
and thatch/grass as presented in the table below:
Table 3: House Building Materials for the affected structures
House section Building material %
Floor Earth 55
Concrete/blocks 4
Cement 31
Timber 10
Wall Earth 23
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
21
Mud/blocks with plaster 31
Concrete blocks 5
Clay (burned) bricks 12
Thatch- sticks 12
Iron sheets 5
Stone. 6
Timber. 6
Roofing
Reeds 6
Thatch 11
Iron 83
Source: PAPs household census survey data analysis
5.5.2 Displacement of communal assets/special interest assets
Communal assets to be displaced will include churches, one mosque, power lines and water pipelines.
5.6 Other Surveys
i. Socio-cultural characteristics of PAPs
The project area is inhabited by a number of tribes the main ones being the Taita, Taveta and Kamba. Other
tribes include Kamba, Maasai, Chagaa and Kikuyu among others. Majority of the PAPs in order of numbers
are the Taita, Taveta and Kamba. These are divided into clans as follows:
i. The Taveta - Wandiri, Wasuya, Wazirai, Wanene , Warutu, Ndigiri, Kiro and Kimaru;
ii. The Taita – Kalimbo Kimonge, Vanguruga, Ngolo, Kiringa, Nyambu, Kivelwa, Mzae, Venleo, Mchazi,
Wanyira, Kwa Veni, Wailole, Mnabuwamsasandu and Mwanda;
iii. The Kamba - Ambua, Akitondo, Aombe, Atangwa and Ethanga.
The Weni sub-clan had many (36) members among the PAP households followed by the Mnene, Mrutu, and
Mzirai. The lists of main sub-clans are presented in the figure below:
Figure 10: Main PAP clans
0
5
10
15
20
25
30
35
40
Amutei Katuu Akitondo Ambua Atangwa Mdighiri Msuya Aombe Mzirai Mrutu Mnene The
Wenis
Num
ber
of PA
P h
ouse
hold
s
Clan
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
22
Other clans represented by at least one PAP household include Awilu, Ethaga, Muiini, Muoini, Mwala Sha,
Mwazine, Wa Kiwelwa, Aambua, Mbaangai, mghanga, Mghenyi, mwafure and mwakangalu among the many
others.
ii. Social network systems and membership of PAPs
PAPs households had members belonging to social groups including local associations, financial
establishments and self help groups. Majority of the members were found in financial associations including
SMEP with 23 PAP members, KWFT with 15 members and Vumilia with 12 members. The figure 5-4 below
presents the number of PAPs who are members in various organisations:-
Figure 11: PAPs membership in organisations
Kilungu Ngaghen
yaZaina Unison Hekima
Muinuko
Group
KCB
Haba Na
Haba
Vumilia KWFT SMEP Others
Series 1 4 4 4 5 6 8 9 12 15 23 56
0
10
20
30
40
50
60
Nu
mb
er
of
ho
use
ho
lds
Other self help groups where PAP had enrolled as members included Hekima Group and Children Orphans
group, Jitegemee Women Group, Kariobangi B Welfare, Mashamba Farming Group, Muinuko Group,
Mwachambo Kuku Help Group, Mwangaza Community Unit, Mwatate Welfare Association, Richard
Kwambarata, Silk Women Group, Tamac Welfare, Ujinga Marufuku Upendo Group and Wukeni Women
Group. The survey revealed that 36% of the households had none of their members belonging to any self help
organisation.
iii. Religion
91% of the PAPs are Christians and 9% are Muslims where none indicated to be a traditionalist. Three main
shrines existed including Voilole (Mwatate district) Challa Kendong and Kichongoji (Taveta district) which
are however over 10 kms from the project road.
iv. Graves
24 PAP households indicated to have at least one grave within their land parcels. The total number of graves
on PAPs households when combined totalled to 34. 20 of these PAP households had one grave each, one
household had two graves and two households had three graves each and one of the households had six
graves.
In total, 34 graves will have to be relocated. Grave relocation was raised as a major concern by the PAPs in an
area where some households have as many as six. Relocation of graves will follow any of the following:
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
23
i. Relocation by the family following traditional rites including involvement of the elderly and
customary practices. Many preferred to adopt modern Christian strategies of relocating the
graves. In both cases, all wanted to relocate the graves near their new settlement sites and not
to collective cemeteries.
ii. Relocation by the contractor which was preferred for the graves where family members have
moved and cannot be reached and incase relatives of the diseased are not known (diseased
visitors).
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
24
6. PUBLIC CONSULTATION AND COMMUNICATION
6.1 Consultation and community participation
The goal of consultation and community participation process was aimed at disseminating project information
and soliciting the views of stakeholders in as far as the project design and Resettlement Action Plan
implementation is concerned. This process facilitated collection and collation of PAP and other stakeholder
views as well as in cooperating them into the RAP procedures and structures. The process of consultation and
disclosure of affected properties was conducted through indepth discussions with the provincial administration
and various government departmental head, meetings and interviews with each of the PAP and consultative
meetings with groups of PAPs.
6.2 Stakeholder consultation
As part of meeting GoK and the AfDB policies and guidelines, community consultation and participation was
undertaken in preparation for this RAP. The community consultation and participation provided the
opportunity to raise the PAPS awareness on the proposed road project and its facets. The consultant in
collaboration with the Proponent organised and facilitated PAPs consultations in six different venues of all
affected sub locations during which the RAP study was discussed. A total of six meetings (table 7) were held
during which the potential PAPs were advised on assets affected, the legal aspects asset acquisition and
resettlement, proposed implementation structures and grievance redress mechanisms. All meetings were
conducted by the consultant and facilitated by the local provincial administration. In-depth discussions with
GOK officers and consultations with the PAPs were conducted as follows:
i) In-depth discussions
These included two (2) meetings with the district commissioners in Mwatate and Taveta districts, the Taveta
Town Council and Ministry of Lands – Physical planning (Wundanyi). These discussions centred on:
(a) The design concepts of the proposed project and need for land and asset acquisition;
(b) The project and its impacts including the PAPs and how they will be compensated;
(c) Confirmations and need for participation during the scheduled PAPs consultative meetings.
ii) Community meetings
(a) Project Affected Persons individual household survey
During the individual household census survey, each PAPs household was involved in the consultation
and their concerns on the effects of the project on their assets were addressed.
(b) Project Affected Persons consultative forums
A total of six (6) Consultative meetings were held with the PAPs between 14th and 18th April 2012.
Consultative meetings were attended by a total of 344 (234 males and 110 females) PAPs,
representing 80% of the affected. 32% of the PAP participants were females. The 5 table below
presents summary of PAPs meetings undertaken while the list of participants and minutes of meetings
are annexed to this report:
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
25
Table 4: Detailed PAP participation in consultative forums
Area Venue Date Number of PAP
participants
Male Female Total
Mwatate/Mwachambo
Locations
Mwachambo chief’s office –
Mwatate market
16.4.2012 21 19
40
Bura Location (Nyolo
sub-location)
Mwanjila Polytechnic, Bura
Market
14.4.2012 47 21
68
Mwachuma sub-location Mkamenyi/Starehe market 15.4.2012 27 9 36
Mwakitau sub-location Mwakitau market 15.4.2012 9 4 13
Ngarisha location Ngarisha chiefs camp, Taveta
town
17.4.2012 55 10
65
Timbila/Kimala/Mata
locations
Daranjani public
grounds/Timbila Primary
school
18.4.2012 75 47
122
Totals 6 no. venues 234 110 344
NB: While the total number of PAPs are 397 higher compared to those reflected in the consultative, the
difference arose from some PAPs not attending.
i. Issues presented
During the PAP consultative meetings, the consultant presented the following:
a. The project concepts that:
The road starts at Taveta and ends at Mwatate and is 60 meters wide. It follows the current road
alignment although there are some realignments and therefore will affect some private and
properties
The road is earmarked for financing by AfDB and Government of Kenya. Thus it will be
implemented within the Kenyan constitution (Kenyan laws cap 295) and AfDB policies and
regulations.
The cut-off date will be 30th April 2012 to enable the PAPs to come to terms with the realities
facing them and their developments. “Any development after 30th April 2012 will not be
compensated”. However, the PAPs should continue cultivating on their normal food crops in the
rainy seasons.
Any land that is a subject of a case in court will not be paid for until that case is determined but
this cannot stop the project.
He further explained that some structures may be affected fully or a fraction, although if a fraction
of a house was affected, the balance of the entire house is fully interfered with and the owner
should negotiate for full compensation, and then relocate
The compensation is paid for structures like houses, toilets, animal sheds among other types of
structures. Other items liable for compensation are planted trees, whether for fruit, decoration or
shade. But indigenous trees do not attract any compensation and PAPs may harvest them in good
time to use either for timber, charcoal or other uses they may be put to.
b. The legal perspectives to compensation, procedures to be followed, items to be compensated,
organisational framework for compensation and grievance redress mechanisms.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
26
ii. Participant concerns and suggestions
Following these presentation, participants were allowed time to raise their concerns, make comments and
amendments to the proposed resettlement structures and procedures and raise all their concerns in as far as
the RAP was concerned. Each of these is presented in the following table:
Table 5: PAPs Issues raised and the Responses to the Issues raised
PAPs Issues Raised Responses to the Issues Raised
If affected, what assets will be
compensated?
Land, Structures and trees. In addition, an extra 15% of the
value of the assets affected will be paid as disturbance
allowance
Will the trees and crops be
compensated?
All the trees that will be affected will be valued and
compensation will be undertaken. The valuation will
depend on the type of trees and the owners will be given the
right to salvage. The permanent crops will also be valued
and compensation given. The farm owners will be allowed
to harvest their perennial crops.
How will the project handle the
graves that will be affected by the
project?
The government will support the relocation of graves. This
will require further consultations with the affected
households in order to determine appropriate ways of
handing the matter.
How will the valuation of assets be
undertaken?
All properties affected will be valued at market price and
compensation will be awarded payments made prior to
relocation.
How will grievances be handled? The RAP will develop a grievance redress mechanism and
PAPs awareness on the developed mechanism will be
raised. The PAPs will also be involved in the development
of the grievance redress mechanism.
How will compensation for land
ownership with no titles be
undertaken
All PAPs are encouraged to show the documentations for
the land they occupy. A census of all the persons on the
traverse will also be undertaken. The process of
compensation will also involve the county administration
and local leaders in determination of the owners of the land
parcels affected.
What are the forms of compensation? The PAPs will be given the right to choose on the forms for
compensation that will include either land for land, land for
cash.
How will compensation for structures
on the road reserve be addressed?
Structures on road reserve are illegally constructed. A
Census of all affected will be undertaken and a decision
will be made.
How will the project handle the
relocation of public utility services?
Water and electricity are forms of public utility services;
the contractor will liaise with the relevant stakeholders for
relocations of utility services within the shortest time
possible.
How will the project minimise the
impacts in Taveta town and could the
corridor proposed be reduced to 40
meters as it approaches town
The concern will be documented and raised with proponent
and the design engineers
Who will be the eligible persons for
resettlement and compensation?
A census of all affected persons will be undertaken and a
cut-off date will be determined to ensure no new entries
within the traverse. The eligible persons will include those
who will lose assets, livelihoods, access, and shelter and
will include land owners and tenants.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
27
The PAPs also recommended:-
i. They should be issued with advance notices for relocation once compensation is done;
ii. The modes of compensation (cash or in kind) should be discussed with each individual household just
before compensation is effected;
iii. The venue for PAPs reception of their payments should not be done at the provincial administration
offices. Participants lamented of an earlier compensation process which they claim they were forced
to pay some money before collecting their cheques at the DC’s office. This is an issue that had also
been raised during the ESIA public consultation meetings;
iv. The PAPs urged the proponent to also consider compensation for assets on land that do not have legal
title.
6.3 Future Consultations and RAP Disclosure
Following the preparation of the RAP, disclosure of the RAP report should be undertaken in the Districts and
with the PAPS. This will enhance PAPs and public awareness on the resettlement and compensation
processes.
Further consultation and communication with the PAPs should also be undertaken during the RAP
implementation process. The proponent should also prepare communication materials on the resettlement and
compensation processes, PAPs rights during compensation and resettlement, established grievance redress
mechanism, PAPs relocation and resettlement. These should all be communicated to the PAPs to enhance
smooth implementation of the RAP.
The involvement of the local community will continue during the implementation of this RAP through public
forums, participating in interviews held in the project area and by filling pre-defined questionnaires,
discussing pressing issues with the project team consisting of land valuer, land surveyor, socio-expert and
environmental experts. The PAPs will also continue to participate during the project through:
i. Resettlement Committee and PAPCs
ii. Grievance mechanisms for the RAP implementation
iii. RAP monitoring and evaluation events including social surveys and meeting discussions
iv. Progress review by internal and external auditors
v. Awareness creation and training with other community members
Several stakeholders and community public meetings should be held in the project area and the proponent
present to the community details of the RAP status as well as monitoring findings including possible impacts
and recommendations. The summary of this RAP will be posted in the AfDB’s Public Information Centre
(PIC) and website for public review and comments.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
28
7. IMPACTS OF THE PROJECT
7.1 Impact Activities
A 60 meter road corridor would be required as per the typical designs for road implementation. Construction
of the road will include activities that give rise to resettlement including:
i. Constructing the existing road to bitumen standards with proper two lane facility and
shoulders
ii. Improve the horizontal alignment at selected locations to reduce sharp curves and thereby
provide safe driving conditions,
iii. Widen, repair or reconstruct damaged bridges and culverts including construction of new
drainage structures,
iv. Remove any irregularities that are on the existing vertical profile,
v. Provide service roads and cycle lanes, especially in the town centres
The above activities will lead to land acquisition, physical displacement of people, loss of shelter, loss of
assets, loss of income sources and livelihoods, and restriction of access to economic resources.
7.2 Impact Areas
The Project-Affected Areas for the road will be concentrated along the road corridor and specifically within
the urban towns of Taveta and Mwatate. Administratively, the Project-Affected Areas lies within the 17 sub-
locations in Mwatate and Taveta districts traversed by the project including Bomeni and Jipe divisions in
Taveta district and Mwatate division in Mwatate district with long sections of the project road located within
the Tsavo West National Park. The various administrative units traversed by the project road and where the
above impacts will occur are tabulated in the table below:
Table 6: Administrative areas affected by the project road
District Division Location Sub-location
Mwatate Mwatate Mwatate Mwatate
Mudhabobango
Mwachambo Mruru/maganga
Umari/Sechu
Bura Nyolo
Mwakitau Mwakitau
Mwachuma
Taveta Bomeni Ngarisha Lesesia
Mjini
Mahoo Mahoo
Malukilorito
Mboghoni Njoro
Jipe Timbila Msengoni
Ndilindau
Kimala Kimala
Rekeke
National Park National Park Tsavo West
Source: Taveta and Mwatate District Offices
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
29
7.3 The Project Affected Persons
The Project-Affected Households resulting from upgrading of Taveta – Mwatate road are 397. The total
population of these households is 2365 consisting of 1205 males and 1160 females. Accordingly, all the
affected persons and properties have to be compensated, as required by the AfDB policies and as proposed in
this resettlement action plan (RAP).
The table 7 below presents summary number of Project Affected Persons and households where interviews
were conducted:-
Table 7: Project affected households and persons by administrative locations
Household PAPs
District Location Number of Households Male Female Total
Mwatate
Mwachambo 56 216 201 417
Mwatate 18 43 44 87
Bura 66 163 183 346
Mwaktau 36 107 99 206
Taveta
Timbila 73 172 177 349
Mboghoni 11 51 42 93
Mahoo 7 28 26 54
Luworo 10 43 33 76
Ngarigashi 80 266 253 519
Mata 40 116 102 218
Total 397 1205 1160 2365
In addition, a total of 34 institutions will be affected. The affected institutions are listed below:
Table 8: List of affected institutions
1. A.I.C Mbooni Church(peter mutunga)
2. Bura County Council
3. Bura Health Centre
4. calvary worship centre
5. Catholic Church, Ng'ambwa
6. Evangelical Lutheran Church
7. fisheries department
8. G.o.K Prison, Taveta
9. harvest christian church
10. Heartbeat High School
11. Heartbeat International Ministry
12. Kenya Railways
13. KRA
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
30
14. Lighthouse Ministries Church
15. Mbuyuni Women Group.
16. Mwaktau Dispensary
17. Mwaktau primary
18. mwatate environment and sanitation
19. Nuuman Ibn Bashireer Mosque
20. Postal corparation
21. Redeemed Gospel Church
22. St. Peter's A.C.K church, Bura
23. Taita Academy
24. Taita Taveta County Council
25. Tambila community cattle dip
26. Taveta Fisheries
27. The Kenya Police
28. timbila catholic church
29. Timbila High School
30. Timbila Primary School
31. Town Council of Taveta
32. Tsavo National Park
33. Usafiri self help group
34. Wanjala Youth Polytechnic
7.4 Impacted properties
Construction of Taveta-Mwatate road will affect land (including pastures and farms), trees, structures
(including business, residential, institutions/public and private utilities, businesses and, graves). The table
below summarises the number of impacted properties.
Table 9: Affected properties
Affected property items Number of the affected properties
Abandoned structures/Ruins 2
Bathroom, Bathrooms Ceptic Tank and Latrines 85
Business premises 138
Conservancy tank 5
Dip 1
Floor Slabs and foundations 10
Granary and stores 12
Kiosk 129
Kitchen 50
Offices 9
Religious institotions 8
Residential 240
School Classrooms 5
Shallow well, water points, water stand pipes and
water tanks 27
Varandah 2
Graves 34
Fences 85
Total 842
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
31
7.4.1 Impacts on Land and farmland
Ownership of land to be affected include Private Land, land owned by group ranches, land occupied by
Government Offices, Land held in “trust” (Trust Land) by Taita Taveta County Council and Government land
in the form of roads/road reserves and National Parks. Due to lack of title deeds, land ownership could not be
authenticated and this will be established during property verification and valuation prior to construction of
the project road.
Construction of Taveta - Mwatate road will lead to land acquisition at a length of about 85 Kms. However, the
total land acreage could not be determined at this stage since the existing road reserve is not well defined and
land adjudication is not complete. Except for the Taveta bypass, road realignments, widening and climbing
lanes in some areas, the road will generally occupy same land area as that occupied by the existing gravel
road. In each of the realignment areas and the bypass, the road will affect private and communal land,
permanent and semi-permanent residential and commercial structures and graves1.
Impacts on land loss for PAPs who are left with economically viable land parcel are expected to be low while
the rest will experience high impacts on land loss. Other impacts on land will include:
i. Loos of land and property where in most cases there are no land titles as is the case across the
project area;
ii. As a result of acquisition and increased impetus for more incomes from land sales, there is
likelihood of increased land court cases. In addition, unopennesss in sale of land specially by the
household head will increase and could lead to disenfranchisement in some households;
iii. It will lead to increase in land prices thereby making it difficult to acquire new land due to
competition, this will be worsened if compensation money is inadequate or the funds are
squandered;
iv. Being relocated to a place which is inhabitable or has natural calamities. In addition, resettlement
may be to hostile neighbours and communities where the resettler takes time to cope with the new
neighbours and adapt to the environment. This will be complicated by the challenges faced in
starting life again/afresh
7.4.2 Impacts on structures
A total of 842 structures will be affected by the upgrading of the project road. These will include buildings,
fences, pit latrines, boreholes, hotels/restaurants, pubs, residential houses, cattle sheds, churches, cattle dips,
schools, offices and petrol stations among others. Most of the structures affected are residential houses and
business/commercials. It was however noted that over 60% of these business/commercials are temporary in
nature consisting of Kiosks and open shades which could easily be moved with ease but with major impacts to
livelihoods for those depending on the businesses and inaccessibility by customers during the transitional
period. The main impacts therefore will include loss of living shelters and business premises.
The residential building consists of both permanent and semi-permanent structures. Removal of especially
urban residential houses could have major impacts on rent increase which could deny the poor access to fair
shelter Demolition of these structures will require adequate co-ordination including adequate notices and
timely payments to accord appropriate relocation. Demolition of houses will mean rebuilding another one
which is time consuming as one goes through design and construction. Loose of property coupled with grave
disturbances could further deepen stress and psychological torture,
The impacts that accompany demolition and relocation of structures to the “unknown” new sites was trauma
associated with such shifts especially for construction of new structures, clearance as well as establishment of
farms. To deal with the issue of individual emotional attachments to land, there is need for an intensive social
engineering prior to the project implementation which would ensure harmonious coexistence between the
1 The total land acreage, number of trees and crop acreage are not provided (except under the lump sum budget) as
these were not provided during the schedule survey conducted in November 2011.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
32
residents and their neighbours. In addition, PAPs should be relocated within the vicinity of their current
residence.
7.4.3 Impacts on Loss of Trees and Crops
The proposed project will lead to excision of trees and perennial crops. The area to be acquired crossed
through a number of farms planted with maize, green grams, Cowpeas, Sorghum, Beans and Bananas which
may be affected depending on the time of project implementation. It is however assumed that, by the time the
implementation of the project starts, the affected land will have some crops planted, and this can be confirmed
at the time. Due to lack of title deeds, land ownership could not be authenticated and this will be established
during property valuation prior to construction of the project road.
7.4.4 Impacts of relocation on public facilities and services
The road, as much as possible, has been designed so as to avoid social facilities notably schools, religious and
institutions and churches thereby minimizing relocation/disturbance of services that accompany relocation of
these institutions. The redesigned road has avoided relocation of Bura and Taveta cemeteries. Despite the
efforts undertaken to avoid relocation, 34 institutions consisting of religious facilities, education institutions,
sanitation blocks and a number of government offices that could not be avoided. The public institutions
affected and extend of the impacts on the facilities are tabulated below:
Table 10: Public structures/institutions affected
Building structures affected
Name of institution Use of affected structures Surface (m²)
Calvary Church Mwatate Church 9.80
Toilet 2.00
Toilet 2.00
Heartbeat High School Toilet 9.00
Class room 15.00
A.I.C Mbooni Church House 3.60
Nuuman Ibn Bashireer Mosque Mosque 11.10
Conservancy tank 3.10
Conservancy tank 2.80
Grave -
Redeemed Gospel Church, Bura Church 15.00
Toilet 3.00
Mwanjila Polytechnic Class room 14.00
Class room 6.60
Water tank 4.70
Workshop 12.20
Conservancy tank 2.40
Mwashuma Calvary Worship
Center
Church 2.50
Mwaktau primary Gate 16.40
toilet 6.90
Evangelical Lutheran Church Church 6.60
Lighthouse Ministries Church Foundation 12.00
Church 15.30
G.o.K Prison. Taveta Latrines 10.80
Class rooms 49.56
Latrines 8.93
Timbila Primary School Gate house 10.00
St. Peter's A.C.K church, Bura Toilet 6.90
Pastor Lawrence Igombo Church 94.50
A.I.C Mbooni Church House 11.52
Nuuman Ibn Bashireer Mosque Mosque 95.61
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
33
On the land earmarked for the project, no community cultural value sites were identified. However, at
individual level, the residents indicated to have strong and emotional attachments to land because of social
and cultural reasons. Relocation of public facilities and leaving them with the same capacity could lead to
increased competition and reduced vacancies. This may constrain many from accessing services offered
thereby and especially the marginalised. During construction, there will also be disturbances to social facilities
including water pipes and electricity lines.
7.4.5 Impacts on Loss of Incomes
This RAP proposes compensation and relocation assistance for businesses in the short term. This assistance
for loss of income will be offered during the transitional period between demolition and re-establishment of
businesses which is within three to six months. Impacts on loss of incomes and income sources could lead to:
i. Business breakdown leading to loss of income and will be worsened incases where one has
borrowed a loan. There will also be loss of incomes as businesses lose customers especially
where the shop is relegated to uneconomical sites, rent incomes as tenants move to other
houses;
ii. Insecurity as those who find themselves unemployed could take to thuggery;
7.4.6 Impacts on Socio-cultural network and support systems
The perceived impacts on social groups included breakdown in communication, cessation in reception of
benefits, disconnection/loss of the member/dismissal, failure of organization and activities, increased distance
to organization meetings, interference with savings, loss of premises, and reduced group activity/coordination.
A cultural amenity however that raised issues was on graves as whenever these were affected, the PAPs did
not wish to think twice about. Relocation of graves is an emotional issue that needs to be addressed under this
RAP as cannot be valued; hence the owners need to get a token for its relocation according to the traditional
or modern/religious procedures. In as far as emotional relocation of graves, there is need for an intensive
social engineering prior to the project implementation.
7.5 Impacts on Vulnerable Groups
The physically challenged population in the project districts stands at 10% of the total population in the
districts. The RAP socio-economic baseline survey revealed that the PAPs households had a combined total of
126 people. This implies that, 4.6% of the PAPs constitute the vulnerable members of the society.
Vulnerability indicators are that:
i. They are sick (suffering from various diseases namely TB, Bilharzia HBP)
ii. Those with visual problems, the physically and mentally handicapped
iii. Those below the poverty line
iv. The elderly/aged
v. Widows/female and child headed households
The table below summarises the distribution of the above vulnerable PAPs.
Redeemed Gospel Church, Bura Church 76.50
Evangelical Lutheran Church Church 29.04
Mwaktau primary Fence/Gate 41.00
Grand total 610.36
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
34
Table 11: Vulnerable PAP members
Residence Sex Total
Male Female
Rural 39 25 64
Urban 32 30 62
Total 71 55 126
7.6 Minimising resettlement and losses
The proposed road will generally follow the current alignment. However, resettlements will take plae where
there are needs for realignment and at areas where people have encroached mainly in urban centres. It is
therefore important to avoid or minimize relocation and therefore resettlement and disturbances arising from
land acquisition. The proposed measures to avoid or minimize land acquisition and disturbances include
reducing the road reserve, redesigning the project route at certain points, facilitating consultations and
participation with the PAPs, and putting appropriate impact limitation and mitigation measures in the
construction and design stages. Each of these measures are discussed in the following paragraphs.
Reducing the road width
The road has been redesigned to a width of 35meters only in Taveta CBD section. This has avoided
demolition of the main buildings that make up the Taveta town and significantly reduced the costs to be
incurred in compensation.
Redesigning the project route at certain points
Field investigations and comments obtained from the community members pointed at various sections that
could be re-aligned to avoid destruction of business structures and relocation of graves. During these
consultations, it was proposed that the road should, as much as possible traverse through agricultural land and
open grounds rather than destroying structures in urban centres of Taveta and Bura. In both Bura and Taveta
towns, the road has been redesigned to avoid public cemeteries.
Facilitating Consultation and participation with the PAPs
During the ESIA, the study interviewed people from all walks of life on the construction of the project as well
as efforts that should be put in place to mitigate against adverse impacts. The PAPs participated in the
development of the RAP by generating primary resettlement opinions and data base. Further, PAPs will
participate during RAP implementation in the following ways:
i. Assisting in the update of the detailed site investigation of private and community assets
ii. Determining compensation criteria
iii. Distributing house plots at the Resettlement Sites
iv. Negotiation of compensation agreements to fully reflect resettlers’ interests and opinions and
transparency of the KeNHA resettlement work
v. Resettlers’ selection of house building materials and methods
vi. Regular consultative meetings attended by PAPs to keep the communities informed of the
RAP progress and to continue soliciting opinions and proposals from the affected persons.
vii. Dissemination and sharing of information about relevant policies, laws and regulations and,
compensation criteria.
7.7 Preliminary evaluation of compensation preferences
80% of the PAPs preferred to be compensated with cash for land while 13% opted to be given both land and
while the rest 7% opted for both land and cash. 91% of the PAPs preferred to be compensated with cash for
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
35
their structures while 2% opted to be given both structures and cash while the rest 7% opted for combination
of transport, training and/or house. 86% of the PAPs preferred to be compensated with cash for their
relocation costs while 10% while the opted to be assisted with both transport and training and the rest opted
for other compensation mechanisms including provision of seedlings and loans.
This RAP recommends that compensations to PAPs be paid in cash or in-kind as per AfDB guidelines and the
laws of Kenya depending on entitlements for each group. It is also recommended that a 15% disturbance
allowance and 5 % relocation allowance based on the total value of assets should be paid to each category of
PAPs for re-establishment of livelihoods.
7.8 Impact mitigation measures in the construction stage
Minimizing impacts during construction stage will entail implementing various measures including:
i. Preference for hire of existing rental houses, rather than building workers’ camps, which also will boost
the economy of the area. This would go hand in hand with hiring of local residents who would reside
in their homes;
ii. Roads for earth moving equipments should be strictly confined to existing tracks to limit social
disturbances and destruction of the environment;
iii. Project will be carried out after the harvest of crops so as to minimize damage to crops;
iv. It is proposed that all those that shall be affected by the project should be compensated before project
commencement to ensure that their livelihoods have improved or restored to the pre-impact status.
Overall, the results of efforts to minimise resettlement will be to:
Significantly reduce disturbances and resettlements and therefore lower the costs of resettlement for the
proposed project;
Ensure majority of the residents positively support and participate during the project implementation
and operation;
Enhance and sustainably maintain social integration;
Residents’ livelihoods will be left undisturbed.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
36
8. INSTITUTIONAL FRAMEWORK
8.1 Overview
This chapter provides a list of all agencies and institutions that are to be involved in the RAP implementation
process that includes management of resettlement and compensation as well as monitoring and evaluation.
Each of the agencies/institutions have adequate capacity to accomplish their relevant responsibilities and,
where there are capacity gaps, outsourcing is advised in order to respond to the resettlement and
compensation issues as fast as possible.
8.2 Agencies for the RAP implementation
Primarily, implementation of this RAP and compensation necessitated by upgrading of the Taveta - Mwatate
road requires the following main actors, Ministries of Lands, Agriculture, Forestry and Public Works (for
providing and approving compensation rates), the yet to be sourced developer who will effect the
compensation/resettlement, and Ministry of Roads through KeNHA (for sourcing the contractor, financing,
co-ordinating and monitoring the resettlement), NEMA to monitor implementation of the RAP. The specific
roles and responsibilities for each agency are outlined in the following paragraphs:
8.2.1 Ministry of Roads
Roads implementation in Kenya is vested with the Ministry of Roads. The Ministry is charged with the
responsibility of providing basic infrastructure facilities to the public including development, rehabilitation
and maintenance of the road network in the country
8.2.2 The Kenya National Highways Authority (KeNHA)
The Kenya National Highways Authority (KeNHA) is a State Corporation established under the Kenya Roads
Act, 2007 with the responsibility for management, development, rehabilitation and maintenance of national
roads of class A, B and C. Taveta-Mwatate road is one of the roads whose management falls within the
mandate of KeNHA since it’s classified as Class A. KeNHA (the proponent) have a project implementation
structure that has clear provisions for environmental and social integration, under which the RAP will be
implemented.
8.2.3 Ministry of Lands
The Ministry of Lands, through the chief valuer will undertake to verification of ownership of property, size
of land to be acquired, and values of each asset to be affected. Where no land documents are available, the
Ministry will liase with the village elder, assistant Chief and/chief and clan elders to verify rightful land
owners. The Ministry will then proceed to gazette the acquired land as it changes ownership from private to
public.
8.2.4 Ministry of Agriculture and Ministry of Forestry
The two Ministries of Agriculture and Forestry at district level, will undertake to verify crops and trees
affected and provide and approve the compensation values. The Ministries will in collaboration with the
provincial administration, advice and ensure crops are harvested for the season preceding construction so as to
ensure food security for PAPs.
8.3 The process of Resettlement and compensation
Once the RAP is cleared by AfDB, KeNHA will formally prepare the list of the persons dispossessed by the
project, including their rights of occupancy and the assessed value. The agency (KeNHA) will then disclose
this list to the affected people mobilised, through announcements in the local media and clearly displayed
posters, by the provincial administration at each of the administrative sub-location traversed by the project
road. Confidentiality should be considered during this process for reduce on the PAPs vulnerability to
insecurity.
It is paramount that PAPs be systematically and continuously made aware about the project, and the RAP will
be made available to the affected persons and communities through the County governments. The awareness
creation and consultative process shall be undertaken for the affected and the neighbouring communities, local
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
37
leaders and government officials. Others to participate include County government, community-based
organizations (CBOs), NGOs and the Vulnerable. These meetings will be chaired by KeNHA’s
community/RAP specialist and attended by PAPs in the sub-location and the provincial administration as well
as PAPs co-opted participants.
The County governor will, through chief/sub-chiefs, dispatch the dislocation notices to the affected
households and heads of institutions. The Ministry of Finance will disburse the compensation funds to
KeNHA who will directly pay the PAPs eligible for compensation through the Project Implementation Units
(PIU) in KeNHA’s regional office Mombasa. Following compensation and resettlement, PAPs will be given a
grace period of at least six months and assistance to relocate.
During demolition, PAPs will be given the right to salvage parts and harvest their crops and trees. After
expiry of the six months’ notice, KeNHA will authorize the Contractor to start demolition works clearing the
right of way for construction.
8.4 Organisational Structure for RAP Implementation and compensation
The overall responsibility for implementation of the RAP will be vested in the General Manager (KeNHA)
and staff of the Project Management Unit created specifically for the Taveta – Mwatate road. In addition, the
construction supervision unit will also take part in the RAP implementation.
The implementation management organization for this RAP will be at three levels namely national (PIU),
County Resettlement Committee (CRC) and six Project Affected Persons Committees (PAPCs), one for
each/combination of each of the following: Mwatate/Mwachambo Locations; Bura Location; Mwakitau
location; Mata/Timbila/Kimala locations; Malukilorito/Mahoo/Mboghoni locations and; Ngarisha location.
The outlook of the proposed RAP institutional arrangement is presented in the following figure:
Figure 12: Institutional Arrangement for RAP Implementation
Source: RAP Field visit discussions
This institutional framework was designed with the participation of the stakeholders and should be established
and fully functional before embarking on the construction stage of the project. The institutional framework is
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
38
mandated and should be capable to plan and implement land acquisition, compensation, conflict resolution,
relocation as well as income and livelihood restoration programs. The institutional framework involves all
stakeholders and details the roles of each in the implementation and administration of the RAP. Each of these
institutions is discussed as follows:
Project Implementation Unit
KeNHA will institute a Project Implementing Unit (PIU) that will oversee implementation of the resettlement.
The PIU will consist of the general manager, land valuer, social development officer (community liaison
officer), environmental officer, surveyor, ICT officer (database officer), legal advisor, way-leave officer and a
monitoring and evaluation officer. The PIU will develop the terms of reference for operations of the County
Resettlement Committee (CRC).
The PIU may not have the full capacity to make and implement resettlement policy decisions. There is
therefore a need to co-ordinate and network with Government Ministries and departments as well as
organizations with capacity to fill in the gaps. The personnel to fill in missing capacity gaps could either be
seconded from other government departments or outsourced on consultation basis.
County Resettlement Committee (CRC)
Resettlement Committee will be based either at Taveta/Mwatate town. The CRC will consist of the district
Commissioners, District Land Adjudication and Settlement Officer; KeNHA Representative; local
government (Taita Taveta County Council and Taveta Town Councils), National Environmental Management
Authority (NEMA), Kenya Wildlife Representative, District Social Development Officer, Gender officer, and
Provincial State Counsel.
The CRC will involve and co-ordinate other stakeholders and institutions who will play key roles in
implementation of the Resettlement Action Plan activities that include land acquisition, award of
compensation, assistance and resettlement. Other stakeholders to participate in the resettlement at the CRC
level include representatives in Livestock, Fisheries, Agriculture, Environment and Mineral resources;
Housing and Settlement and; NGOs with legitimate interests in social services, finance/trade, and health.
Project Affected Persons Committees
The Project Affected Persons Committees will be established at locational level and will be moderated by the
area chief or other government officer at the grassroots level. The PAPs will elect a committee of not more
than five members amongst themselves including a Chairperson and a Secretary. The PAPCs will work under
the guidance and coordination of CRC and PIU. Each of the PAPCs committees will be trained and involved
in finalisation of the actual PAPs list. PAPCs will be formed two to three weeks after the formation of the
CRC. Other stakeholders who can be co-opted to participate in PAPs meetings will include clan elders, village
elders, representatives in livestock, trade, finance, agriculture, lands and housing as may be deemed necessary.
PAPCs will act as the voice of the PAPs and its functions will include:
i. Conducting extensive public awareness and consultations with the affected people so that they can
air their concerns, interests and grievances. This consultation will ensure that they own the whole
process of resettlement.
ii. Resolving disputes that may arise relating to resettlement process. If it is unable to resolve any
such problems, will channel them through the appropriate grievance procedures laid out in this
RAP.
iii. Monitor and evaluate the RAP process at the grassroot level
iv. Enhance employment opportunities (for those who cannot find alternative employment) and,
conduct training and counselling of the PAPs (socially and economically).
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
39
9. GRIEVANCE REDRESS MECHANISM
Grievance redress mechanisms are essential tools for facilitating PAPs to voice their concerns about the
resettlement and compensation processes as they arise and, if necessary, for corrective action to be taken
promptly. Such mechanisms are fundamental to achieving transparency in the land acquisition and
resettlement processes.
9.1 Sources of Grievances /Disputes
As part of PAPs involvement, the proposed grievance redress mechanism was presented and with comments
of the affected persons, amendments were made during PAP consultative meetings. However, further
disclosure will be provided prior to the compensation process. Arising from PAP consultative meetings so far
held, the key grievance subject matters likely to arise in case of the Taveta-Mwatate road include:
(i) Mistakes on inventory of the affected properties that might have occurred during the census
survey
(ii) Disagreements over land parcel boundaries for the affected
(iii) Court pending cases, that by law cannot be discussed outside the court, unless such are
withdrawn,
(iv) Disagreements on plot /asset valuation where the PAP feels that his/her properties have been
undervalued. This is also the case where the PAP demands are far higher than both the
government and market value arising from the perception that “the government is rich”
(v) Divorce among couples, succession by heirs and other family disagreements;
(vi) Dispute over ownership of given Assets between two or more affected individual(s);
(vii) PAPs opting for compensation for land in kind (land for land) and the choice of location site has
no willing seller;
(viii) Delays in compensation payment.
(ix) Dealing with relocation of graves;
(x) Extend and values for the resettlement assistance, relocation as well as disturbance and
compensation for livelihoods.
These grievances necessitate the setting up of appropriate grievance and appeals redress mechanisms to
address the grievances and disputes that may arise from time to time.
9.2 Proposed procedure for grievance redress and management
It is for the benefit of both the proponent and the PAPs to devise procedures and mechanisms through which
complaints and disagreements can be resolved. These procedures and mechanisms should meet the following
criteria:
(i) Simple and transparent
(ii) Accessible to all the affected irrespective of their location and/or socio-economic status mechanism
for recording of grievances and their timely resolution.
(iii) Flexible and open to scrutiny
(iv) Speedy, just and fair
Complaints will be launched through either one or combination of the following methods:
i. Filling a specifically pre-designed complaint form and appending the PAPs signature and formally
submitting it to the GRC office; or
ii. Widely disseminating, through consultative fora and the media, information about PAPs disputes
and grievances.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
40
KeNHA will make every effort to resolve grievances at the community level without impeding access to any
judicial or administrative remedies that may be available but turn out to be slow and expensive.
All complaints from the PAPs received in writing or verbally by the PAPC will be documented. A copy will
be maintained by the PAPC. The specific terms of reference for the PAPC will include settling, monitoring
and facilitating effective and timely dispute resolution thereby reducing the risk of escalation of conflicts and
avoiding unnecessary delays. The proposed step-by-step procedures of Grievance Redress mechanism for the
proposed road project are:
a) Step 1
PAPs are informed of their losses and entitlement in writing and through the PAPC.
b) Step 2
If satisfied, the PAP claims resettlement payment from the PIU through the PAPC via the CRC. If
dissatisfied or the PAP do not clearly understand the entitlement/any aspect of the resettlement plan, s/he
approaches the PAPC for clarification. The PAPC makes a note and explains the unclear issues to the PAP
according to the RAP. If the issue(s) are resolved, the PAP collects the payment from the PIU. If not
solved PAP moves to step 3
c) Step 3
The PAP writes up or a fills a complaint’s form appended with his signature formally to the CRC at their
office. The CRC holds a session with the aggrieved PAP, minutes recorded and duly constituted. If
resolved, the PIU approves and the PAP collects his/her entitlements. The CRC has 2 weeks from
submission to hold a session with the PAP.
If necessary, the Project Affected People Committee (PAPC), will be asked to provide recommendations
as to how the grievance is to be addressed. If deemed necessary by the PAP committee the case will be re-
investigated, depending on the nature of the issue or referred to the Public Compliant Committee/Land
Compensation Tribunal.
d) Step 4
The PAP appeals to the Public Compliant Committee/Land Compensation Tribunal. If the outcome
decision is not acceptable, the PAP proceeds to the final step.
e) Step 5
The PAP can appeal to a court of law for settlement of the case.
A schematic diagram of the grievance redress is represented in figure 9-1.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
41
Figure 13: Grievance Redress Procedure
Legal Action
CRC hears grievances and Rules -2
weeks from submission date to
respond
Unresolved grievance is forwarded
to CRC through the PAPC
Land Compensation Tribunal, Public
Compliant Committee
PAPC unit hears grievance and
rules – 2 weeks from
submission to response
No Further Action PAP satisfied &
Grievances Resolved
Affected Party declares a
grievance and forwards it to
his/her PAPC unit
No Further Action
No Further Action PAP satisfied &
Grievances Resolved
PAP satisfied &
Grievances Resolved
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
42
10. ELIGIBILITY
10.1 Introduction
In this resettlement plan, eligibility is the criteria under which one would qualify to receive benefits under the
resettlement program.
10.2 Eligibility criteria
The eligible individual(s) are those who are directly affected socially and economically as a result of
improvements of the project road which in effect results to compulsory acquisition of land and other assets.
Properties that are eligible for compensation are buildings, land, assets on the land such as crops, trees and
graves and affected public social utilities such as power supply, water pipelines. The compulsory acquisition
of land and other assets will result to relocation or loss of shelter; loss of assets, loss of access to assets
(including land, structures, trees and crops and graves); loss of income sources or means of livelihoods even if
the affected persons is not forced to relocate and; forceful denial to access to legally designated social and
economic services. Based on this criterion, this RAP identified the following categories of PAPs as being
eligible for compensation:
i. Owners of structures that are to be affected by the development;
ii. Owners of land affected by the road;
iii. People who have leased land for cultivation and their crops or trees are to be removed or damaged due
to land acquisition activities.
iv. People residing in the areas surveyed during the census and asset inventory survey of the proposed
road reserve and working sites
v. Any other persons or group of persons, who though not mentioned, are entitled to compensation
according to Kenya laws and African Development Bank policies.
10.3 Cut-Off Date for Eligibility of Compensation
In order to determine compensation eligibility of persons and their assets, 30th April 2012 was declared as the
cut-off date. 30th April 2012 was the last day of the census survey and final meeting of the six extensive
consultative meetings with PAPs for the preparation of the Resettlement Action Plan. During the stakeholder
meetings, the cut-off date for eligibility of compensation and its purpose was communicated to stakeholders,
the local communities and PAPs. Consequently, any claim for compensation by the affected people after this
cut-off date will not be eligible for compensation.
The Contractors shall compensate for use of local (community/private) materials and for any impact resulting
from his activities following the same principles as those in the resettlement process at market value. The
project will have to provide alternate access wherever the access is blocked during construction. In case of
restriction of access to community owned facilities or common property resources due to project related
interventions, the project will rebuild such facilities and provide alternative access.
10.4 PAPs’ Entitlements
Under the Kenyan Law, PAPs are categorized so as to include property owners, residential tenants, business
tenants and affected communities. However, AfDB’s categorization of PAPs is broader and includes the
following:
i. Those who have formal legal rights including customary law and traditional usage as outlined under
the Kenyan constitution;
ii. Those who have no recognized legal rights or claims to land they are occupying including those on the
road reserve and shutters.
iii. Those who do not have formal legal rights to land at the time of conducting census, but have a claim
to such land or assets provided that such claims are recognized under the Kenyan constitution
Table 11 below presents a summary of entitlement matrix for eligible PAPs:-
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
43
Table 12: Entitlement Matrix
PAP Category Entitlement
Individuals who have formal
legal rights to land
Compensation for loss in land and assets at full replacement cost.
If they are physically relocated, provide assistance during relocation
including transport allowance
Right to salvage
Transitional support spanning for six months after displacement to
facilitate restoration of livelihoods and standards of living to pre-
displacement levels.
Development assistance inform of capital, credit facilities, training
and job opportunities
15% disturbance fee
Individuals who do not have
formal legal rights to land, but
have a claim to such land or
assets if the claims fall within the
Kenyan law or/or local
ownership systems
Compensation for loss in land and assets at full replacement cost.
If they are physically relocated, provide assistance during relocation
including transport allowance
Right to salvage
Transitional support spanning for six months after displacement to
facilitate restoration of livelihoods and standards of living to pre-
displacement levels.
Development assistance inform of capital, credit facilities, training
and job opportunities
15% disturbance fee
Individuals who have no
recognizable legal right or claim
to the land they are occupying
including squatter settlements
and disputed ownership
Resettlement assistance and the replacement values for
structures/assets.
Transitional support spanning for six months after displacement to
facilitate restoration of livelihoods and standards of living to pre-
displacement levels.
Right to salvage
15% disturbance fee
Vulnerable PAPs Support (direct and indirect –through other agencies and programmes
e.g fund for the disabled and aged) and facilitation to access the
needed services including medical care, capital support
Organization
Persons who encroach on the
earmarked road after the cut-off
date
No entitlements for compensation
Despite the above, all PAPs will equally be eligible for compensation and rehabilitation assistance,
irrespective of their land ownership status, to ensure that those affected by the Project shall be at least as well
off, if not better off, than they would have been without the Project. Absence of a title will not therefore be a
hindrance to receiving compensation and livelihood assistance.
The economic census covered all categories of PAPs based on their site location as at 30th April 2012 which
is the cut-off date for eligibility to resettlement entitlements for the this RAP.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
44
11. VALUATION OF AND COMPENSATION FOR LOSSES
11.1 Valuation Methodology
Valuation can simply be defined as the art or science of establishing the value (worth) of a particular interest
in property for a specific purpose and at a particular moment in time; taking into considerations all the
features of the property and also considering all the underlying factors of the market.
All valuation techniques rely on the collection and analysis of data such as social, economic, government and
environmental attributes. Specific data include local market conditions and details of property transactions
such as location, physical and functional form and legal characteristics. The value of the property is affected
by the rights of enjoyment or compensation when such benefit may be alienated. In Kenya, compensation
value in case of compulsory acquisition requires that the value paid to include all the other miscellaneous
expenses as well as the injurious affection due to the disturbance to them. Thus in such circumstances, the
value paid is higher than normal open market value. The disturbance allowance is normally 15% of the value
of the property acquired.
During preparation of this RAP asset inventory survey was conducted according to the following
methodology:
• Determination of the final road alignment and ROW requirements on 1/2,000 scale (or 1/1,000 scale in
built-up areas) mapping, resulting from survey of the current situation.
• Analysis of the survey (types and numbers of properties marked for expropriation), and data collected
from ongoing Northern Corridor Projects regarding costs of relocation; and preparation of an estimated
global budget of indemnification, to be included in the whole project budget.
11.2 Data Collection
An accurate topographical site survey was carried out along the road corridor. The field work for asset
inventory survey was carried out on different dates from 15th June 2011 to 30
th October 2011.
Plans were prepared during the process from the proposed road centreline alignment, and from the
topographical survey drawings; the buildings and properties within the project road corridor were identified
and listed on a schedule.
The site visit’s aim was to collect the following information:
• For buildings and structures: type of building/structures, type of walls and roofing, number of rooms
and owner’s name;
• For trees: type of trees, maturity and owner’s name;
• For boundary fences and hedges: type of fence, length and owner’s name.
Each property surveyed was recorded on a survey sheet and allocated a reference number in relation to its
location along the road section in terms of the village, and ownership.
11.3 Analysis of Field Data
The results of the field assessment were analyzed according to the different types of properties encountered, as
described below.
11.3.1 Buildings and Houses
Buildings and houses surveyed were classified into three main categories; by standard of construction,
condition, or by materials used for construction:
• In terms of standard of construction and condition: they were categorized as being in good, fair or
poor condition depending on the construction standards.
• Material used: affected structures were classified as permanent, semi-permanent, or temporary.
Permanent: their walls made of masonry or concrete blocks, roofing of corrugated iron sheets (CIS)
with floor finish, good or fair condition. Semi-permanent: their walls made of wood and mud but
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
45
plastered, or made of stones cemented by mud, with floor finished or unfinished. Temporary: these
included all other structures including traditional huts and sheds.
This classification ultimately had an impact on the unit cost applicable to each category.
11.3.2 Boundary Fences
The following types of fences were encountered;
• Vegetal live fences: these consisted of either of the following, euphorbia, local shrubs like
‘samanderi’, or exotic trees like cypress and other exotics.
• Barbed wire fences: consisting of wooden posts and barbed wires.
• Chain link fences: consisting of wire chain link and wooden, concrete, or steel posts.
Generally, barbed wire and vegetal fences were of low quality and were constructed from locally available
materials i.e. unprocessed wood, with just a few of them well constructed. Chain link fences were mostly of
good quality, with the majority of this type of fence used around institutions like church missions, schools,
health centres, etc.
11.3.3 Trees and Crops
Types of trees encountered and surveyed along the road corridor were both indigenous and exotic species. For
crops, being mostly seasonal in nature, they were not considered under this valuation. Further, even at the time
of actual acquisition, the land owners would be allowed to harvest their crops before surrendering the pieces
of land acquired. However, few perennial crops encountered have been included.
11.3.4 Forests and Bushes
The project road does not pass through classified forests but between km 25 – km 60 is considerably bushy.
A number bushes and trees will have to be cut but the effect of road construction on the bushes shall be
minimal, as the existing horizontal alignment has been maintained as much as possible. Trees affected have
been estimated and compensation cost included.
Mitigation measures have also been put in place to mitigate against any destruction that may be caused to the
environment.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
46
12. RESETTLEMENT SITE
In Kenya, guidelines and availability of vacant land for resettlement can be provided by the commissioner for
lands except in cases where land is purchased specifically for PAPs to resettle. In case of the Taveta -
Mwatate road, no resettlement site was identified.
12.1 Resettlement alternatives and choices
Resettlement alternatives in the project area are:
i. Remaining on the same piece of land where only a part of it is acquired. 48% of the PAPs preferred this
option of resettling within the same land they resided;
ii. To purchase land within or beyond the same neighbourhood, an alternative chosen by 38% of the PAPs.
However in this case, there were concerns that land may become extremely expensive to purchase
thereby inhibiting the PAPs from accessing any with the amounts paid for compensation;
iii. Identification, purchase and resettlement of the PAPs by the proponent through the Lands
Commissioner. This was not preferred by majority of the PAPs as the noted that they could purchase
land by themselves and still save some money from the compensation. This option however needs to
be explored further before compensation commences. Possible Resettlement Sites
The method for site selection was based on alternatives proposed by community members during PAPs
interviews and public participation. Generally, the affected community members were not ready to move out
of their communities. Majority opted to resettle within their remaining land parcels. There was therefore no
host communities considered under this RAP as PAPs will fizzle into their existing communities.
12.2 Measures to prevent influx of ineligible persons at the selected sites;
Since no site for resettlement was identified, there may be no danger of influx of ineligible persons except
land speculators and crop buyers as well as sellers of agricultural inputs. Influx management strategies will
only be necessary to prevent land speculation and will be undertaken by the PAPCs and CRC.
12.3 Integration with host communities
The RAP did not identify any resettlement site. However, majority of the PAPs likely to lose their structures
stated that if they were to choose their preferred area of resettlement, they would choose to be resettled in the
same community. Those affected should be conducted early enough and the host community be sensitized on
the proposed move to enable them understand how this will affect them and ensure co-existence of the host
and the resettlers. It is advisable that during the sensitization of the host community the two parties should
meet to enable initiate interactions. Alternatively the PAPs who are likely to lose their structures and still
remain with sustainable land should be offered monetary compensation to cover at least six months rents for
them to leave in rented houses as they develop their houses.
12.4 Resettlement Options
The community members preferred to be resettled in the same community or with family members. Since land
parcels in the project area are small, majority of those whose land will be acquired preferred suggested
alternative rerouting of the canal at the project design stage.
12.5 Environmental protection
Construction of thee Taveta – Mwatate road will lead to increased population along the road corridor and
especially in market and urban centres. The increased population is likely to result to overexploitation of
natural resources as well as increased waste. The environmental impacts of the proposed project are dealt with
under the Environmental and Social Impact Study Report. However, the negative impacts and proposed
mitigation measures for the resettlement are presented in the following paragraphs:
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
47
i. Removal of vegetation will occur as populations concentrate in one area and seek crushing plants
and exploitation for fuel wood. This will be mitigated by encouraging the population to plant
especially indigenous and native trees. In addition, there is need to encourage the population to use
clean energy sources.
ii. There is potential for serious dangers on wildlife due to population influx of workers who may
provide a ready market for game meat. To mitigate against this impact, there is need sensitize the
workers against consumption of game meat and the dangers thereof. Further, a code of conduct to
ensure that workers do not consume game meat from the area, whether supplied by the locals or
killed by themselves should be developed and enforced strictly within the wildlife dispersal areas
and the park itself.
iii. Inaccessibility by customers to shops and business premises due to distant relocation of the business
and reduction of stock. This will lead to business breakdown leading to loss of income and will be
worsened incases where one has borrowed a loan. There will also be loss of incomes as businesses
lose customers especially where the shop is relegated to uneconomical sites and reduction in rent
incomes as tenants move to other houses. Gratuity allowance is proposed under this RAP to cushion
against business loses.
iv. Being relocated to a place which is uninhabitable or has natural calamities. In addition, resettlement
may be to hostile neighbours and communities where the resettler takes time to cope with the new
neighbours and adopt to the environment. This will be complicated by the challenges faced in
starting life again/afresh.
Alternatives of relocation sites should be offered to the PAPs to choose. In addition, adequate
preparations including social engineering should be undertaken prior to resettlement
v. Demolition of houses will mean rebuilding another one which is time consuming as one goes
through design and construction. Loose of property coupled with grave disturbances will further
deepen stress and psychological torture.
vi. It will lead to increase in land prices thereby making it difficult to acquire new land due to
competition, this will be worsened if compensation money is inadequate or the funds are
squandered. Speculative land buying and disposal should be checked.
vii. There will be increased competition and reduced vacancies in public social facilities. This may
constrain many from accessing services offered thereby.
There is need to expand and establish more public facilities especially in areas where more resttlers
are expected.
viii. During construction, there will be disturbances to social facilities including water pipes and
electricity lines. Advance notices be given to the public and facilities should be repaired
immediately
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
48
13. LIVELIHOOD RESTORATION
The PAPs derive their livelihoods from a number of sources as follows:- farmers 25%, 29% traders, 14% civil
servants and the rest are either in school or engaged in other economic activities including charcoal burning,
employed in the private sector and the retired. The various engagements of PAPs is illustrated in figure 7-4:
13.1 Livelihood disturbance and dislocation
Once the road project is effected, the PAPs livelihoods and economic activities will be affected as a result of
implementation of the proposed project both during and after relocation when the PAPs incomes may be
substantially reduced. The livelihoods will be affected through relocation of businesses hence loss of
customers and increased distance to supply sites and reduced size of land for crop and livestock grazing
among others.
13.2 Strategies for livelihoods restoration
The strategies for these livelihood restoration are aimed at enhancing restoration of the residents’ economic
and income bases, mostly by promoting diversification and adoption of alternative economic activities. To
realize these, there is need for the proposed project to incooprate other activities beyond ordinary
compensation. The proposed strategies to ensure minimal shock as well as fast recovery of losses and eventual
realization of stability of incomes and livelihoods will include efforts that are aimed at improving the PAPs
land percels; capacity building and training, expanding the existing social facilities and; promoting economic
diversification.
Since majority of the PAPs opted to shift to another site of their remaining land parcels, there should be
concerted efforts to improve the land in line with peasantry economic modes of production. This will facilitate
the crop dependent PAPs, majority of them being peasant farmers, to adopt themselves to the changing
conditions within the shortest time possible. Further, the land improvement should ensure that the per unit
production is higher or equivalent to that before resettlement. This will ensure that the resettlers’ production
and standard is higher or equivalent to the original pre resettlement level. Ensuring that the PAPs resume
production and land is transformed will include the following key activities:
i. Introduction of the PAPs to the characteristics and appropriate production as well as profitable
economic activities;
ii. Providing appropriate training in farming methods including farm management, tree production,
agro forestry, soil improvement and animal production;
iii. Setting up demonstrative fields and tree nurseries;
iv. The resettlers and host community members are facilitated to develop a common plan of action for
a appropriate and relevant diversified economic activities in the Resettlement Areas mostly micro-
projects for which the PAPs were found to have some experience.
v. Support to stimulate private transportation and other services including hotel and restaurant,
information and communication, tourism as well as shop keeping
vi. Before resettlement, social adjustment is a priority for the PAPs so that they are able to cope with
the anticipated psychological constraints that come with changes. During the field visit and
discussions, the PAPs clearly emphasized that inorder to enhance social adjustments, the following
activities are necessary:
Resettle the homestead, not a household, as a unit to one site to ensure continued social
support
As much as possible, where a PAP has his portion of land remaining, he should be allowed
to move his homestead there rather than relocating to “foreign” land. Thus the
resettlement should be done in sanity manner where the PAPs are resettled on basis of
village/greater household social units. If the relocation takes place, the resettlers should
be taken to the nearest possible land within their original homes
Resettlement sites should as much as possible have the same characteristics as the former
sites.
vii. Vulnerable Groups including the Poor, sick, orphaned and vulnerable children should be given
priority in employment opportunities arising from the project. Further during construction, there is
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
49
need to identify appropriate micro-programs that could be provided under the project such as
revolving fund financial incentives (including tax rebates, interest free loans and subsidies) and
assistance for housing construction among others;
viii. Public Information Campaign: Awareness creation to enlighten the residents on the importance as
well as the need for attitudinal change towards the projects impacts;
ix. In order to reduce the project impacts, the PAPs should be allowed to harvest resources on right of
way before they are cleared by the contractors;
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
50
14. IMPLEMENTATION ARRANGEMENTS AND SCHEDULE
14.1 Overview
An implementation schedule covering all resettlement activities from preparation through implementation,
including target dates for achievement of expected benefits to PAPs and monitoring and evaluation until
termination of the various forms of assistance.
14.2 Implementation Schedule
The responsibility for the RAP implementation will lie with the CRC under the supervision of the PIU. It is
anticipated that the PAP’s would be resettled as agreed before commencement of the project construction.
The RAP anticipates that the project implementation schedule will consist of three phases namely preparation,
implementation and operation. The resettlement schedule for land acquisition, house demolishment and
relocation will be coordinated by KeNHA. The construction schedule and key activities anticipated prior to,
during and after are outlined under the implementation schedule namely Resettlement Action Plan Activity
Schedule (RAPAS) covering all resettlement activities from project preparation through implementation to
monitoring and evaluation indicating timelines for achievement of expected benefits to PAPs. The
Resettlement Action Plan Activity Schedule (RAPAS) is spread over twelve months including approval of the
RAP as presented in the table below and will consist of the following activities:
i. Preparation of RAP
ii. Mobilisation and consultation with PAPs
iii. Verification of property/asset ownership and valuation for compensation including offering of
awards
iv. Bank account opening and/or revival for those that are dormant
v. Payment of compensation and delivery of other entitlements within 6 months after serving
notices;
vi. Issue a vacate communiqué for removal of all movable structures and assets, six months for
complete remove of all affected structures and assets ;
vii. Dispute /grievances resolution;
viii. Complete removal of all affected structures and assets, six months after issuing of the vacate
communiqué
ix. Monitoring, evaluation and final audit
Table 13: RAP implementation schedule
Activity Month
1 2 3 4 5 6 7 8 9 10 11 12
RAP approval
Verification of property/asset
ownership
valuation and offering of awards
Bank account opening
Payment of compensation
Issuance of vacate notice
PAPs consultation and communication
Formation and functioning of PAPs
committees, CRC and PIU
Livelihood restoration activities
Contractor identification
Removal of all affected structures
Dispute /grievances resolution;
Monitoring and evaluation
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
51
15. COSTS AND BUDGET
Tables indicating breakdown of cost estimates for all resettlement activities, including allowances for inflation
and other contingencies; timetable for expenditures; sources of funds; and arrangements for timely flow of
funds.
15.1 The RAP Compensation Budget
The figure gives estimates for acquired land value, affected structures, trees and crops and miscellaneous
(graves and other cultural sentimental allowances) and disturbance allowance is legally added to the declared
value as stated by Compulsory Acquisition Act. The itemised and total cost estimates for compensation is
presented in the table below.
The total cost for compensation summed to approximately Kenya shilling Kenya Shillings three hundred
ssixty four million, seven hundred and thirty six thousands, six hundred and seventy three and seventy cents
(Say Kshs. 364,736,673.60). The breakdown was as follows, acquired land value estimated to Kenya Shilling
ninety four five million, five hundred and thousands (Ksh. 94,500,000.00); affected buildings and other
structures one hundred ninty four million, four hundred eighteen thousands, nine hundred nineteen and ninety
cents (Kshs. 194,418,919.90); Fences (4,668,405.00), Electricity lines (17,250,000.00); Trees and perennial
crops (26,402,445) and; miscellaneous (graves and other cultural sentimental allowances) approximately two
million and two hundred thousand (2,200,000). 15% disturbance allowance is legally added to the declared
value as stated by Compulsory Acquisition Act totalling to approximately forty seven million five hundred
seventy four thousand, three hundred forty seven and seventy shilling (47,574,348.70).
The allowance caters for economic, social and physical disturbance caused to a PAP who is required to
relocate from areas they had gotten used to and sometimes lose their livelihood. The land value adopted was
an average calculated value based on the land yields, within the project area. This is due to lack of reliable
comparable land prices in the area. The cost of relocation and development of other facilities was not included
because the timeframe and the type of facilities to be provided were not indicated. The summary of the
compensation is as outlined on table 13 below:
Table 14: Cost estimates for compensation and RAP implementation
Compensation item Total Cost
Land 94,500,000.00
Buildings and other structures 194,418,919.90
Fences 4,668,405.00
Electricity lines 17,250,000.00
Trees and perennial crops 4,125,000.00
Miscellaneous (Graves removal and other cultural sentimental allowances) 2,200,000.00
Total Budget 317,162,324.90
15% statutory allowance 47,574,348.70
Sub - Total Compensation Budget 364,736,673.60
Costs for implementation of the RAP 33,075,000.00
GRAND TOTAL COMPENSATION BUDGET 397,811,673.60
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
52
15.2 The RAP Implementation Budget
The cost for implementation of this RAP is 33,075,000.00 including the costs of professional services, project
management, capacity building of PAPs and monitoring services as presented in the following table:
Table 15: Costs for implementation of the RAP
Expense Description Unit Total Cost
Professional Services Verification of assets 5 3,000,000.00
Livelihood restoration
Resettlement assistance to the
vulnerable groups
Lump sum 9,000,000.00
Stakeholder participation Future consultations, awareness
creation and communication
42 meetings 2,100,000.00
RAP implementation RAP documentation and
implementation
Lump Sum 7,500,000.00
Resettlement Committees
costs
Allowances for RAP districts steering
committee and agents (CRCs)
9 Members 1,900,000.00
Allowances for RAP steering
committee and community agents
Local RAP/PAPCs
42 Members 1,500,000.00
Monitoring and evaluation Cost of monitoring and evaluation of
the process
Lump Sum 6,500,000.00
Subtotal - - 31,500,000.00
Administration cost based at
5% of Total RAP Cost
Administration cost for managing the
RAP process
Percentage of
cost
1,575,000.00
TOTAL 33,075,000.00
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
53
16. MONITORING AND EVALUATION
Monitoring and evaluation is one of the central activities in ensuring successful implementation of any RAP.
Consequently, RAP monitoring and evaluation should be in cooperated into the Resettlement and
compensation management processes through provision of funds and employment of qualified personnel.
Due to its central place, implementation of the RAP for upgrading of Taveta – Mwatate road will be subject to
both internal and external monitoring and evaluation. The monitoring plan covers performance monitoring,
impact monitoring and completion audit. Monitoring, evaluation and final audit of the resettlement
implementation will be founded on the baseline survey generated in the RAP and ESIA reports for Taveta –
Mwatate road.
Arrangements for monitoring of resettlement activities by the implementing agency; supplemented by
independent monitors as appropriate, to ensure complete and objective information; performance monitoring
indicators to measure inputs, outputs, and outcomes for resettlement activities; evaluation of the impacts of
resettlement for a reasonable period of time after the resettlement activities have been completed.
16.1 RAP Monitoring Framework
During the RAP implementation, monitoring will be conducted on a continuous basis by the PIU through the
PAPC/CRC who will collect and record the information of resettlement activities and submit the monitoring
reports, on timely basis, to the PIU and attend its meetings. In the overall internal monitoring framework,
there will be continuous information circulation from the village level through the PAPC/CRC to the PIU
Office accompanied by periodic supervision and verification by the CRC Office. The monitoring and
evaluation involves both the internal and external monitoring.
16.2 Internal monitoring
Internal monitoring will be conducted at different levels. At the locational level, it will be conducted by the
PAPC. At the districts/County level, it will be conducted by the CRC and PIU. Monitoring will be done on a
continuous basis to ensure that all responsible implementing agencies follow the schedule and comply with
the principles of the RAP. The PIU/CRC will develop an internal monitoring framework to supervise the
resettlement activities. The PIU will maintain the basic database of land acquisition, house relocation and
resettlement. It will monitor all of the relocated households, and supervise the whole process of resettlement
preparation and implementation. The process will involve both performance and impact monitoring:
Performance monitoring will be conducted to assess the efficiency with which the RAP activities have been
implemented. It will include environmental audit and an independent compensation committee to spearhead
the grievance and verification of the compensation.
Impact monitoring will be conducted to assess the change in living standards of PAPs e.g. whether the RAP is
effective in maintaining or restoring PAPs livelihoods, especially the vulnerable groups e.g housing
conditions, access to basic amenities, demographic characteristics and indebtedness among other.
16.3 External monitoring
External resettlement monitoring will be conducted by an External Monitoring Assistance team (EMA) who
shall be engaged by the PIU. External monitoring will be in two phase namely compliance monitoring and
impact evaluation. The overall objective of the EMA will be to carry out the following:
i. Review the results of the internal monitoring and overall compliance with the RAP;
ii. Assess whether relocation objectives have been met especially with regard to housing, living
standards, compensation levels, etc;
iii. Assess general efficiency of relocation and formulate lessons for future guidance; and
iv. Determine overall adequacy of entitlements to meet the objectives.
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
54
16.4 Monitoring indicators
These indicators will facilitate monitoring of resettlement performance based on set timelines as per the RAP.
Monitoring and evaluation will assist in ensuring that compensation measures are correct, all eligible persons
have received their entitlements and that implementation of the RAP is proceeding well. Lists of indicators are
tabulated below:
Table 16: Monitoring Indicators
Subject Indicator
Land Number of acres of land (private, communal or government) land acquired for
the road way leaves
Number of land parcels and plots acquired
Road markings
Acquisition of
buildings and /
Structures
Number of structures (private, residential and commercial) buildings acquired
Number of demolished structures
Number of newly constructed structures
Trees and Crops Number of trees cut
Crops destroyed by area, type and ownership
Compensation, Re-
establishment and
Rehabilitation
Number of homesteads affected (buildings, land, trees, crops)
Number of owners compensated by type of loss
Number and type of replacement houses constructed
Number, capital endowment and profitability of replacement businesses
operating
Number of community structures replaced
Number of seedlings supplied by type
Number of trees planted
Hazards and
Disturbances
Number of homesteads affected by hazards and disturbances from
construction (noise levels, blasting, increased traffic levels, etc)
Social/ Demographic Homestead size (births, deaths, migration in and out)
Age and gender distribution
Marital status
Status of “vulnerable” homesteads
Distance/travel time to nearest school, health centre, church, shop,
administrative areas and water
Nutritional status of PAPs
Number of people with disease, by type (STDs, malaria, diarrheal, ARI,
immunizable disease)
Extent of awareness and educational programmes
Literacy and educational attainment of homestead members
School attendance rates by age and gender
Skills of homestead members
Landholding size, area cultivated and production volume/value, by crop (cash
and subsistence crops)
Landholding status (tenure)
Employment status of economically active members
Amount and balance of income and expenditure
Realisation of homestead income restoration plans (components implemented,
net income achieved)
Organisational membership of homestead members
Leadership positions held by homestead members
Leadership positions held by women
Growth in market areas
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
55
Subject Indicator
Consultation Number of local committees established and dates of their meetings
Type of issues raised at local committees meetings
Involvement of local committees in the development planning
Number of participating NGOs and CBOs
Number of grievances registered by type
Number of grievances resolved
Number of cases referred to court
Training Number of PAPc committee members trained
Number of affected population trained in project-related training courses
Management Number of implementing agencies by function
Number of GoK ministry officials available by function
Number of office and field equipment, by type
Census and asset verification/quantification procedures in place
Effectiveness of compensation delivery system
Number of land transfers effected
Co-ordination between local community structures, KeNHA and GoK
officials
Vulnerable PAPs Number of agencies/organizations supporting or programmes targeting the
vulnerable PAPs
Number of vulnerable accessing various products and services including
medical care, capital support
16.5 Agency responsibilities
The monitoring responsibilities of the PIU during the RAP implementation will be as follows:
i. Set up the resettlement office, train resettlement staff to investigate the project affected area and
persons.
ii. Facilitate the appointment of an external agency to provide consulting services to the project office
and institute the final census survey.
iii. Conduct surveys jointly with the PAPC and CRC
iv. Train the PAPC
v. Conduct external monitoring
Kenya National Highways Authority
Resettlement Action Plan for the Upgrading of Taveta – Mwatate Road
56
REFERENCES
1. African Development Bank, Policies on Environment and Involuntary Resettlement, 2003.
2. Egis; Preliminary and Detailed Engineering Design of Mwatate-Taveta/Holli Road (A23) - Environmental
and Social Impact Assessment Report, May 2012;
3. GOK, (2009). Sessional Paper No. 3 on National Land Policy. Government Printers
4. Government of Kenya, Taita District Development Plan, 2008-2012.
5. Government of Kenya, Taveta District Development Plan, 2008-2012.
6. Ogolla B D and Mugabe J. (1996). Land Tenure Systems, in Land; Initiative Publishers, Nairobi Kenya
7. Okoth-Ogendo H. W. O (1999). Land policy Development in East Africa. A survey of recent trends: A
regional overview Paper for the DFID Workshop on “Land Rights and Sustainable development in Sub-
Saharan Africa” held at Sunningdale Park Conference Centre, Berkshire, England 16-19 February, 1999.
8. Okoth-Ogendo H.W.O (1989). Some issues of theory in the study of tenure relations in African
Agriculture. International African Institute. Cambridge University press.
9. Republic of Kenya, Constitution, 1963.
10. Republic of Kenya, Physical Planning Act, No. 6 of 1996.
11. Resettlement Plan of World Bank Funded Road Sector Assistance Project – December 2008.
12. http://www.flickr.com/photos/albertkenyaniinima/6105962864/sizes/o/in/photostream
13. International Finance Corporation, Handbook for Preparing a Resettlement Action Plan