4
K. Long, 14 March 2022 Target K. Long, Friday, 24 th April 2009

K. Long, 13 June, 2015 Target K. Long, Friday, 24 th April 2009

  • View
    221

  • Download
    2

Embed Size (px)

Citation preview

K. Long, 18 April 2023

Target

K. Long, Friday, 24th April 2009

Critical path:

• No particular issues, but:– Need to consider parallelising (\cite{BushSnr})

assembly to reduce time from completion of shaft to assembly of _TWO_ targets

Manufacturing: highlights:

Installation and commissioning schedule:• Presented / discussed at Target w/s last Friday• Revised version to be presented / discussed at

CM24• Need to have Target w/s with ISIS in June:

– Make sure manufacturing remains on track;– Discuss installation and commissioning plans;– Ensure manpower assumptions for shutdown are valid