Upload
julie-tyler
View
213
Download
0
Tags:
Embed Size (px)
Citation preview
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
1
Small Muon Ring for a Cooling Demonstration
Steve KahnFor
S. Kahn, H. Kirk, A. Garren, F. Mills and D. Cline
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
2
The Need for Muon Cooling Muon beams will be needed for Neutrino Factories and eventually
Muon Colliders. Because muons mostly come from the decay of pions and the
pion capture process generally produces a large phase space, reduction of phase space is required.
This is particularly necessary for a muon collider which requires cooling by ~10-5. Neutrino Factories would benefit by a reduction of muon phase space by ~10-2.
The approach is to use ionization cooling to reduce the phase space. Specifically, we want
A compact ring with edge focusing dipole magnets. The beam enclosure filled with high-pressure hydrogen gas to
serve as the energy loss absorber. RF cavities to restore the longitudinal energy loss.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
3
Demonstration Ring Design Parameters
Pressurized H2 gas filled ring. The gas is the absorber.
40 Atm @ 300 K 10 Atm @ 77 K
Four Weak focusing dipoles Dipoles use edge focusing. Iron yokes for flux return.
Nominal dipole field of 1.8 T 2.3 T would be possible with
Vanadium Permendur. RF cavities in the drift region
between magnets to replace energy loss in gas.
Using 201.25 MHz cavities. 10 MV/m gradient.
Parameter Value Dipole Field 1.8 T
Number of Cells 4 Reference Momentum 172.12 MeV/c Ring Circumference 3.81 m
X Aperture 20 cm Y Aperture 10 cm
Pz Acceptance 10 MeV/c Minimum X 38 cm Maximum X 92 cm Minimum Y 54 cm Maximum Y 66 cm
Hydrogen Gas Pressure 40 Atm @ 300º K RF Gradient 10 MV/m
RF Frequency 201.25 MHz Total RF Length 1.2 m Total Orbit Turns 100
Table 1: Parameters that describe the muon cooling ring.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
4
Sketch of One Cell of the Cooling Ring
Cavity
Magnet
rho=31.8
gamma=22.5
Xc=22.5 cm
Yc=22.5 cm
25 cm
Cavity
Cavity
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
5
1.6 m
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
6
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
7
Cooling with the Hard-edge Model
rp Scalable Ring:
The ring operates on the 3rd Harmonic
Observe cooling with a Merit factor of 20 (without decays).
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
8
Comparison of Closed Orbits with and without Iron
With IronCoils Only
Note the reverse curvature between magnets
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
9
By Field Along the Closed Orbit Path
Coils only—No Iron
Coils plus Iron
Constant Hardedge Field
•Since coil only field has large negative field between the magnets, it must have larger field in the magnet to give the same integrated bend.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
10
Pole Shaping to Improve the Horizontal Aperture
We have shaped the poles of the magnet to make the field on the symmetry plane field more uniform.
This improves the horizontal aperture.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
11
Cooling Results Using the Shaped Iron Poles
Admittance Equilibrium
X17.2 mm 5.8 mm
Y3.5 mm 2.1 mm
Z18.0 mm 5.0 mm
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
12
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
13
Injection into This Demonstration Ring
Kicker Scenarios: In order to kick the entire beam into the ring on orbit would
require ~10 kjoules in 7 ns! We can kick in different parts of the beam and add them
together in analysis. This still would require a substantial kicker.
Proton beam Insertion. Pions produced in the gas would decay to muons. We need to study if enough muons are produced and captured by this method.
Muon (or pion) beam insertion. Bring in higher momentum (or ) to the outer edge of the ring and let them lose energy by dE/dx loss until it is captured on orbit and momentum by the rf.
This seems like the most promising approach at this moment. Simulation studies of this scheme need to be done.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
14
Conclusions
We have just successfully finished a phase I SBIR and have submitted a phase II SBIR. The phase I SBIR was to do a feasibility
study of this cooling ring which we have succeeded in doing.
The phase II SBIR will be to do an engineering study of this ring and to build a principle component such as a magnet.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
15
Backup Slides
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
16
Why a Small Cooling Ring? We would like to pursue a small muon cooling ring as a
demonstration experiment that we can afford to build. We have set as a goal to design a ring that should cost
about $5M. We are not sure that this precise cost will be achieved but we are choosing this as a guide.
We would like to obtain enough cooling so that it would be quite clear that we have actually cooled the beam.
We have just successfully finished a phase I SBIR and have submitted a phase II SBIR.
The phase I SBIR was to do a feasibility study of this cooling ring which we have succeeded in doing.
The phase II SBIR will be to do an engineering study of this ring and to build a principle component such as a magnet.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
17
Beam Dynamics Simulations
The storage ring was designed using SYNCH. ICOOL was used for particle tracking through the lattice taking into
account energy loss in the absorbers and energy recovery from the rf cavities.
A merit factor is used as a measurement of the cooling performance:
In this study decaying muons will be excluded for this merit factor since this is a demonstration and they can be corrected for.
Studies for some cooling ring variations have shown merit factors as high as 400.
The high merit factor solutions typically require aggressive parameters (~5T magnets, 45 MV/m rf or 100 bar H2 gas) which are beyond the needs of a demonstration.
F
i
F
i
F
i
z
z
y
y
x
xonTransmissiMerit
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
18
A Realistic Field Description Using Tosca The hard edge cooling simulations for the small cooling
ring have shown promising results yielding demonstrable cooling.
It is essential to examine the ring using fields from magnets that can actually be built. (This is more than merely obeying Maxwell’s equations.)
Tosca can supply fields from a coil and iron configuration. Tosca can provide field maps that can be used by ICOOL
and GEANT for tracking. Tosca can also track particles through the field it
generates. We can actually find the closed orbit in Tosca itself.
Since the closed orbit is in the x-z plane we need merely find the track which has x’=0 and x=0 after one turn. This is a 1 parameter minimization.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
19
History of Magnet Models That Have Been Used for This Cooling Ring: Coils Only Model
Advantages. Simple model gives a good
description of the field. Lattice parameters are
consistent with Synch Model. Edge focusing works well. Essentially no quadrupole
component inside magnet. Maximum field not constrained by
iron. Can design to higher fields. Disadvantages.
Spray flux over all space. Can insert entire cooling ring
into iron box for external shielding.
Need structural support system that is not ferro-magnetic.
Field Harmonics Along Path
B0 B1Edge Inside
MagnetReverse Field between Magnets
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
20
Magnets with Iron Yokes Iron magnets with flat poles.
We see very little reverse field between magnets.
We see less edge focusing than expected. We see a non-zero quadrupole component
present in the center of the magnet. Consequently the lattice parameters
obtained from this magnet do not agree with the design values from Synch.
Also we did not get as large a dynamic aperture as we had hoped.
I will discuss dynamic aperture later. This was the situation last December at Miami
There was a positive note. We did see cooling if we turned off the random processes. (Multiple scattering, straggling).
Field Harmonics along the Path Non-zero quad
inside magnetLess edge focusing
No return flux
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
21
Vertical Field for the Three Cases Compared The dynamic aperture that
we see appears to be limited by the field quality.
The figure shows By at y=0 in the vertical symmetry plane for three pole widths.
We would like a good field over 25 cm.
We have limited physical space due to RF cavity constraints.
The hard edge has a perfectly uniform transverse field profile by definition. This gives it a large dynamic aperture.
Comparison of Symmetry Plane Fields
-0.5
0
0.5
1
1.5
2
2.5
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6
Radius, m
By, t
esla
+-25
-25,+40
+-40
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
22
Using the Field Map We can produce a 3D field map from TOSCA.
We could build a GEANT model around this field map. I will discuss this later.
We have decided that we can provide a field to be used by ICOOL.
ICOOL works in a beam coordinate system. We know the trajectory of the reference path in the
global coordinate system. We can calculate the field and its derivatives along
this path. We can describe the field everywhere from this.
The limitation of this technique is that the field errors grow with radial distance from the reference path.
This could limit our computation of the dynamic aperture.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
23
Representation of the Field in a Curving Coordinate System Chun-xi Wang has a magnetic field
expansion formulism to represent the field in curved (Frenet-Serret) coordinate system.
This formulism is available in ICOOL.
Up-down symmetry kills off the an terms; bs is zero since there is no solenoid component in the dipole magnets.
The bn(s) are obtained by fitting
to the field in the midplane orthogonal to the trajectory at s
The field is obtained from a splining the field grid.
nny xsbsxB )(),(
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
24
Fourier Expansion of bn(s)
The bn(s) can be expanded with a Fourier series:
These Fourier coefficients can be fed to ICOOL to describe the field with the BSOL 4 option.
We use the bn for n=0 to 5.
T
sikN
knkn ecb
1
0,
T
sik
T
nnk esbT
c )(1
0
, where
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
25
Determining the Dynamic Aperture
For the x-Px (y-Py) phase space we launch n tracks, each track starting 1 cm apart along the x (y) axis.
The position in x-Px (y-Py) phase space is sampled after every cell.
The stable orbits form ellipses; the unstable ones have trajectories that are lost.
A measure of the size of the stable phase space is the number of rings.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
26
Horizontal Dynamic Aperture (x vs. px)Without Iron
My Hardedge model
Realistic Field Model Realistic Model with no sex
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
27
Vertical Dynamic Aperture (y vs. py)Without Iron
My Hardedge Model
Realistic Field ModelRealistic field w/ no sex
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
28
Dynamic Aperture with the Iron Yokewithout Pole Shaping
x vs. Pxy vs. Py
All harmonics
No sex and above
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
29
Dynamic Aperture with a Shaped Pole
Shaping the pole significantly increases the horizontal dynamic aperture.
It does not affect the vertical dynamic aperture. This can be done only by
Reducing the distance between magnets. This would also reduce the space allowed for the RF. We can’t afford to do that.
Reducing the vertical magnet aperture (gap). We will reduce it from 15 cm to 10 cm.
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
30
Summarizing Dynamic Aperture Plots
Below the size of the dynamic aperture is measured by counting rings. Each ring represents 1 cm spatial aperture.
Case x Px y Py x Px No High Order
y Py
No High Order
Hard Edge 12 14
Coils Only 5 4 8 7
Iron Flat Poles 6 5 7 5
Iron Shaped Poles 13 7
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
31
Cooling Results Using the Shaped Iron Poles
June 21, 2005 S. Kahn -- Small Muon Cooling Ring
32
How Well Does This Magnet Reproduce the SYNCH Lattice Description?
Min Beta vs Quadrupole
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1 1.2 1.4 1.6 1.8 2 2.2 2.4
Quadrupole Factor
Be
ta,
m Beta X
Beta Y
Synch Nominal Added Quad
x 99.88º 117.58º 101.68º
x 37.85 cm 27.01 cm 32.91 cm
x 0 -0.00315 -0.0039
y 92.63º 68.11º 94.95º
y 56.89 cm 81.96 cm 62.70º
y 0 0.00092 0.00180
Phase Advance vs Quad Factor
0
20
40
60
80
100
120
140
1 1.2 1.4 1.6 1.8 2 2.2 2.4
Quadrupole Factor
Mu
, d
eg
ree
s
Mu X
Mu Y
•The lattice parameters determined from transfer matrix for this storage ring with the nominal iron magnets has moved from the original SYNCH values.
•Adding quadrupole does seem to bring the lattice parameters closer to the SYNCH values
•So far we have merely scaled the quadrupole component. We need to modify the poles to include this quadrupole. This is in progress.