Upload
prabhjotkaur02
View
2.080
Download
1
Embed Size (px)
Citation preview
JOB AND CONTRACT COSTING
PREPARED BY: Prabhjot Kaur Ruchi Puri
Amanpreet Kaur Poonam Nimoria
Kanupriya Malhotra Mehak Jhamb
INDEX• JOB COSTING• CONTRACT COSTING• PRACTICAL QUESTION• DIFFERENCE• EMPLOYMENT OF JOB COSTING• APPLICATION OF JOB COSTING
JOB COSTINGCIMA defines it as:
“that form of specific order costing which applies when work is undertaken to customers’ special requirements and each order is of comparatively short duration (compared to those to which contract costing applies). The work is usually carried out within a factory or workshop and moved through processes and operations as a continuously identifiable unit. The term may also be applied to work such as property repairs and the method may be used in the costing of internal capital expenditure jobs.”
Features:
•Costs of materials, labor and overheads accumulated
•Profit or loss determined
•Costs are estimated and price is quoted
OBJECTIVES OF JOB COSTING•Finding out the cost of production•More accurate estimates about the cost•Control operational inefficiency
A system of job costing should be adopted after considering the following two factors:
A) Continuously identifiable (raw material stage ->stage of completion)
B) The system is very expensive
CONTRACT COSTING
According to CIMA, London
“ CONTRACT COSTING is that form of specific order costing which applies where work is undertaken to customer’s special requirements and each order is of long term duration.”
SPECIAL ASPECTS
MATERIALS
- Materials are specially purchased for a contract. - Any material returned to stores. - Sale of surplus material at contract site. - Contractee himself has supplied materials for
the contract.
CONTINUED….
LABOUR - Labour employed or working at site are treated
as direct labour.
PLANT - Plant specifically purchased for a contract. - The services of a particular plant are required
only for a short period.
COMMON TERMS IN CONTRACT COSTING
Escalation clause/material and labour variance clause A provision in a contract for adjustment in prices quoted and accepted, in the event of specified contingencies.Avoid future disputesSafeguarding principle for both contractor and contractee
Work certified and Payment-
• Progress payment• Certificate stating satisfactory progress by the contractee or his nominee • Retention money
TREATMENT Contractee’s account dr. To contract account (being the value of work certified) Bank account dr. To contractee’s account (being amount of cash received)
Second method
Work in progress account dr. To contract account (being the value of work certified)
Bank account dr. To contractee account (being cash received )
Work uncertified
Work done has not reached a stipulated stage at the end of a period:
Work in progress account dr. To contract account
Materials and stored at site
Unutilized material at the end of accounting period:
Material or site account dr. To contract account
Work-in-progress: It includes value of work certified & cost of work uncertified.
Balance sheet as on………….
ASSETS AMOUNT
Work in progress:Value of work certified XXX
Cost of work uncertified XXX
Less: Reserve for unrealised profit (XXX)
Less:Amount received from contractee(XXX)
XXXXX
Work-in-progress Account
Particulars Amt Particulars Amt
To Contract A/c:
Work certified
Work uncertified
XXX
XXX
By contract A/c
(Profit reserved)
By balance c/d
XXX
XXX
XXXX XXXX
Profit on incomplete contracts: Rules:-•When work certified is less than 1/4th of the contract price-No portion of profit will be transferred to P&L A/c.•When work certified is more than 1/4th of contract price but less than ½ of the contract price-
1/3rd of the profit disclosed should be taken to P&L A/c
• When work certified is more than ½ of the contract price-
2/3rd of the profit disclosed should be taken to P&L A/c
PROFIT ON COMPLETED CONTRACTS:-
Contratee's account is debited and Contract account is credited with contract price.
CONTRACT ACCOUNT for the year ended 31st March, 1994 DR. CR. PARTICULARS AMT
(Rs.)
PARTICULARS AMT
(Rs.)
To Materials issued to site
To Planning & Estimating
costs
To Direct wages paid 400000
Add: Wages due 27000
To Plant
To Plant hire charges
To Wage related costs
To Site office cost
To Head office expenses
To Direct expenses
To Profit T/F to
Profit & loss A/C 166200
Reserve 166200
750000
100000
427000
200000
175000
50000
67800
37500
90200
332400
2229900
By Plant at site
(200000 – 30000)
By Materials at site
By Materials returned
from site
By Work-in- Progress :
Work Certified 2000000
Work Uncertified 14900
170000
20000
25000
2014900
2229900
CONTRACTEE ACCOUNT
for the year ended 31st March ,1994
DR. CR .
PARTICULARS AMT
(Rs.)
PARTICULARS AMT
(Rs.)
To Balance c/d 1500000
1500000
By Bank A/C 1500000
1500000
EXTRACTS FROM BALANCE SHEET As on 31st March, 1994
LIABILITIES AMT
(Rs.)
ASSETS AMT
(Rs.)
Direct Wages Due 27000 Work-in-progress : Work Certified 2000000
Work Uncertified 14900
2014900
Less : Reserve 166200
1848700
Less: Cash 1500000
Received
Plant at site
Material at site
348700
170000
20000
DIFFERENCEJOB COSTING
Is carried in premises An order, unit, lot or batch of
product maybe taken as cost unit. Cost is first allocated to cost center
and then charged to individual jobs. It is a system of costing in which the elements of cost are accumulated separately for each job or work undertaken by an organization.
The process of jobs are fixed basing on the cost and policy of the firm.
The duration of job work is smaller. The value of job work would be
lesser
CONTRACT COSTING Contract work is carried out at site. Each contract is a cost unit. Most of the expenses are of direct
nature and are directly charged to respective contract accounts. Only general overheads and head office expenses are apportioned to individual contracts.
The pricing is generally through bidding and external forces have major influence in fixing the offer price.
Generally the contract work will take more time to complete.
The contract works is bigger in nature and the value of contract would also be higher.
Employment of Job CostingJob costing is employed (used) in the following
cases:- Where the production is against the order of the
customer or jobs are executed for different customers according to there specifications.
Where each job needs special treatment and no two orders are necessarily alike.
There is no uniformity in the flow of production from one department to another.
Where the work in progress differ from period to period basis of the number of jobs in hand.
Application of Job Costing
Job costing is applicable to printing, furniture, hardware, ship-building, heavy machinery, general engineering work, machinery tools, interior decoration, repairs and other similar work.
THANK YOU