© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw-Hill 6-1 Cost Flows and Job Costing Student Tutorial 6

Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

  • Upload
    dinhnga

  • View
    232

  • Download
    12

Embed Size (px)

Citation preview

Page 1: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-1

Cost Flows and JobCosting

Student Tutorial

6

Page 2: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-2

Evaluating Major Types of CostingSystems

vs.JobCosting

ProcessCosting

Each jobtreated as a

separate unitof output.Costs are

allocated toeach job.

Each jobtreated as a

separate unitof output.Costs are

allocated toeach job.

All unitsprocessed aretreated as theunit of output.

Costs areallocated toeach unit.

All unitsprocessed aretreated as theunit of output.

Costs areallocated toeach unit.

Operation Costing isa hybrid.

Operation Costing isa hybrid.

Page 3: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-3

The Basic Cost Flow Model

Job Cost + Resource - Resource = Job Cost

Beginning

Balance

Transfers

In

Transfers

Out

Ending

Balance(BB) (TI) (TO) (EB)

The use of the model serves as acontrol that helps to ensure goals

and objectives are met.

The use of the model serves as acontrol that helps to ensure goals

and objectives are met.

Page 4: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-4

Managing and Using Cost FlowInformation

Job CostRecord

A record of allthe costs (directand indirect) fora specific job.

A record of allthe costs (directand indirect) fora specific job.

The sum of allthe costs on all

the job costrecords =

The sum of allthe costs on all

the job costrecords =

Work-in-ProcessInventory

Page 5: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-5

Managing and Using Cost FlowInformation

Work-in-ProcessInventory

Representsthe cost of allthe unfinished(in-process)

jobs.

Representsthe cost of allthe unfinished(in-process)

jobs.

As jobs arecompleted, the

costs aremoved to . . .

As jobs arecompleted, the

costs aremoved to . . .

FinishedGoods

Inventory

Page 6: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-6

Managing and Using Cost FlowInformation - Example

Boss, Co. began May with $6,000 of costs inWork-in-Process (WIP) Inventory and $32,000

of completed units in Finished GoodsInventory. During May, Boss incurred

$86,000 of production costs. Goods costing$78,000 were sent to Finished Goods duringthe month. Also, during May, goods costing

$98,000 were sold.

Boss, Co. began May with $6,000 of costs inWork-in-Process (WIP) Inventory and $32,000

of completed units in Finished GoodsInventory. During May, Boss incurred

$86,000 of production costs. Goods costing$78,000 were sent to Finished Goods duringthe month. Also, during May, goods costing

$98,000 were sold.

Page 7: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-7

Managing and Using Cost FlowInformation - Example

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

Click Here to Review OriginalInformation

Make yourcomputationsand click on theanswer youthink is thecorrect one.

Page 8: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-8

Managing and Using Cost FlowInformation - Example

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

Click Here to Review OriginalInformation

Sorry, review therelationshipsand try again.

Page 9: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-9

Managing and Using Cost FlowInformation - Example

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

Click Here to Review OriginalInformation

Nope, that’s notright. Give itanother try.

Page 10: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-10

Managing and Using Cost FlowInformation - Example

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

Click Here to Review OriginalInformation

Uh oh! Maybeyou should giveit a little morethought. Thentry again.

Page 11: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-11

Managing and Using Cost FlowInformation - Example

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12000

D. $ 32,000

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12000

D. $ 32,000

Congratulations! You maynow proceed!

Work-in-Process

Beginning Balance $ 6,000 + Transfers In 86,000 – Transfers Out (78,000) = Ending Balance $ 14,000

Page 12: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-12

Managing and Using Cost FlowInformation - Example

Boss, Co. began May with $6,000 of costs inWork-in-Process (WIP) Inventory and $32,000

of completed units in Finished GoodsInventory. During May, Boss incurred

$86,000 of production costs. Goods costing$78,000 were sent to Finished Goods duringthe month. Also, during May, goods costing

$98,000 were sold.

Boss, Co. began May with $6,000 of costs inWork-in-Process (WIP) Inventory and $32,000

of completed units in Finished GoodsInventory. During May, Boss incurred

$86,000 of production costs. Goods costing$78,000 were sent to Finished Goods duringthe month. Also, during May, goods costing

$98,000 were sold.

Page 13: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-13

Managing and Using Cost FlowInformation - Example

What is the value of Finished GoodsInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

What is the value of Finished GoodsInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

Click Here to Review OriginalInformation

Make yourcomputationsand click on theanswer youthink is thecorrect one.

Page 14: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-14

Managing and Using Cost FlowInformation - Example

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

Click Here to Review OriginalInformation

Sorry, review therelationshipsand try again.

Page 15: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-15

Managing and Using Cost FlowInformation - Example

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

Click Here to Review OriginalInformation

Nope, that’s notright. Give itanother try.

Page 16: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-16

Managing and Using Cost FlowInformation - Example

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

Click Here to Review OriginalInformation

Uh oh! Maybeyou should giveit a little morethought. Thentry again.

Page 17: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-17

Managing and Using Cost FlowInformation - Example

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

What is the value of Ending Work-In-ProcessInventory?

A. $ 6,000

B. $ 14,000

C. $ 12,000

D. $ 32,000

Congratulations! You maynow proceed!

Finished Goods

Beginning Balance $ 32,000 + Transfers In 78,000 – Transfers Out (98,000) = Ending Balance $ 12,000

Page 18: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-18

Tracing and Assigning Costs to Jobs

ActualCosting?Actual

Costing?

BudgetedCosting?

BudgetedCosting?

NormalCosting?NormalCosting?

Page 19: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-19

Setting Predetermined Cost-DriverRates

Simple Process! Identify the higher-level activities to be

assigned to jobs.

"Estimate the costs supplied for higher-levelactivities.

#Select the cost-driver base(s).

$Estimate the amounts of the cost-driverbases identified in Step #3.

%Compute the predetermined cost-driver rate.

Simple Process! Identify the higher-level activities to be

assigned to jobs.

"Estimate the costs supplied for higher-levelactivities.

#Select the cost-driver base(s).

$Estimate the amounts of the cost-driverbases identified in Step #3.

%Compute the predetermined cost-driver rate.

Page 20: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-20

Using Predetermined Cost-DriverRates

Identify eachcost-driverbase for the

job.

Identify eachcost-driverbase for the

job.

Identify thecost-driver

rate for eachbase.

Identify thecost-driver

rate for eachbase.

Identify cost-driver baseamounts for

each cost-driverbase for the job.

Identify cost-driver baseamounts for

each cost-driverbase for the job.

××

Sum the cost-driver

amounts todeterminetotal cost

allocated tothe job.

Sum the cost-driver

amounts todeterminetotal cost

allocated tothe job.

Page 21: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-21

Using Predetermined Cost-DriverRates - Example

Bass, Inc. produces several jobs a year,and uses ABC to allocate costs to each

job. Bass generally works 10-hour days.Employees make $8 per hour on average

for a 2,000-hour work year.

As an exercise, compute thePredetermined Cost-Driver Rate for each

G&A Activity identified in the table.

Bass, Inc. produces several jobs a year,and uses ABC to allocate costs to each

job. Bass generally works 10-hour days.Employees make $8 per hour on average

for a 2,000-hour work year.

As an exercise, compute thePredetermined Cost-Driver Rate for each

G&A Activity identified in the table.

Page 22: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-22

G&S Activities

Total Activity

Cost Estimate

Cost-Driver Base

Estimates Base UnitsPredetermined

Cost-Driver Rate

Supervision $90,000 2,000 Hours Payroll

Processing36,000 360,000 Man-Hours

Insurance 15,000 $2,880,000 Labor $General

Accounting52,000 1,600

Jobs Worked

Office Occupancy

75,000 1,600Jobs

WorkedMiscellaneous 90,000 360,000 Man-Hours

Bass, Inc. General and Administrative Spending

Using Predetermined Cost-DriverRates - Example

?

Page 23: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-23

Using Predetermined Cost-DriverRates - Example

G&S Activities

Total Activity

Cost Estimate

Cost-Driver Base

Estimates Base UnitsPredetermined

Cost-Driver Rate

Supervision $90,000 2,000 Hours $45.000Payroll

Processing36,000 360,000 Man-Hours 0.100

Insurance 15,000 $2,880,000 Labor $ 0.005General

Accounting52,000 1,600

Jobs Worked

32.500

Office Occupancy

75,000 1,600Jobs

Worked46.875

Miscellaneous 90,000 360,000 Man-Hours 0.250

Bass, Inc. General and Administrative Spending

Page 24: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-24

G&A Activity

Job 1079 Cost-Driver

UnitsPredetermined

Cost-Driver Rate

G&A Cost Assigned to

Job 1079

Supervision 36 $45.000Payroll Processing 1,000.00 0.100

Insurance 8,000 0.005General Accounting 1 32.500Office Occupancy 1 46.875

Miscellaneous 1,000 0.250

Total G&A Costs Assigned to Job 1079

Using Predetermined Cost-DriverRates - Example

?

Job 1079 required 12 working days and the services of 10employees in 2,000 sq. ft. for those 12 days. Supervision time

was 3 hours per day. How much should we assign to Job 1079?

Page 25: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-25

Using Predetermined Cost-DriverRates - Example

Job 1079 required 12 working days and the services of 10employees in 2,000 sq. ft. for those 12 days. Supervision time

was 3 hours per day. How much should we assign to Job 1079?

G&A Activity

Job 1079 Cost-Driver

UnitsPredetermined

Cost-Driver Rate

G&A Cost Assigned to

Job 1079

Supervision 36 $45.000 $1,620.00Payroll Processing 1,000.00 0.100 100.00

Insurance 8,000 0.005 40.00General Accounting 1 32.500 32.50Office Occupancy 1 46.875 46.88

Miscellaneous 1,000 0.250 250.00

Total G&A Costs Assigned to Job 1079 $2,089.38

Page 26: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-26

Basic Job-Cost Flows

Job-cost accounting systemsrecord cost flows

systematically.

Job-cost accounting systemsrecord cost flows

systematically.

Transactionsare

journalized.

Info is postedto ledgeraccounts.

Overhead

Raw Materials

Gen'l & Admin

Labor

Page 27: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-27

Basic Job-Cost Flows

Accounts related to Jobsare posted to various Job

WIP accounts.

Accounts related to Jobsare posted to various Job

WIP accounts.

Overhead

Raw Materials

Gen'l & Admin

Labor

Job 1 - WIP

Job 2 - WIP

Job 3 - WIP

Page 28: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-28

Basic Job-Cost Flows

Three events can trigger theposting of info from the job cost

record to WIP- Summary:

1. Completion of a Job

2. Sale of a Job

3. End of an accounting period.

Three events can trigger theposting of info from the job cost

record to WIP- Summary:

1. Completion of a Job

2. Sale of a Job

3. End of an accounting period.

Job 1 - WIP

Job 2 - WIP

Job 3 - WIP

WIP - Summary

Page 29: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-29

Completion of Jobs

As stated earlier, costs then move from WIP toFinished Goods and then to COGS.

As stated earlier, costs then move from WIP toFinished Goods and then to COGS.

Finished Goods

COGS

Job 1 - WIP

Job 2 - WIP

Job 3 - WIP

WIP - Summary

Page 30: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-30

Remember, theoverhead

assigned to theWIP was anESTIMATE.

Actual overheadmay differ from

the estimate.

Remember, theoverhead

assigned to theWIP was anESTIMATE.

Actual overheadmay differ from

the estimate.

Overhead Adjustments

Finished Goods

COGS

WIP - Summary

Page 31: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-31

The amountstransferred fromWIP to FinishedGoods include:

•Direct material

•Direct labour

•AssignedOverhead

The amountstransferred fromWIP to FinishedGoods include:

•Direct material

•Direct labour

•AssignedOverhead

Overhead Adjustments

Finished Goods

COGS

WIP - Summary

Page 32: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-32

Overhead Adjustments - Example

Which of the following is included in theamount transferred from Work-In-Process to

Finished Goods Inventory?

A. Direct labour

B. Direct Materials

C. Manufacturing Overhead

D. All of the Above

Which of the following is included in theamount transferred from Work-In-Process to

Finished Goods Inventory?

A. Direct labour

B. Direct Materials

C. Manufacturing Overhead

D. All of the Above

Page 33: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-33

Which of the following is included in theamount transferred from Work-In-Process to

Finished Goods Inventory?

A. Direct labour

B. Direct Materials

C. Manufacturing Overhead

D. All of the Above

Which of the following is included in theamount transferred from Work-In-Process to

Finished Goods Inventory?

A. Direct labour

B. Direct Materials

C. Manufacturing Overhead

D. All of the Above

Overhead Adjustments - Example

Sorry, try again.

Page 34: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-34

Which of the following is included in theamount transferred from Work-In-Process to

Finished Goods Inventory?

A. Direct labour

B. Direct Materials

C. Manufacturing Overhead

D. All of the Above

Which of the following is included in theamount transferred from Work-In-Process to

Finished Goods Inventory?

A. Direct labour

B. Direct Materials

C. Manufacturing Overhead

D. All of the Above

Overhead Adjustments - Example

Nope, give itanother try.

Page 35: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-35

Which of the following is included in theamount transferred from Work-In-Process to

Finished Goods Inventory?

A. Direct labour

B. Direct Materials

C. Manufacturing Overhead

D. All of the Above

Which of the following is included in theamount transferred from Work-In-Process to

Finished Goods Inventory?

A. Direct labour

B. Direct Materials

C. Manufacturing Overhead

D. All of the Above

Overhead Adjustments - Example

Uh oh! Maybeyou should try

again.

Page 36: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-36

Which of the following is included in theamount transferred from Work-In-Process to

Finished Goods Inventory?

A. Direct labour

B. Direct Materials

C. Manufacturing Overhead

D. All of the Above

Which of the following is included in theamount transferred from Work-In-Process to

Finished Goods Inventory?

A. Direct labour

B. Direct Materials

C. Manufacturing Overhead

D. All of the Above

Overhead Adjustments - Example

Congratulations!You may now

proceed!

Congratulations!You may now

proceed!

Page 37: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-37

Reconciling Overhead Spending andApplication

Job 2 - WIP

We can determine DirectMaterials Cost and Direct

labour Cost for a Job as wedo the work.

We can determine DirectMaterials Cost and Direct

labour Cost for a Job as wedo the work.

But we won’t know actual OverheadCost until the end of the accountingperiod, so we apply overhead to thejob using the Predetermined Cost-

Driver Rates.

But we won’t know actual OverheadCost until the end of the accountingperiod, so we apply overhead to thejob using the Predetermined Cost-

Driver Rates.

Page 38: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-38

Reconciling Overhead Spending andApplication

Job 2 - WIP

Each time we assign overhead to ajob, we Debit the Job and Credit the

Overhead Control account.

Each time we assign overhead to ajob, we Debit the Job and Credit the

Overhead Control account.

Overhead Control

Debit

.

.

Credit

Page 39: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-39

A/P or Cash

Reconciling Overhead Spending andApplication

When overhead costs are actuallyincurred, Debit the Overhead Control

account and Credit the AccountsPayable (or Cash) account.

When overhead costs are actuallyincurred, Debit the Overhead Control

account and Credit the AccountsPayable (or Cash) account.

Overhead Control

Credit

.

Debit

.

Page 40: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-40

Reconciling Overhead Spending andApplication

Overhead Control

The difference betweenactual overhead for theperiod, and estimated

overhead for the periodis called the

OVERHEAD VARIANCE.

The difference betweenactual overhead for theperiod, and estimated

overhead for the periodis called the

OVERHEAD VARIANCE.

Page 41: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-41

Reconciling Overhead Spending andApplication

Overhead Control

The difference betweenactual overhead for theperiod, and estimated

overhead for the periodis called the

OVERHEAD VARIANCE.

The difference betweenactual overhead for theperiod, and estimated

overhead for the periodis called the

OVERHEAD VARIANCE.

Write off theimmaterial

difference toCOGS.

Write off theimmaterial

difference toCOGS.

Page 42: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-42

Reconciling Overhead Spending andApplication

The OVERHEADVARIANCE isseparated into

twocomponents.

The OVERHEADVARIANCE isseparated into

twocomponents.

Page 43: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-43

Reconciling Overhead Spending andApplication

The OVERHEADVARIANCE isseparated into

twocomponents.

The OVERHEADVARIANCE isseparated into

twocomponents.

Overhead SpendingVariance (or Budget

Variance)

Overhead ActivityVariance (or Volume

Variance)

Page 44: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-44

Reconciling Overhead Spending andApplication

We compare theActual

Overhead toEstimated

Overhead(alsocalled Applied

Overhead)

We compare theActual

Overhead toEstimated

Overhead(alsocalled Applied

Overhead)

Page 45: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-45

Reconciling Overhead Spending andApplication

We compare theActual

Overhead toEstimated

Overhead(alsocalled Applied

Overhead)

We compare theActual

Overhead toEstimated

Overhead(alsocalled Applied

Overhead)

Actual > EstimatedOverhead is

UNDERAPPLIED

Actual < EstimatedOverhead is

OVERAPPLIED

Page 46: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-46

Job Cost and Project Improprieties

The following conditions canlead to improper job costing:

& Misstating the stage ofcompletion.

& Charging costs to the wrongJob.

& Misrepresenting the cost of jobs.& Intentional misrepresentation in

contracts.

The following conditions canlead to improper job costing:

& Misstating the stage ofcompletion.

& Charging costs to the wrongJob.

& Misrepresenting the cost of jobs.& Intentional misrepresentation in

contracts.

Page 47: Cost Flows and Job Costing - McGraw-Hill Education … ·  · 2004-12-16Cost Flows and Job Costing ... Evaluating Major Types of Costing Systems vs. Job Costing Process Costing Each

© The McGraw-Hill Companies, Inc., 2000Irwin/McGraw-Hill

6-47

End of Chapter 6

Work-in-Process canbe a special

thing.