Project Overview
The Jervis Pump Station helps to safely move wastewater from the City of Vancouver to the Iona Island Wastewater Treatment Plant. Construction will begin in 2019 and will involve adding a back-up power supply to the existing pump station to provide a reliable supply during power outages.
Construction will take approximately eight months and will require the existing building at Sunset Beach Park to be expanded.
Metro Vancouver is working closely with Vancouver Park Board staff to ensure that design of the new and old building is well integrated into the surroundings. The design will enhance the experience of visitors at this location while preserving the natural beauty of the park. An increased amount of seating facing the water will allow a greater number of park users to stop and enjoy the view.
This spring, there will be a number of opportunities for the public to provide feedback on the proposed building design and on ways Metro Vancouver can minimize construction impacts.
Location of new generator building.
PARKING
Existing JervisPump Station
SUNSET BEACHPARK
ENGLISH BAY
Beach Ave
Jerv
is St
Pacific Ave
Seawall
New Building
Construction
2019
PublicConsultation
Vancouver Park BoardApproval
Detailed Design and Other Permitting
Spring 2018 Fall 2018 Fall 2018 – 2019
Timeline
JERVIS PUMP STATION UPGRADE June 2018
Metro Vancouver is upgrading the Jervis Pump Station to protect public health and the environment. Metro Vancouver plays an essential role in providing safe, effi cient conveyance and treatment of wastewater for over 2.5 million people in the Lower Mainland. Operating this vast liquid waste system requires ongoing upgrades, improvements, and maintenance.
MARCH 201 7LIQUID WASTE
To provide feedback on this project, take part in our online survey.
See reverse for more information.
Project UpdatesFor additional information on this project, please visit www.metrovancouver.org and search: “Jervis Pump Station”.
Contacting Metro VancouverMetro Vancouver Information Centre: 604-432-6200 (Monday to Friday from 8 a.m. to 4:30 p.m.)
After Hours Emergency: 604-451-6610
Email: [email protected] (Please include“Jervis Pump Station” in the subject line)
@MVRoadwork
Give Us Your FeedbackTo provide feedback on this project, please view our online display panels and take part in our survey. To access the survey, visit www.metrovancouver.org and search “Jervis Pump Station”.
Construction Activities
Associated construction impacts may include:
• construction vehicles in the area
• survey work in the area
• noise
Work HoursWork will generally occur between Monday to Saturday from 7:00 a.m. to 8:00 p.m. and Sunday 10:00 a.m. to 8:00 p.m. However, there may be times when crews will need to work longer hours or on weekends to complete certain sections of work. Residents will receive notifications if longer work hours are required.
Construction will be limited to the months of September 2019 to May 2020 to avoid peak park visitor season.
Our Commitment to You
Metro Vancouver is committed to minimizing the impacts of this project on the surrounding community. As part of our commitment Metro Vancouver will:
• Work with residents, businesses and park users to identify potential project impacts and gather feedback on the proposed design of the facility
• Provide multiple opportunities for the community to provide input, including online surveys and information tents along the seawall
• Develop and implement a traffic management plan to ensure pedestrian, cyclist and vehicle access around the construction area are not significantly interrupted
• Provide a Community Liaison Officer to respond to questions and concerns
• Provide regular project updates via newsletters and web updates
Proposed new design of the Jervis Pump Station facing northeast.