Upload
damir-ramazanov
View
216
Download
0
Embed Size (px)
Citation preview
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
1/28
Using @RISK in Cost RiskAnalysis
Javier Ordez, Ph.D.Director of Custom SolutionsPalisade Corporation
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
2/28
Outline
Introduction
Background
Project Performance Record
Definitions
Cost Risk Analysis
Correlation Schedule Integration
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
3/28
Introduction
Most projects are conducted in a changing environment;
this makes the schedule and cost analysis difficult in the
early stages.
Traditionally, cost and duration estimates are point
estimates. Estimation based on the most likely values.
It is necessary to study uncertainties involved in the
project
.
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
4/28
Project Performance Record
Project Success (RMC Project Management) Only 28% of all projects succeed Time to market can be improved by 65%
Projects can be completed in 50% of the time
IT Projects (Chaos Report) 31% of project cancelled before completion 53% of projects will cost 189% of their original
estimate
Average time overrun is 222% Average project success is 16.2% (software
projects)
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
5/28
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
6/28
Background: PRA Adoption in Federal &State Agencies
Federal Transit Administration (FTA) requires a riskassessment/mitigation study for any new transit project applying forfederal funding
Department of Transportation of the State of Washington (WSDOT)has a risk-based approach to validate cost estimates
OMB Capital Programming Guide, 2007: Risk Adjusted Budget andSchedule (ANSI/EIA Standard 748)
DoD Integrated Master Plan and Integrated Master SchedulePreparation and Use Guide: Schedule Risk Analysis
Risk Management Guide for DoD Acquisition (2003)
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
7/28
Definitions: Project Risk & Uncertainty
Project risk is defined as the possibility that the outcomeofan uncertain eventaffects negatively or positively the costand time performance of project activities and/or theirplanned execution
Risk = Consequence x Probability of Occurrence
Uncertainty is defined as the lack of knowledge about the
parameters that characterize the system
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
8/28
Project Budgeting
Typically budgets are deterministic
Simulation Approach Individual cost components are unimodal and skewed
Common use of 3 point estimate and triangular, beta,lognormal distributions
Model cost items prone to variation with suitablestatistical distributions
Generate random numbers hundred of timesaccording to specified distributions and calculate total
cost Total cost dist is used to calculate probability of cost
overrun and to establish adequate contingencies
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
9/28
9
Triangular DistributionsDescription
Used when minimum,maximum, and most likelyvalues are known.
Used when high and lowthresholds are of equal
distance to expectedoutcome.
Easy to calculate andgenerate, but limited abilityto accurately model real-
world estimates.Examples
Product pricing
Cost to manufacture
Most likely (mode) Minimum & maximum values Shift (optional)
Inputs
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
10/28
10
PERT DistributionsDescription
Alternative to Triangular
Same 3 parameters, butuses smooth curvedeemphasizes tails
Provides most-likely caserather than extreme values
Describes outlying impactsmore realistically
Examples
Product pricing
Manufacturing costs
Sales volumes
Raw material pricing
Most likely (mode) Minimum & maximum values Shift (optional)
Inputs
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
11/28
11
Triangular vs. PERTDistributions
Comparison
More closely resemblesrealistic probability distribution.
Provides close fit to normal orlognormal distributions
Like the Triangular distribution,emphasizes most likely value
over minimum and maximumestimates.
Unlike Triangular, proves asmooth curve thatprogressively emphasizesvalues around (near) the mostlikely, over values around
edges. Can trust estimate for most
likely value. Even if it notexactly accurate, will be close.
Produces a curve similar toNormal, without knowingprecise parameters.
Triangular distributions are fine for symmetrical data PERT more accurately depicts normal distributions Use PERT when the min, max, and most likely are known
Key Takeaways
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
12/28
Risks Events vs. Uncertainty
Probability
$ o Time
Risk Events ImpactsUncertainty
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
13/28
Qualitative Risk Analysis
1 2 3 4 5
1
2
3
4
5
Likelihood
Consequence
Likelihood ScoreNot Likely 1
Low
Likelihood 2
Likely 3
High Likely 4
Near
Certainty 5
Schedule Cost Technical Score
Minimal or no impact Minimal or no impact Minimal or no impact 1
Additional activities required; able to meet
key datesBudget increase
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
14/28
Binomial DistributionsDescription
RiskBinomial(n,p) = probabilityof achieving certain number ofsuccesses in nindependenttrials, where probability ofsuccess for each trial is p, andeach trial has only two possible
outcomes (success or fail)
Describes the outcome of aseries of trials that can only bea success or failure.
As the average increases, theprofile approaches the Normaldistribution. Under someconditions, you can use theNormal distribution as anapproximation.
n = number of outcomes p = probability of each outcomes occurrence
Min, max & shift (optional)
Inputs
Examples
Heads or tails in coin tosses
Occurrence of a risk event14
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
15/28
RiskCompoundFunction
It uses two distributions to create a single new inputdistribution.
The first argument specifies the number of samples whichwill be drawn from the distribution entered in the secondargument.
For example, the function:
RiskCompound(RiskPoisson(5),RiskLognorm(10000,10000))
It would be used in the insurance industry where the frequency or
number of claims is described by RiskPoisson(5) and the severityof each claim is given by RiskLognorm(10000,10000).
15
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
16/28
Contingency calculation w/o PRA The percentage figure is, most likely, arbitrarily arrived at and not
appropriate for the specific project.
There is a tendency to double count risks because some estimators
are inclined to include contingencies in their best estimate.
A percentage addition still results in a single-figure prediction of
estimated cost, implying a degree of certainty that is simply not
justified.
The percentage added indicates the potential for detrimental or
downside risk; it does not indicate any potential for cost reduction and
may therefore hide poor management of the execution of the project.
Because the percentage allows for all risk in terms of a costcontingency, it tends to direct attention away from time, performance,
and quality risks.
It does not encourage creativity in estimating practice, allowing it to
become routine and mundane, which can propagate oversights.
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
17/28
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
18/28
Correlation and
Interdependence Variables move together
Positive vs. Inverse relationship
Predictive sampling (magnitude)
Correlation coefficient
Calculating rho r
Methodology (rank vs. data)
Impact
Comparing effect on m vs. s18
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
19/28
19
Correlation Characteristics
Variables must relate to each other in some manner
Correlations are often calculated from actual historical data
Correlation coefficients range between -1 and 1
0 = no relationship
-1 = complete inverse correlation
1 = complete positive correlation
Variables without correlation create non-realistic situations
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
20/28
20
Correlation Concept
Measures the degree of associationbetween 2 variables
y
x
r = -1
y
x
r = 1y
x
r = 0
y
x
r = -.8
y
x
r = .8
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
21/28
Cost Correlation Issues
If correlation is ignored the total cost variance is
underestimated
Data limitations during planning stages of mostengineering projects
Correlation between variables makes use of historical
data or subjective estimation from experts
Relationship between variables are shaped by manyuncontrollable factors, and are best at subjectiveestimates based on experience and judgment
PDF that cost estimator specifies is the marginaldistribution of that cost item; if cost items arecorrelated, the joint density function of the cost itemsneeds to be calculated
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis
22/28
Correlation Effects
S-Curve for Correlated and Not
Correlated Durations
0.00.10.20.30.4
0.50.60.70.80.91.0
11/1
11/14
11/27
12/11
12/24
1/7
1/20
2/2
2/16
3/1
Date
Prob
Value