28
8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis http://slidepdf.com/reader/full/javier-ordonez-using-risk-in-cost-risk-analysis 1/28 Using @RISK in Cost Risk Analysis Javier Ordóñez, Ph.D. Director of Custom Solutions Palisade Corporation

Javier Ordonez - Using @RISK in Cost Risk Analysis

Embed Size (px)

Citation preview

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    1/28

    Using @RISK in Cost RiskAnalysis

    Javier Ordez, Ph.D.Director of Custom SolutionsPalisade Corporation

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    2/28

    Outline

    Introduction

    Background

    Project Performance Record

    Definitions

    Cost Risk Analysis

    Correlation Schedule Integration

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    3/28

    Introduction

    Most projects are conducted in a changing environment;

    this makes the schedule and cost analysis difficult in the

    early stages.

    Traditionally, cost and duration estimates are point

    estimates. Estimation based on the most likely values.

    It is necessary to study uncertainties involved in the

    project

    .

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    4/28

    Project Performance Record

    Project Success (RMC Project Management) Only 28% of all projects succeed Time to market can be improved by 65%

    Projects can be completed in 50% of the time

    IT Projects (Chaos Report) 31% of project cancelled before completion 53% of projects will cost 189% of their original

    estimate

    Average time overrun is 222% Average project success is 16.2% (software

    projects)

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    5/28

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    6/28

    Background: PRA Adoption in Federal &State Agencies

    Federal Transit Administration (FTA) requires a riskassessment/mitigation study for any new transit project applying forfederal funding

    Department of Transportation of the State of Washington (WSDOT)has a risk-based approach to validate cost estimates

    OMB Capital Programming Guide, 2007: Risk Adjusted Budget andSchedule (ANSI/EIA Standard 748)

    DoD Integrated Master Plan and Integrated Master SchedulePreparation and Use Guide: Schedule Risk Analysis

    Risk Management Guide for DoD Acquisition (2003)

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    7/28

    Definitions: Project Risk & Uncertainty

    Project risk is defined as the possibility that the outcomeofan uncertain eventaffects negatively or positively the costand time performance of project activities and/or theirplanned execution

    Risk = Consequence x Probability of Occurrence

    Uncertainty is defined as the lack of knowledge about the

    parameters that characterize the system

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    8/28

    Project Budgeting

    Typically budgets are deterministic

    Simulation Approach Individual cost components are unimodal and skewed

    Common use of 3 point estimate and triangular, beta,lognormal distributions

    Model cost items prone to variation with suitablestatistical distributions

    Generate random numbers hundred of timesaccording to specified distributions and calculate total

    cost Total cost dist is used to calculate probability of cost

    overrun and to establish adequate contingencies

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    9/28

    9

    Triangular DistributionsDescription

    Used when minimum,maximum, and most likelyvalues are known.

    Used when high and lowthresholds are of equal

    distance to expectedoutcome.

    Easy to calculate andgenerate, but limited abilityto accurately model real-

    world estimates.Examples

    Product pricing

    Cost to manufacture

    Most likely (mode) Minimum & maximum values Shift (optional)

    Inputs

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    10/28

    10

    PERT DistributionsDescription

    Alternative to Triangular

    Same 3 parameters, butuses smooth curvedeemphasizes tails

    Provides most-likely caserather than extreme values

    Describes outlying impactsmore realistically

    Examples

    Product pricing

    Manufacturing costs

    Sales volumes

    Raw material pricing

    Most likely (mode) Minimum & maximum values Shift (optional)

    Inputs

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    11/28

    11

    Triangular vs. PERTDistributions

    Comparison

    More closely resemblesrealistic probability distribution.

    Provides close fit to normal orlognormal distributions

    Like the Triangular distribution,emphasizes most likely value

    over minimum and maximumestimates.

    Unlike Triangular, proves asmooth curve thatprogressively emphasizesvalues around (near) the mostlikely, over values around

    edges. Can trust estimate for most

    likely value. Even if it notexactly accurate, will be close.

    Produces a curve similar toNormal, without knowingprecise parameters.

    Triangular distributions are fine for symmetrical data PERT more accurately depicts normal distributions Use PERT when the min, max, and most likely are known

    Key Takeaways

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    12/28

    Risks Events vs. Uncertainty

    Probability

    $ o Time

    Risk Events ImpactsUncertainty

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    13/28

    Qualitative Risk Analysis

    1 2 3 4 5

    1

    2

    3

    4

    5

    Likelihood

    Consequence

    Likelihood ScoreNot Likely 1

    Low

    Likelihood 2

    Likely 3

    High Likely 4

    Near

    Certainty 5

    Schedule Cost Technical Score

    Minimal or no impact Minimal or no impact Minimal or no impact 1

    Additional activities required; able to meet

    key datesBudget increase

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    14/28

    Binomial DistributionsDescription

    RiskBinomial(n,p) = probabilityof achieving certain number ofsuccesses in nindependenttrials, where probability ofsuccess for each trial is p, andeach trial has only two possible

    outcomes (success or fail)

    Describes the outcome of aseries of trials that can only bea success or failure.

    As the average increases, theprofile approaches the Normaldistribution. Under someconditions, you can use theNormal distribution as anapproximation.

    n = number of outcomes p = probability of each outcomes occurrence

    Min, max & shift (optional)

    Inputs

    Examples

    Heads or tails in coin tosses

    Occurrence of a risk event14

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    15/28

    RiskCompoundFunction

    It uses two distributions to create a single new inputdistribution.

    The first argument specifies the number of samples whichwill be drawn from the distribution entered in the secondargument.

    For example, the function:

    RiskCompound(RiskPoisson(5),RiskLognorm(10000,10000))

    It would be used in the insurance industry where the frequency or

    number of claims is described by RiskPoisson(5) and the severityof each claim is given by RiskLognorm(10000,10000).

    15

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    16/28

    Contingency calculation w/o PRA The percentage figure is, most likely, arbitrarily arrived at and not

    appropriate for the specific project.

    There is a tendency to double count risks because some estimators

    are inclined to include contingencies in their best estimate.

    A percentage addition still results in a single-figure prediction of

    estimated cost, implying a degree of certainty that is simply not

    justified.

    The percentage added indicates the potential for detrimental or

    downside risk; it does not indicate any potential for cost reduction and

    may therefore hide poor management of the execution of the project.

    Because the percentage allows for all risk in terms of a costcontingency, it tends to direct attention away from time, performance,

    and quality risks.

    It does not encourage creativity in estimating practice, allowing it to

    become routine and mundane, which can propagate oversights.

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    17/28

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    18/28

    Correlation and

    Interdependence Variables move together

    Positive vs. Inverse relationship

    Predictive sampling (magnitude)

    Correlation coefficient

    Calculating rho r

    Methodology (rank vs. data)

    Impact

    Comparing effect on m vs. s18

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    19/28

    19

    Correlation Characteristics

    Variables must relate to each other in some manner

    Correlations are often calculated from actual historical data

    Correlation coefficients range between -1 and 1

    0 = no relationship

    -1 = complete inverse correlation

    1 = complete positive correlation

    Variables without correlation create non-realistic situations

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    20/28

    20

    Correlation Concept

    Measures the degree of associationbetween 2 variables

    y

    x

    r = -1

    y

    x

    r = 1y

    x

    r = 0

    y

    x

    r = -.8

    y

    x

    r = .8

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    21/28

    Cost Correlation Issues

    If correlation is ignored the total cost variance is

    underestimated

    Data limitations during planning stages of mostengineering projects

    Correlation between variables makes use of historical

    data or subjective estimation from experts

    Relationship between variables are shaped by manyuncontrollable factors, and are best at subjectiveestimates based on experience and judgment

    PDF that cost estimator specifies is the marginaldistribution of that cost item; if cost items arecorrelated, the joint density function of the cost itemsneeds to be calculated

  • 8/6/2019 Javier Ordonez - Using @RISK in Cost Risk Analysis

    22/28

    Correlation Effects

    S-Curve for Correlated and Not

    Correlated Durations

    0.00.10.20.30.4

    0.50.60.70.80.91.0

    11/1

    11/14

    11/27

    12/11

    12/24

    1/7

    1/20

    2/2

    2/16

    3/1

    Date

    Prob

    Value