Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
ITC Midwest Partners in Business
ITC Midwest Partners in Business
May 7, 2009Iowa State University
Scheman Building
Welcome!Welcome!
Mike DabneyManager – Stakeholder Relations
ITC Midwest
3
Facility and Meeting AccommodationsFacility and Meeting Accommodations
Registration for meeting: Sign in….Win a PRIZE
Rest Room Locations:
Cell Phone – on stun or vibrate
Lunch – Menu
Partners in Business: Web Site Located at www.itctransco.com
4
ITC Midwest ManagementITC Midwest Management
Manager OverviewDoug Collins-Executive Director
Jeff Eddy, Manager – Planning
Ken Cackoski, Manager – Design Engineering
Dwayne Boelter, Manager – Project Engineering
Terry Gucciardo, Manager – Asset Care
Lisa Stump/Dave Grover, Manager – Regulatory Strategy
Dick Coeur, General Manager – Community and Customer Relations
Tom Petersen, Director – Communications
Mike Dabney, Manager-Stakeholder Relations
5
Project timing and overviewsProject timing and overviews
While the following slides identify general timetables for line and substation construction projects, several factors could impact the company’s ability to complete projects according to those timetables.
Those factors include, but are not limited to, regulatory approvals, access to construction resources, availability of materials, and even weather.
The dates and schedules identified in these slides represent our best estimates for projects to be initiated and completed, but please understand that many factors could alter those schedules.
Green Power ExpressGreen Power Express
Doug CollinsExecutive Director
ITC Midwest
7
Green Power ExpressGreen Power Express
Population Centers
Green Power Express
Potential Future Collector System
• 3,000 miles 765 kV
• 10-12 GW transfer capacity to support approximately 20 GW of new wind generation
• Crosses 7 states, 20 utility service territories, 2 RTOs and non RTO areas
• Expected cost of $10-12 billion
Why GPE and Why Now?Why GPE and Why Now?
9
President Obama’s VisionPresident Obama’s Vision
“One of… the most important infrastructure projects that we need is a whole new electricity grid. … if we’re going to be serious about renewable energy, I want to be able to get wind power from North Dakota to population centers, like Chicago.”
Source: Transcript from appearance on Rachael Maddow Show of October 28, 2008: http://www.msnbc.msn.com/id/27464980/.
10
Timing of Filing - Why GPE Now?Timing of Filing - Why GPE Now?
Over a year of internal study prior to filing— Submitted to MTEP; to be studied in RGOS in compliance with
Order 890— Discussions with developers and stakeholders ongoingInitiated by federal policy discussions— Private capital is available for major transmission investmentFinancial disclosure and competitive considerationsRegional planning initiatives (UMTDI, RGOS, JCSP, CARP/RECB)— ITC supports these efforts— Timing concerns— Studies do not build transmissionState of current project evaluation and cost allocation criteria— Not conducive to regional project to move renewable sources
11
Facilitates the movement of large amounts of high efficiency wind throughout the footprintReduces carbon emissions by approximately 37 million metric tons annually, equivalent to seven to ten 600 MW coal plants or nine to twelve million automobilesLargely resolves Midwest ISO generation interconnection queue issues for regionEfficient use of landAddresses concerns with system congestion as wind comes onlineIncreases electric reliability
Green Power Express BenefitsGreen Power Express Benefits
12
Benefits: Competitive Fuel PricesBenefits: Competitive Fuel Prices
Source: The Brattle Group
Levelized All-In Costs for New Capacity in MAPP(Excluding Firming, Storage, and Transmission Costs)
$525
$0
$25
$50
$75
$100
$125
$150
$175
$475
$500$501.7
$145.3
$162.5
$98.3 $84.6
$87.5
$66.7$82.4$76.8$72.8
$98.6 $71.2
$50.4
Biomass CC Adv. CC Conv. Coal CT Adv. CT Conv. CoalSeq.
Nuclear PV Wind(32% c.f.)
Wind(42% c.f.)
2008
$/M
Wh
CO2 Cost
Fuel Costs
VOM
FOM
Capital Costs
Total with PTC
Non-dispatchable - may need additional storage and firming
Dispatchable - no firming required
13
765 kV provides greatest capacity increases with least land consumption— One 765 kV facility can carry as
much power as six 345 kV lines— Reduced right-of-way lowers cost as
well as impacts to consumers and environment
Supports competitive markets, reliability, and renewable energy development
Power carried greater distances and facilitates renewable resources market
Availability is greater than 99% of the time
“On-ramps” and “off-ramps” provide for easy generation connections and future transmission integration
Why 765kV instead of 345kV?Why 765kV instead of 345kV?
VS
14
DC is a good technology for certain applications, namely point to point without off ramps— GPE has a number of pick-up and drop-
off points for power along the pathDC does not allow for easy redirection of power in the case of a line outage— Could make system vulnerable from a
reliability standpoint if used as a first step— May require a significant system belowDC overlays may be required in the Eastern Interconnect once a robust backbone system exists to accommodate renewable development
Why Not DC for GPE?Why Not DC for GPE?
15
State/Federal Rules and Contractual Rights
Underlying system planning— ITC will support incumbent to
address planning concerns and submit to RTO
— Substation location and other planning items
— Strong backbone to build on to support future development on local utility system
Local Siting Issues— Local color on approaches to siting,
including location
Partnership Structure— Must be developed in a way that
maintains independence
Working with Local UtilitiesWorking with Local Utilities
16
Lack of Federal Policy Direction— Federal RPS— CO2 Policy— FERC role in siting
Planning Processes— Regional approaches
(UMTDI, RGOS, JCSP— Timing— RTO metrics
Cost Allocation— RECBTF— CARP/OMS— Current Structures
What Else Has to be Addressed? What Else Has to be Addressed?
17
FERC Order on GPE – April 10, 2009FERC Order on GPE – April 10, 2009
Approved the following incentives as in line with the project risks:
— Regulatory assetApproved effective April 11, 2009 and January 1 each year for subsequent year205 filing required to show prudence and just and reasonableness
— CWIPCompliance filing for authorization to include in rates required at least 60 days prior to requested effective date
— Abandoned plantMust file future 205 to show costs are just and reasonable and identify the cost allocation method that will be applied
— Hypothetical capital structure
60 percent equity and 40 percent debt until any portion of the project is placed in service
ROE - approved total ROE of 12.38%, which includes 100 points for independence, 10 points for scope of project, and 50 points for RTO participation which is effective when entity becomes an RTO member and places project under RTO operational control
Formula rate and protocols – set for hearing and subject of ongoing settlement discussions
Requires filings on partnership structure as development occurs to ensure independence is maintained
18
Green Power Express ActivitiesGreen Power Express Activities
Future activities include the following:— Negotiations with potential partners and gathering of input from
incumbent utilities and stakeholders— Participation in MISO regional planning studies— Implementation of a multi-regional cost allocation mechanism— Routing studies, EIS, and preliminary engineering— Application for transmission line siting in accordance with existing state
protocols— Detailed design of the first phase of the project, including right-of-way
acquisition and ordering of long-lead items— Construction
• Phase 1 can be placed in service in as little as 2 to 3 years from when construction begins
19
The GPE is a project conceived by ITC to reach the wind-rich areas of the upper Midwest with extra-high voltage transmission — The GPE aligns with the development of renewable resources— The GPE supports a national energy vision for the development of
renewable resourcesGPE integrates with other Regional planning processes and visions:— MISO Planning processes (e.g., MTEP)— National green energy vision — Joint Coordinated System Plan (JCSP) transmission overlay for a
20% Renewable Energy Standard— Upper Midwest Transmission Development Initiative in the states of
ND, SD, MN, WI, IAITC intends to add local partners on the GPE to bring the project to fruitionITC is uniquely positioned, independent, and qualified to see this project built, without government money
Green Power Express SummaryGreen Power Express Summary
Francie BrownDirector – State Governmental Affairs
ITC
Federal and State Legislative Update
Federal and State Legislative Update
21
Status of Federal Transmission LegislationStatus of Federal Transmission Legislation
Transmission “just a part of the picture”Democratic leaders (especially in House) want to address transmission upgrades, nationwide renewable energy standards (RES), and climate change together in one large bill. While others (including Sen. Bingaman) want to deal with transmission alone, the “omnibus energy bill” approach appears likely to win out.
Several bills - which one will win out?Currently, three major bills (sponsored by Congressional leaders) control the debate. Two (the lead House bill, and Sen. Reid’s bill in the Senate) couple transmission with RES and climate change, but moderate Democrats’ opposition may prevent those measures from succeeding. Only time will tell which proposal wins the day, if any.
What’s the timeline?Democratic leadership and the White House have said they want to pass major energy legislation (including transmission) by the end of 2009. Committee activity is expected to be completed by the end of May. Most of the bills would not require any interconnection-wide plans to be developed for a year after enactment.
22
Key Issues for ITCKey Issues for ITC
Planning for National Transmission ProjectsITC supports using existing planning processes and structures to assist in development of an interconnection-wide planning process. In order to plan for remote resources that are distant from load, the existing planning footprints are inadequate. The process must be open, transparent, and mandatory. All transmission owners must participate in the process.
Siting AuthorityITC believes that the states are best situated to determine where transmission facilities should be located. However, for large, multi-state projects, designed to meet national energy and environmental goals, the determination of whether such projects are needed
should be a federal decision.
Cost AllocationThe cost associated with extra high-voltage projects with broad regional benefits should be spread as broadly as possible, preferably interconnection-wide. Feeder lines that bring renewable resources into the EHV overlay should also be broadly allocated.
23
Key Legislation – Waxman-MarkeyKey Legislation – Waxman-Markey
Lead House Bill – American Clean Energy and Security Act (Waxman-Markey)
Planning: FERC would adopt transmission planning principles within a year— Principles must take into account “all significant demand-side and supply-
side options”— Regional planning entities must submit plans to FERC within 18 months of
release— FERC must review for Waxman-Markey compliance; resolve any disputes— But – no authority for a meaningful interconnection-wide planning processSiting: Waxman-Markey does not address siting or certificationCosts: Waxman-Markey does not address cost allocation or funding
Takeaway – The bill does very little to promote transmission development, ITC is advocating amendments to the bill and focusing on the Senate that deals more comprehensively with transmission reforms Blue Dog Democrats (moderates) have expressed desire to amp up transmission requirements when House Energy & Commerce Committeeconsiders amendments
24
Key Legislation – Reid Bill (S. 539)Key Legislation – Reid Bill (S. 539)
Senate Bill #1 – Clean Renewable Energy and Economic Development Act (Reid bill, S. 539)
Planning: Designated regional planners to design interconnection-wide plans— FERC-designated entities must adopt interconnection-wide green transmission grid
project plans within one year of FERC designation— FERC does not have approval or review authority over regional plans, but can
enforce default plans on states that do not participate in their interconnection-wide plan
Siting: FERC can issue siting permits after consultation with states— FERC still serves as backstop authority; developers can only go to FERC for
certificate if they fail “to make reasonable progress” in siting facility under state/regional plan
Costs: Regional planners to design allocation method; FERC approval required— States and/or planning entities can collect “prudently-incurred” costs— Funds collected in surcharge on load serving entities not greater than $80mil/yr
Takeaway – ITC supports many elements of the bill. But, ITC does not believe that regional entities will be able to resolve the cost allocation impasse – as has been the case to date.
25
Key Legislation – Bingaman DraftKey Legislation – Bingaman Draft
Senate Bill #2 – Senate Energy and Natural Resources Draft (Bingaman Draft)Planning: FERC and regional entities to share authority for developing plans— FERC must coordinate development of interconnection-wide plans that promote
policy goals, to be published in a rule within one year of enactment— FERC can defer planning to interconnection-wide entity, but FERC must review and
approve regional plans and can modify once submitted— FERC may enforce default plans on interconnections if no regional entity develops
planSiting: FERC to receive boosted backstop authority for high priority projects— States have one year from time regional proposal is filed to site high priority projects— FERC automatically obtains jurisdiction to site if states fail to complete siting within a
yearCosts: FERC to establish allocation methods by rule— Methods must be “just and reasonable,” but no further detail in draft— FERC may allocate costs across a region if found beneficial for region by FERCTakeaway – ITC supports the most recent Bingaman draft, but feels it should be more explicit as to FERC’s role in integrating regional plans and Congress should providemore guidance to FERC for the cost allocation rulemaking
26
Other Legislation Other Legislation
National Energy Security Act of 2009 (Dorgan Bill, S. 774)— Addresses transmission in coordination with RES and increased domestic oil
production— Requires FERC review and approval of interconnection-wide plans developed by
designated regional authorities; plan must be updated every two years— FERC has primary and exclusive citing authority for extra high voltage line projects— Regional entities will set cost allocation plans (with FERC approval)
SMART Energy Act of 2009 (Nelson bill, S. 807)— FERC has exclusive jurisdiction over planning, permitting, siting and construction
decisions necessary for national transmission projects— FERC must submit plans to Congress within one year, then begin work within 18
months— FERC receives backstop siting authority for all secondary connections— Transmission project sponsors can collect payment and recover costs of
incremental transmission capacity for renewable electricity sources if plan is approved by FERC
Takeaway – ITC’s position is most closely reflected in the Dorgan bill.
27
State Legislative ReportState Legislative Report
ITC Midwest states— Iowa — Minnesota — Illinois — Missouri
Advocacy with State Legislature, Governor’s office, and State Agencies
Issue monitoring and advocacy: — Energy, ROW, transmission siting, jobs, economic development,
franchise provisions, regulatory reform, job training, taxes, and provisions dealing with federal stimulus $ through ARRA
Advocacy for Green Power Express in all states
28
Iowa Iowa Legislature adjourned Sunday, April 26, 2009 at 5:00 a.m.
Budget issues took center stage – resolution of a $1.4 B hole
Senate File 279 adopted and signed by the Governor Culver— Provides utilities with an abbreviated process for upgrading 34.5 kV
lines to 69 kV;— Franchised and non-franchised lines;— Rules process and waiver process included in legislation;— Worked with Coops, Farm Bureau, and the IUB on acceptable
language; — Governor Culver signed the bill on April 17, 2009
Federal stimulus $ in ARRA— Opportunities for Smart Grid projects;— 50/50 Matching grants for Smart Grid projects;— Availability of funds for worker training activities
29
Minnesota Minnesota
Legislature scheduled to adjourn May 18, 2009
Budget – projected budget deficit of $4.6 Billion — Revenues down 13% from forecasts — Combination of cuts and delays if no new revenues are identified
Senate File 526 introduced by Senator Prettner-Solon— Requires annual legislative report on adequacy of electric
transmission infrastructure over the next 15 years— Report to identify barriers to meeting transmission needs; legislative
recommendations
Senate File 550/House File 867— Omnibus Energy Bill — Addresses myriad of issues all relating to renewable energy — Definitions of Large and Small Wind Energy Conversion Systems— Bill does not have Senate transmission study language
30
Illinois and MissouriIllinois and Missouri
Illinois Legislature scheduled to adjourn May 31st.
Budget deficit of $ 11.6 Billion— Deploy federal stimulus $— Increase personal income taxes from 3% to 4.5% — Program cuts, other savings, other fee increases
Attorney General meeting with utilities and consumer groups— April 16th to discuss legislation on: uncollectibles, exemptions for
large industrial customers, energy efficiency for natural gas customers, ability of the AG to present oral argument on proposed rate increases.
Missouri Legislature scheduled to adjourn May 15th
Missouri to use federal stimulus $ to reduce income tax rate from 6% to 5.5%
Federal Regulatory UpdateFederal Regulatory Update
Tom Wrenbeck
Director – Regulatory Strategy
ITC
32
FERC rejected MISO’s Proposed “Market Coordination Services” under Module F part III of the Tariff. — This proposal suggested these services be offered to non RTO
members as “A Trial Membership to MISO.”
The ITC Companies filed jointly with AEP in protest of the cross border economic project cost allocation methodology proposed by MISO and PJM.
The ITC Companies, along with Great River Energy and Xcel Energy, filed a Schedule 26 true up methodology. This mechanism allows for a true up by project, by independent pricing zones.
AEP has filed a petition for review of FERC’s rehearing decision on the rate design for the PJM/MISO region with the 7th Court of Appeals. — The ITC Companies filed to be a party in the case.
Regulatory UpdateRegulatory Update
33
FERC dismissed IPL’s Section 206 complaint against ITC Midwest.
FERC approved all of the requested incentives (abandoned plant, CWIP in rate base, regulatory asset, ROE adders, and hypothetical capital structure) for the Green Power Express Project. The requested formula rate and protocols are set for hearing.
The ITC Companies filed FERC Form 1’s on April 16, 2009.
There will be a meeting explaining the 2008 Attachment O true up calculation on June 10, 2009 in Ames, Iowa. Details of the meeting will be sent out soon.
Regulatory UpdateRegulatory Update
Iowa Regulatory UpdateIowa Regulatory Update
Lisa StumpManager – Regulatory Affairs-Iowa
ITC Midwest
35
ITC MidwestRegulatory Group and ContactsITC MidwestRegulatory Group and Contacts
Lisa Stump – Manager100 East Grand Ave., Suite 230Des Moines, Iowa 50309(515) 282-5300, Ext. [email protected]
Terry Erickson – Regulatory Associate100 East Grand Ave., Suite 230Des Moines, Iowa 50309(515) 282-5300, Ext. [email protected]
36
Iowa Regulatory (Progress)Iowa Regulatory (Progress)
Opened Des Moines office
Developed detailed procedures for:Outage reporting
Compliance reporting
Accident reporting
Addressing probable violations found during Utilities Board inspections
Franchising
Working towards acquiring franchises to allow construction of projects needed to meet customer, reliability and regulatory commitments
37
Franchising 101Franchising 101
Existing Franchises require extension after five yearsNew franchises are needed when constructing a 69kV or higher voltage line outside of city limits or on property not owned by the utility or end-use customerAmended franchises are needed when upgrading the voltage on existing franchised linesPublic information meetings are required when requiring additional interests in private real estate of a mile or moreA hearing is required if any objection is on file at the Utilities BoardTypical Timeframes for Regulatory Approvals:
Extensions (No Objections) – 4 to 6 monthsAmendments (No Objections or Public Information Meeting) – 4 to 6 monthsNew and Amendments Requiring Public Information Meetings – 6 to 12 monthsAny Petition with an Objection on File at Utilities Board – 12 months
38
Projects Requiring Franchise WorkProjects Requiring Franchise Work
Network Upgrades/Interconnections for Wind Development
Franchise Extensions (7 granted and 1petition pending)
Reliability Driven Projects
Salem-Hazleton 345kV Project
34.5kV to 69kV Upgrades
39
Network Upgrades/Interconnections for Wind DevelopmentNetwork Upgrades/Interconnections for Wind Development
A new franchise is not needed if interconnection is made on property owned by ITC Midwest or the developerAn amended or new franchise is not needed if interconnection is made by relocating an existing line where less than a mile of new ROW is requiredFranchising work related to interconnections:
— Three public information meetings held— Three Petitions filed with three franchises granted— Future Petitions – Easement acquisition ongoing on three
petitions for network upgrades to enable future wind development in Boone, Story and Marshall counties
40
Reliability-Driven ProjectsReliability-Driven Projects
Marshalltown to Stoney Pt. Voltage upgrade and rebuild— Four public information meetings held (Marshall,
Tama, Benton and Linn)— Two petitions filed and two franchises granted
(Marshall and Tama Counties)— Remaining counties – Easement acquisition phase
Grand Mound – Public info. meeting heldLehigh Relocate – Franchise granted and construction completeRose Hollow – Franchise granted and construction ongoing
41
34.5kV to 69kV Upgrade Projects34.5kV to 69kV Upgrade ProjectsUpgrade driven by reliability and development concernsProgress:
Construction Completed: Tama to Toledo (also a highway move)
Franchises granted:— North Grand Jct. to Paton REC Tap (one county)
Petitions pending regulatory approval:— Boone to Jewell (two counties)— Eldora Area Upgrades (three counties)— Monticello-Amber & East Lovell REC Tap (one county)— West Branch to West Liberty (three counties)
Work Ongoing or Public Information Meetings Scheduled— Fairfax to Williamsburg (three counties)— Wyoming to Massillon (two counties)— Andrew Sub. Tap and Monmouth (one county)— Anita Area Upgrades (five counties)— Dyersville West
Utilities Board legislation passed and enacted
42
Franchise LegislationFranchise Legislation
ITC Midwest worked with the Utilities Board to pass legislation designed to expedite the franchising process for 34.5kV to 69kV upgrade projects where substantial new ROW is not needed.
SF 279 was passed and signed by the Governor in April. It is currently in effect.
Under new process, public information meetings and public notice will not be necessary for qualifying projects.
Next Step: Utilities Board Rulemaking
43
Salem-Hazleton ProjectSalem-Hazleton Project
Regulatory commitment to build Salem-Hazleton Project by December 31, 2011Regulatory Progress:
Noticed over 1,000 landowners for four public information meetings held in early 2009— Dubuque and Jackson
Counties: 2/10/2009— Delaware and Buchanan
Counties: 2/9/2009Currently acquiring easementsOngoing communications effort with landownersLandowner objections only filed in Dubuque County where new line is being built on new ROW
44
Goals of Iowa RegulatoryGoals of Iowa Regulatory
100% compliance with Utilities Board rules and regulations
Participate in all relevant rulemakings and inquiries
Mange the regulatory process to:
— Meet commitments made during transaction approval proceedings
— Meet the needs and schedules of new generation wanting to interconnect to the ITC Midwest system
Develop or improve relationships with state, county, municipal and industry leaders
Meet customer expectations (both internal & external)
Bob MulqueenPolicy Director for the State of Iowa
Office of Energy Independence
Iowa Renewable ProgramIowa Renewable Program
LunchLunch
Dr. Elwynn TaylorIowa State University
2009 Summer Weather Forecast2009 Summer Weather Forecast
Dede SubaktiManager West Regional Operations Engineering
Midwest Independent Transmission System Operator (MISO)
MISO Wind IntegrationMISO Wind Integration
Managing Wind Energy:From Interconnection Planning to
Real Time Operations
An Integrated Approach to Ensure Energy and Transmission Capacity
Michael McMullen Kris Ruud Dede Subakti
Who We Are• Independent, non-profit organization
responsible for maintaining reliable transmission of power in 15 states and one Canadian province
• First Regional Transmission Organization (RTO) approved by the Federal Energy Regulatory Commission (FERC)
Our Role• Midwest ISO is a service company that provides
reliability to the electric grid
• Midwest ISO administers the market for electricity producers and users on a wholesale level
• Midwest ISO does not generate or buy electricity
Agenda• Introduction – Wind Energy Growth
• Challenges in the Generation Interconnection
Process
• Transition From LGIA to Real Time Operations
• Challenges in Real Time Operations
• MISO Centralized Wind Forecasting
• Other New Initiatives within Midwest ISO for
Integration of Wind Energy
Introduction – Wind Energy Growth
The map shows the annual average wind power estimates across the US at 50 meters above the surface
Introduction – Wind Energy Growth
0
1000
2000
3000
4000
5000
6000
7000
In Facilities Study Phase SIS/DPP Total
2005 2006 2007 2008 2009
Projects still in Queue: Approximately 685 MW with executed Generator Interconnection Agreement (GIA) and planned in-service date in 2009. Nearly 6000 MW still in
queue with requested in-service date prior to 2010
High Level Process of Integrating Wind Energy
IA being signed
CommercializationGI Process ConstructionApplication
Generation Interconnection Process
Challenges in the Old Generation Interconnection Process
• Process driven by the Queue Order (i.e. first in first served)• Queue position being significantly valuable• Having a relatively lower cost of entry into the queue• Inordinately high amount of interconnection requests against a highly
constrained transmission system• High attrition driven primarily by the apparent oversupply of requests,
and resultant rework, delays and uncertainty for subsequently queued projects
• No cost/penalty for suspension, resulting in large number of projects being suspended
– adverse impacts on timelines and uncertainty for later queued generators dependent on the transmission upgrades of the suspended generators.
Old GI Studies Compared toNew GI Studies*
* This page illustrates comparison of studies’ procedural differences; differences in milestones, deposits, and paths through the phases are not shown.
Feasibility Feasibility Feasibility System Impact System Impact System Impact
ThermalThermalShort CircuitShort CircuitStabilityStability
OldPhases
Facility Facility Facility IA/FCAIA/FCAIA/FCA
System Impact Study
System Impact Study
Facility Study
Facility Study
Feasibility Study
Feasibility Study
Interconn. AgreementInterconn. Agreement
Translates to
Translates Translates toto
ApplicationReview
ApplicationApplicationReviewReview
Pre-QueuePre-Queue Systems Planning &
Analysis
Systems Planning &
Analysis
Definitive PlanningDefinitive PlanningDefinitive Planning
Facility Study
Facility Study
Contour Map
Contour Map
Application validation
Feasibility Study
SIS (Review, Study, or Restudy)
SIS (Review, Study, or Restudy)
ThermalShort CircuitStability
New (current)Phases
ThermalShort CircuitStability
Interconn. AgreementInterconn. AgreementSystem
Impact Study (SIS)
System Impact
Study (SIS)Relationship buildingCustomer discussionPre-entry review
Facilities Construction Agreement
Facilities Construction Agreement
Facilities Construction Agreement
Facilities Construction Agreement
New phaseNew phaseNew phase Replaced by
Replaced Replaced byby
Translates to
Translates Translates toto
59
GI Study Milestones & Deposits
$440,000$90,000$5,000
501 - 999 MW
$360,000$60,000$5,000
201 - 500 MW
$260,000$60,000$5,000
101 - 200 MW
$210,000$60,000$5,000
51 - 100 MW
$150,000$30,000$5,000
21 - 50 MW
$100,000$20,000$5,000
7 - 20 MW
$40,000$10,000$5,000
<6 MWRef Description/Rationale Refund 1000+ MW
D1 Application Fee/Fund FeS* No $5,000D2 Fund System Impact Study Yes $120,000D3 Fund Definitive Planning Partial $520,000
ApplicationReview
ApplicationReview
Pre-QueuePre-Queue System Planning & Analysis
(SPA)
System Planning & Analysis
(SPA)
Definitive Planning
Definitive Definitive PlanningPlanning
M3M3
Milestones
IA
Facilities Study
Facilities Study
Contour Map
Contour Map
SPA Review (SIS)
SPA Review (SIS)
System Impact
Study (SIS)
System Impact
Study (SIS)
RPGIPs(future)
RPGIPs(future)
Process EducationProcess
Education
Ad HocSessionAd HocSession
Application Validation
Application Validation
Feasibility Study
Feasibility Study
M1M1
Application SubmissionApplication Submission
IA / FCA NegotiationIA / FCA
Negotiation
Milestones Milestones
M2M2
1. Constrained transmission
1. Constrained transmission
2. Transmission available2. Transmission availableD2
D3
D1
Sample Contour Map
Gives an idea of relative incremental injection capability
Introduction – Wind Energy Growth
The map shows the annual average wind power estimates across the US at 50 meters above the surface
After Interconnection Agreement is Signed – During Construction
Transition From LGIA to Real Time Operations
• Operating Guide for the new facility that shows the impacts of wind
– This often needs 2 months especially when
it needs agreement from multiple TOs• Asset Registration – For Online tools
– Needs to be aligned with Model Update schedules:
• Quarterly model updates timing requirement vs. Wind Farm project timeline
e.g.: Wind Farm that needs to test by Aug 1, 2009 will need to be registered and
submit network model data by March 15, 2009 (for June 1, 2009 model)
– Additional data for Wind Forecast needs to be submitted 30 days prior to
commercialization.
• Latitude, Longitude, Hub Height, and Turbine Type
• MOD Registration – For Offline tools– Data needs to be submitted by the 15th of the month prior to commercialization.
Proposed Process – High Level View
Project Time Line will need to be continuously communicated between IC, TO, TOP and MISO
Operating Studies• More often than not, a number of system topology
changes have occurred since the interconnection planning study was performed. These may include, but are not limited to, suspension or withdrawal of prior-queued generation and their associated transmission upgrade.
• In addition, often wind facilities come online before the needed upgrades in the transmission network are completed.– Some Customers would like operating guide– Some Customers would like to have SPS– Customers might choose to have Temporary IA
Operating Studies• Sensitivity studies are also performed to look for
potential issues with different energy transfer bias with different regional wind output level. A minimum of four scenarios are accounted in the sensitivity study. These are done for system intact and prior outage condition– Minimum load with 100% regional wind output– Minimum load with 20% regional wind output– Peak load with 100% regional wind output– Peak load with 20% regional wind output
• Any potential transmission congestion is documented in the Operating Guide
Operating Guides• Curtailment Process for Transmission Congestion:
– If it is not yet commercial, test energy will be curtailed first prior to LMP Binding Procedure/TLR
– If it is local and not impacted by any other generators:
• Manual curtailment of wind on a pro-rata basis respecting their Transmission Service priority
– If it is regional and it can be impacted or solved by other generators:
• Use TLR/Binding Process first• If SOL is approaching and/or LMP/TLR is not providing enough
relief, then:– Manual curtailment of wind on a pro-rata basis respecting their
Transmission Service priority
Commercialization and Operation
Challenges in Real Time Operations
• Impact of Wind Energy on Congestion
Management
• Impact of Wind Energy on Generation Commitment
Wind Farms in The Midwest
Impact of Wind Energy in Generation Commitment and Ramp
• Between June – Nov 2008, the Midwest ISO wind output peaked at 2779 MW. – The max 15 min change observed was
+ 325.9 MW and – 623 MW. – The max 60 min change observed was +622.5 MW and -
700.5 MW • Between Dec 2008 – Feb 2009, the Midwest ISO
wind output peaked at 3730 MW. – The max 15 min change observed was
+ 356.3 MW and – 390.2 MW. – The max 60 min change observed was +959.5 MW and -
711.4 MW
Wind Energy Ramp June-Nov
-500 -400 -300 -200 -100 0 100 200 300 400 500
15 min change 60 min changeSix Sigma Bound for 15 min change Six Sigma Bound for 60 min change
Wind Energy Ramp Dec-Feb
-500 -400 -300 -200 -100 0 100 200 300 400 500
MW Change
15 min change 60 min changeSix Sigma Bound for 15 min change Six Sigma Bound for 60 min change
Wind Energy Ramp June-Nov
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 100 200 300 400 500 600 700 800 900 1000
Absolute MW change
Cum
ulat
ive
%
Cumulative % of 15 min Change Cumulative % of 60 min change
Wind Energy Ramp Dec-Feb
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 100 200 300 400 500 600 700 800 900 1000
Absolute MW Change
Cum
ulat
ive
%
Cumulative % of 15 min change Cumulative % of 60 min change
Impact of Wind Energy in Generation Commitment
• MISO performs Economic Dispatch every 5 minutes
• Changes of wind ramp in 5 minutes are not significant yet
• MISO allows intra-hour scheduling. Wind ramp in 15 minutes are not significant yet
MISO Centralized Wind Forecasting
Wind & Wind Forecasting
• There is ~4500 MW of wind generation installed in the MISO Market footprint– Central Region – 100+ MW– East Region – 700+ MW– West Region – 3500+ MW
• Additional 1500-2000 MW in the rest of the Reliability Footprint (MEC, DPC, MHEB, WAPA)
MISO Wind Forecasting• Midwest ISO evaluated proposals for a
centralized forecasting system early 2008– Approximately 2500 MW of wind in service at the time
– Started training the forecasting tool in May 2008
– Forecasts started in June 2008
– As forecast have become more mature, additional uses in Control Center and integrated into tools
MISO Wind Forecasting
• Data needed for accurate wind power forecasts– Latitude and Longitude of wind farm*
– Turbine type, turbine hub height*
– Real Time MW values*
– Availability of turbines at each site
* Currently in use at Midwest ISO
MISO Wind Forecasting• Energy & Meteo providing wind forecasting
services
• Forecasts at the CpNode level, Zones, Regions and MISO Market total
• Currently doing hourly forecasts for 7 days updated hourly at each CpNode and aggregated to Zones, Regions, and MISO Market totals
MISO Wind ForecastingTotal Market Footprint
Regional level
Zones
CpNode level
Wind Forecasting and Numerical Weather Predictions - NWP
• Numerical weather prediction uses current weather conditions as input into mathematical models of the atmosphere to predict the weather. Use of model ensemble forecasts helps to define the forecast uncertainty and extend weather forecasting farther into the future than would otherwise be possible. (From Wikipedia)
• Midwest ISO uses a multiple NWP forecasting model
Wind Forecasting and Numerical Weather Predictions - NWP
Wind Forecasting - AccuracyM
ean
Abs
olut
e E
rror
(%)
Integrating Wind Forecasting into Market Operation
• Current Market Rules– Intermittent Resource
• Can Offer an amount up to the Maximum output into the Day Ahead Market
• Cannot offer in the Real-Time Market, does not set price• Not subject to deviation uplift charges (if Real Time amounts different
from Day Ahead cleared amounts)*– Tariff says each Market Participant has to submit a Day Ahead
Intermittent Resource forecast• Set up Business Practice Manual and Portal site for this submission –
began May 1, 2009• Will be used in Forward and Intra Day Reliability Assessments
Integrating Wind Forecasting into Market Operation
• Current Market Uses– Wind forecast used in Transmission Outage Coordination
• Example – With the West Region wind forecast being low for the next day, the outage of (xxx line) has been delayed until Thursday due to transmission constraints (otherwise would have to commit extra Combustion Turbines)
– Wind Impact Tool• Automated tool that shows impact of wind increases and decreases on
Flowgates
– Currently uses a delta equal to the largest hourly increase and decrease over the last 24 hours
– Will also work with the wind forecast change for the next hour
Integrating Wind Forecasting into Market Operation
• Current Market Uses– Wind forecast used in Transmission Security Planning
• Wind forecast used to model wind generation for next day peak load analysis
– Accuracy of wind resources affect overall accuracy of the analysis
– Forward and Intra Day Reliability Assessments• Forecast used to help determine reliability unit commitment for next
day and real time
– Many cases of not starting a conventional generator because wind forecast shows adequate wind to keep transmission constraints manageable
– Currently a manual process, but is being automated into various operator tools
Other New Initiatives
New Initiatives
• Interconnection Queue Process Reform
• Regional Generation Outlet Study
• Wind Impact Tool
• Reviewing Tariff/Market Design with regard to
Intermittent Resources
• Wind Integration Workshops
New GIA Process Highlights• Transition from a “first-in, first-served” approach to
“first-ready, first-served” as demonstrated through the achievement of specific milestones
• Creation of: – a Pre-Queue phase in the process
– a “fast-lane” for projects in less-constrained areas
• Up front deposit for all studies based on project size
• Elimination of the ability to suspend projects for economic reasons
Regional Generation Outlet Study(RGOS)
• Regional transmission plans that would facilitate the integration of wind in Midwest ISO footprint
• The first RGOS focuses on only Illinois, Iowa, Minnesota, and Wisconsin. These RPS mandates generally are for the timeframe of 2010 to 2020 and later.
• Studies have shown that the existing and planned transmission system will likely not be able to deliver the energy/capacity required by the state mandates for 2013 and beyond.
• These transmission plans will eventually be fed into the Midwest ISO Transmission Expansion Planning (MTEP) process
Wind Impact Tool
2 Different scenarios are run:
Max Wind Increase and Max Wind Decrease (based on the last 24 hour wind trend)
(click button to see detail results)
Results are sorted by its impact on FG.
If there is 95% overload, it will be at the top
Review of Tariff/Market Design
• Several internal and external groups are investigating potential enhancements to Market Design to better accommodate the growth of Wind Generation
• Any changes will be fully vetted through stakeholder process
Wind Integration Workshops
• First Workshop held March 24th
• Next Workshop scheduled for June 10th
• Materials posted on www.midwestmarket.org
Summary• Challenges in the Generation Interconnection
Process
• Transition From LGIA to Real Time Operations
• Challenges in Real Time Operations
• New Initiatives within Midwest ISO for Integration
of Wind Energy
For More Information• Kris Ruud• Technical Manager• Operations Resource Integration• [email protected]
• Dede Subakti• Manager• West Regional Operations Engineering• [email protected]
BreakBreak
Summer ReadinessSummer Readiness
Elizabeth HowellVice President – Operations
ITC
103
Operational TransitionOperational Transition
ITC assumed operational control of the ITC Midwest 69kv and above transmission system from ATC on December 15, 2008Operations are directed from ITC’s Operations Control Room in Novi, MichiganUnder the Transition Service Agreement, Alliant Energy continues to operate the 34.5kV system from the DDC in Cedar Rapids
104
2009 Weather Forecast2009 Weather Forecast
Anticipating a warmer summer than last year— Summer will be warmer and drier than normal (on average)— Hottest periods in early June, July with a cooler August
50
60
70
80
90
100
2002
2003
2004
2005
2006
2007
2008
2009
?
Deg
rees
Average Temp on Peak Day
105
Cooling Degree Days – Ames, IowaCooling Degree Days – Ames, Iowa
0
200
400
600
800
1,000
1,200
1,400
1969 1972 1975 1978 1981 1984 1987 1990 1993 1996 1999 2002 2005 2008
Normal 888
2114
27
37
18
33
2326
11
20
3934
29
38
15
25
36
19
64
32
24
1
40
1612
5
22
35
79
28
13
3
30 31
2
17
810
Median
34th
106
Example - Effect of TemperatureExample - Effect of Temperature
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
0 10 20 30 40 50 60 70 80 90 100
Average Hourly Temperature (Deg F)
Peak
Dem
and
(MW
)
A Winter Month
A Summer Month
A Shoulder Month
107
Temps Versus PeaksTemps Versus Peaks
Range of Average Hourly Temps on Days of ITC Midwest Monthly Peaks, 2002-2008
-4
15
39
68
77747366
26
13
1
-5
18
29
8078
838481
7876
3231
21
-4
15
39
68
77747366
26
13
1
-5
18
29
8078
838481
7876
3231
21
-10
0
10
20
30
40
50
60
70
80
90
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Month
Ave
rage
Hou
rly
Tem
pera
ture
(Deg
F)
108
2009 Load Forecast2009 Load Forecast
2008 summer peak loads were lower than the prior several years
Based on forecast weather and load performance YTD, expecting higher loads this summer than last, but not too significant
ITC Midwest Peak LoadITC Midwest Peak Load
2,500
2,750
3,000
3,250
3,500
Jun Jul Aug
MW
2004 2005 2006 2007 2008
109
Summer Assessment SummarySummer Assessment Summary
ITC Operations Engineering conducted power flow studies based on various assumptions for the summer and identified possible thermal and voltage violations for system normal and for single contingencies
Developed mitigation plans for all possible violations, including system reconfiguration, generation re-dispatch, and load shedding
Mitigation plans are being coordinated with Midwest ISO, Alliant Energy, and other third parties as appropriate
110
Operational State of the SystemOperational State of the System
Prairie Creek and Sixth Street substations were severely damaged, resulting in a loss of generation, breaking up of the 115kV network, and the loss of the 115/34.5kV sources into the Cedar Rapids metropolitan area
June 2008 Flood
111
Operational State of the SystemOperational State of the System
By July 4, 2008 the following restoration had occurred:— The 115kV stations at Prairie Creek and Sixth Street were
partially restored in order to reconnect the 115kV network — Two 115kV capacitors were installed to provide voltage support
to the area— The 345/161kV transformer at Duane Arnold Energy Center
was reconfigured to help support voltages in the Cedar Rapids area
— Two new 34.5kV sources were added to serve load— Distributed generation was made available to Alliant Energy to
help serve load in the area
Mild temperatures, slow load recovery and repairs/investments resulted in reliable transmission throughout summer 2008 in the Cedar Rapids area
112
Operational State of the SystemOperational State of the System
The 34.5kV source at Sixth Street station was restored and the 34.5kV source at Beverly station was made permanent to provide permanent sources to the area
Jumpers on several 115 kV lines in the area will be upgraded to increase system capacity
Post-Flood Preparations for Summer 2009
113
Operational State of the SystemOperational State of the System
Prairie Creek units are expected to be in service to serve load and support voltages in the Cedar Rapids area
MidAmerican’s Coralville units (also damaged during the flood) are expected to be in service, which will further help to support the area
Mitigation plans will be developed between ITC Midwest and Alliant Energy if anticipated generation is not restored by summer
114
Operational ChallengesOperational Challenges
If anticipated Cedar Rapids generation isn’t available by summer, we may experience voltage problems— If Duane Arnold generation is lost, load shedding would
be the only solution
If certain contingencies occur, equipment overloads will need to be managed
115
Operational ChallengesOperational Challenges
Storm Season— Responding to equipment damage or operations
resulting from severe weather
116
Summer 2009 Major ProjectsSummer 2009 Major Projects
Dysart-Vinton 161kV rebuild is continuing through summer 2009 as part of the entire Duane Arnold-Vinton-Dysart-Washburn path reconstruction to dramatically reduce congestion through Iowa
In-service date for entire rebuild December 2009
117
Summer 2009 Major ProjectsSummer 2009 Major Projects
Upgrades on the Adams-Barton 161kV line to accommodate Barton Wind Farm will occur during the summer
118
Completed ProjectsCompleted Projects
Since acquiring the system, ITC Midwest has already completed projects to improve operations and reliability
Re-conductoring of 161kV Dysart-Washburn line
Multiple breaker replacements across the ITC Midwest system due to age and condition
119
Summer PreparationsSummer Preparations
Summer readiness equipment inspections:— Performing functionality
testing of transformer Load Tap Changers (LTCs) to ensure reliable operation
— Aerial inspection of lines
120
Summer PreparationsSummer Preparations
Vegetation management— Enhanced vegetation
management program
— High priority for outage reduction on 34.5 and 69kV
— Significant hot-spotting completed during third, fourth and first quarters
121
Summer PreparationsSummer Preparations
Issued generator voltage schedules for all large generators, including wind farms, to conform to NERC Standard VAR-001— This will help ITC to better control system voltages, especially
during high summer loads
Conservative operations policy— Will follow MISO’s business practices for conservative
operations, including limiting work at critical sites on high load days
— ITC restricts maintenance and construction work on power plant mats and on critical transmission assets during high load periods
— On critical days, all non-emergency work will be stopped
Questions?Questions?
Jon JippingChief Operating Officer
ITC
Smart Grid at ITCSmart Grid at ITC
124
Table of ContentsTable of Contents
Smart Grid Defined and The Smart Grid PromiseThe ITC ApproachCommunications NetworkReal-time Monitoring and ControlEvent AnalysisConclusion
Smart Grid Defined/The Smart Grid Promise
Smart Grid Defined/The Smart Grid Promise
126
The Smart Grid DefinedThe Smart Grid Defined
A precise definition of the Smart Grid remains elusive…
Common themes:EfficiencyDemand responseConsumer savingsReduced emissions
TechnologyTwo-way communicationAdvanced sensorsDistributed computing
ReliabilityInterconnectivityRenewable integrationDistributed generation
IEEE: “The term ‘Smart Grid’ represents a vision for a digital upgrade of distribution and transmission grids both to optimize current operations and to open up new markets for alternative energy production.”
Wikipedia: “A Smart Grid delivers electricity from suppliers to consumers using digital technology to save energy, reduce cost, and increase reliability.”
FERC: “Grid advancements will apply digital technologies to the grid and enable real-time coordination of information from both generating plants and demand-side resources.”
DOE: “A smarter grid applies technologies, tools, and techniques available now to bring knowledge to power –knowledge capable of making the grid work far more efficiently…”
GE: “The Smart Grid is in essence the marriage of information technology and process-automation technology with our existing electrical networks.”
127
The Smart Grid Defined (Cont’d)The Smart Grid Defined (Cont’d)The Smart Grid is the convergence between electrical and new “intelligence” infrastructure.
Two-way flow of electricity and information that strengthens reliability and resource management
Data, control, and automation providing increased efficiencies, responsiveness, flexibility, and resiliency
“Time-based” decisions and transactions between energy suppliers, buyers, and markets
Market-side resources operating with traditional supply-side resources as a “portfolio”
Sustainability—environmental compliance and resource stewardship benefits
Convergence
Smart grid transforms the electric industry model from a “centralized, producer-controlled energy grid” to a more “distributed, customer interactive energy network”
– DOE, “The Smart Grid: An Introduction ... ,” 2008
128
The Smart Grid PromiseThe Smart Grid Promise
*Source: Department of Energy: “The Smart Grid – An Intro”
Vision of a Vision of a Future with a Future with a Smart GridSmart Grid
Descriptions of the Smart Grid paint a grand picture of the future.*
EfficientEfficient
AccommodatingAccommodating
MotivatingMotivating
OpportunisticOpportunistic
QualityQuality--focusedfocused
ResilientResilient
““GreenGreen””
IntelligentIntelligent
129
The Smart Grid Promise (Cont’d)The Smart Grid Promise (Cont’d)Several hurdles must be overcome to reach this future.
Technology— Many of the technologies needed to reach the full promise of the Smart Grid are only in the early
stages of development or are not yet commercialized
Policy— The FERC has issued a preliminary policy, but various stakeholders need to weigh in — States’ utility commissions will make the decisions about what is appropriate at the retail level
Interconnectivity and standardization— Various devices and protocols are currently being developed; ensuring interoperability across
devices will be key
Rate recovery— Depending on the type of entity, FERC, state regulators, or both will determine the degree to
which investments in Smart Grid technologies are recoverable
Technology is not a panacea for aging infrastructure (i.e., the Smart Grid does not replace the “real grid”)
The real grid is the hard assets that make up the traditional infrastructure (i.e., wires, substations).
The Smart Grid is the application of advanced technologies that enhance the operation of the real grid
The ITC ApproachThe ITC Approach
131
ITC Smart Grid StrategyITC Smart Grid Strategy
The ITC strategy is to continue to actively invest in new technology such that it:
Adds value for our investors and our customers – ensure the business case makes sense—benefits outweigh the costs and assets are used and useful
Improves reliability of our service – upgrade transmission assets with more effective monitoring and control technology
Retains flexibility for the future – retain maximum degrees of freedom—technologies employed are flexible enough to accommodate innovation over time
Enables a smarter future – deploy Smart Grid alternatives in transmission to serve as an enabler for generation and distribution Smart Grid applications
Smart Grid is What We Do
132
Three fundamental areas that ITC views as aligned with Smart Grid for transmission today:
1. Communications Network: a robust communication network is fundamental to Smart Grid deploymentSystem requires a secure broadband logical network
2. Real-time Monitoring and Control: Sensors and intelligent devices enhance real-time observation and rapid analysis and response to system disturbances
Substation security enhancements Transmission asset health monitoring
3. Event Analysis: Enhanced monitoring and data analytics provide robust analysis of system eventsAdvanced system fault monitoringData analysisGPS time-stamped data
Fundamental Areas for ImplementationFundamental Areas for Implementation
Enhanced event analysis— Accurate response to events— Identification of corrective actions
Increased reliability— Fewer interruptions to business— Improved customer satisfaction
Customers benefit; the use of select Smart Grid technologies provides ITC customers with
133
Transmission Smart GridTransmission Smart GridWidely distributed assets via a digital, private, broadband communication network.
Engineering
OperationsControlRoom
SUBSTATION (typ.)NOVI HEADQUARTERS
NetworkCommunication
FaultEvent
Recorder
Transformer
Asset Health Monitoring
System (i.e. T-Medic) Breaker
LocalNetwork
SCADAData
Signals
Dispatch Work Crew
Eng’gDataSignals
ControlSignal
GPS TimeSynch Data
ControlSignal
Time Stamped SCADA Data
Eng’gDataSignal
IntelligentRelayDevice
Relay Trip Signal
Communications NetworkCommunications Network
135
Communications Network –IntroductionCommunications Network –IntroductionA robust telecom network is required to support the increased data transmission needs of Smart Grid technologies
Communication System:— Today, communications is provided over a variety of technologies
Microwave, radio and analog phone linesThese are low speed, non-networked point-to-point lines
Ideal Network and Communication Features:— An IP-based, networked communications for speed, bandwidth, reliability, and
security— Open-industry protocols and standards provide the fundamental building blocks for
interoperabilityCybersecurity:— The network bandwidth and reliability enable cyber and physical security features at
substations that were not possible with the previous telecom infrastructure
Communications is critical for understanding system status and responding quickly to system disturbances
136
Network Features and CybersecurityNetwork Features and Cybersecurity•
The network provides redundancy with no single point of failureUses off-the-shelf hardware that can be scaled or upgraded as technology advances
Schematic representation of a logical communication network; packets of data can be routed through many potential paths ensuring reliability as well as mitigation of network congestion
OCRTMS
RouterMARS
Novi SONET Ring
AT&T
FRAME RELAY NETWORK / AVPN
Substation(typical)
Router
RTU
OCRTMS
RouterMARS
Substation(typical)
RTU
Ann Arbor SONET Ring
Conceptualization of layers of security on
ITC data traffic
Cybersecurity is achieved at the ends
System fully meets FERC cybersecurity standards
State of the art technology is employed to centrally monitor substations, providing detection and mitigation of cyber-threats
Real Time Monitoring and ControlReal Time Monitoring and Control
138
Real-Time Monitoring and Control –IntroductionReal-Time Monitoring and Control –IntroductionSmart Grid technologies provide enhanced monitoring and control capabilities
Real-Time Monitoring and Control:— A system based on information technology has been developed to monitor and
control equipment in the field from a central locationGrid Intelligence:— Data are provided in real time to the Operations Control Room (OCR), enabling
Transmission System Coordinators (TSC) to see what is happening on the grid— Applications provide graphical representations of system conditions— Analysis programs constantly search for potential overloads and voltage issuesCritical Equipment Monitoring:— Intelligent electronic devices (IEDs) are capable of self-diagnosis— Provides real-time data on the status (i.e., temperature, oil analysis, etc.) of key
pieces of equipment — Analysis programs process the collected data to trend changes and anomalies
that may indicate problems in specific pieces of equipment
Real-time monitoring is at the very core of operating a Transmission system
139
Grid IntelligenceGrid IntelligenceField intelligence enhances system operations
New/enhanced remote terminal units (RTUs) and intelligent electronic devices (IEDs) provide SCADA data to the Transmission Management System (TMS)
Dynamic displays improve trackingDisplays are configured to provide Transmission System Coordinators (TSCs) with information related to system integrity with regard to established operating limits
Advanced tools help mitigate instability and secure system integrity
State Estimator — Approximates system status— Runs once per minute – leading in the
industryContingency Analysis — Tests system integrity by simulating failure
of individual grid components— Provides results of contingencies and their
impact, in order of severity for both voltage and thermal limits
These analytical tools alert TSCs to system instabilities that might otherwise go unobserved
140
Critical Equipment MonitoringCritical Equipment Monitoring
Relays and other IEDs are utilized in the field— Where once only general status alarms
were provided to Transmission System Coordinators, IEDs allow intelligence to be distributed beyond the Control Room and RTU and into the device itself
— IEDs are able to self diagnose their condition and report back to the Control Room, virtually eliminating the need for field calibration and inspection to ensure the device will operate reliably when needed
The Transformer Monitoring Project (T-Medic) provides protection for transformers by analyzing system conditions and sending alerts to ITC subject-matter experts for further analysis— Dissolved gas in oil analysis— Power factor bushing monitor— Full range of temperature monitoring— Current monitoring of fans and pumps— Active cooling control as primary control
system— Traditional fan and pump (as back-up)
Intelligent electronic devices (IEDs) and online monitoring of equipment make it possible to take preventive measures based on changes in key indicators.
Event AnalysisEvent Analysis
142
Event AnalysisEvent Analysis
Digital support for event analysis:— With deployment of a networked communication platform, devices in the
substations now have IP addresses and are accessible via the network enabling faster, more accurate, and more reliable analysis
— RTUs are supplemented by microprocessor relays with digital fault recording capabilities
— GPS clocks in its substations to provide a common time stamp that enables sequence of events analysis across multiple locations on the grid
Analytics capability:— In order to realize the full benefits of ITC’s Smart Grid investments, the
organization’s analytics capabilities needed to evolve
In addition to enhanced real-time monitoring and control, Smart Grid technologies facilitate analysis of system events after they take place.
143
Smart Grid Means a New Way of WorkingSmart Grid Means a New Way of Working
ITC continues to develop complementary organizational capabilities.
The use of Smart Grid technologies requires skill sets not traditionally found in electric utilities— An understanding of telecom networks— The ability to use advanced data analysis tools
These capabilities enable ITC to— Accurately and reliably collect data— Make decisions quickly and with confidence— Send the right people with the right tools to the right location
Smart Grid technologies have implications for the work force— Utility engineers are now required to understand the complex analysis tools and
networks that have evolved over the past 20 years— As the utility workforce ages, the need for these skills presents an opportunity to
attract and retain new engineering graduates interested in the advanced applications being implemented
— The focus on cyber security, common protocols, and interconnectivity across systems will only increase these requirements in the years to come
ConclusionConclusion
145
In SummaryIn Summary
ITC and the transmission system in general have been early adaptors of Smart Grid
Network communications capability is key to the deployment of Smart Grid technologies
ITC will continue to upgrade the transmission system with appropriate Smart Grid technologies as their value to the operation of the grid is proven
This approach ensures that ITC will retain interoperability with various Smart Grid applications as they are deployed
There is a place for Smart Grid concepts, but it will not replace needed investments and upgrades in the “Real Grid”
The benefit for ITC customers is a more robust and reliable grid with fewer service interruptions and faster
restoration when they do occur
146
THANK YOU for YOUR DAY!!!!!THANK YOU for YOUR DAY!!!!!
ITC Midwest Appreciates your time and effort to participate with today’s Partners in Business meeting:
Please take a few minutes to complete our evaluation to help us meet your expectations next year!!!!!!
For copies of today’s ITC presentations please visit our Oasis web-site at: http://oasis.midwestiso.org/oasis/ITCM
Mike Dabney Keith [email protected] [email protected]
www.itctransco.com
Next Partners in Business MeetingNext Partners in Business Meeting
June 10, 2009Rate True-up MeetingIowa State University
Scheman Building Time TBA
Please Drive SafelyPlease Drive Safely