ISR Intralink Management System
Step By Step Configuration Guide
ISR Step By Step Configuration 13/7/2010
2
Contents A. GETTING STARTED............................................................................ 3 1. INSTALL JAVA PLATFORM. ............................................................ 3 2. ASSIGN AN IP ADDRESS TO THE PC.............................................. 3 B. GETTING CONNECTED ..................................................................... 5 1. LOGGING IN ......................................................................................... 5 C. CHECKING FUNDAMENTAL HARDWARE
OPERATION .......................................................................................... 7 D. UPGRADING THE ISR FIRMWARE................................................. 9 E. CHANGING NETWORK CONFIGURATION.................................. 15 F. LINK CONFIGURATION .................................................................... 16 1. SET DEVISE NAMES ........................................................................... 16 2. SET THE CLOCK.................................................................................. 16 3. MAKE LINK CONFIGURATION....................................................... 17 4. SET ODU TX MUTE CONFIG. (ONLY FOR STANDARD
MODE 1+0) ............................................................................................. 21 5. SET PROTECTION CONFIGURATION. (ONLY FOR
PROTECTED NON-DIVERSITY 1+1) ............................................... 22 6. SET ODU CONFIGURATION ............................................................. 22 7. CHECK DATA LINK ............................................................................ 23 G. REMOTE SYSTEM CONFIGURATION ........................................... 23 H. LINK MONITORING............................................................................ 24 1. STATUS PANEL .................................................................................... 24 2. ALARM CONFIGURATION ............................................................... 25 3. ACTIVE ALARMS ................................................................................ 25 4. ALARMS THRESHOLDS .................................................................... 26 5. ALARM HISTORY................................................................................ 26 I. UPGRADING THE ODU FIRMWARE .............................................. 27 1. CHECKING ODU FIRMWARE .......................................................... 27 2. DISABLE SPIRAL SEARCH MODE .................................................. 27 3. FTP TOOL .............................................................................................. 28 4. ODU UPGRADE..................................................................................... 29 5. UPDATING TX POWER LEVEL........................................................ 31 6. ENABLE SPIRAL SEARCH MODE ................................................... 32 7. REPEAT THE STEPS 1-6 FOR THE REMOTE STATION............. 32
ISR Step By Step Configuration 13/7/2010
3
A. Getting Started 1. Install Java Platform.
The ISR does not require a specific management application, instead it uses a browser (e.g Internet Explorer, Firefox). Nevertheless java platform is required in or-der for the browser to display all aspects (get java platform free at http://www.java.com/).
Connect the PC to the ISR NMS port.
2. Assign an IP address to the PC.
1. Select StartConnect ToShow all connections. 2. Right-click the Local Area Connection and select Properties. 3. Select the Internet Protocol (TCP/IP) check box and click Properties.
The manufacturer provides the ISR units with 192.168.0.1 as the default IP addresses.
Note: Make sure that the IDU is not connected to the network (if necessary discon-nect IF cable).
a) Check if it is the default IP. Set:
1. IP Address:192.168.0.254* 2. Subnet Mask:255.255.255.0 3. Default Gateway: -
Note: * When connected to the Network use any from (2-254) as long as it is not used as an IDU IP.
Ping the IDR-LC: 1. Select: StartRun 2. Type cmd & press ENTER. 3. Type ping 192.168.0.1 & press
ENTER.
1. Click Properties
2. Select TCP/IP
3. Click Properties
ISR Step By Step Configuration 13/7/2010
4
If the IDU does have IP 192.168.0.1 you will get a reply.
b) If there is no reply:
Check connectivity. Change NMS port
c) If it doesnt seem to be hardware related: Use Serial Connection to find out the IP (see User Manual). Use the IP you find to log in.
d) If serial cable is not available: Set ISR to default IP address (see User Manual). Repeat step a) (Check if it is the default IP) to verify IDU IP address has
been set to default.
ISR Step By Step Configuration 13/7/2010
5
B. Getting Connected 1. Logging In
To get connected to the ISR, follow the steps below:
1. To launch the browser (during this documentation Internet explorer will be used), double-click the application icon on the desktop:
The browser window appears:
2. Type the IP address of the IDU in the Address Bar and press Enter.
3. The Authentication Window will appear. Type User Name Type Password Set to Remember my password
Address Bar
2. Type Password
3. Set Remember my password
1. Type User Name
4. Press OK
ISR Step By Step Configuration 13/7/2010
6
4. The Web Graphical User Interface Screen will appear.
Final View
Menu Navigation Panel
Status Panel
Configuration Panel
1. Click to view
ISR Step By Step Configuration 13/7/2010
7
C. Checking Fundamental Hardware Operation
a) Perform an ODU Loop.
1. Select the Intralink ISR AnalysisLoopback Panel to view the ISR loop-back capabilities.
Note: Make sure that the remote site is not transmitting in the same frequency.
2. Check Status Panel for Loopback operation
Note: If status reveal problem (not Green) check the troubleshooting guide.
1. Select Loopback
2. Select the Local ODU
3. Set Duration to Indefinite
4. Press Start
2. Check that Loopback is enabled
3. Check that Tx Power is enabled
4. Check that RSL are green
5. Check that S/N is green (>19)
1. Check that ODU is Locked
ISR Step By Step Configuration 13/7/2010
8
b) Disable Loopback Test
1. Select the Intralink ISR AnalysisLoopback Panel to view the ISR loop-back capabilities.
2. Check Status Panel for normal operation
1. Select Loopback
2. Select the Local ODU
3. Press Stop
1. Check that ODU is Unlocked
2. Check that transmitter is active
3. Check that Tx Power is enabled
4. Check that RSL is red
5. Check that S/N is N/A
ISR Step By Step Configuration 13/7/2010
9
D. Upgrading the ISR Firmware
a) Install iPorter SW tool.
1. Run the executable (.exe) file to install the iPorter SW tool.
Note: The x.x.x will indicate the iPorter SW tool version.
2. Follow the wizard until the installation is complete.
b) Store in a familiar location the latest firmware package.
Note: The x.x.x will indicate Application Firmware _ Modem Firmware _ r Pack-age Revision.pkg
c) Check ISR firmware at Intralink ISR Administration Maintenance Reprogramming
Check Application
Check Modem Firmware
ISR Step By Step Configuration 13/7/2010
10
d) Run iPorter
1. To launch the iPorter tool press the windows Start button and select Start All Programs ISR iPorter
2. Click Browse to find and select the ISR firmware package of files to be used in this upgrade.
Note: Make sure that the firmware package versions (Application & Modem firm-ware) are newer than the ones loaded on the ISR (downgrade if not).
Click Next
3. Click Next
1. Click Browse
2. Select latest firmware package
ISR Step By Step Configuration 13/7/2010
11
3. Create a Summary Report.
4. Connect to the ISR
Note: User Name & Password will be provided by Intracom Telecomm (same as log-ging to ISR)
1. Select Text Option
2. Click Browse to specify Location & Title of the Report
3. Click Next
1. Indoor IP Address
2. User Name
3. Password
4. Click Next
ISR Step By Step Configuration 13/7/2010
12
5. Select SNMP Version
Note: The Community String will be provided by Intracom Telecomm.
6. iPorter will display the upgrade plan.
Note: By clicking Next the upgrade procedure will start.
1. Select Version 2
2. Type the Community String
3. Click Next
1. View Upgrade Plan
2. Click Next
ISR Step By Step Configuration 13/7/2010
13
7. The Status bar will display the update progress.
Note: If, while performing the firmware upgrade, the message "Lost network con-nection to ISR" appears, click Finish and re-do the firmware upgrade from step 1. The iPorter tool will start upgrading from the file it had stopped when the network connection loss occurred.
8. Modem Update
The iPorter will ask for approval before Modem Upgrade.
Note: If Modem firmware in package is older select Skip Next Action to continue the rest of the upgrade.
9. IDU Reboot
Click Continue
Click OK
ISR Step By Step Configuration 13/7/2010
14
10. Upgrade Finished
Note: If the application (iPorter) is not closed, it retains the last info typed. Thus if you need to upgrade more IDUs, you can avoid typing most of the fields.
11. Check ISR firmware at Intralink ISR Administration Maintenance Reprogramming
i. Make sure that the firmwares are the latest. ii. Toggle all firmware to Bank 1 (except if different Mode or FPGA used)
Click Finish
1. Check Firmware
3. Toggle to Bank1
2. Select Firmware that has Bank2 Active
ISR Step By Step Configuration 13/7/2010
15
E. Changing Network Configuration
1. Select the Intralink ISR AdministrationNetwork Configura-tionGeneral to view the Network Configuration Parameters.
2. Click OK to the popup window to change settings.
3. When new settings are applied connection will be lost.
4. Repeat step B(Getting Connected) using the new IP
1. Select General
2. Set IP
3. Set Netmask
4. Set Gateway
5. Press Update
Status Panel
ISR Step By Step Configuration 13/7/2010
16
F. Link Configuration 1. Set Devise Names
Select the Intralink ISR AdministrationDevise InformationDevise Names.
2. Set the Clock Select the Intralink ISR AdministrationDevise InformationSet Date & Time.
3. Press Update
2. Fill in Information
1. Select Device names
1. Select Set Date & Time
2. Select European
3. Set Date & Time
4. Press Update
ISR Step By Step Configuration 13/7/2010
17
3. Make Link Configuration
Select the Intralink ISR Link Configuration Radio Link Link Con-figuration.
a) Select ODU Operational Mode
Make appropriate selection as specified on WO. Standard Mode: Unprotected (1+0) Protected Non-Diversity: Hot Standby (1+1) {Uses only one frequency} Protected Diversity: Frequency Diversity (1+1) {Uses two frequencies} East-West Mode: Repeater Mode (2+0) {One IDU transmitting to two sites}
b) Select IDU Operational Mode
Select IDU Mode (Capacity-Channel Size-Modulation) according to WO.
Note: For full operation of the selected Mode the appropriate interfaces must be pre-sent.
1. Select Link Con-figuration
2. Select Operation Mode
3. Click Next
1. Select Operation Mode
2. Click Next
ISR Step By Step Configuration 13/7/2010
18
c) Select ODU Configuration
For Protected Diversity & East-West Mode you need to set the Tx power to each ODU.
Note: The range of the available Tx Power values will depend on the current modula-tion. Thus, if the required value is not present select the nearest one.
d) Select ODU Channel Selection.
For Protected Diversity & East-West Mode you need to set the frequency (different value) to each ODU.
1. Select Tx Power
2. Click Next
1. Select Manual Frequency Entry
2. Type the Frequency
3. Click Next
Only if link is established
ISR Step By Step Configuration 13/7/2010
19
e) Summary of Configuration Check the summary of the configuration that you have set and proceed to update. If incorrect settings have been set, select Redo to repeat Configuration.
f) Link Configuration will star.
12. Wait until Successful message appear.
1. Verify Configuration
2. Click Update
ISR Step By Step Configuration 13/7/2010
20
g) Restart IDU Select the Intralink ISR Administration Maintenance Reboot
Note: After the reboot repeat steps B Getting Connected to log in.
h) Set ODU Power
Select the Intralink ISR Link Configuration Radio Link ODU Power
Note: This step is required only if power was not set according to WO during step c) Select ODU Configuration
1. Select Reboot
2. Select IDU
3. Press Reboot
1. Select ODU Power
2. Select Tx Power
3. Press Update
Only if link is established
ISR Step By Step Configuration 13/7/2010
21
i) Set ODU Channel
Select the Intralink ISR Link Configuration Radio Link ODU Channel
For Protected Diversity & East-West Mode you need to set the frequency (different value) to each ODU.
Note: This step is required even if frequency was set according to WO during step d) Select ODU Channel Selection
4. Set ODU Tx Mute Config. (Only for Standard Mode 1+0)
Select the Intralink ISR Link Configuration Radio Link ODU Tx Mute Config.
1. Select ODU Channel
3. Type Frequency
4. Click Next
1. Select ODU Tx Mute Config.
2. Select Output Remains the Same
3. Click Update
2. Select Manual Frequency Entry
ISR Step By Step Configuration 13/7/2010
22
5. Set Protection Configuration. (Only for Protected Non-Diversity 1+1)
Select the Intralink ISR Link Configuration Radio Link Protection Con-figuration
Power down ODU after switch: Disabled Preferred ODU: East APS Switch: Enabled Remote Transmitter Switching: Enabled
6. Set ODU Configuration
Select the Intralink ISR Link Configuration Radio Link ODU Configura-tion
1. Select Protection Configuration
2. Select Settings
3. Click Update
1. Select ODU Con-figuration 2. Set SSW to 500 kHz
3. Select Enable
4. Click Update
ISR Step By Step Configuration 13/7/2010
23
7. Check Data Link
a) Select the Intralink ISR Link Configuration Data Link E1/T1 Ports
Make sure that the E1 configured are active (dark black letters). Click the E1/T1 link a second time to make sure the window is refreshed.
Note: If some E1 are inactive check ISR User Manual for E1/T1 Cannel Map con-figuration
G. Remote System Configuration
Repeat steps A to F for the remote station and then start the alignment procedure. Continue alignment until the specified receiving signal (RSSI) is reached. After the alignment check link correct operation.
1. Select E1/T1 Port Active
Not Active
2. Check if Active
3. Reselect E1/T1 Port
ISR Step By Step Configuration 13/7/2010
24
H. Link Monitoring 1. Status Panel
EAST MODEM: Bottom Modem WEST MODEM: Top Modem
ACTIVE: Transmitting & Receiving STANDBY: Receiving NA: Not Available ERROR: Available but with problems
RSL: Receiving Signal Level
S/N > 19 (Depends on Modulation)
1. Check if modems are locked
2. Check Status of the modems
3. Check correct Tx Power
4. Check correct RLS (3)
5. Check S/N Level
6. Check correct Frequency
7. Check correct Mode (Capacity)
8. Check correct IP
9. Check correct Local Host
ISR Step By Step Configuration 13/7/2010
25
2. Alarm Configuration
Select the Intralink ISR Analysis Alarms Configuration
Note: You can mask unnecessary alarms later on if required.
3. Active Alarms
Check if any of the alarms are unjustifiable.
Note: If unjustifiable alarms exist check troubleshooting in User Manual.
1. Select Configuration
2. Click Uncheck All Mask
3. Click Update
2. Check Alarms 1. Select Active
ISR Step By Step Configuration 13/7/2010
26
4. Alarms Thresholds
Select the Intralink ISR Analysis Alarms Threshold
Unless specified differently in WO, make the following settings:
5. Alarm History
Select the Intralink ISR Analysis Alarms History
1. Select Thresholds
1. Select History
2. Click Clear History
2. Set Thresholds
ISR Step By Step Configuration 13/7/2010
27
I. Upgrading the ODU Firmware
1. Checking ODU Firmware
Select the IntralinkISR Administration Maintenance Reprogramming Check ODU East & West (in case of 1+1) Firmware
Note: Make sure that the firmware version is newer than the ones loaded on the ODU (downgrade if not).
2. Disable Spiral Search Mode
East Firmware
West Firmware
1. Select Reprogramming
1. Select Disabled
2. Click Update
ISR Step By Step Configuration 13/7/2010
28
3. FTP Tool
For the upgrade procedure a FTP tool (Filezilla) will be used. DO NOT POWER DOWN THE IDU OR RESET ANY MODULE during the upgrade (even if the connection is lost).
a) Requirements
Filezilla version (3.2.6.1 and later). You can find a version from http://filezilla-project.org east_odu_fw.s19 is the ODU firmware for EAST ODU west_odu_fw.s19 is the ODU firmware for WEST ODU
b) Filezilla Settings
Open the Filezilla FTP Client. On the menu toolbar, select Edit Settings.
In the FileZilla Options window click Connection in the navigation tree. In the Timeout group-box, type 999 seconds.
2. Settings
1. Edit
ISR Step By Step Configuration 13/7/2010
29
In the Maximum Number of retries group-box, type 1 to set the number of retries.
In the FileZilla Options window click Transfers in the navigation tree. Click File types in the navigation tree. Select the Binary option button.
Click OK to apply settings
4. ODU Upgrade
a) Upgrade ODU West Firmware (only in 1+1)
Retries
Timeout
Binary
OK
ISR Step By Step Configuration 13/7/2010
30
Using Filezilla, upgrade West ODU firmware with the file provided (west_odu_fw.s19).
Open the Filezilla FTP Client. Type the Address of the ISR as well as the Username and Password
in the respective boxes and click Quickconnect.
In the Local Site (left bottom two panels) browse for the folder where ODU firmware is located.
Locate the west_odu_fw.s19 file and drag the file to the Remote Site panel. The file Status Bar will go to some percent below 100 and stop.
You have to wait ~10min even if the bar disappears. In the Management Tree window follow the links:
IntralinkISR Administration Maintenance Reprogramming Refresh the reprogramming screen in order to see at West firmware the new version (if not perform a controller reboot and check after if new Firmware has been up-loaded successfully). If not, repeat the procedure again with the West ODU firm-ware.
b) Upgrade ODU East Firmware
At this moment the West ODU is transmitting at both stations. Using Filezilla, up-grade East ODU firmware with the file provided (east_odu_fw.s19).
Open the Filezilla FTP Client. Type the Address of the ISR as well as the Username and Password in the
respective boxes and click Quickconnect.
1. Address Box
2. UserName Box
3. Password Box
4. Connect Button
Local (PC) Remote
(ISR)
ISR Step By Step Configuration 13/7/2010
31
In the Local Site (left bottom two panels) browse for the folder where ODU firmware is located. Locate the east_odu_fw.s19 file and drag the file to the Remote Site panel. The file Status Bar will go to some percent below 100 and stop.
You have to wait ~10min even if the bar disappears.
In the Management Tree window follow the links:
IntralinkISR Administration Maintenance Reprogramming Refresh the reprogramming screen in order to see at East firmware the new version (if not perform a controller reboot and check after if the new Firmware has been up-loaded successfully). If not, repeat the procedure again with the East ODU firm-ware.
5. Updating Tx Power level
In the Management Tree window follow the links: j) IntralinkISR Link Configuration Radio Link ODU Power and up-
date Tx power to required level (see h) Set ODU Power).
1. Address Box
2. UserName Box
3. Password Box
4. Connect Button
Local (PC) Remote
(ISR)
ISR Step By Step Configuration 13/7/2010
32
6. Enable Spiral Search Mode
7. Repeat the steps 1-6 for the remote station
1. Select Enable
2. Click Update