4. Inspection by Vendor / Subvendor
IRT for Cathodic Protection System
1. Inspection by ONGC/CA
Inspection Category: C
2. Inspection by ONGC / Third Party Inspection Agency (TPI of Company)
3. Inspection by Afcons / Afcons appointed TPI
Project: HRD Process Platform Inspection Requirement Table (Indicative)
A
C
T
I
V
I
T
I
E
S
No
Item:
IRT No. 00812-200-IRT-2410-01 Rev. 0
5. Certificate / Data to be submitted
STAGES OF INSPECTION INVOLVED.
Client: ONGCL
ONGC / CA
Note 2:Inspection and Certification by COMPANY / CA ; TPI / CONTRACTOR does not take away the responsibilities of the
vendor to supply a product conforming to the Purchase Order / Specification requirements.
CAT- BULK: Category BULK:Items under this category shall be inspected by Afcons/TPI (RINA) and issue the
releae note.Afcons/TPI (RINA) shall endorse all QC documents as " Reviewed and Accepted ''
Date:
Name:
Signature:
Note 3:If there is involvement of AI (Authrised Inspector) it shall be the responsibility of vendor to arrange for the same. TPI
CA shall not replace AI. Cost towards AI fees is deemed to be included in the quoted price for such equipment.
Note 4:This IRT is issued for the purpose of RFQ / Enquiry only and is subject to approval by CA / COMPANY.
Afcons / TPI (RINA)
Note 5: This IRT is for guidance and will be replaced by formal ITP / QAP to be submitted by the Vendors for Approval, base
on complete Engineering.Inspection will be based on approved vendor ITP / QAP and Project Technical Specifications