Page 1: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

IR-75 THRU THE VALLEY PRESENTATION • TRAFFIC ENGINEERING WORKSHOP, JUNE 5, 2019

Page 2: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

2 |

IR-75

THRU THE VALLEY

UPDATE R Scott Kramer, P.E.

D-8 Bridge Design Engineer

TTV Coordinator

ODOT District 8 Engineering

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Page 3: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

3 |

PROJECT OVERVIEW

o TTV – Thru The Valley is the

rehabilitation, and one lane

addition in each direction, of IR 75

from a little south of Cross County

Interchange to just south of the

IR 275 Outerbelt.

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 4: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

4 |

PROJECT OVERVIEW

o The project initially started out in

8 phases plus building demolition,

and now consists of 7 separate

phases plus demolition.

o Original phase numbering have

been retained to maintain

continuity with the NEPA

Document. TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 5: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

5 |

PROJECT OVERVIEW

• District sequenced construction

and prioritized the order of the

phases. • Building Demolition

• Phases in order of priority

• Fully Funded Phases: 1&2, 3

• Unfunded Phases: 8, 4, 5, 6

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 6: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

6 |

INDIVIDUAL PHASES

• Phase 1&2 is under construction with

additional needed funding being

provided though National Highway

Freight, SIB Loan and District

Preservation.

• Total: $118.2M, $90.0M for Const.

• Construction: 2017 through 2020

• Video

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 7: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

7 |

INDIVIDUAL PHASES

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 8: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

8 |

INDIVIDUAL PHASES

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 9: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

9 |

INDIVIDUAL PHASES

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 10: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

10 |

INDIVIDUAL PHASES

• Phase 3,

• I75 and Cross County Interchange.

• Replaces high speed NB Galbraith off ramp

with a fly over ramp configuration.

• Construction needs have been funded with

$51.4 million Multi-Lane Major Rehab.

• Total $53.4M

• Construction: 2024 through 2025

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 11: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

11 |

INDIVIDUAL PHASES

• Phase 8 (Not funded for Construction)

• IR-75 and Sharon Road Interchange.

• Will complete the IR75 4th lane addition from

the IR75 Split to the Montgomery County line

and connect the completed Phase 1&2 to

IR275 Outerbelt.

• Asking TRAC for $37.9M construction funding.

• Total Project Cost about $51.6M

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 12: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

12 |

INDIVIDUAL PHASES

• Phase 4 (Not funded for Construction)

• Prephase to replace NS Railroad’s bridge

north of Galbraith Road.

• Miami Erie Canal Built by the State of

Ohio in 1820’s.

• 1906, Railroad built bridge over canal.

• Rule of Causality - Railroad caused the

bridge to be built so the railroad owns

and maintains the bridge.

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 13: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

13 |

INDIVIDUAL PHASES

Phase 4 (Not funded for Construction)

• 1940’s, canal drained and 4 lane SH987

built.

• reduce impacts and costs.

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 14: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

14 |

INDIVIDUAL PHASES

Phase 4 (Not funded for Construction)

• 1960’s Converted to SB 75. As seen today.

• Up until 2013, ODOT was sending monthly

letters to railroad with structural concerns

for years.

• Railroad claimed bridge was in satisfactory

condition, and ODOT should pay for,

maintain, and own the future bridge.

• Railroad performed repairs in 2013

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 15: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

15 |

INDIVIDUAL PHASES

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 16: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

16 |

INDIVIDUAL PHASES

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 17: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

17 |

INDIVIDUAL PHASES

Phase 4 (Not funded for Construction)

• Reevaluated with an Alternative Technical

Concept that resulted in the railroad

taking over the ownership and

maintenance of the bridges for a savings of

$16 M in future maintenance.

• Estimated Construction cost $32M.

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 18: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

18 |

INDIVIDUAL PHASES

• Phase 5 (Not funded for Construction)

• Removes deficient on and off ramps to

Cooper Ave.

• Adds connection to Milsdale St. and CD

ramp to Galbraith Road.

• Adds a new connection from Galbraith to

WB SR 126.

• Estimated Construction cost $46M.

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 19: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

19 |

INDIVIDUAL PHASES

• Phase 6 (Not funded for Construction)

• Northbound 75 in the split.

• Traffic will be maintained with 3 lanes

south and north in the southbound split.

• New connection of westbound SR126 to

IR75 northbound.

• Loosing NB off ramp to Davis St.

• Construction Costs about $139M

• RW Cost about $40M

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 20: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

20 |

INDIVIDUAL PHASES

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124

Page 21: IR-75 THRU THE VALLEY PRESENTATION TRAFFIC ENGINEERING

21 |

SUMMARY

• Phase 1&2 • Construction till fall of 2020

• Phase 3 • Construction from 2024 through 2026

• Unfunded Phases in order of priority

• Phase 8, Sharon Road Interchange

• Phase 4, Replace RR Bridge in SB IR 75

• Phase 5, SB IR 75

• Phase 6, NB IR 75

TTV TRAFFIC ENGINEERING WORKSHOP UPDATE

Phase 8

HAM-75-14.61

PID 76256

Phases 1 & 2

HAM-75-12.60

PID 82288

Phase 5

HAM-75-10.87

PID 88132 Phase 6

HAM-75-10.62

PID 88133

Phase 4

HAM-75-11.09

PID 88129

Phase 3

HAM-75-10.10

PID 88124