OutlineBasic Definitions and Ideas• Reasons to Hold Inventory• Inventory CostsInventory Control Systems• Continuous Review Models

• Basic EOQ Model• Quantity Discounts• Safety Stock• Special Case: The News Vendor Problem

• Discrete Probability Example• Continuous Probability Example

• Periodic Review Model

What is Inventory?

• Inventory is a stock of items held to meet future demand.

• Inventory management answers two questions:– How much to order– When to order

Basic Concepts of Inventory Management can be expanded to apply to a broad array of types of “inventory”:

– Raw materials– Purchased parts and supplies– Labor– In-process (partially completed)

products– Component parts– Working capital– Tools, machinery, and equipment– Finished goods

Reasons to Hold Inventory

• Meet unexpected demand• Smooth seasonal or cyclical

demand• Meet variations in customer

demand• Take advantage of price discounts• Hedge against price increases• Quantity discounts

Two Forms of Demand

• Dependent– items used to produce final products

• Independent– items demanded by external

customers

Inventory Costs

• Carrying Cost– cost of holding an item in inventory

• Ordering Cost– cost of replenishing inventory

• Shortage Cost– temporary or permanent loss of sales

when demand cannot be met

Inventory Control Systems

• Fixed-order-quantity system (Continuous)– constant amount ordered when

inventory declines to predetermined level

• Fixed-time-period system (Periodic)– order placed for variable amount after

fixed passage of time

Continuous Review Models

• Basic EOQ Model• Quantity Discounts• Safety Stock

The Basic EOQ Model(Economic Order Quantity)

Assumptions of the Basic EOQ Model:

– Demand is known with certainty – Demand is relatively constant over

time– No shortages are allowed– Lead time for the receipt of orders is

constant– The order quantity is received all at

once

Inventory Order CycleBasic EOQ Model

-250

0

250

500

750

0 50 100 150 200 250 300 350 400 450 500 550 600 650 700

Days

Inve

nto

ry

EOQ Model Costs

S = cost of placing order D = annual demand

H = annual per-unit carrying cost Q = order quantity

Annual ordering cost = SD/ Q Annual carrying cost = HQ/ 2

Total cost = SD/ Q + HQ/ 2 Q* = Economic Order Quantity

EOQ Cost CurvesEOQ Example

0

250

500

750

1000

0 100 200 300 400 500 600 700 800 900 1000

Order Quantity

To

tal A

nn

ua

l Co

st OrderingHoldingTotal

EOQ Example

If D = 1,000 per year, S = $62.50 per order, and H = $0.50 per unit per year, what is the economic order quantity?

Q* HDS2

5.0

5.62*1000*2

500

Quantity DiscountsPrice per unit decreases as order quantity increases:

Quantity Price 1-49 $35.00 50-74 $34.75 75-149 $33.55 150-299 $32.35 300-499 $31.15 500+ $30.75

Quantity Discount Costs

demand annual=

priceunit per2

D

C

CDQH

QDS

TC

Quantity Discount Cost Curves

EOQ with Quantity Discounts

$70,000

$72,500

$75,000

$77,500

$80,000

$82,500

$85,000

0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 1000

Order Quantity

To

tal A

nn

ual

Co

st

0-4950-7475-149150-299300-499500+

Quantity Discount Algorithm

Step 1. Calculate a value for Q*.Step 2: For any discount, if the order

quantity is too low to qualify for the discount, adjust Q upward to the lowest feasible quantity.

Step 3: Calculate the total annual cost for each Q*.

Quantity Discount Algorithm

Step 1. Calculate a value for Q*.

Q* HDS2

33.3

10*400,2*2

120

Quantity Discount Algorithm

Step 2: For any discount, if the order quantity is too low to qualify for the discount, adjust Q* upward to the lowest feasible quantity.

Quantity Price Min Q* Adj. Q* 1-49 $35.00 1 120 120 50-74 $34.75 50 120 120 75-149 $33.55 75 120 120 150-299 $32.35 150 120 150 300-499 $31.15 300 120 300 500+ $30.75 500 120 500

EOQ with Quantity Discounts

$70,000

$72,500

$75,000

$77,500

$80,000

$82,500

$85,000

0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 1000

Order Quantity

To

tal A

nn

ual

Co

st

0-4950-7475-149150-299300-499500+

Quantity Discount Algorithm

Step 3: Calculate the total annual cost for each Q*.

Quantity Price Min Q* Adj. Q* Holding Cost Ordering Cost Purchasing Cost Total Cost 1-49 $35.00 1 120 120 $ 199.90 $ 199.90 $ 84,000.00 $84,399.80 50-74 $34.75 50 120 120 $ 199.90 $ 199.90 $ 83,400.00 $83,799.80 75-149 $33.55 75 120 120 $ 199.90 $ 199.90 $ 80,520.00 $80,919.80 150-299 $32.35 150 120 150 $ 249.75 $ 160.00 $ 77,640.00 $78,049.75 300-499 $31.15 300 120 300 $ 499.50 $ 80.00 $ 74,760.00 $75,339.50 500+ $30.75 500 120 500 $ 832.50 $ 48.00 $ 73,800.00 $74,680.50

EOQ with Quantity Discounts

$70,000

$72,500

$75,000

$77,500

$80,000

$82,500

$85,000

0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 1000

Order Quantity

To

tal

An

nu

al C

ost

When to Order

Reorder Point = level of inventory at which to place a new order (a.k.a. ROP, R)

R = dL

Where

d = demand rate per period

L = lead time

-250

0

250

500

750

0 50 100 150 200 250 300 350 400 450 500 550 600 650 700

Days

Inve

nto

ry

Lead time for one of your fastest-moving products is 21 days. Demand during this period averages 100 units per day. What would be an appropriate reorder point?

R dL

21*100

100,2

-1000

-500

0

500

1000

1500

2000

2500

3000

3500

4000

0 50 100 150 200 250 300 350

Days

Inv

en

tory

What About Random Demand?

(Or Random Lead Time?)

• Safety stock–buffer added to on-hand inventory

during lead time

• Stockout –an inventory shortage

• Service level –probability that the inventory

available during lead time will meet demand

Reorder Point with Variable Demand

(Leadtime is Constant)

stocksafetyz

z

L

d

zLdR

d

level service desired for deviations standard of number=

time lead during demand ofdeviation standard

demand daily ofdeviation standard

time lead=

demand daily average=

where,

A carpet store wants a reorder point with a 95% service level and a 5% stockout probability during the leadtime.

day per yards 5

days 10=

day per yards 30=

d

L

d

Determining the z-value for Service Level

L=

L=

L=

=

d

2d

2d

deviation Standard

time) lead of days of (number x variances) (dailyDemand Time Lead of Variance

yards 1.26)10)(5)(65.1(stock Safety

yards 1.3261.26300)10)(5)(65.1()10)(30(

day per yards 5

days 10=

day per yards 30=

z

zLdR

L

d

d

Determining the Safety Stock from the z-value

What If Leadtime is Random?

Random Variable Mean Standard Deviation

L = Leadtime L L

d = Demand d d

dL = Demand during Leadtime Ld 222Ld dL

Special Case: The Newsboy Problem

The News Vendor Problem is a special “single period” version of the EOQ model, where the product drops in value after a relatively brief selling period. The name comes from newspapers, which are much less valuable after the day they are originally published. This model may be useful for any product with a short product life cycle, such as • Time-sensitive Materials (newspapers,

magazines)• Fashion Goods (some kinds of apparel)• Perishable Goods (some food products)

Two new assumptions:

• There are two distinct selling periods: • an initial period in which the product is sold at a

regular price• a subsequent period in which the item is sold at a

lower “salvage” price.

• Two revenue values: • a regular price P, at which the product can be sold

during the initial selling period• a salvage value V, at which the product can be sold

after the initial selling period.

The salvage value is frequently less than the cost of production C, and in general we wish to avoid selling units at the salvage price.

“Damned if you do; damned if you don’t”: • If we order too many, there will be extra

units left over to be sold at the disadvantageous salvage price.

• If we order too few, some customer demand will not be satisfied, and we will forego the profits that could have been made from selling to the customer.

C = $8.00

P = $20.00

V = $4.00

Demand Probability 300 0.05 400 0.10 500 0.40 600 0.30 700 0.10 800 0.05

Discrete Probability Example

Newsboy Solution

In this case, it is useful to examine the marginal benefit from each unit purchased. The expected profit from any unit purchased is:

Expected Profit = P(Selling at Regular Price)*(Profit if Sold at Regular Price) + P(Selling at Salvage Price)*(Profit if Sold at Salvage Price)

= P(Selling at Regular Price)*(P - C) + P(Selling at Salvage Price)*(V - C)

Demand Probability 300 0.05 400 0.10 500 0.40 600 0.30 700 0.10 800 0.05

Demand P(Sell) P(Not Sell) 300 1.00 0.00 400 0.95 0.05 500 0.85 0.15 600 0.45 0.55 700 0.15 0.85 800 0.05 0.95

Demand Prob. P(Sell) Profit if Sold P(Not Sell) Profit if Not Sold Weighted Average Profit 300 0.05 1.00 $ 12.00 0.00 $ (4.00) $ 12.00 400 0.10 0.95 $ 12.00 0.05 $ (4.00) $ 11.20 500 0.40 0.85 $ 12.00 0.15 $ (4.00) $ 9.60 600 0.30 0.45 $ 12.00 0.55 $ (4.00) $ 3.20 700 0.10 0.15 $ 12.00 0.85 $ (4.00) $ (1.60) 800 0.05 0.05 $ 12.00 0.95 $ (4.00) $ (3.20)

Based on this analysis, we would order 600 units.

Marginal Expected Profit

$(4)

$(2)

$-

$2

$4

$6

$8

$10

$12

$14

0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 9501000

Quantity Ordered

Total Expected Profit

$-

$1,000

$2,000

$3,000

$4,000

$5,000

$6,000

$7,000

0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 9501000

Quantity Ordered

Continuous Probability Example

Using the same mean and standard deviation as in the previous case (545.0 and 111.7), what would be optimal if demand were normally distributed?

Define CO and CU to be the “costs” of over-ordering and under-ordering, respectively.

In this case: CO CV

84

00.4$

CU CP

820

00.12$

It can be shown that the optimal order quantity is the value in the demand distribution that corresponds to the “critical probability”:

Critical probability OU

U

CCC

412

12

1612

75.0

From the standard normal table, the z-value corresponding to a 0.75 probability is 0.6745.

Q 6745.0

7.1116745.00.545

3.620

Periodic Review Models

Sometimes a continuous review system doesn’t make sense, as when the item is not very expensive to carry, and/or when the customers don’t mind waiting for a backorder. A periodic review system only checks inventory and places orders at fixed intervals of time.

A basic periodic review system might work as follows:

Every T time periods, check the inventory level I, and order enough to bring inventory back up to some predetermined level.

This “order-up-to” level should be enough to cover expected demand during the lead time, plus the time that will elapse before the next periodic review.

ILTdQ

We might also build some safety stock in to the “order-up-to” quantity.

IzLTdQ LT

B01.2314 -- Operations -- Prof. Juran

53

What is Supply-Chain Management?

Supply-chain management is a total system approach to managing the entire flow of information, materials, and services from raw-material suppliers through factories and warehouses to the end customer

B01.2314 -- Operations -- Prof. Juran

54

What is a Supply-Chain?

Supply-chain is a term that describes how organizations (suppliers, manufacturers, distributors, and customers) are linked together

Services Suppliers Service Support

Operations Local Service

Providers Customers

Supply Networks

Inputs Transformation Localization Output

Manufacturing Suppliers Manufacturing Distribution Customers

B01.2314 -- Operations -- Prof. Juran

55

Measures of Supply-Chain Performance• One of the most commonly used measures in all of

operations management is “Inventory Turnover”

• In situations where distribution inventory is dominant, “Weeks of Supply” is preferred and measures how many weeks’ worth of inventory is in the system at a particular time

valueinventory aggregate Average

sold goods ofCost turnoverInventory

weeks52 sold goods ofCost

valueinventory aggregate Averagesupply of Weeks

B01.2314 -- Operations -- Prof. Juran

56

Example: Supply-Chain Performance

Measurement Suppose a company’s new annual report claims their costs of goods sold for the year is $160 million and their total average inventory (production materials + work-in-process) is worth $35 million. This company normally has an inventory turn ratio of 10.

What is this year’s Inventory Turnover ratio?

What does it mean?

Suppose a company’s new annual report claims their costs of goods sold for the year is $160 million and their total average inventory (production materials + work-in-process) is worth $35 million. This company normally has an inventory turn ratio of 10.

What is this year’s Inventory Turnover ratio?

What does it mean?

B01.2314 -- Operations -- Prof. Juran

57

valueinventory aggregate Average

sold goods ofCost turnoverInventory

123

A B CCOGS 160,000,000$ Avg Inventory 35,000,000$ Turnover 4.57

=B1/B2

B01.2314 -- Operations -- Prof. Juran

58

Since the company’s normal inventory turnover ratio is 10, a drop to 4.57 means that the inventory is not turning over as quickly as it had in the past.

In other words, they now have more inventory relative to their cost of goods sold than before.

What else would you want to know about this situation?

B01.2314 -- Operations -- Prof. Juran

59

Supply Chain Strategy

Marshall Fisher:• Adverse effects of price

promotions• Functional vs. Innovative products

B01.2314 -- Operations -- Prof. Juran

60

Hau Lee’s Supply Chain Concepts

• Hau Lee’s approach to supply chains centers on aligning the supply chain with process side uncertainties (focus on the supply side)

• A stable supply process has mature technologies and an evolving supply process has rapidly changing technologies

• Types of Supply Chains– Efficient– Risk-Hedging– Responsive– Agile

B01.2314 -- Operations -- Prof. Juran

61

Demand Characteristics Supply Characteristics Functional Innovative Stable Evolving

Low demand Uncertainty High demand Uncertainty Few breakdowns Vulnerable to breakdowns More predictable demand Difficult to forecast Stable and higher yields Variable and lower yields Stable Demand Variable Demand Few quality problems Potential quality problems Long product life Short selling season More supply sources Limited supply sources Low inventory cost High inventory cost Reliable suppliers Unreliable suppliers Low profit margin High profit margin Few process changes More process changes Low product variety High product variety Few capacity constraints Potential capacity constraints Higher volume Low volume Easy to change over Difficult to change over Low stockout cost High stockout cost Flexible Inflexible Low obsolescence High obsolescence Dependable lead times Variable lead times

B01.2314 -- Operations -- Prof. Juran

62

Hau Lee’s Uncertainty Framework

Low Demand Uncertainty

(Functional Products)

High Demand Uncertainty

(Innovative Products)

Low Supply Uncertainty

(Stable Process)

Efficient Supply Chain

(Grocery, Basic Apparel, Food, Oil and Gas)

Responsive Supply Chain

(Fashion Apparel, Computers, Popular Music)

High Supply Uncertainty

(Evolving Process)

Risk-hedging Supply Chain

(Hydroelectric Power, Some Food Produce)

Agile Supply Chain

(Telecom, High-end Computers, Semiconductors)

B01.2314 -- Operations -- Prof. Juran

63

Value Density

• Value density is defined as the value of an item per pound of weight

• An important measure when deciding where items should be stocked geographically and how they should be shipped

B01.2314 -- Operations -- Prof. Juran

64

Mass Customization

• Mass customization is a term used to describe the ability of a company to deliver highly customized products and services to different customers

• The key to mass customization is effectively postponing the tasks of differentiating a product for a specific customer until the latest possible point in the supply-chain network

B01.2314 -- Operations -- Prof. Juran

65

Mass Customization• Principle 1: A product should be

designed so it consists of independent modules that can be assembled into different forms of the product easily and inexpensively.

• Principle 2: Manufacturing and service processes should be designed so that they consist of independent modules that can be moved or rearranged easily to support different distribution network strategies.

B01.2314 -- Operations -- Prof. Juran

66

Mass Customization

• Principle 3: The supply network — the positioning of the inventory and the location, number, and structure of service, manufacturing, and distribution facilities — should be designed to provide two capabilities. First, it must be able to supply the basic product to the facilities performing the customization in a cost-effective manner. Second, it must have the flexibility and the responsiveness to take individual customers’ orders and deliver the finished, customized good quickly.

B01.2314 -- Operations -- Prof. Juran

67

Summary

• Supply-Chain Management• Measuring Supply-Chain Performance• Outsourcing• Value Density• Mass Customization

SummaryBasic Definitions and Ideas• Reasons to Hold Inventory• Inventory CostsInventory Control Systems• Continuous Review Models

• Basic EOQ Model• Quantity Discounts• Safety Stock• Special Case: The News Vendor Problem

• Discrete Probability Example• Continuous Probability Example

• Periodic Review Model