51
Introduction to the China-ADS project and accelerator design Jingyu Tang Jingyu Tang Institute of High Energy Physics, CAS Institute of High Energy Physics, CAS Beijing, China Beijing, China FNAL Seminar, August 18, 2011 FNAL Seminar, August 18, 2011

Introduction to the China-ADS project and accelerator design

  • Upload
    maj

  • View
    55

  • Download
    0

Embed Size (px)

DESCRIPTION

Introduction to the China-ADS project and accelerator design. Jingyu Tang Institute of High Energy Physics, CAS Beijing, China. FNAL Seminar, August 18, 2011. Contents. Introduction to the C-ADS project Some information about China nuclear power Roadmap of C-ADS program - PowerPoint PPT Presentation

Citation preview

Page 1: Introduction to the China-ADS project and accelerator design

Introduction to the China-ADS project and accelerator design

Jingyu TangJingyu Tang

Institute of High Energy Physics, CASInstitute of High Energy Physics, CASBeijing, ChinaBeijing, China

FNAL Seminar, August 18, 2011FNAL Seminar, August 18, 2011

Page 2: Introduction to the China-ADS project and accelerator design

Contents

Introduction to the C-ADS projectSome information about China nuclear powerRoadmap of C-ADS program Organization of the C-ADS project phase I

Preliminary accelerator designPhysics design schemeKey technology R&D for C-ADS accelerator

2

Page 3: Introduction to the China-ADS project and accelerator design

Introduction to the C-ADS project

Page 4: Introduction to the China-ADS project and accelerator design

Nuclear Power in ChinaOperating reactors : 10.23 GWe/13 setsConstructing reactors : 25.90 GWe/23 setsPrepare to construct : 44.27 GWe/39 setsPropose to construct : 120.0 GWe/120 sets

2020 70GWe ( 5% total electricity ) 2030200GWe ( 10% total electricity ) 2050400GWe ( 22% total electricity )May be more than total nuclear power in the world right now !

Page 5: Introduction to the China-ADS project and accelerator design

Nuclear waste accumulated by 2050 in China

5

Year 2000 2010 2020 2050

Power (GW) 6 20 40 240

Spend fuel (t) 7200 >50000

Minor actinides (t) 4 >30

Long live fission products (t)

17 >120

Page 6: Introduction to the China-ADS project and accelerator design

The strategy of sustainable fission energy in China consoled by top Chinese scientists:

Gen-IV reactors for nuclear fuel breeding ADS for transmutation

Nuclear waste is a bottleneck for nuclear power development. ADS has been recognized as a good option for nuclear waste

transmutation. As a long-term program, ADS and TMSR (Thorium-based Melten

Salt Reactor) R&Ds will be supported by CAS. Budgets for C-ADS and TMSR (both Phase 1) have been

allocated by the central government.

Advanced Nuclear Energy Programs in China

6

Page 7: Introduction to the China-ADS project and accelerator design

Special Nuclear Energy Program in CAS TMSR - Diversify nuclear fuel source (Thorium is richer than uranium and

more dispersed on the earth, less waste etc.)

ADS - Transmutation of long-lived nuclear

waste

~2032, - Demo facilities for industrial

applications

Page 8: Introduction to the China-ADS project and accelerator design

Schematic of C-ADS

8

ProtonNeutron

Proton Linear Accelerator (IHEP, IMP)

Liquid-metal Target (IMP)

Reactor (PbBi coolant )(IPP, USTC)

Page 9: Introduction to the China-ADS project and accelerator design

Roadmap of C-ADS program

RFQ + HWR

RFQ + Spoke

2013~5 MeV

201525~50 MeV

201X50/150 MeV

~20220.6~1 GeV

~20321.2~1.5 GeV

5~10 MWt 100 MWt ≥1 GWt

Development of injectors

IndividualIntegrations

Integral test Phase II target/reactor

Phase III target/reactor

10 MeV

Phase I R&D Facility

Phase II Experiment Facility

Phase III DEMO. Facility

Page 10: Introduction to the China-ADS project and accelerator design

R&D Team & Sites for C-ADS

Team• CAS: IHEP, IMP, IPP, USTC, …• 3 NP Com. + Univ.• Local government cooperation • International collaboration

Host of the future facility• A new CAS institute will be established to host the C-ADS facility Site candidate: Erdos (Inner Mongolia)

R&D infrastructure Labs and infrastructure at the home institutes before the new

institute is ready

10

Page 11: Introduction to the China-ADS project and accelerator design

Organization of C-ADS Phases 0&I Three major systems

Accelerator: IHEP as leader, responsible for one injector and the main

linac andIMP as collaborator, responsible for another injectorJoint IHEP-IMP group on accelerator physics Target: IMP as leader Reactor: IPP (Institute of Plasma Physics, as leader) and

USTC (University of Science and Technology of China)

Page 12: Introduction to the China-ADS project and accelerator design

Infrastructure (to be built in leading institutes) Superconducting RF test platform Radio-chemistry study platform Pb-Bi core simulation and mock-up platform Nuclear database Integrated test and general technical support platform

Page 13: Introduction to the China-ADS project and accelerator design

Preliminary design of the C-ADS accelerator

Page 14: Introduction to the China-ADS project and accelerator design

Main specifications of the C-ADS driver linac

Particle Proton Energy 1.5 GeVCurrent 10 mA

Beam power 15 MW

Frequency 162.5/325/650 MHz

Duty factor 100 %Beam loss <1 (or 0.3) W/m

Beam trips/year

<25000<2500<25

1s<t<10s10s<t<5m

t>5m

Page 15: Introduction to the China-ADS project and accelerator design

Design philosophy Accelerator choice: superconducting linac is

preferred. Straight trajectory: easy extraction and injection. Easy upgrading. Large aperture. Low AC power consumption. Independently powered structures.

To meet the very strict reliability requirement De-rating of critical components (over-design). Component redundancy and spares on line. Component failure tolerance.

Page 16: Introduction to the China-ADS project and accelerator design

LEBT MEBT1RFQ 162.5MHzECR

SC-HWR 162.5MHz16 cavities

LEBT MEBT1RFQ 325.0MHzECR

Spoke012 325MHz

18 cavities

Spoke021 325MHz 32 cavities

Spoke040 325MHz80 cavities

Elliptical 063 650MHz32 cavities

Elliptical 082 650 MHz85 cavities

Injector II

Injector I

MEBT2

10MeV 40 MeV 180 MeV 360 MeV 1500 MeV

2.1 MeV

3.2 MeV

Layout of the C-ADS linac

Main linac

‘ Hot stand-by’

Local compensation

Two identical injectors on line, either with scheme injector-1 or with scheme injector-2

Page 17: Introduction to the China-ADS project and accelerator design

Lattice design requirements for high-intensity proton linacs

Zero current phase advance of transverse and longitudinal oscillations should be kept below 90o per focusing period to avoid parametric resonance.

Transverse and longitudinal wavenumbers must change adiabatically.

Avoid energy exchange between the transverse and longitudinal planes via space-charge resonances.

Provide proper matching in the lattice transitions to avoid serious halo formation.

Page 18: Introduction to the China-ADS project and accelerator design

The RFQ RFQs are the only accelerating components in

room- temperature It is very difficult to develop a CW proton RFQ due to

very large heat load density Four-rod structure Different choice on RF frequency: 162.5 or 325 MHz

Design constraints from the previous RFQ experience at IHEP: Section length: <1.2 Number of sections: <4

Page 19: Introduction to the China-ADS project and accelerator design

Max Density:

(3.77 kW/cm2)

Page 20: Introduction to the China-ADS project and accelerator design

MEBT1 layout

Page 21: Introduction to the China-ADS project and accelerator design

Spoke012 cavities

g

Freq.

MHz

Uacc. Max

MV

Emax

MV/m

Bmax

mTR/Q

0.12 325 0.63 25 42 125

R = 216 mm

79 mm

30 mm

190 mm

100 mm

110 mm

50 mm120 mm

0.08 0.10 0.12 0.14 0.16 0.18 0.20

0.2

0.4

0.6

0.8

1.0

Veff. V/Vmax

V/Vm

ax

0.1

0.2

0.3

0.4

0.5

0.6

Veff /MV

Page 22: Introduction to the China-ADS project and accelerator design

螺线管,长度300mm

BPM, 长度50mm

190424

超导腔,长度424

190424

190424

190424

190424

190424

190424

190424

190424

190424

40020013060400190424

190424

190424

190424

190424

190424

190424

190424

190424

400 200 130 60 400

8206 mm

Lattice design of spoke012 section: Solution 1

190

424

Anti-symmetric lattice18 cavities16 solenoids2 cryomodules with length of 8.2 m;

Page 23: Introduction to the China-ADS project and accelerator design

Dynamics study results

RMS envelope <3 mmMaximum envelope < 10 mm

Page 24: Introduction to the China-ADS project and accelerator design

Emittance growth

Transverse emittance growth < 7%Longitudinal growth: <10%

Page 25: Introduction to the China-ADS project and accelerator design

Solution 2: one crymodule with increased acceleration gradient

Solenoid length=300 mm

BPM, length=100 mm

190424

Cavity 012,length=424 mm

190424

190424

190424

190424

190424

190424

190424

190424

190424

400

11.112 m

190424

190424

190424

190424

400

Total: 13 cavities, 12 solenoids

Maximum surface electric field is increased from 25 to 33 MV/m

Maximum surface magnetic field is still below mT

Page 26: Introduction to the China-ADS project and accelerator design

Dynamics study results

RMS envelope: < 2 mmMaximum beam size: < 6 mm

Page 27: Introduction to the China-ADS project and accelerator design

Emittance growth

Transverse emittance growth: < 2%Longitudinal emittance growth:< 4%

Page 28: Introduction to the China-ADS project and accelerator design

Solution 3: based on spoke cavities on 3/2 mode

Motivation Poor performance of very

low beta cavityMechanical stabilityFrequency stability

Method with 3/2 mode Increasing the gap width

and stem thickness Gains

Rigidity, Frequency sensitivity, Voltage

Demerit Narrower range (one

more type cavity)

238 mm

160 mm

250 mm

80 mm60 mm

144 mm

140 mm

120 mm

Page 29: Introduction to the China-ADS project and accelerator design

Lattice based on 3/2 cavities

Solenoid length=250 mm

BPM, length=100 mm

250

484

250

484

250

484

250

484

250

484300

534

300

534

300

534

300

534

300

534

300

534

300

534

Total number of cavities: 12 M_spoke026: 5 M_spoke036: 7 Maximum surface field: 32.5 MV/m CM length: 10.8 m;

Page 30: Introduction to the China-ADS project and accelerator design

Dynamics study results

Page 31: Introduction to the China-ADS project and accelerator design

MEBT2

No buncher in dispersive section

5 Quad+ 2 bend for achromatism and keep beam envelope smooth

3 bunchers for longitudinal matching (2 are standard Spoke021 cells)

Translational distance 45cm for magnet installation

One branch (of two): 10 Quad +5 Buncher + 2 solenoid+2 Bend Total length is 12 m.

Page 32: Introduction to the China-ADS project and accelerator design

List of superconducting cavities in main linac

Cavity type

gFreq.MHz

Uacc. MaxMV

EmaxMV/m

BmaxmT

single spoke 0.21 325 1.32 25/32.5 44.8/58.2

Single spoke 0.40 325 2.79 25/32.5 64.8/84.2

5-cell elliptical 0.63 650 7.68 35/45.5 48.3/62.8

5-cell elliptical 0.82 650 15.47 35/45.5 70.4/91.5

Page 33: Introduction to the China-ADS project and accelerator design

Acceleration efficiency

1 、 Efficiency for each cavity is greater than 0.5;

2 、 Acceleration gradient changes smoothly at the transition between different sections;

Page 34: Introduction to the China-ADS project and accelerator design

Lattice design: Spoke021 and Spoke040

•Period length: 2.168 m•Total periods: 14•Total cavities: 28•Energy range: 10~34 MeV

•Period length: 3.8 m •Total periods: 18•Total cavities: 72•Energy range: 34~178 MeV

SolenoidCavity 021

250

484

Cavity 021

250

484

BPM

400 400100300

Cavity 040

380

600

Cavity 040

380

600

Cavity 040

380

600

Cavity 040

380

600

BPM

400 100 100300

100 400

Page 35: Introduction to the China-ADS project and accelerator design

Lattice design: Ellip063

727 727 727 727

500 500 500900 900

500

300

500

•Period length: 7.508 m•Total periods: 7•Total cavities: 28•Energy range: 178~367 MeV

Page 36: Introduction to the China-ADS project and accelerator design

Lattice design: Ellip082

946 946 946 946

504851.5

852

500

300

946

504 504 504 300

500

852

•Period length: 9.75 m•Total periods: 17•Total cavities: 85•Energy range: 367~1500 MeV

Page 37: Introduction to the China-ADS project and accelerator design

Dynamics study results

Page 38: Introduction to the China-ADS project and accelerator design

Zero-current phase advance

Page 39: Introduction to the China-ADS project and accelerator design

Emittance evolution

Page 40: Introduction to the China-ADS project and accelerator design

Energy gain

No:14*2=2810-33.8MeV

No:18*4=7233.8-178MeV

No: 7*4=28178-367MeV

No:17*5=85367-1541MeVSpoke cavities: 100

Elliptical cavities: 113

Page 41: Introduction to the China-ADS project and accelerator design

Local compensation of failures

Preliminary studies on local compensation of cavity and solenoid failures have been carried out for Spoke021 section and Spoke040 section.

One cavity failure in a cell can be well compensated by adjusting neighboring cavities. (rms emittance growth less than 10%)

One solenoid failure is difficult to be compensated, especially at the beginning of the Spoke021 section

Page 42: Introduction to the China-ADS project and accelerator design

Failure compensation at Spoke021 section

Energy compensation

pointMatching solenoids

Matching cavities

Page 43: Introduction to the China-ADS project and accelerator design

Key technology R&D for C-ADS linac

43

Strategy Parallel developments of different scheme or technical solutions for

the injector (IHEP and IMP) Development by steps (Phase 0, I, II, III)

Some key technology R&D Ion Source: stable operation CW RFQ: cooling problem SC Spoke cavities: development, unproven performance SC CH cavities: very challenging (candidate for IMP injector) High power couplers: especially for CW RFQ Cryomodule: long cryomodule with many cavities and solenoids RF power source (CW Klystron, CW SSA, LLRF) Control & Instrumentation …

Page 44: Introduction to the China-ADS project and accelerator design

R&D studies (Phase 0) The budget has been approved (1.8 BCHY or 280 M$ in total)

Accelerator: 640 MCHY (425 M for IHEP and 215 M for IMP) 2011-2013

Physics design and technical designsDeveloping CW RFQ, SC cavity prototypes (spoke, HWR and CH) for the injectorsCW test of first 5 MeV of two injectorsInfrastructure or laboratory building-up

2014-2016Two different injectors testing with CW, 10-MeV and 10-mAConstruction of main linac section (10-50 MeV)CW test of the 50-MeV linac

44

Page 45: Introduction to the China-ADS project and accelerator design

x 7.200mm 181.973mrad

x*******Deg 2.400KeV

x 7.200mm 181.973mrad

x*******Deg 2.400KeV NP1= 1 NP2= 5 100.00 mm(Horizontal) 480000.0 Deg.(Longitudinal)

100.00 mm(Vertical) Length= 1306.00 mm

1

2SOL

3

4SOL

5

H A= 0.00 B=0.267E-01 V A= 0.00 B=0.267E-01

Z A=-4.40 B=0.222E+09

BEAM AT NEL1= 1H A= 1.35 B=0.773E-01 V A= 1.35 B=0.773E-01

Z A=-4.27 B=0.222E+09

BEAM AT NEL2= 5 I= 54731.3 mAW= 0.0500 0.0500 MeV

FREQ= 325.00 MHz WL= 922.44 mmEMITI= 150.000 150.000109163.58EMITO= 150.000 150.000109163.58

N1= 1 N2= 5

MATCHING TYPE = 5DESIRED VALUES (BEAMF) alpha betax 1.3540 0.0773

MATCH VARIABLES (NC=2)MPP MPE VALUE 1 2 2389.25818 1 4 2137.42273

P B O Lab T R A C E DATE: 02-05-2010TIME: 08:29:48

H A= 0.00 B=0.267E-01 V A= 0.00 B=0.267E-01

Z A=-4.40 B=0.314E+09

BEAM AT NEL1= 1

H A= 6.48 B= 14.4 V A= 6.48 B= 14.4

Z A=-4.22 B=0.314E+09

BEAM AT NEL2= 5

H A= 0.00 B=0.267E-01 V A= 0.00 B=0.267E-01

Z A=-4.40 B=0.385E+09

BEAM AT NEL1= 1

H A=-4.41 B= 29.9 V A=-4.41 B= 29.9

Z A=-4.19 B=0.385E+09

BEAM AT NEL2= 5

H+ 、 H2+ & H3

+

Beam profile

Some R&D work already carried out

45

Ion Source: ECR & LEBT (IMP)

Page 46: Introduction to the China-ADS project and accelerator design

High-duty factor RFQ (IHEP)

973 RFQ ADS RFQ

Frequency 352MHz 325MHz

Energy 3.5MeV 3MeV

Duty Factor ~15% CW

Operating Short time Long time

A 3.5 MeV - 40 mA RFQ of 7-15% duty factor (supported by “973” program) was constructed and commissioned at IHEP, one of the most powerful RFQs under operation condition.

46

Page 47: Introduction to the China-ADS project and accelerator design

High power input couplers (IHEP)

47

≥400kW

(Supported by the BEPC SC cavity development program)

Page 48: Introduction to the China-ADS project and accelerator design

Cryomodules (IHEP)

4848Cryomodule named PXFEL1 was passed the cryogenic test at DESY in July. 2009.

Cryomodule for BEPCII 500MHz SC Cavity

Page 49: Introduction to the China-ADS project and accelerator design

Control & Instrumentation (IHEP)

Controls: Digitalized control system has been developed for the

CSNS project, and can be used in the C-ADS EPICS, XAL etc. developed with the CSNS project

(BEPCII) Instrumentation

Many beam diagnostic devices have been developed or are under development under the “973” program and the CSNS project. They can be used in the C-ADS, such as BLM (including ion chamber, FBLM), BPM, BCT, Wire Scanner, double-slit emittance measurement system.

49

Page 50: Introduction to the China-ADS project and accelerator design

SummaryI. Sustainable nuclear energy has high priority in China.II. The C-ADS program has been officially started under the

coordination of CAS, and is led by three CAS institutes.III. The R&D phase for the driver linac is to build a SC linac with a

CW beam of 50-MeV and 10-mA, and relevant infrastructure.IV. It is a great challenge to build a high-performance CW proton

linac. Strong collaboration with international leading laboratories is very important. This is not only an important step towards the ADS but also a contribution to the accelerator community.

50

Page 51: Introduction to the China-ADS project and accelerator design

Thanks for your Thanks for your attentionattention!!

51