Upload
anhuga
View
65
Download
10
Embed Size (px)
Citation preview
AN INTRODUCTION TO LNG
Presentation to the 45 th Annual GGA Measurement School
Presentation to 45th Annual CGA Measurement School 2 June 7, 2006
Presentation Outline
Ø What is LNG? Ø Uses of LNG Ø Components of an LNG Plant Ø LNG Storage Ø LNG Risks and Vulnerabilities Ø Safety Record Ø LNG – the Past Ø LNG – the Future Ø Canadian LNG Standard Ø New Technical Developments
Presentation to 45th Annual CGA Measurement School 3 June 7, 2006
What is LNG? Ø LNG (Liquefied Natural Gas) is natural gas cooled until it condenses into a clear liquid.
Ø Odourless, colourless, noncorrosive and nontoxic
Ø Normally stored at 162 o Celsius (260 o F) at atmospheric pressure in a “thermos” like storage container.
Ø Takes up far less space – about 1/600 th of its original volume as a gas.
Ø Weighs approximately 45% as much as water
Ø LNG (the liquid itself) is not flammable or explosive.
Ø Vapour is initially heavier than air. Ø As the vapour warms it becomes lighter
thanair Ø Natural Gas is flammable when it occurs
in a 5% to 15% concentration in air.
Presentation to 45th Annual CGA Measurement School 4 June 7, 2006
Uses of LNG
Ø Peak Shaving Ø Base Load (import / export) Ø Gas Supply to Remote Facilities Ø Emergency / Temporary Supply Ø Vehicle Fuel
Presentation to 45th Annual CGA Measurement School 5 June 7, 2006
The Terasen Gas Peakshaving Plant
The Tilbury Island LNG Plant: •Converts pipeline gas to Liquefied Natural Gas (LNG) through a refrigeration process •Stores the LNG at cryogenic temperatures (260 0 F) until needed •Regasifies LNG and injects it into the Lower Mainland transmission system during short periods of peak customer demand
Presentation to 45th Annual CGA Measurement School 6 June 7, 2006
Production of LNG 4 Key Steps Step 1Gas pretreatment Ø Molecular sieve removes CO2, water, odourant and
other impurities Ø These impurities, normally present in pipeline gas,
would freeze during LNG liquefaction process and plug the heat exchangers in the coldbox (see below)
Step 2Liquefaction Ø Warm gas is passed through a series of complex
heat exchangers Ø Gas is cooled by the vapourization of liquid
refrigerants (butane, propane, ethane, methane and nitrogen) which progressively lower the termperature of the gas until it changes to liquid state
Presentation to 45th Annual CGA Measurement School 7 June 7, 2006
Production of LNG (cont.) Step 3LNG Storage Ø LNG is maintained at 162 0 C (260 0 F) Ø Tank volume is 28,000 cubic metres (1 million
cubic feet) or 6 million Imperial gallons Ø Tank is 36 metres high (118 feet), 39 metres
diameter (127 feet) Ø The one million cubic feet of LNG stored in the tank
is equivalent to 600 million (0.6 billion) cubic feet of natural gas once regasified
Step 4LNG Regasification (or vapourization) Ø LNG is heated from 162 0 C (260 0 F) to
approximately 5 0 C Ø During peak demand, the vapourizers can send out
as much as 150 million cubic feet of gas per day
Presentation to 45th Annual CGA Measurement School 8 June 7, 2006
Pictorial Summary of LNG Plant Processes
Preheater
Boiloff Compressor
LNG Vaporizers
LNG Tank
LNG Tanker Unloading & Loading
to Transmission Pipeline System
LNG Pumps
Feed Gas
Tail Gas
Dessication Liquefaction
Pretreatment
(From Transmission System)
Step 1 Step 2
LNG Storage
Step 3
Step 4
Presentation to 45th Annual CGA Measurement School 9 June 7, 2006
Peakshaving Applications
Ø Small plants (relative to baseload plants) Ø Seasonal use Ø Improve load factor for Local Distribution Companies (LDC)
Gas Supply Savings Ø Operational benefits include Security of Supply, System
Reinforcement, and Operation Flexibility (trim) Ø Most North American plants built in 1960s to mid 1975
(70+) Ø More plants are built starting in late 1980s and 1990s (3+)
Presentation to 45th Annual CGA Measurement School 10 June 7, 2006
LNG Plants in North America
Presentation to 45th Annual CGA Measurement School 11 June 7, 2006
Production (Export) Terminal
LNG Storage
Loading Jetty and Ship
LNG Pumps
Feed Gas (From Production Field)
Pretreatment
Liquefaction
Ship Loading
Step 2
Step 4
Step 1
Step 3
Presentation to 45th Annual CGA Measurement School 12 June 7, 2006
Alaska Liquefaction (Export) Plant
Presentation to 45th Annual CGA Measurement School 13 June 7, 2006
Arzew (Algeria) Liquefaction (Export) Plant
Presentation to 45th Annual CGA Measurement School 14 June 7, 2006
Facilities in Asia
Presentation to 45th Annual CGA Measurement School 15 June 7, 2006
Facilities in Japan
Presentation to 45th Annual CGA Measurement School 16 June 7, 2006
Facilities in Europe
Presentation to 45th Annual CGA Measurement School 17 June 7, 2006
Facilities in North and South America
Presentation to 45th Annual CGA Measurement School 18 June 7, 2006
Marine Tanker (Spherical Tanks)
Presentation to 45th Annual CGA Measurement School 19 June 7, 2006
Marine Tanker (Cubic Tanks)
Presentation to 45th Annual CGA Measurement School 20 June 7, 2006
Receiving (Import) Terminal
LNG Storage
LNG Pumps
Pretreatment
Ship Unloading Step 1
Step 2
Step 3
Step 4
To Transmission Pipeline System
LNG Vaporizers
Loading Jetty and Ship
Presentation to 45th Annual CGA Measurement School 21 June 7, 2006
Import Facility – Cove Point, Maryland
Presentation to 45th Annual CGA Measurement School 22 June 7, 2006
Import Facility Tokyo
Presentation to 45th Annual CGA Measurement School 23 June 7, 2006
Proposed Irving Oil Import Terminal (St John, New Brunswick)
Presentation to 45th Annual CGA Measurement School 24 June 7, 2006
Other Uses of LNG
Ø Supply Remote Facilities Ø Emergency / Temporary Supply Ø Vehicle Fuel
Presentation to 45th Annual CGA Measurement School 25 June 7, 2006
Remote Facilities
Ø Supply to remote communities or industrial facilities Ø LNG Supply from baseload facility or peakshaving plant Ø LNG Trailers used for transportation of LNG
Presentation to 45th Annual CGA Measurement School 26 June 7, 2006
Supply to Sawmill in BC Interior
Presentation to 45th Annual CGA Measurement School 27 June 7, 2006
Emergency or Temporary Supply
Ø LNG Tanker and Ambient Vapourizer used for various temporary gas supply situations
Ø Supply small sections of a distribution system or critical customers during system alterations
Ø Supply small communities in emergency situations
Presentation to 45th Annual CGA Measurement School 28 June 7, 2006
Temporary LNG Supply
Presentation to 45th Annual CGA Measurement School 29 June 7, 2006
LNG as a Vehicle Fuel
Ø Commonly Used for Trucks Ø LNG has been used for other Transportation Modes Ø Railway locomotives Ø Marine vessels Ø Planes (experimental)
Presentation to 45th Annual CGA Measurement School 30 June 7, 2006
Truck Being Fueled with LNG
Presentation to 45th Annual CGA Measurement School 31 June 7, 2006
Houston Metro LNG Bus
Presentation to 45th Annual CGA Measurement School 32 June 7, 2006
Burlington Northern LNG Locomotive
•20,000 Gallon LNG Tender (coal train) •Test run from Wyoming to Minnesota
Presentation to 45th Annual CGA Measurement School 33 June 7, 2006
Storage
Ø Well insulated, nonrefrigerated tank Ø LNG @ near atmospheric pressure (a maximum of 2 psig) Ø LNG @ 160 oC (or 260 oF) near the boiling point of LNG Ø Boiloff (evaporation) keeps the remaining LNG refrigerated. Ø Excessive boiloff is removed by boiloff compressor to prevent over
pressurizing the tank Ø Additional relief valves to prevent rapid buildup of vapour due to
sudden drop in atmospheric pressure (e.g. low pressure storm) Ø Two Levels of Earthquake Design: Ø Operating Basis Earthquake (OBE) Ø operational during and after OBE
Ø Safe Shutdown Earthquake (SSE) Ø no loss of containment during and after SSE
Presentation to 45th Annual CGA Measurement School 34 June 7, 2006
Types of LNG Storage Tanks
ØNext series of slides will illustrate several types of LNG Storage tanks and containment systems ØPrimary tank types are: Ø Single Containment Ø Double Containment Ø Full Containment
Presentation to 45th Annual CGA Measurement School 35 June 7, 2006
Single Containment Tank with Earthen Dyke
Presentation to 45th Annual CGA Measurement School 36 June 7, 2006
Single Containment Tank
Presentation to 45th Annual CGA Measurement School 37 June 7, 2006
Double Containment Tank
Presentation to 45th Annual CGA Measurement School 38 June 7, 2006
Full Containment Tank
Presentation to 45th Annual CGA Measurement School 39 June 7, 2006
LNG Risks and Vulnerabilities
Ø Primary Hazards Ø Pool Fires (Thermal Radiation) Ø Flammable Vapour Clouds
Ø Secondary Hazards Ø Freezing Liquid and Cold Vapour Ø Rapid Phase Transitions (Flameless Explosions) Ø Rollover
Presentation to 45th Annual CGA Measurement School 40 June 7, 2006
Potential Failure Mechanisms
Ø Land Facilities Ø Natural Hazards Ø Earthquakes
Ø Material Failures Ø Operating Errors
Ø Marine Vessels Ø Ship Accidents
Ø Common Threats Ø Terrorism
Presentation to 45th Annual CGA Measurement School 41 June 7, 2006
Hazard Mitigation
Ø Conservative Codes and Standard Ø Prescriptive Separation Distances Ø Conservative Design Criteria Ø Good Design and Construction Management Practices Ø Good Operating, Maintenance and Training Programs
Presentation to 45th Annual CGA Measurement School 42 June 7, 2006
Safety Record A Few Worldwide Statistics Ø 17 export facilities Ø 40 import facilities Ø 113 active LNG facilities in the US Ø 136 LNG Ships Ø In 40 years, 33,000 LNG carrier voyages covering more than 60 million miles Ø Ships frequently operate in high density areas Ø In 2000, one ship entered Tokyo Bay every 20 hours on average Ø Some incidents (some LNG spillage but no cargo fires) but no major
accidents either in port or on the high seas
Ø Source – Introduction to LNG, University of Houston Law Center, Institute for Energy, Law & Enterprise, January 2003
Presentation to 45th Annual CGA Measurement School 43 June 7, 2006
Safety Record – Major Accidents
Ø Cleveland, Ohio, 1944 Ø Tank failure with 128 deaths
Ø Staten Island, New York, 1973 Ø Industrial accident unrelated to presence of LNG Ø 40 workers died
Ø Cove Point, Maryland, 1979 Ø Explosion in electrical substation due to vapour migration Ø 1 operator died, another seriously injured
Ø Skikda, Algeria, 2004 Ø Explosion and Fire Ø Multiple deaths
Presentation to 45th Annual CGA Measurement School 44 June 7, 2006
LNG – The Past
1873 Karl Von Linde built first practical compressor refrigeration machine
1917 First US LNG plant begins operation in West Virginia 1941 First commercial LNG plant, Cleveland, Ohio 1959 First LNG tanker (Methane Pioneer) delivered LNG from Lake
Charles, LA to Canvey Island, UK 1964 UK becomes the world’s first LNG importer and Algeria the first
exporter 1964 – Alabama Gas begins construction of a peakshaving plant 1969 – First US export of LNG (Alaska to Japan) 1971 to 1980 – 4 import terminals built in the US 1999 – First Atlantic Basin liquefaction plant (Trinidad)
Presentation to 45th Annual CGA Measurement School 45 June 7, 2006
LNG – The Future (North America)
Presentation to 45th Annual CGA Measurement School 46 June 7, 2006
LNG – The Future (North America)
Presentation to 45th Annual CGA Measurement School 47 June 7, 2006
CSA LNG Standard – Z276 Liquefied Natural Gas (LNG) – Production, Storage and Handling
This standard applies to the design, location, construction, operation and maintenance of facilities at any location for the liquefaction of natural gas and for the storage, vapourization, transfer, handling and truck transport of LNG as well as the training of personnel involved.
The standard does not apply to Ø The transportation of refrigerants by any means Ø The transportation of LNG by railcar, marine vessel, or pipeline Ø Facilities designed to allow the use of LNG as a fuel for highway
vehicles, railroad locomotives or marine vessels
Presentation to 45th Annual CGA Measurement School 48 June 7, 2006
CSA Z276 Technical Committee
Owner/Operators Ø Enbridge Ø Gaz Metro Ø Irving Oil Ø Terasen Gas Ø TransCanada Ø Union Gas
Government/Regulatory Ø NEB Ø BC Ø NS Ø NB Ø NRCan Ø PQ
Other Interests Ø Brytech Ø CB&I Ø CDS Research Ø Ind Consultant (Seismic) Ø Ind Consultant (TC Chair) Ø Westport Innovations Ø Cdn Welding Bureau
Presentation to 45th Annual CGA Measurement School 49 June 7, 2006
Proximity to the Public
Presentation to 45th Annual CGA Measurement School 50 June 7, 2006
Off Shore ReGasification and Connecting Pipeline (Excelerate Energy – Energy Bridge System)
Presentation to 45th Annual CGA Measurement School 51 June 7, 2006
Off Shore Gravity Based Structure (CB&I)
Presentation to 45th Annual CGA Measurement School 52 June 7, 2006
Off Shore Gravity Based Structure
Presentation to 45th Annual CGA Measurement School 53 June 7, 2006
That’s All Folks!!
Thanks for your attention
Questions ???