94
School of Engineering and Information Technology Integrated Water Systems of The Grove Library: Optimisation via Data Analysis from an Automated Building Management System (BMS) A report submitted to the school of Engineering and Information Technology, Murdoch University in partial fulfilment of the requirements for the Bachelor of Engineering” Gelareh Khakbaz Unit Coordinator: Dr. Gareth Lee Academic Supervisor: Dr. Martin Anda Industry supervisors: Dr. Stewart Dallas, JBA Michael Whitbread, Shire of Peppermint Grove

Integrated Water Systems of The Grove Library

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

School of Engineering and Information Technology

Integrated Water Systems of The Grove

Library: Optimisation via Data Analysis from an

Automated Building Management System (BMS)

“A report submitted to the school of Engineering and Information Technology,

Murdoch University in partial fulfilment of the requirements for the Bachelor of

Engineering”

Gelareh Khakbaz

Unit Coordinator:

Dr. Gareth Lee

Academic Supervisor:

Dr. Martin Anda

Industry supervisors: Dr. Stewart Dallas, JBA

Michael Whitbread, Shire of Peppermint Grove

2

Executive Summary

This study is an attempt to uncover the underlying operation and maintenance issues in

sustaining the operation of an automated green building with focus on its water systems. The

Grove Library is a public building in Peppermint Grove, Western Australia, with smart design

aimed to address environmentally sustainable concepts in their entirety.

A sophisticated Building Management System (BMS) integrates the operation of the entire

Environmentally Sustainable Design (ESD) systems in operation at The Grove. However a

number of continual breakdowns in the operation of the ESD water systems, namely wastewater,

rainwater and irrigation systems, lead to high levels of disappointment for the people managing

and operating these systems. This is the first time that data have been extracted from the BMS.

Prior to this study, it was possible to quantify the performance of any of the ESD water systems.

This has resulted in the inability of external contractors to monitor the ESD systems’ operation.

This study discussed the factors contributing to this situation using data analysis as the main

method for troubleshooting and investigating the causes to these breakdowns. Upon achieving a

good understanding of the situation, the recommendations were able to be formulated.

It was found that the current situation with the ESD water systems at The Grove is a

consequence of some interrelated factors forming a ‘vicious circle’. The ESD systems, their

maintenance, the BMS and the management were the key factors identified as responsible for the

issues in The Grove. The recommendations produced in this study were mainly on the technical

side of the problem, that is, the BMS, ESD water systems and their maintenance. In order to

overcome the issues at The Grove this relationship among these factors should be recognised and

established.

3

Acknowledgement

I would like to acknowledge Dr. Martin Anda of Murdoch University; Dr. Stewart Dallas,

Josh Byrne & Associates; Michael Whitbread, Shire of Peppermint Grove; Dr. Ross

Mars, Water Installations, Andrew Crabtree, IBMS; and Don Jagodage, Honeywell, who

made this work possible with their support throughout the course of this project.

4

List of Abbreviations & Acronyms

ABGR: Australian Building Greenhouse Rating scheme

NABERS: National Australian Built Environment Rating Systems

BEMS: Building Energy Management System

BMCS: Building Monitoring and Control System

BMS: Building Management System

BW: Brown Water (system at The Grove)

DoH: Department of Health

DEWR: Department of the Environment and Water Resources

EMS: Energy Manager Server

ESD: Environmentally Sustainable Design

GBCA: Green Building Council of Australia

GHG: Greenhouse Gas

GW: Greywater (system at The Grove)

HVAC: Heating, Ventilation, and Air Conditioning

I/O Schedule: Input Output Schedule document

O/M: Operation and Maintenance

RW: Rainwater (system at The Grove)

SW: Stormwater (system at The Grove)

UV: Ultraviolet (disinfectant unit at the Grove)

WA: Western Australia

YW: Yellow Water (system at The Grove)

5

Table of Contents

Executive Summary ........................................................................................................... 2

Acknowledgement .............................................................................................................. 3

List of Abbreviations & Acronyms .................................................................................. 4

Table of Contents ............................................................................................................... 5

List of Figures .................................................................................................................... 8

Chapter 1: Introduction .................................................................................................. 11

1.1. Background .................................................................................................................... 11

1.2. Literature Review ........................................................................................................... 13

1.3. Objectives ....................................................................................................................... 14

1.4. Scope .............................................................................................................................. 15

1.5. Methodology .................................................................................................................. 16

1.6. Structure of Thesis ......................................................................................................... 16

Chapter 2: Systems at The Grove .................................................................................. 18

2.1. Building Management System (BMS) ........................................................................... 18

2.1.1. Introduction to the BMS ......................................................................................... 18

2.1.2. BMS at The Grove .................................................................................................. 18

2.2. Environmentally Sustainable Design (ESD) Systems .................................................... 20

2.2.1. Rainwater Systems .................................................................................................. 20

2.2.2. Wastewater Systems ............................................................................................... 23

2.2.3. Irrigation ................................................................................................................. 29

Chapter 3: The Performance of the ESD Systems ....................................................... 32

3.1. BMS Performance .......................................................................................................... 32

3.1.1. Data Access and Extraction .................................................................................... 33

6

3.1.2. Reporting Output .................................................................................................... 33

3.1.3. Maintenance Scheduling ......................................................................................... 34

3.1.4. Document Complications........................................................................................ 34

3.1.5. Tag-naming System ................................................................................................ 35

3.2. ESD Water Systems’ Performance ................................................................................ 35

3.2.1. Rainwater (RW) Status ........................................................................................... 35

3.2.2. Wastewater Systems Status..................................................................................... 37

3.2.3. Irrigation Status ....................................................................................................... 39

Chapter 4: Data Analysis of the ESD Water Systems .................................................. 42

4.1. Rainwater Systems (RW) Data Analysis ....................................................................... 42

4.2. Yellow Water (YW) Data Analysis ............................................................................... 45

4.3. Greywater (GW) Data Analysis ..................................................................................... 46

4.4. Brown Water (BW) Data Analysis................................................................................. 48

Chapter 5: Problems and Recommendations ............................................................... 52

5.1. Problems with the BMS ................................................................................................. 52

5.2. Problems with the ESD Water Systems ......................................................................... 53

5.2.1. Rainwater (RW) Systems ........................................................................................ 53

5.2.2. Wastewater Systems ............................................................................................... 55

5.2.3. Irrigation ................................................................................................................. 58

5.3. Problems with Documentation ....................................................................................... 59

Chapter 6: Conclusion..................................................................................................... 61

6.1. Project Conclusion ......................................................................................................... 61

6.2. Future Research Opportunities ....................................................................................... 63

Chapter 7: Reflection ...................................................................................................... 64

7.1. “Vicious Circle” at The Grove ....................................................................................... 64

7

7.2. Lessons Learnt on the Performance of Smart Buildings ................................................ 68

References ......................................................................................................................... 69

Appendices ....................................................................................................................... 73

Appendix A: Instructions on Data Extraction from the BMS................................................... 73

Appendix B: The BMS Backup Support .................................................................................. 78

Appendix C: ESD Water Systems’ Layout at The Grove......................................................... 81

Appendix D: Field Visit with the Water Contractor ................................................................. 88

8

List of Figures

Figure 1 Location of The Grove Library, taken from (Google Maps, 2013) .................................. 12

Figure 2 A snapshot of the BMS homepage ................................................................................. 19

Figure 3 A snapshot of the BMS showing some historical trends ................................................. 19

Figure 4 Schematic presentation of rainwater design system at The Grove (The Grove Precinct,

2012) ............................................................................................................................................. 21

Figure 5 Cross section drawing of the stormwater system, adapted from (adapted from COX

Howlett & Bailey Woodland, 2008) .............................................................................................. 22

Figure 6 Picture showing inside of a settling tank at The Grove .................................................. 22

Figure 7 Schematic design of integrated wastewater systems at The Grove (adapted from (The

Grove Precinct, 2012) .................................................................................................................... 23

Figure 8 Diagrammatic presentation of wastewater systems setup ............................................ 24

Figure 9 A picture of the YW system components ........................................................................ 25

Figure 10 Schematic diagram of the YW operation at The Grove ............................................... 25

Figure 11 A picture of the GW system components ..................................................................... 26

Figure 12 Schematic diagram of the GW system at The Grove .................................................... 26

Figure 13 A picture of the BW system components ...................................................................... 27

Figure 14 Schematic diagram showing the Biolytix operation according to its design ................ 28

Figure 15 Drip-line setup at The Grove (Picture from (Anda, 2012), from the early stages of

setting the irrigation line) ............................................................................................................. 29

Figure 16 Landscape of The Grove with irrigation hydrozones, adapted from (Huxtable, 2012) 31

Figure 17 A schematic of the BW system operation after its shut down (All the BW is diverted to

the sewer) ..................................................................................................................................... 38

Figure 18 Picture of damaged greywater line at The Grove......................................................... 40

Figure 19 Picture of damaged BW irrigation line at The Grove ................................................... 41

Figure 20 Historical trends of rainwater tanks’ levels for the period of July 2011 to March 2013

....................................................................................................................................................... 42

9

Figure 21 Rainfall events during the period of July 2011 to March 2013 (Bureau of Meteorology,

2013) ............................................................................................................................................. 43

Figure 22 Historical Trends of rainwater tanks’ levels for the period of Jan 2013 to May 2013.. 44

Figure 23 Rain gauge status in 6 minute intervals during 25 April 2013 to 02 May 2013 ........... 44

Figure 24 Cumulative rainwater volume at The Grove during Feb 2013 to May 2013 ................ 45

Figure 25 Historical trends of yellow water tanks’ levels for the period of August 2011 to March

2013 .............................................................................................................................................. 46

Figure 26 Historical trends of greywater tank level for the period of July 2011 to March 2013.. 47

Figure 27 Historical trends of greywater tank level for the period of Jan 2012 to August 2012 . 48

Figure 28 Historical trends of greywater tank level for the period of June 2012 to March 2013 48

Figure 29 Historical trends of brown water tank level for the period of July 2011 to March 2013

....................................................................................................................................................... 49

Figure 30 Historical trends of brown water tank level for the period of August 2011 to

September 2012 ............................................................................................................................ 50

Figure 31 Historical trends of brown water tank level for the period of mid-September 2012 to

March 2013 (after shutting the Biolytix system) .......................................................................... 50

Figure 32 Brown water tank level changes in 10-11 March 2012 ................................................ 51

Figure 33 Interrelated factors contributing to the complications and issues at The Grove ......... 64

Figure 34 A Snapshot of the The Grove BMS Trends page ........................................................... 74

Figure 35 A Snapshot of the The Grove BMS Trends configuration page .................................... 75

Figure 36 A Snapshot of the The Grove BMS Trends configuration page with points names ...... 75

Figure 37 Snapshots of the The Grove BMS Trend Configuration a) View b) Period, c) Interval, d)

Selector and e)Scale selection tabs ............................................................................................... 76

Figure 38 Snapshot of the The Grove BMS final trend ................................................................. 77

Figure 39 Rainwater system’s layout and details at The Grove (Water Installations, 2009) ....... 81

Figure 40 Plan view of the stormwater system's layout at the Grove (COX Howlett & Bailey

Woodland, 2008) .......................................................................................................................... 82

Figure 41 Layout of the wastewater systems at The Grove, (Water Installations, 2009) ............ 83

Figure 42 Yellow water system’s layout and details at The Grove (Water Installations, 2009) ... 84

10

Figure 43 Greywater system's layout and details at The Grove (Water Installations, 2009) ....... 85

Figure 44 Brown water system's layout and details at The Grove (Water Installations, 2009) ... 86

Figure 45 Irrigation design layout of The Grove (Water Design International, 2008) ................. 87

Figure 46 Picture showing the inside of a full yellow water tank ................................................ 90

Figure 47 Picture showing the inside of the greywater pump tank at The Grove ........................ 91

Figure 48 A picture of inside of the Biolytix tank at The Grove .................................................... 93

11

Chapter 1: Introduction

This dissertation forms the final assessable component of the ENG460 Engineering Thesis for

the Bachelor of Engineering at Murdoch University. The aim of performing a specialised study is

to demonstrate the following competencies for an engineering student:

To be able to examine, analyse and report on a design or research of a problem and

demonstrate a level of mastery of the subject area;

To be able to undertake the necessary research and/or design practice to produce a

solution/outcome for the set task; and

To be able to present the results/ findings of the work through both verbal and written

presentations

1.1. Background

The Grove Library is recognised as a state-of-art building in terms of green building technology

in Western Australia. The Grove building comprises a new library, community learning centre

and administration office for the Shire of Peppermint Grove located at 1 Leake St (Corner of

Stirling Hwy), Peppermint Grove, Western Australia. The design of the building commenced in

2007 with the collaboration of the Shire of Peppermint Grove (Shire of Peppermint Grove,

2012), the Town of Mosman Park (Town of Mosman Park, 2012) and the Town of Cottesloe

(Town of Cottesloe, 2012). Figure 1 presents an aerial map showing the location of The Grove

(Google Maps, 2013; Whereis, 2011). The Grove is an iconic building in terms of the

‘Environmentally Sustainable Design’ (ESD) systems incorporating a sophisticated Building

Management System (BMS) in charge of monitoring and to some extent controlling the water

and energy use in the building and landscape irrigation systems.

12

Figure 1 Location of The Grove Library at the a) country scale; b) region scale; c) street scale (Google Maps,

2013)

The main purpose of The Grove creation is to demonstrate the environmental benefits of the

ESD systems in a green building to encourage the community to adopt these practices for their

personal use. This will ideally result in the reduction in water and energy consumption levels and

subsequent reduction in greenhouse gas (GHG) emissions. The BMS was established to report on

the operation and quantify the environmental benefits of the ESD systems.

However, some breakdowns of the ESD water systems, namely, wastewater, rainwater and

irrigation, caused disappointment for people operating and managing them. This raised the

opportunity for involvement of a third party to study and comment further on the operation of

these systems.

This work is the first attempt to study and troubleshoot these systems since the commencement

of their operation in 2011. This study represents that data were accessed from the BMS for

13

analysing and commenting on the operation of the ESD system for the first time. It is expected

the findings will provide a base for future studies at The Grove.

1.2. Literature Review

Research into smart buildings and their monitoring systems found most of the current studies to

be focused on energy management systems (Ahmed, et al., 2010; Levermore, 2003; Marinakis,

et al., 2013; Medved, 2006). Not many studies are dealing with data analysis of the ESD water

systems. It is also noteworthy that there is not a widespread agreement on the definition of a

BMS, considering its capabilities and limitations. Different terms are used in this sense, such as

Building Monitoring and Control System (BMCS), Building Automation and Control Tool

(Marinakis, et al., 2013), or Building Information and Control System ICT-based BMS’s

(Aghemo, et al., 2013). For more details refer to section “‎2.1.1. Introduction to the BMS”.

In general most of the smart buildings worldwide using automated systems for monitoring their

performance have limitations in processing the monitored data in order to produce practical

information to improve the building’s performance (Ahmed, et al., 2010; Marinakis, et al.,

2013). In that sense the data analysis for the environmental optimisation of the building is an

issue that most of the building automation and control systems are facing.

One purpose of green public buildings is for them to demonstrate innovative sustainable designs

which can reduce consumption and GHG emissions (Deng, et al., 2011). One case study on a

multi-functional green building in Shanghai Jiao Tong University is on energy systems design

and GHG emission reduction being the main emphasis (Deng, et al., 2011). This paper relates to

The Grove study in terms of an automated control system for different systems and the multi-

level functioning building with ESD energy systems.

The Green Building Council of Australia (GBCA) provides guidelines and education for

promoting sustainable building construction or renovation in Australia (GBC Australia, 2012).

The GBCA provides green star guidelines for particular requirements for BMS, ESD,

commissioning and monitoring of buildings (GBC Australia, 2012). One case study exemplifies

a six-star commercial building located on 40 Albert Road, Melbourne incorporating innovative

sustainable technologies to aim for the first zero-emission building in Australia (GBC Australia,

14

2008). Some other examples of GBCA accredited buildings in Australia are the 5-star rated 8

Brindable Circuit building in Canberra, City Central Tower 1 in Adelaide and the Morgan

Stanley Tenancy at 30 The Bond, Sydney (GBCA, 2012). BMS and ESD features in these

building are specially designed for commercial buildings under urban conditions. All these

buildings showcase the integration of BMS into a green stared building.

The Australian Building Greenhouse Rating scheme (ABGR, 2013) and the National Australian

Built Environment Rating Systems (NABERS, 2013) are two performance benchmarks for

commercial buildings. These initiatives for environmental performance are used as commercial

buildings’ rating systems. The ABGR scheme is a universal rating system dealing with GHG

emissions of buildings, whereas the NABERS is the sustainability rating system for existing

buildings developed by the Department of the Environment and Water Resources (DEWR).

In recent years, the concept of sustainable buildings has been developed substantially. New

clarifications in determining a sustainable building have emerged. Environmental factors

together with socio-economic aspects form critical issues to a sustainable building (Berardi,

2013). Relevant to this research, the new concept of ‘sustainable building’ was introduced in

assessing The Grove.

The environmental and economic challenge of transformation to a green building industry is

another area of special interest for many of the related papers. For example, LSE Cities (2012)

introduces a comparison for the green technology barriers and opportunities of 53 cities around

the world. This study provides a deeper insight into the present and future of green and smart

building technology and can be used as a reference.

1.3. Objectives

Identify the faults with the ESD water systems

In order to find the solution to the problems, it was first important to identify the individual faults

with each system, e.g., a tank’s faulty water level sensor resulting in malfunctioning of the

rainwater system.

15

Extract data from the BMS and analyse data to study operational trends of the ESD water

systems

Extracting and analysing the stored data from different sensors of the ESD water systems from

the BMS was next objective. This will allow an understanding of the historical trends and

possible anomalies in the operation of the water systems.

Liaise with external contractors and the Peppermint Grove Shire to study past and future

decisions regarding the ESD water systems

External contractors who were involved in designing and maintaining the systems as well as the

Shire of Peppermint Grove are important sources for uncovering the past and future trends of

decisions made and subsequent actions for different systems. Therefore liaising with these

parties will produce invaluable information and possible solutions for the current problems at

The Grove.

Outline issues with the ESD systems according to the data retrieved from the BMS

The next objective of this study is to investigate the underlying causes of the problems at The

Grove. By determining the underlying factors causing the current problems with the ESD water

systems, it is hoped to find the answers to them.

Produce recommendations for optimisation of the ESD water systems and the BMS

The final stage of this study is to produce recommendations for rectification of the faults and

shortcomings with the BMS and ESD water systems at The Grove.

1.4. Scope

The scope of this study mainly concerns data analysis to define the problems with the ESD water

systems at The Grove. The recommendations will then be produced for the optimisation of the

situation. The choice of the ESD systems requires further analysis; this is not within the scope of

this study. The final decision is to be made by the Shire upon considering the final costs and

other policies involved. A list of further research opportunities is included in Chapter 6.

16

1.5. Methodology

The main method used in this study was an analysis of data from the BMS to study the historical

trends and the anomalies in the ESD water systems. From this point semi-structured interviews

with involved parties in maintenance, operation and management of the systems shed light on the

cause of the issues with the water systems. Speicific and general recommendations for the

problems were then developed to enhance the operation of the ESD water systems at The Grove.

The list of tasks throughout The Grove project is as follows:

a) Researching the principal ESD features at The Grove and similar systems worldwide

(with main focus on water systems)

b) Becoming familiarised with the BMS and the principal ESD water systems’ technologies

c) Liaising with persons involved in operating and managing the systems to capture their

experience of the ESD water systems’ operations

d) Extracting data from the BMS and document the process for future references

e) Analysing the extracted data from the BMS

f) Investigating the performance of the ESD technologies using data analysis strategies

g) Producing recommendations for improving the ESD systems’ operations

1.6. Structure of Thesis

The structure of this study as follows:

Chapter 2: Introduces different systems at The Grove that make it a smart and green building,

namely the BMS and the ESD systems.

Chapter 3: Elaborates on the problems with different ESD water systems as well as the BMS

status at The Grove.

Chapter 4: Analysis of data taken from the BMS on different ESD water systems, explaining

historical trends and anomalies in each system.

17

Chapter 5: Lists the faults and associated recommendations to rectify the problems with the

BMS, ESD water systems and document control at The Grove.

Chapter 6: Summarises the findings on the operation of the ESD water systems and suggests

future research opportunities on The Grove building.

Chapter 7: Provides a reflection on the cause of the current issues by introducing a ‘vicious

circle’ at The Grove with remedial recommendations for improving the situation.

18

Chapter 2: Systems at The Grove

2.1. Building Management System (BMS)

2.1.1. Introduction to the BMS

BMS is a general term referring to an automation and control tool used for monitoring and

controlling the operation of different systems in a building (Medved, 2006). The presence of

such an automated control system makes a building ‘smart’. It is noteworthy that different

terminologies are used to refer to such systems, specifying their main operation. Building

Monitoring and Control System (BMCS) is a more specific term used when an automated system

is in charge of both monitoring and controlling building operations. Not all the BMSs are

BMCSs, but all of the BMCSs are considered to have the capabilities of a BMS. Other automated

systems are mainly in charge of controlling and monitoring the energy and alarm systems in a

building (Levermore, 2003); these systems which prevail more in the ‘smart’ building industry,

are referred to as Building Energy Management Systems (BEMS) (Levermore, 2003).

2.1.2. BMS at The Grove

The automated system at The Grove is referred to as the BMS which is mostly in charge of

monitoring and to some extent controlling the systems as cited in Honeywell website, accessed

May 13, 2013 (Honeywell, 2010). The BMS was installed by Honeywell; integrating all the ESD

energy, HVAC, alarm and water systems into one automated ‘smart’ setup as shown in Figure 2.

This version of BMS is outdated being of 2007 vintage, so having some limitations in accessing

data and setting up sensors (Refer to section “‎3.1. BMS Performance”).

There are two computerised control stations located at The Grove from which the BMS can be

accessed, one being in the Shire’s office and the other in the car park area. The system is

designed to display the status of each ESD system (Figure 3) and its historical trends. The BMS

has the capability of both controlling and monitoring the lighting, alarm, and HVAC systems.

Water systems, on the other hand, can mainly be monitored and the controlling of them is not

supported through the current BMS.

19

Figure 2 A snapshot of the BMS homepage

Figure 3 A snapshot of the BMS showing rainwater summary

20

2.2. Environmentally Sustainable Design (ESD) Systems

The ESD systems at The Grove are comprehensive to all the energy, water, lighting and HVAC

systems in the building.

Grid-connected photovoltaic solar panels are installed to provide part of the energy requirements

of the building. The system consists of 72 x 300W panels producing a total of 32,000kWh per

year which is equivalent to a 26,000kg reduction in GHG emissions per year (The Grove

Precinct, 2012). In addition, two wind turbines, which are currently not functional due to

mistakes in initial sizing of the height of the turbines, are designed to produce 2,400kWh per

year equivalent to an approximately 2,000kg reduction in GHG emissions annually (The Grove

Precinct, 2012).

The orientation and eco-architectural design of the building not only serve as an aesthetically

pleasing feature, but also are intended to reduce energy requirements during hot and cold

seasons. An open loop geothermal system utilises a shallow groundwater supply as a direct

energy source in charge of the HVAC. Water at 21°C is taken out from the first bore and re-

injected to the second bore at 28°C (Pujol, 2013).

The focus of this study is on the ESD water systems and their operation at The Grove. Therefore

a more comprehensive explanation of each of the ESD water systems and their design follows.

2.2.1. Rainwater Systems

Rainwater (RW)

The Grove’s rainwater system’s design is comprised of 6 in-ground concrete tanks and 11 above-

ground steel tanks in the basement of the building. Rainwater storage was designed to meet

100% of the water demand for internal usage, saving up to 730,000L per annum (Dallas, et al.,

2009). The total capacity of all the tanks is 254,000L which is carefully designed to meet the

internal demand considering the high and low occupancy rates of the building (Josh Byrne &

Associates, 2011b). Figure 4 presents a schematic diagram of how rainwater is distributed at The

Grove.

21

The rainwater is used internally after going through the UV disinfectant and micro-filtration

units that treat the water for potable use (Josh Byrne & Associates, 2011b). There is the

provision for a mains water supply as a backup in case of a fault with the system or shortage of

rainwater supply. For detailed design drawings of the rainwater systems refer to Appendix C.

Figure 4 Schematic presentation of rainwater design system at The Grove (The Grove Precinct, 2012)

Stormwater (SW)

The term stormwater refers to the runoff from roads, car parks and other surfaces after each rain

(Josh Byrne & Associates, 2011a). The sedge beds at The Grove are designed to use the first

flush of rain from each rain event to treat the SW biologically and direct it to the filtration basins

to recharge the local aquifer.

The SW system at The Grove is comprised of one SW pump station, one settling tank, and the

sedge beds (Figure 5). The runoff from the roads is pumped to the settling tank (Figure 6) to

remove the rubbish from the road runoff flow, before it is directed to the sedge beds. The

overflow of the sedges at the treatment cells (Zone 2 in Figure 16) is directed to the sedges in the

dampland area (Zone 3 in Figure 16). Provision is also made for overflow from the dampland

sedges to be directed to the infiltration chamber located at the base of the building, thereby

functioning as a recharge basin for the local aquifer. Refer to Appendix C for detailed design

drawings of the stormwater system.

22

Figure 5 Cross section drawing of the stormwater system, adapted from (adapted from COX Howlett &

Bailey Woodland, 2008)

Figure 6 Picture showing inside of a settling tank at The Grove

23

2.2.2. Wastewater Systems

The innovative wastewater system at The Grove is designed to separate the wastewater into

greywater, brown water and yellow water streams on-site. In this case the greywater is the

wastewater from shower and hand basins; the brown water is from toilets and the kitchen; and

the yellow water is from male urinals. It should be noted that local regulations prevented

installation of urine separating toilet pans for females available in Europe. Each of these

wastewater streams is treated and reused onsite to provide part of the landscape irrigation and

supply of nutrients for the plant requirements (Josh Byrne & Associates, 2011c). A projected

saving of over 700,000L per annum of water can be achieved by this innovative wastewater

system (Dallas, et al., 2011).

Figure 7 presents the schematic diagram of how these systems are integrated to provide water for

different external uses in the Grove. For a diagrammatic representation of the wastewater

systems’ components refer to Figure 8, and for detailed design drawings of the systems refer to

Appendix C.

Figure 7 Schematic design of integrated wastewater systems at The Grove (adapted from (The Grove

Precinct, 2012)

24

Figure 8 Diagrammatic presentation of wastewater systems setup

Yellow Water (YW)

The YW system includes three urine tanks, one sedimentation tank and one pump tank (Figure

9). Urine enters any of the three urine tanks after going through the sedimentation tank where the

external particles in the urine are settled and removed. When one of the tanks is full, it is closed

for maturing for six months (Dallas, et al., 2011). At the time of this investigation one of the

tanks was at the maturing stage. Once the maturing phase has passed, the pump draws the

matured YW, sending it to the dozing tank from which the dozing pump will suck the liquid out

before pumping it to the GW, BW, bore-water or irrigation line as a fertilizer. Refer to Figure 7

for details on how the YW is injected into the irrigation for fertigation. All this is carried out

25

manually by the water contractor. Figure 10 presents a schematic diagram of the operation of the

YW system.

Figure 9 A picture of the YW system components

Figure 10 Schematic diagram of the YW operation at The Grove

26

Greywater (GW)

The GW system is comprised of a sedimentation tank, a pump tank and an ozonation unit (Figure

11) to treat the greywater for substrata irrigating. There are two pumps in the GW system, one to

pump the water from sedimentation tank to the ‘pump tank’, and one from the pump tank to the

irrigation system. The ozonation process ensures that all the bacteria and other macro-organisms

are destroyed before being pumped out to the irrigation line. All the components of GW system

are operational. Figure 12 presents a schematic diagram of the GW system’s design. The GW is

used for irrigating the exotic plant species (zone 8 in Figure 16).

Figure 11 A picture of the GW system components

Figure 12 Schematic diagram of the GW system at The Grove

27

Brown Water (BW)

Biolytix (Biolytix, 2013) provides the BW treatment system at the Grove. This system is

comprised of one Biogrinder and two Biolytix filtration units (Figure 13). The BW enters the

Biogrinder tanks first and is then split evenly between the two Biolytix units where the BW is

treated by an aerobic process using macro-organisms such as earthworms, beetles, and mites

(Biolytix, 2013). Figure 14 presents a schematic representation of the BW system’s design. For

the current operation diagram of the BW system refer to Figure 17.

The Biogrinder is connected to the BMS to ensure that no more than approximately 1,000L/day

of wastewater enters each Biolytix unit to avoid overloading (The Grove Precinct, 2012). This

estimate would be sufficient to handle a typical daily wastewater flow; more than 90% of all BW

can be treated by the Biolytix system with the minimal volume being diverted to the sewer in this

design (The Grove Precinct, 2011). The treated BW is used for subsurface irrigation to the lawn

area (zone 9 in Figure 16).

Figure 13 A picture of the BW system components

28

Figure 14 Schematic diagram showing the Biolytix operation according to its design

29

2.2.3. Irrigation

The landscape irrigation is based on a drip-line setup (Figure 15) which minimises the quantity

of water employed for watering the plants. Different hydro zones are allocated to different

planted areas with respect to their location and water requirements. For the design drawing of

The Grove irrigation refer to Appendix C.

Figure 15 Drip-line setup at The Grove (Picture from Anda (2012), from the early stages of setting the

irrigation line)

Table 1 lists the hydro zones for different sections of The Grove’s landscape, while Figure 16

displays the zoning of The Grove’s landscape. The zone numbers (1-9) in Figure 16 correspond

to those in Table 1 which reflect the irrigation design layout (Figure 45 in Appendix C)

overlaying these zone numbers.

The water sources for all the zones are mainly from wastewater or bore water. The YW

component which acts as the fertilizer provides the Phosphorous and Nitrogen to the plantation

in all zones. Figure 7 presents the schematic design of how the YW is injected into all different

irrigation sources (bore-water, BW and GW).

30

The 400 m2 of lawn area is designed to be watered by BW using subsurface irrigation (Zone 8 in

Figure 16). The drip-line for subsurface irrigation is placed about 100 mm below the lawn as per

Department of Health (DoH) regulations (The Grove Precinct, 2012). There is provision for bore

water top up during summer months.

The GW is used mainly for irrigating the exotic plants spreading over about 240 m2 of the

landscape. The substrata irrigation for GW refers to the drip-lines on the surface of the turf

covered by mulch (Zone 9 in Figure 16).

Zones 2 and 3 are designed to use SW during the rain events; however during the dry season they

are irrigated using bore water. Other zones (zones 1, 4, 5, 6 and7) are incorporated with bore

water arrangements.

This hydro zoning with drip-line irrigation ensures the optimum usage of water, saving about

700,000 L of groundwater per year (The Grove Precinct, 2011).

Table 1 Irrigation line zoning at The Grove, adapted from Anda (2012)

Zone Irrigation

1 Native Shrubs Bore + urine

2 Sedges (Treatment Cell) Bore + urine + SW

3 Sedges (Dampland) Bore + urine +SW

4 Native Shrubs Bore + urine

5 Native Shrubs Bore + urine

6 Native Shrubs Bore + urine

7 Trees Bore + urine

8 Fruit & Exotic Garden GW

9 Lawn BW

31

Figure 16 Landscape of The Grove with irrigation hydrozones, adapted from Huxtable (2012)

32

Chapter 3: The Performance of the ESD Systems

3.1. BMS Performance

The BMS at The Grove has failed to meet the requirements of its promised initial design.

Interviews with external water contractors (JBA and IBMS) concerning the initial stages of the

systems’ design suggests that the BMS should promise to provide remote monitoring access of

the performance of all the ESD systems to the external contractors for at least the first year of

operation at The Grove. At the practical level this condition has not been met, posing great

difficulty for the contractors in accessing the data and monitoring the ESD systems for the

contractors. This has resulted in no information being available on the operation of the ESD

water systems since their commencing in July 2011. For data analyses of different ESD water

systems in the historical context of their operation refer to Chapter 4.

From the backup-support perspective, Honeywell operators have poorly served The Grove in

terms of knowledge about the design, operation and limitations of the system when it is

requested (Appendix B).

The following issues were identified with the BMS and are discussed further:

3.1.1. Data access and extraction;

3.1.2. Report output;

3.1.3. Maintenance scheduling;

3.1.4. Document complications; and

3.1.5. Tag-naming system.

33

3.1.1. Data Access and Extraction

The current BMS is not user friendly for monitoring the ESD systems’ performance and data

extraction for research. The extent of data, both recorded and stored in the BMS, is massive;

however access and extraction of them is not an easy or self-explanatory process and no

document or report exists which explains the process. When contacted, the backup support from

the BMS provider (Honeywell) was not resourceful in this sense either (Appendix B). Hence the

data extraction was not possible for this study upon request from Honeywell. Only after

involvement of The Grove’s former commissioning agent (IBMS) was the data extraction

process achieved; which is captured and documented in Appendix A). The best practice for data

extraction tracks the following steps:

1) Open the BMS

2) View > Trend Summary

3) From the list choose the relevant set of data for your research (Figure 36)

4) Choose View Trend with Tabular History (Figure 37.a)

5) Select the Period and Interval as applicable to the set of data of particular interest

6) Click on Edit > Copy

7) Go to Excel and paste.

For a more detailed explanation of each step with corresponding screenshot refer to Appendix A.

A newer server to be used alongside the current BMS has been proposed by Honeywell enabling

access to data extraction called the “Energy Manager Server”. The current BMS license does not

enable upgrading to the new server, thereby requiring the complete and costly replacement with

the new server, estimated at $20,000 (Refer to Chapter 5).

3.1.2. Reporting Output

Although the provision of a reporting system is provided in the BMS to produce different output

formats, such as Excel, Word or PDF, this has not been configured in such a manner as to

produce any outputs for the Shire or anyone undertaking research. No report or manual exists

34

which explains the configuration process for external parties. When assistance was requested,

Honeywell was not able to provide the support necessary to solve the problem (Appendix B).

Contrary to the purpose of the promoting of The Grove as a smart building, the BMS does not

provide any structure for monitoring the operation of different ESD systems against their design

benchmarks. Therefore no evidence shows the performance of the building in terms of savings

and environmental impacts for commentary.

3.1.3. Maintenance Scheduling

The maintenance and operation of the ESD water systems are not supported or recorded in the

BMS. The maintenance contractor, who is the party in charge of servicing and looking after the

water systems, has no interaction with the BMS. This has limited the level of accountability from

the perspective of the data as the breakdowns with the ESD water systems cannot be explained

by referring to the BMS, and the contractor cannot monitor any change made to the water

systems (Appendix D).

This state of affairs conflicts with the remote access option intentioned by the BMS to be used by

external contractors to monitor the operation of the ESD systems; this facility was not available

to them at the time of this study. Access remotely for the water contractor could have prevented

some breakdowns with water systems, such as clogging of the BW pump resulting in flooding of

the area.

3.1.4. Document Complications

The BMS was intended to be used by unspecialised operators; however, the design is

sophisticated requiring continuous and supportive backup from Honeywell. On the practical

level, poor back-up support and lack of any documentation system in place has caused

difficulties for the people operating the BMS.

Although the operator’s manual or functional specifications documents were generated when the

BMS was installed at The Grove, none of these documents was to be found at The Grove. Nor

was Honeywell able to provide this documentation upon request, claiming this item was not in

their archive (Refer to Appendix B). However a 2011 copy of the manual (version 6.a) was

35

retrieved after further investigation from the external contractors, JBA and IBMS, and placed at

The Grove.

Another significant document required for data extraction is the Input Output (I/O) Schedule, a

comprehensive document listing the sensors at the monitoring points with their tag names in the

BMS. Accessing data from the BMS for research requires an understanding of the point names

referred to in the BMS (Appendix B), and thus the presence of the I/O Schedule is significant for

undertaking investigation using it. The first version of the I/O Schedule, dating back to 2009,

was retrieved from external contractors, JBA and IBMS. Being an outdated document, it does

not include many of the sensors’ tag names.

3.1.5. Tag-naming System

The tag-naming system, which addresses each monitored point (sensor), is not consistent and the

current I/O schedule retrieved from external contractors is not easily comprehensible by an

unspecialised operator. For example, the brown water tank level sensor is called

“BW_Tank_Lvl” in the BMS but is referred to and described as “P_L_BWAeroSys_TankLevel”

in the I/O Schedule document.

The simple conclusion is that the naming system should be consistent so as to enable the

monitored point (sensor) for research or practice to be found. Considering the numerous sensors

for the different ESD systems, finding the corresponding BMS sensor name for the I/O schedule

or vice versa is not an efficient and effective process.

3.2. ESD Water Systems’ Performance

3.2.1. Rainwater (RW) Status

Rainwater has not been accessible for internal use because of a number of issues with some

components of the system, namely, the UV disinfectant unit, the rainwater pump, and the in-

ground tank water level sensors.

36

UV Disinfectant Unit (UV)

The RW design requires UV activation before the rainwater pump is started; this process is

automated and controlled by the BMS. Although all individual components of the RW system

are operational (Appendix D), currently the BMS does not recognise the operation of the UV,

thereby hindering the start of the rainwater pump.

Further investigation revealed that this concept of the RW design had been unknown by the

water contractor until recently, that is, Feb 2013, and after replacing the UV with a new system

(Appendix D).

The initial UV, sophisticated and expensive, was replaced after a breakdown during the first year

under warranty. However when for the second time the UV became faulty, it was no longer

under warranty and, due to its high cost of replacement; it was decided to change it with a much

simpler system which is in current use. At the time of purchasing the new system it could not be

confirmed whether it had the capacity to be connected to a monitoring system (Appendix D).

Therefore the current system was not set to send signals to the BMS. This explains the current

situation where the BMS does not allow the start of the rainwater pump.

RW Tanks’ Water Level Sensors

The BMS display informs that both above-ground and below-ground tanks are full (Section “‎4.1.

Rainwater Systems (RW) Data Analysis”). This was proven wrong when the rainwater tanks

were inspected by the water contractor in March 2013. Although there was water in the above-

ground tanks, the below-ground tanks were reported as empty. This anomaly can be traced back

to being the result of a faulty sensor in the rainwater tank not being identified by the BMS.

On the other hand, as there has not been a monitoring system accessible for the external

contractors in place, this fault was not diagnosed in its early stages when it could have been

replaced under warranty (Appendix D).

37

3.2.2. Wastewater Systems Status

Yellow Water (YW) Status

The YW system is operating satisfactorily according to its design. All the components are

serviced regularly according to the operation and maintenance (O/M) requirements.

When one of the tanks is full, a determination made by the direct inspection of the water

contractor without any interaction with the BMS, it is closed manually and left for six months for

maturing. This date is recorded into the BMS to reckon the six months maturing period required

by the Shire. Every time the water contractor came for servicing according to the maintenance

contract, he inspected inside the tanks to determine their level without any interaction with the

BMS or recording anything into it.

At the time of writing this paper (May 2013), the tank which was closed for maturing in

September, 2012, has passed its six months maturing period with the contents being ready for

use as a fertilizer in the irrigation line. However the maintenance contract for this year has not

yet been signed by the Shire, thus hindering the commencement of YW use (Appendix D).

Greywater (GW) Status

The GW system operates satisfactorily as well. The only matter is the small amount of GW

produced which is much less than what it was anticipated in the design level. However there is a

provision for bore water top up to fill the tank every 30 sec with bore water (as quoted from the

water contractor, Appendix D), so that whenever the pump is activated, the tank is filled up with

bore water and is pumped out to the irrigation.

However the bore has been turned off since June 2012 which has resulted in decreased flow of

GW entering the irrigation line, thereby affecting the pressure in the irrigation line. The BMS

had not recognised the bore pump being switched off. This has been due to the setting in the

BMS that had put the bore pump activation in manual instead of automatic mode. It was not

known who had made that change in the BMS.

38

Thus, at the time of writing this paper, the GW was not being used in the landscaped areas due to

the decrease in its flow; therefore hand watering of the zone 8 was undertaken instead.

Brown Water (BW) Status

Biolytix was the system with low energy intensity at the time of its installation; however after

one year the system started to fail due to clogging of the pump and flooding the area (Appendix

D). The reason for the pump’s failure was due to the geotextile liner being clogged up resulting

in entrance of untreated material in the pump chamber.

Some retrofit on the system was undertaken in 2012, such as using an air blower in the

Biogrinder and Biolytix tanks to improve the aerobic conditions for the macro organism’s

environment. This improved the situation for some time; however due to continual breakdowns

with the Biolytix system, it was decided to shut down in Sep 2012. The manufacturer could not

provide backup due to bankruptcy. This resulted in BW diversion to the sewer without any

treatment (Figure 17).

Figure 17 A schematic of the BW system operation after its shut down (All the BW is diverted to the sewer)

39

At the time of undertaking this research as the Biolytix system was shut down, the tanks were

dry and no evidence of macro-organism were present (Appendix D). Interviews with water

contractor on the reason behind the poor quality of the effluent, at the time of the operation of the

Biolytix system, revealed that the environment for the macro organisms (worms and bacteria)

had not been optimal. During the operation of the Biolytix system, the worm community was

dying due to the high temperatures (Appendix D).

This maintenance issue revealed that the lids of the Biolytix should have been covered in mulch

to reduce the heat and thus provide optimal environment for the macro organisms. This condition

was not known by the water contractor prior to diversion of the BW system from the irrigation

line (Appendix D).

3.2.3. Irrigation Status

Irrigation became a problem after the reinjection bore machinery damaged the turf and the

irrigation lines in 2012. They caused damage to BW and GW irrigation lines for zones 8 and 9

(Figure 16). Figure 18 and Figure 19 present the current condition of the GW and BW lines

respectively. It is apparent that the GW line setting has completely been distorted and there can

be breakage in the line as well (Figure 18). The BW line, on the other hand, has been exposed

while it is required to be 100mm below ground in accordance with the DoH guidelines (Figure

19). As a remedial action, the Shire decided to employ sprinklers using mains water instead to

irrigate zone 9 (lawn area) in September 2012, and using hand watering for irrigating zone 8

(exotic garden).

On the other hand, as the bore water was turned off for the summer irrigation, all other zones

(Zones 1-7 in Figure 16) were not receiving water during these months. This explains the poor

condition of vegetation at The Grove. This could not have been explained until recently when it

was revealed that the bore water had not been turned on and the BMS had not recognised this.

Further investigation with BMS operator involvement revealed that in the BMS the bore pump

status had been set on the manual. It is not known by whom and when this setup has been

implemented; indicating another shortcoming in operation with the BMS.

40

In order to re-establish the drip-line system, the irrigation lines for zones 8 and 9 must be

repaired. The water contractor is required to examine the drip-line and reset the settings in these

zones.

Figure 18 Picture of damaged GW line at The Grove

41

Figure 19 Picture of damaged irrigation turf at The Grove exposing the BW line

42

Chapter 4: Data Analysis of the ESD Water Systems

Analysis of the data from the BMS for the ESD systems (rainwater and wastewater systems)

identified the operational trends presented in this chapter. Some anomalies between the data from

the BMS and real physical evidence of the ESD systems were noticeable. Further investigation

and site-visit observations of each system having these trends were used to determine the source

of the problems. For site layout and design of each of the ESD water systems refer to Appendix

C.

4.1. Rainwater Systems (RW) Data Analysis

a) No variation in the tanks’ levels was observed, except for a very short period of time, within

two months of the start of their operation (Figure 20). This does not correlate with the rainfall

events for this period (Figure 21).

On 12th

Dec 2011 the tanks’ levels were changed without explanation and since then they

have remained the same. There were no accessible documents at The Grove pointing to any

special events on this date.

Figure 20 Historical trends of rainwater tanks’ levels for the period of July 2011 to March 2013

43

Figure 21 Rainfall events during the period of July 2011 to March 2013 (Bureau of Meteorology, 2013)

b) The BMS displays both the above- and the below-ground tanks to be full (Figure 20);

however after physical inspection of the rainwater tanks, the water contractor stated that the

below-ground tanks were empty (Appendix D) despite the BMS indicating they were full.

The below-ground tank’s sensor was replaced in April 2013, Figure 22 displaying the change

in the tank’s level. The new data show existence of some water in the tank, contrary to the

water contractor’s claim made in March 2013. It is not certain whether the sensor is

displaying the correct data or that the water contractor’s report has been inaccurate.

The rain gauge displayed ‘Dry’ weather for every hour during the period of the rainfall event of

2nd

May 2013 (Figure 23). The rainwater meter did not show any changes in the level of rain

(Figure 24) on that day either.

44

Figure 22 Historical trends of rainwater tanks’ levels for the period of Jan 2013 to May 2013

Figure 23 Rain gauge status in 6 minute intervals during 25 April 2013 to 02 May 2013

45

Figure 24 Cumulative rainwater volume at The Grove during Feb 2013 to May 2013

c) The design of the stormwater (SW) system is to receive the first flush of every rain to the

sedge beds onsite. However, an observation on a day of a substantial rain event on 2nd

May

2013 noticed no trace of the rain going to the sedge beds.

The reason could lie in a faulty pump or the blocked gutters. As the SW pump is not

monitored through the BMS there is no way of checking data on its operation.

The cleaning and maintenance of the gutter is part of the water contractor’s arrangement.

However, the current year’s contract has not been finalised and signed by the Shire, and further

information is awaited before checking the system by the water contractor; thus certain

conclusions on the source of the SW system’s lack of operation could not be retrieved without

arrangement with the water contractor to check the pump and the gutters. It is understood that a

new maintenance contract is imminent.

4.2. Yellow Water (YW) Data Analysis

a) Figure 25 presents the operational trends of YW since the start of operation by the facility. It

can be observed that the YW has entered Tank 2 and for some time into Tank 3 also. In

September 2012 the contents of Tank 2 were emptied into Tank 1 and closed for maturing.

46

The six months period of maturing having passed, the YW is ready for use in the garden;

however lack of a new maintenance contract has resulted in no action taking place.

b) It is noteworthy that the YW can enter any of the tanks and go to the pump tank. The water

contractor fully controls and looks after the operation of the tanks. He determines into which

tank the YW enters and when the tank is ready to be closed for maturing. None of these is

recorded into the BMS as no maintenance scheduling capability has been configured in the

BMS.

Figure 25 Historical trends of yellow water tanks’ levels for the period of August 2011 to March 2013

4.3. Greywater (GW) Data Analysis

a) Figure 26 presents the operational trends of GW system since the start of its operation. For

the first 6 months of 2012 the level of GW tank has been within the range of 0.8 -1.2m;

however since June 2012 the level of GW tank dropped to 0.2 - 0.4m.

This sudden change of about one metre in the tank levels was found to be due to the bore top

up for winter irrigation being switched off. This was done manually (by an unknown party)

and has not been recorded into the BMS to a reminder for turning it on for summer irrigation.

The poor vegetation conditions at The Grove at the time of writing (April 2013) are

47

explained because the bore water has been turned off. Additionally, the bore pump switch

had been set on manual mode in the BMS (by an unknown party) which resulted in inaction

of the alarm/reminder system of the bore water pump during the summer months.

The new Shire year started in September 2012 and apparently in any necessary handover

procedure for the bore top up has not been explained.

b) A closer look at the first six months of 2012, when bore water top up was operational (Figure

27), reveals that the tank level follows cycles of increase and decrease, that is, filling up and

emptying of tanks by bore water, which confirms the operability of GW system.

Figure 28 on the other hand shows the GW tank level changes during the second 6 months of

2012. It is apparent that the GW production at The Grove has been considerably lower; thus

the bore top up has been required for the summer.

Two spikes in the trend are noticeable during this period; these may be explained as being

due to sensor’s error and will be disregarded.

There are some parts of the graphs with no data available for them (Figure 26, Figure 27 and

Figure 28 for GW, and Figure 31 for BW data analysis). The reason for lack of data for these

periods is due to turning off the whole BMS for maintenance purposes during which no data

has been logged to the system.

Figure 26 Historical trends of greywater tank level for the period of July 2011 to March 2013

48

Figure 27 Historical trends of greywater tank level for the period of Jan 2012 to August 2012

Figure 28 Historical trends of greywater tank level for the period of June 2012 to March 2013

4.4. Brown Water (BW) Data Analysis

a) Figure 29 presents the BW system’s operational trends since the start of its operation in July

2011. In mid-September 2012, the Biolytix system was shut down due to clogging of the

pump and flooding of the surrounding area. Since then the BW has been directed to the sewer

without being treated (Figure 17).

b) Figure 30 represents the trends produced from the BMS data, showing some flat-lining

periods in the level of BW. The contractor explained these as the pump being clogged before

49

servicing. After the pump service in February 2012, the level of BW in the tank has

increased. The reason for this high level is not due to higher BW production; but because

when the bore top up enters the tank, the raised levels could not be discharged due to the

pump being clogged.

c) Before shutting down the BW system, there have been times that the operation of the BW

system has been satisfactory and as per design. For example, Figure 32 presents the cyclic

patterns of tank filling and emptying which correlates with starting the BW pump out to the

irrigation line. In this sense, once the BW level in the tank reaches a certain level, the BW

pump is activated and pumps the effluents out to the irrigation line.

d) Figure 31 shows the BW tank level after the Biolytix was clogged and the BW was diverted

to the sewer. It is apparent that the level of BW in the tank has not been steady, and

fluctuations similar to those during the operational period can be observed.

The reason for this is that the design requires the BW entering into the Biogrinder tank and

then diverting to sewer (Figure 17). Thus the BW pump stays operating although the system

is closed. Therefore, when the BW reaches a certain level, the pump is activated to empty the

tank, thereby explaining the cyclic rise and fall in the tank levels after it being shut down.

Figure 29 Historical trends of brown water tank level for the period of July 2011 to March 2013

50

Figure 30 Historical trends of brown water tank level for the period of August 2011 to September 2012

Figure 31 Historical trends of brown water tank level for the period of mid-September 2012 to March 2013

(after shutting the Biolytix system)

51

Figure 32 Brown water tank level changes in 10-11 March 2012 before shutting down the BW system

52

Chapter 5: Problems and Recommendations

5.1. Problems with the BMS

The proposal was for the BMS to provide a high level of precision and easy access in controlling

and monitoring the ESD systems to make The Grove the showcase of a ‘smart’ green building.

At the practical level however, the BMS has not met these conditions completely. Table 2 lists

the identified shortcomings of the BMS at The Grove as provided by Honeywell.

Table 2 List of problems with the BMS

Problems with the BMS

The reporting system does not provide any outputs

Monitored points’ tag-names are not consistent posing great difficulty in accessing data

Poor documentation of manual and I/O Schedule

Poor backup support and knowledge of Honeywell

The BMS did not recognise and identify some of the sensors’ faults (e.g. rainwater tank or bore top up switch)

Many points that are present at the BMS do not log any data (e.g. rain gauge)

The Stormwater pump is not integrated into the BMS

No maintenance scheduling is set up in the BMS

The alarm system in the BMS can be turned off from the station without any subsequent actions

No access for the external ESD water systems’ contractors to monitor the systems remotely

The energy management is not possible through the current BMS

Considering the above list of shortcomings with the BMS, three solutions can rectify the

specifications of a smart building.

a) Install the “Energy Manager Server” (EMS) with the same provider, namely Honeywell. As

the current BMS server cannot be upgraded to the new EMS one, complete installation of the

EMS is required. The price of this new server is estimated to be $20,000 (Appendix B).

53

This new server has the capabilities of reporting on the performance of the energy and water

systems against industry/design benchmarks as well as data extraction and analysis tools (as

quoted from the Honey agent).

b) Use add-ons to the current system with the same provider. For example adding the SW

system to be controlled by the BMS will cost around $4000-5000 as quoted by the

Honeywell agent. Other algorithm inclusion will cost separate costs that needs estimation by

Honeywell.

c) Install a new automation and control system with another provider. In this sense, further

research on available providers of such systems is required. The cost analysis of a new

system to compare it with the present system should also be undertaken.

5.2. Problems with the ESD Water Systems

- Table 5 present a comprehensive list of problems with different ESD water systems and the

recommendations for their rectification. Some of these problems are simply component

breakdown, such as, a faulty tank level sensor, which would require sensor replacement. Some

other issues are more complicated, for example, BW system breakdown. In this case, further

research and analysis is required to provide the systems’ long term perspective as well as a cost

analysis.

5.2.1. Rainwater (RW) Systems

Table 3 lists the identified problems with their necessary rectification incorporating the RW and

stormwater (SW) systems.

54

Table 3 List of problems with the rainwater systems and recommendations for their rectification

Problems Recommendations Estimated Cost

Rainwater (RW)

1) Faulty tank level sensor Sensor replacement $1000

(quoted by the

water contractor)

2) Failure of UV connection to the

BMS

a) Contact with the UV provider in New Zealand

and find a solution

b)

c) Contact with Honeywell to change settings in

the algorithm of the BMS

d)

e) Replace with a new UV unit with the ability

to connect to the BMS

f)

Stormwater (SW)

1) The SW pump is not integrated

into the BMS

New add-on to the BMS $4-5K

(quoted by

Honeywell)

2) No signs of first flush entering

the sedge beds after a rain event

Further investigation by the water contractor

(testing the SW pump and checking the

rainwater gutters)

3) A SW pipe’s tap to the

infiltration chamber was turned

off during and after the rain

a) The contract for the water contractor be

signed and be inclusive of the SW system’s

maintenance

b)

c) The SW pump to be connected to the BMS d)

RW System:

Currently the main problem with the RW system is that the UV does not send a signal to the

BMS to start the pump. The BMS did not have the capability of diagnosing the problem. This

caused unnecessary expense investigating the source of the problem by both Honeywell and the

external water contractor.

The collaboration of external water contractors has not been comprehensive in the sense that the

water maintenance contractor had not been aware of the design of the rainwater system at the

time of purchasing the new UV unit (as stated by water contractor in Appendix D); thus a UV

incompatible with the BMS was purchased.

55

In order to rectify this problem, it is recommended that the UV provider first be contacted to

explore the UV design and its competencies when connected to the BMS. The ultimate solution

could be to purchase a new UV with the capability of being connected to the BMS.

SW System:

The main problem with the SW system is that it cannot be monitored through the BMS and thus

no alarm system is in place in case of a breakdown with system’s components. As part of the

maintenance contract, the water contractor checks and services the system; however, not having

a contract at this time of the research (15th

May 2013), he is not responsible for its operation.

The rectification of the SW system requires integrating the SW pump with the BMS to monitor

its operation. This will require the involvement of Honeywell, if the current BMS is retained, or

of a new BMS provider. More interaction between the water contractor and the SW system to

maintain its operation should be undertaken so aligning with connecting to the BMS.

5.2.2. Wastewater Systems

Table 4 lists the identified problems and recommended solutions with the YW, GW and BW

systems.

Table 4 List of problems with the wastewater systems and recommendations for their rectification

Problems Recommendations

Yellow Water (YW) System

1) No interaction between the water

contractor and the BMS when

monitoring the YW tanks’ levels

a) Train the water contractor with the BMS operation

b) Establish a maintenance section in the BMS

2) Water is not tested before sending to

the irrigation line

a) Undertake water testing in the maintenance

process

b) Report on the quality of matured YW to DoH so

enabling YW usage for other public buildings

Greywater (GW) System

1) Bore water top up was switched off

last winter and not turned on again

a) Should be a requirement to record everything into

the BMS

56

b) Comprehensive handover to the new Shire officer

2) Greywater production is low Bore top up to be used according to the design

Brown Water (BW) System

1) The Biolytix system is shut down and

BW is diverted to the sewer

a) Retrofit to a new system, e.g. aerated activated

sludge return

b) Rectify the current system with regular

maintenance

c) Remove the Biolytix and replace it with a new

system

2) Poor quality of effluent Maintain the optimal environment for bacterial life

YW System:

The YW system is operational; however use of the matured YW has not been undertaken even

though the six months maturing period has passed. The Shire has not signed the new contract for

maintenance of the water systems which is a major hindrance. It is understood that a new

maintenance contract is imminent.

Although it is not necessary as part of the maintenance process, it is recommended that water

quality testing such as (pH and Nitrate testing) be undertaken on the YW before using it onsite.

This will provide documentation on the effects of the process and the quality of the matured YW

for further research.

GW System:

The GW system is also operational; however the low volume of GW production has resulted in

the necessity of a bore-water top up before its use in irrigation. The bore water top up was turned

off in June 2013 during winter; however it was not turned back on for summer irrigation. On the

other hand, the resultant poor vegetation condition brought distrust from the Shire as having the

ability to design a GW system and its maintenance, without awareness of the bore-water

switched off being in conflict with the design intent.

The bore pump status is incorporated into the BMS and the data on its status is logged, but not

the bore switch status. It is recommended to incorporate the status of the bore into the BMS. This

57

requires involvement of Honeywell to setup a logging and alarm system for the bore status with

seasonal considerations included, to preclude the bore alarm being switched off during the

summer or on during winter months.

BW system:

The Biolytix failure and its discontinuance from the irrigation line in Sep 2012 brought such

disappointment for the operators and Shire on the BW system design and its operation that it was

decided to exclude the system from the irrigation line completely. However three main

rectification strategies were identified that will enable the re-establishment of the BW system at

The Grove. They are discussed below. However, further research and risk analysis of these

strategies are required, but are not within the scope of this study.

a) The first option for retaining the Biolytix system is to improve the servicing methods. The

current service requirement of the system is for such action once a year (Biolytix, 2013), but

according to the DoH requirements quarterly service is required (DoH, 2012). According to

the water contractor, utilising more frequent servicing of the pump and filters as regularly as

once a month, and undertaking water testing to monitor effluent quality (such as temperature

and turbidity) and macro organisms environment (such as dissolved oxygen and wetness),

will prevent clogging of the pump, thereby retaining the current Biolytix system.

The cost of this option is estimated to be $2000 for resetting the system with $1000 per year

maintenance costs as quoted from the water contractor.

b) Retrofitting the BW system with new available systems is the second option. As the Biolytix

system has failed in the past, causing many breakdowns in its operation, this option is

preferred.

The cost of retrofitting the BW system is estimated to approximate $6000 for a rebuild (e.g.

conversion to an aerated activated sludge return system) and re-setup, with $500 per year for

maintenance as quoted by the water contractor.

Removing the Biolytix system and tanks completely and establishing a new BW treatment

system is the third option. Many different providers are approved by the DoH in WA (DoH,

58

2012). The Fuji Clean (Fuji Clean, 2011) is the provider suggested by the water contractor as

a replacement for the current Biolytix system (Appendix D).

The approximate cost of Fuji Clean is approximately $3500 per tank which is $10,500 for the

three tanks, with additional costs for removing the Biolytix tanks and installing the new

system.

Further investigation on the best option in terms of cost analysis and risk assessment should

be undertaken.

5.2.3. Irrigation

Table 5 lists the problems and recommendations for their rectification of the irrigation system at

The Grove.

Table 5 List of problems with the Irrigation and recommendations for their rectification

Problems with Irrigation Recommendations

1) The irrigation line and turf is

distorted and exposed

New drip-line to be established

2) The BW line (lawn area) is exposed

whereas it is supposed to be 100mm

below ground (according to DoH

requirements) (Figure 19).

3) The GW line (exotic plants area) is

damaged and distorted from its

design (Figure 18).

4) Bore water is turned off, and the

bore water pump setting in the

BMS was set to manual instead of

automatic.

(Thus alarm was not activated when

top-up to GW was required.)

a) The bore switch to be put on ‘automatic’ mode in

the BMS.

b) An alarm system to be configured for the bore pump

switch status

The problems with the irrigation system are the damaged line and turf problems of the GW and

BW hydro-zones at zones 8 and 9 (Figure 16). The GW line is completely distorted and dis-

located (Figure 18). The BW line at the lawn area on the other hand is exposed and there is the

59

possibility of breakage in the line as well (Figure 17). This has resulted in the use of sprinklers

with mains water for the lawn (zone 9), and hand watering for the exotic garden (zone 8).

It is recommended that the drip-line be re-established at an estimated cost of approximately $400

(as quoted by the water contractor) for finding the possible breakage and faults in the line and re-

establishing the drip-line.

Another option is the establishment of sprinklers which is more costly, approximately $3000

according to the water contractor. However this option is considered not to be environmentally

sustainable due to its reliance on mains water and excessive water usage.

5.3. Problems with Documentation

Table 6 lists the identified shortcomings with The Grove document control system. The lack of a

comprehensive document control system with regard to the BMS and the ESD water systems is

obvious at the management system level. A database keeping a record of submitted reports and

manuals to the Shire was not available. This has brought up many underlying issues (Chapter 6)

concerning the operation of the whole building. Establishment of a document-control database

inclusive of all the documents, manuals and reports is highly recommended.

Table 6 List of problems with the documentation control at The Grove

Problems with Document control Recommended Solutions No BMS manual present at The Grove Contact Honeywell or other external contractors

(e.g. JBA or IBMS) to obtain these documents,

print them and place them next to the BMS

station.

No I/O Schedule document for the BMS available

at The Grove

No evidence of access to contingency manual Contact the external contractors involved to

obtain this document and place it in a

predetermined place at The Grove.

No evidence of documentation with the BMS

alarm system and remedial actions

Contact the Honeywell to obtain this document

and place it next to the BMS station.

No direct access to the O/M manuals at the Grove Contact the external water contractors (e.g.

60

JBA) for access to this document and place it in

a predetermined place at The Grove.

Lack of documentation explaining the roles and

interactions between the water contractor,

management and the BMS

This document needs to be provided by external

water contractors involved in design of the ESD

water systems and placed in a predetermined

place at The Grove.

No database to keep track of the documents,

reports and manuals submitted to the Shire

This needs to be done by defining a new role to

start archiving all the documentations and make

a database for them.

61

Chapter 6: Conclusion

6.1. Project Conclusion

At the design level, The Grove has utilised best practice ESD features for a ‘green’ building. The

water, energy, HVAC and alarm systems are selected ESD systems to showcase the sustainable

design in a public building. The BMS design was meant to integrate all these systems at one

control station so fully automating the operation of these ESD systems. Savings on energy, water

and greenhouse gas emissions were expected to be achieved through the design and operation of

these systems.

At the operational level, however, some breakdowns, mainly with ESD water systems, resulted

in the anticipated performance and savings not being achieved. The breakdowns with the

rainwater and wastewater systems resulted in the employment of mains water internally and

externally, thereby hindering achievement of the anticipated savings. Irrigation has been another

area of concern due to damaged lines and turfed areas which required a re-setup of the drip-line

for irrigation. These breakdowns have caused dissatisfaction for the operators and managers of

these systems.

The high sophistication level of the BMS and absence of an accessible operational manual at The

Grove has resulted in dissatisfaction for its operators. On the other hand, the BMS does not have

a capable reporting system enabling the performance of the ESD water systems, in accordance

with its environmental benchmarks, to be determined.

In order to have such a sophisticated system, interaction between Shire personnel, maintenance

staff and the BMS should be established. This is because the ESD systems showcase the best

design, but in order to have them operated according to their design, regular maintenance is

essential. Presence of support from the Shire is critical because this organisation influences the

budget for the continual operation of the systems. On the other hand, presence of a methodical

training program and handover procedure for the Shire and operators of the BMS and the ESD

systems is critical to achieve appreciation and support for the existence of these systems at The

Grove.

62

If this relationship is established, the breakdowns and faults can be regulated and managed to

enable the optimal performance of the building. This will provide a chance for the community to

appreciate the sustainable design systems and provide confidence for more widespread adoption.

63

6.2. Future Research Opportunities

The following areas of research were identified for further study:

a) Life cycle analysis of the ESD water and energy systems

The significance of life cycle analysis is in documenting the environmental impacts associated

with all stages of the ESD systems’ life cycles as a green library compared to a conventional

library. This will produce confidence for relying more on environmentally sustainable design

systems. Also as the water system has shown faults and breakdowns to this point, undertaking a

life cycle analysis for water systems can reveal significance of design and maintenance in the

performance of these systems, and possible solutions may be reached.

b) Benchmarking the performance of the ESD water systems

To this date, there has not been any benchmarking on the performance of the ESD systems to

determine their current performance against industry and design benchmarks. Performing

benchmarking may enhance the pathway for attaining Green Star-Performance (GBCA, 2013)

and NABERS rating (NABERS, 2013).

c) Ongoing performance monitoring of the water systems

This will be the continual of the current study with more focus in the remedial action. Now that

the areas of faultiness in the ESD water systems are identified, through ongoing performance

monitoring of them against their design benchmarks, faults with these systems may be traced.

d) Retrofitting or fully removing Biolytix, replacing it with different system

Detailed study on possible options for the BW system with cost benefit analysis may attract the

Shire’s trust to re-establish the BW system.

e) YW application to gardens, its usage and effectiveness

As this is the first time that the YW is used on the garden, study on its quality and effectiveness

may be highly beneficial especially for increasing awareness on its usage for other buildings.

64

Chapter 7: Reflection

7.1. “Vicious Circle” at The Grove

Through the course of this study, four components were identified as the underlying causes of

issues and problems at The Grove, namely the BMS, ESD systems, maintenance and

management (Figure 33). The relationship of these interrelated factors has contributed to the

current issues and complications noted there. Table 7 is a summary of the current status of these

four factors in relationship to each other at The Grove.

Figure 33 Interrelated factors contributing to the complications and issues at The Grove

65

Table 7 Summary of relationships between the four interrelated factors contributing to the situation at The

Grove

BMS ESD System Maintenance Management

BMS Outdated version with

many glitches

Not all systems fully

integrated into the

BMS

Does not provide

maintenance

scheduling

Lack of appropriate

training to operate

the BMS

ESD System Not all systems fully

integrated and

controlled by the

BMS

Best sustainably

designed systems at

the time

Not adequate

support for the

maintenance of the

systems

No appropriate

clarification about

support capacity

Maintenance No interaction

between the

maintenance

contractor and the

BMS

Sophisticated design

results in only a few

contractors being

able to maintain the

systems

Ongoing

maintenance

required for optimal

performance of the

systems

Lack of support from

Shire for budget

allocation needed for

on-going

maintenance

Management Not fully able to

operate the BMS due

to sophisticated design

and lack of training

Not trained on the

ESD systems’

purpose and not

supportive of their

operation

Not supportive on

budget allocation

necessary for the

systems’

maintenance

Handover to the new

Shire without

appropriate

acknowledgment of

the ESD systems at

The Grove

BMS

a) The BMS was designed to be in charge of controlling and monitoring the ESD systems, and

to be accessible for Shire personnel and the operators of the BMS who were not specialised

in its operation. The design of the BMS at the user level is very sophisticated, but there are

not methodical training and handover procedures for the Shire and the operators of the BMS.

Moreover, absence of an operation and maintenance manual has caused disappointment and

frustration for the Shire management.

b) The BMS has not been configured to produce reports on the performance of the ESD system.

Therefore there is no evidence on performance of the building ESD systems which can be

compared to the environmental benchmarks of their initial designs. Breakdowns with the

ESD water systems and inability to monitor their performance contributed to a lack of trust in

these systems for the Shire, and a dearth of support for maintaining and sustaining their

66

operation. This may affect the ESD systems’ optimum operation and cause more

breakdowns.

c) The ESD water systems are not fully integrated into the BMS, for example, the stormwater

pump’s operation has not been incorporated into the BMS. Also the level of tanks and their

operational status can be monitored but not fully controlled through the BMS.

Additionally, maintenance is not scheduled or recorded in the BMS resulting in the water

contractor, who is in charge of maintaining the water systems, not having any interaction

with the BMS or remote monitoring of the status of the ESD water systems.

Some breakdowns with the systems, for instance, rise in BW tank level resulting in flooding

of the area, could have been prevented if remote access was available to the water contractor.

These many shortcomings of the BMS cause dissatisfaction for the Shire and operators of the

ESD systems, resulting their lack of support for the continual operation and maintenance of

the facility.

ESD Systems

d) Although the best, sustainably-designed systems were selected, the level of interaction

between different contractors was not settled so that they could become familiar with each

system’s operational specifications. For example, the water contractor was not aware of the

rainwater design requiring BMS recognition of UV activation before it starts the pump for

internal usage.

e) At the design stage, the long-term support capacity of the Shire management as the party

whose long term support is essential for optimal performance of the systems was not

clarified. This is significant as the continued sustaining of the ESD systems can be affected

by lack of budget for their ongoing maintenance.

f) The sophisticated and innovative design of the ESD systems means that only a few aptly

qualified contractors are capable of maintaining and servicing the systems. For example, the

innovative design of the YW system requires specialised contractors for its maintenance.

Their unavailability has exacerbated the management’s distrust in the optimum design of the

systems.

67

Maintenance

g) The total cost of the construction at The Grove was about $18 million, including

approximately $3.6 million for the ESD systems’ contracts and a $1.5 million grant from the

Australian Government’s Green Precinct Program (The Grove Precinct, 2011).

Conventionally, about 1.3% of total cost of construction is assigned for annual maintenance,

however for such sophisticated green building this amount is up to 2.7% (as quoted from the

Shire officer). The resulting budget for annual maintenance of The Grove is equivalent to

$36-72K for ESD systems only to ensure the optimal performance of the systems. Lack of

support from the Shire will result in a reduction in budgets for operation and maintenance of

these systems. Consequently this may cause breakdowns, thereby contributing to increased

dissatisfaction by the Shire.

h) There is not a section in the BMS for maintenance scheduling. No interaction with the water

contractor and the BMS has inhibited the optimal monitoring and controlling of the ESD

water systems. This omission will hinder preventive actions for some breakdowns within the

water systems.

Management

i) A lack of a methodical training program for the operators and the managers of the ESD

systems underlies the dissatisfaction which has affected their support in sustaining the ESD

systems. On the other hand, the complications with the BMS have contributed to the distrust

of Shire management at The Grove about ‘smart’ design.

j) The significance of the relationship between management, BMS and the ESD systems is that

it has the potential to ensure continual operation of the ESD systems thereby showcasing a

state of art public building in WA. Conversely it can affect the performance of the systems

negatively if a good relationship among all concerned is not maintained in long term.

68

7.2. Lessons Learnt on the Performance of Smart Buildings

a) The smart green buildings are sophisticated systems requiring involvement of all external

contractors at the commissioning stage, including critical interaction between

management, BMS and the maintenance operators.

b) A periodical report system to monitor the performance of the operating systems against

the environmental benchmarks can provide trust and support for ongoing sustainment of

the building systems.

c) Allocation of sufficient annual maintenance budget for ongoing operation of the building

and its operating systems should be established at the initial design stages.

d) Risk assessment and life cycle assessment of the ESD systems should be undertaken at

design stage to contemplate long term performance of the systems. In case of a

breakdown with a particular component, responsible parties should be able to take action

according to contingency guidelines.

e) Document control is significant in the sense that all the reports, manuals and guidelines

need to be easily accessible for operation and upon arousal of a breakdown in the system.

69

References

ABGR, 2013. Australian Building Greenhouse Rating Scheme. [Online]

Available at: www.abgr.com.au

Aghemo, C. et al., 2013. Management and monitoring of public buildings through ICT based

systems: Control rules for energy saving with lighting and HVAC services. Frontiers of

Architectural Research.

Ahmed, A., Ploennings, J., Menzel, K. & Cahill, B., 2010. Multi-dimensional building

performance data management for continuous commissioning. Advanced Engineering

Informatics, Volume 24, pp. 466-475.

Anda, M., 2012. Landscape irrigation nutrients management & future research opportunities.

The Grove Seminar: Integrating Sustainable Technologies in Public Building.

Berardi, U., 2013. Clarifying the new interpretations of the concept of sustainable building.

Sustainable Cities and Society, Volume 8, pp. 72-78.

Biolytix, 2013. Biolytix Wastewater. [Online]

Available at: http://www.biolytix.com

Bureau of Meteorology, 2013. Daily rainfall totals for Australia. [Online]

Available at: http://www.bom.gov.au/jsp/awap/rain/index.jsp

COX Howlett & Bailey Woodland, 2008. Landscape Architectural: Sedge Treatment Terraces

Stormwater Sedgeland. CPGMP Library and Community Learning Centre, PG Shire Offices.

Dallas, S., Anda , M., Byrne, J. & Mars, R., 2011. A yellow water reuse system for a public

building in perth, western australia. International Conference on Integrated Water Management.

Dallas, S., Anda, M., Byrne, J. & Menage, X., 2009. A fully integrated water cycle system for a

public building in Perth, Western Australia. OzWater.

70

Deng, S., Dai, Y., Wang, R. & Zhai, X., 2011. Case study of green energy system design for a

multi-function building in campus. Institute of Refrigeration and Cryogenics, Shanghai Jiao

Tong University. Volume 1, pp. 152-163.

DoH, 2012. Approved Aerobic Treatment Units, Department of Health, Western Australia.

Fuji Clean, 2011. Fuji Clean Australia: Domestic Wastewater Treatment Systems. [Online]

Available at: http://www.fujiclean.com.au/

[Accessed 2013 May 20].

GBC Australia, 2012. Green Building Council Australia. [Online]

Available at: http://www.gbcaus.org.au/

[Accessed 9 May 2013].

GBC Austrlia, 2008. Case Study: 40 Albert Road, GBC Australia.

GBCA, 2012. ESD Design Guide- Office and Public Buildings, Green Building Council of

Australia.

GBCA, 2013. Delivering the next generation of Green Star rating tools, s.l.: Green Building

Council of Australia.

Google Maps, 2013. Peppermint Grove Library. [Online]

[Accessed 15 May 2013].

Honeywell, 2010 Honeywell Building Solutions: Building Management Systems. [Online]

Available at: https://buildingsolutions.honeywell.com/Cultures/en-

US/ServicesSolutions/BuildingManagementSystems/

[Accessed 13 May 2013].

Huxtable, M., 2012. Landscape & Architecture & The Grove. The Grove Seminar: Integrating

Sustainable Technologies in Public Building.

Josh Byrne & Associates, 2011a. Stormwater treatment- Environmentally sustainable design

(ESD) fact sheet 5, The Grove Precinct.

71

Josh Byrne & Associates, 2011b. Rainwater harvesting: Environmentally sustainable design

(ESD) fact sheet 4, The Grove Precinct.

Josh Byrne & Associates, 2011c. Wastewater treatment and reuse: Environmentally sustainable

design (ESD) fact sheet 6, The Grove Precinct.

Levermore, G., 2003. Building Energy Management Systems: Applications to Low-energy HVAC

and Natural Ventilation Control. 3rd ed. Taylor & Francis.

LSE Cities, 2012. Going Green: How Cities are Leading the Next Economy, London: LSE

Cities.

Marinakis, V. et al., 2013. A building automation and control tool for remote and real time

monitoring of energy consumption. Sustainable Cities and Society, Volume 6, pp. 11-15.

Medved, S., 2006. Intelligent Controls and Advanced Building Management Systems. In: M.

Santamouris, ed. Environmental Design of Urban Buildings: An Integrated Approach. Earthscan.

NABERS, 2013. National Australian Built Environment Rating System. [Online]

Available at: www.nabers.com.au

Pujol, M., 2013. Geothermal heating and cooling for the Peppermint Grove Library, The Grove

Precinct.

Shire of Peppermint Grove, 2012. The Shire of Peppermint Grove. [Online]

Available at: www.peppermintgrove.wa.gove.au

The Grove Precinct, 2011. Final Report for the Green Precincts Fund, The Grove Precinct.

The Grove Precinct, 2012. [Online]

Available at: www.thegroveprecinct.com.au

Town of Cottesloe, 2012. [Online]

Available at: www.cottesloe.wa.gov.au‎

Town of Mosman Park, 2012. [Online]

Available at: www.mosmanpark.wa.gov.au

72

Water Design International, 2008. Irrigation Plan. CPGMP Library and Community Learning

Centre PG Shire Offices.

Water Installations, 2009. CPGMP Library and Community Learning Centre Drawings.

73

Appendices

Appendix A: Instructions on Data Extraction from the BMS

In order to extract data from The Grove Building Management System in the form of an

Excel or Word file, use the following instructions:

1) Open the BMS

2) View > Trend Summary

3) From the list of the already configured trends choose the one you are most interested in

(Figure 36). Alternatively you can configure a new trend-log for your specific points:

a. Click on a number with no trend name assigned to it, e.g. 50. A new page will

open. (Figure 35)

b. Click on the first cell in ‘Point ID‘ column, a new window will open which lists

all the points in BMS database from which to choose data. Choose the point from

which data is to be taken (Figure 36)

c. Click on the cell under ‘Parameter’ and select ‘Present Value’

d. Repeat previous steps for as many other points as required

e. Choose the period and interval of interest from the tab on the very top right side

of the page (Figure 37.b and Figure 37.c)

f. Save

4) Choose View Trend with Tabular History (Figure 37.a)

5) Select the Period and Interval as applicable to the set of data of particular interest, e.g. 1

year interval with 8 hours average (Figure 37.b andFigure 37.c).

6) Select ‘Show Selector Left and Right’; this will show the data selection for both start and

end of the period (Figure 37.d)

7) Auto Scale all Plots (Figure 37.e)

8) Click on Pause button and then Play to reveal the trends on screen (Figure 38).

9) Click on one row of data or on the graph

10) Click on Edit > Copy (this is the only way to copy the data); the usual ‘Ctrl+C’ does not

work in this version of the BMS.

11) Go to Excel or Word and Paste.

74

12) Now the data for that specific point with the selected intervals can be seen on the screen.

In order to find the units for each corresponding number:

a. Go to Welcome Page

b. Go to the ‘Hydraulic Services’ tab for information on Hydraulic services

c. Click on the feature of interest, e.g., rainwater

d. Find the Point of interest and double click on it; this will show the units of

measurement for that point.

Figure 34 A Snapshot of the The Grove BMS Trends page

75

Figure 35 A Snapshot of the The Grove BMS Trends configuration page

Figure 36 A Snapshot of the The Grove BMS Trends configuration page with points names

76

Figure 37 Snapshots of the The Grove BMS Trend Configuration a) View b) Period, c) Interval, d) Selector

and e)Scale selection tabs

77

Figure 38 Snapshot of the The Grove BMS final trend

78

Appendix B: The BMS Backup Support

Chronological events on accessing and extracting data from the BMS are listed below with

people involved and communications taking place:

19 Feb 2013

A technician from Honeywell came to fix the log-in problems with the BMS. This was

the first time he visited The Grove and he did not have any background on the venue.

However Don Jagodage, who was one of the main technicians involved in The Grove

BMS installation, was on-call providing back-up.

This technician was able to fix the log-in problem of the BMS; however the BMS still did

not show any data. It displayed '0' level for all tanks and systems. Finally he discovered

that another program was not activated thereby triggering this issue.

This was the first time access to the BMS was provided for this study. Different sections

of the BMS were observed.

One section of most interest for this study was the ‘Report’ section in the BMS. The

operator and the Researcher tried to extract data from it; however no output was

produced. Additionally it was not clear how the ‘Report’ section was to be used for

producing outputs. The operator could not explain the system either.

21 Feb 2013

Don Jagodage from Honeywell came to The Grove to solve the data extraction problem.

He had been previously involved at The Grove so possessed a good knowledge of the

system and the ESD systems.

This operator explained that extracting data for the ESD systems other than energy and

alarm systems could not be undertaken for this, the 2007 version of the BMS. The

version enabling data extraction for all systems is named the "Energy Manager Server"

(EMS).

He suggested visual observation of the trends, as shown in the ‘Trend’ section, though

without copying those data into an external file (e.g. Excel). He further suggested the

79

direct use of these trends for this study., the Researcher noted this could pose a serious

time constraint on the progress of the project.

Another issue was to determine the specific sensors’ tag names for the ESD monitoring

points. There are numerous monitored points in the BMS for different ESD systems and

features in its operation. A manual/document was required to find descriptions for them.

This document was not available in The Grove, the operator stating that Honeywell did

not possess that document either. As a solution he suggested direct contact to him for any

enquiries about the monitored points’ tag names.

7 March 2013

Andrew Crabtree from IBMS, who was previously involved in commissioning The Grove

ESD systems, came to help with data extraction into Excel.

Being knowledgeable about the system and its limitations, he explained exactly how to

save the logged data using the trends summary (Appendix A).

This was the first time data were extracted from the BMS to an Excel file for further

analysis. The specific monitored points for most of the ESD water systems were already

established. Further configuration of other points not already configured in the system

would be a complement to more comprehensive results.

The IBMS technician stated that access to the latest Input-Output (I/O) Schedule

document would be necessary in order to determine the points’ name tags. The version to

which he had access was an older version dating back to 2009. He stressed that an

updated version would be required especially following the new irrigations settings of

2012.

Michael Whitbread (Shire of Peppermint Grove) however could not find any I/O

Schedule document stored at The Grove.

80

27 March 2013

E-mail contact with Don Jagodage, the Honeywell operator in order to establish access

to an updated version of the I/O Schedule for The Grove BMS, had him replying that as

Honeywell did not have the document in question he should be contacted directly for

confirmation of the name tag for each monitoring point.

Another problem with the available I/O schedule of 2009, other than it being an outdated

document, was that the points described in the schedule did not have a matching tag name

in the BMS, causing further difficulties for mapping the correct abbreviation of the

required points.

12 May 2013

Upon email contact with Don Jagodage concerning the approximate price of upgrading

the BMS to a newer version, he stated that the current version at The Grove did not have

provision for upgrading to the “Energy Manager Server” (EMS) which enables extraction

and reporting on the entire ESD systems. Therefore complete replacement is required, the

total installment cost being estimated at $20,000 as quoted by Don Jagodage.

81

Appendix C: ESD Water Systems’ Layout at The Grove

Rainwater Systems

Figure 39 Rainwater system’s layout and details at The Grove (Water Installations, 2009)

82

Figure 40 Plan view of the stormwater system's layout at the Grove (COX Howlett & Bailey Woodland, 2008)

83

Wastewater Systems

Figure 41 Layout of the wastewater systems at The Grove (Water Installations, 2009)

84

Figure 42 Yellow water system’s layout and details at The Grove (Water Installations, 2009)

85

Figure 43 Greywater system's layout and details at The Grove (Water Installations, 2009)

86

Figure 44 Brown water system's layout and details at The Grove (Water Installations, 2009)

87

Irrigation Layout

Figure 45 Irrigation design layout of The Grove (Water Design International, 2008)

88

Appendix D: Field Visit with the Water Contractor

Field visit with Ross Mars, water contractor of The Grove

This report provides an understanding of the different ESD water systems’ operation from a site

visit to The Grove with Ross Mars, Water Installation, on 26th

April 2013.

Rainwater (RW)

a) The RW has not been accessible for internal use for a long time. The contractor explained the

series of actions which had taken place to correct the problem. The reason for the actions was

thought to be the pump, the controller or the UV. During February 2013 the UV was replaced

for the third time as it seemed to be the faulty component of the system. The system was

tested wherein the pump, pressure and the rainwater system were working properly. However

the RW system did not start to pump water automatically for internal usage.

b) Upon further investigation, it was only recently realised by the contractor that the rainwater

system’s design required UV activation before the pump operated. During all this time, the

BMS was preventing the pump from starting because it did not recognise the UV to be

operating. However, he did not know this at the time the UV was being replaced.

c) The initial UV was a sophisticated and expensive facility which was replaced under warranty

after a breakdown during the first year of operation. However, when for the second time the

UV became faulty it was not under warranty; it was deemed not worth paying approximately

$5,000 for such expensive system. Therefore it was decided to use a much simpler UV

system, the current one. But this new system was not checked for compatibility in connecting

to a monitoring system. The end result was that the system was not set so as to signal the

BMS to start the pump. Now the UV provider in New Zealand must be contacted to check

whether there is a method for connecting the UV to the BMS.

d) The BMS displays that both above-ground and below-ground tanks are full (Figure 20 of

Chapter 4), whereas the below ground tanks were empty when inspected by the contractor in

March 2013.

89

e) The problem was thought to be most likely with the sensor. The sensors have to be digital to

send data to the BMS, unlike the normal water level sensors that are analogue. The sensor

was calibrated by the contractor in 2011 before the systems were operated positively at The

Grove.

f) Later it was recalibrated for the BMS by the Honeywell operators. No further information on

the sensor has been available until the present when the item’s warranty has expired. If the

sensor has been faulty all this time, it was not noticed by the BMS or the contractors due to

the lack of monitoring capability of the BMS by external contractors.

Yellow Water (YW)

a) There are three urine tanks, one sedimentation tank and one dosing pump. The urine is filling

tank 2 and 3 presently after passing through the sedimentation tank; tank 1 is currently full

and maturing (Figure 46). The pump can draw YW from any of the three urine tanks and

send it to the pump tank before the dosing pump sucks the urine from the pump into the BW,

GW or irrigation.

b) Regarding the YW system, everything is operational. In terms of servicing, the levels are

monitored according to the current contract. The YW in tank 1 has passed the six months

maturing period and is ready to be pumped into the irrigation line as a fertilizer.

c) When one of the tanks is full, as determined by direct inspection of the water contractor

without any interaction with the BMS, it is closed manually and ignored for six months while

maturing. This date is recorded into the BMS which reckons the six months maturing period

mandated by the Shire and the BMS. When the water contractor comes for servicing

according to the maintenance contract, he looks inside the tanks to determine their levels

without interacting with the BMS or recording anything into it.

d) At the time of the Researcher’s visit, the contractor opened the yellow water tanks for

inspection; it was noticeable that the maturing tank had no odour, whereas the other tanks,

which are filing with urine, had the very intense ammoniacal smell of urine. Testing the pH

level of the matured YW before using it into the irrigation line was not required; however as

90

this was the first time for the YW to be used onsite, some testing of the quality (e.g. pH,

Nitrate, Phosphate and total dissolved solids) of the matured YW may be beneficial.

Figure 46 Picture showing the inside of a full yellow water tank

Greywater (GW)

a) The GW system is comprised of a sedimentation tank, a pump tank and an ozonation unit to

use the greywater for the substrata irrigation of the exotic garden. There are two pumps in the

GW system, one to pump the water from sedimentation tank to the pump tank, and one to

pump to the ozonation unit before sending to the irrigation line.

b) All the components of GW system are functional; however, upon inspecting the pump tank,

which requires the bore water top up, the water level was found to be quite low. Figure 47

shows the inside of the GW pump tank.

91

Figure 47 Picture showing the inside of the greywater pump tank at The Grove

c) The amount of GW produced is much less than anticipated in the design because not many

people are using showers and there is no laundry to produce GW. However provision has

been made for topping up with bore water. The design intends that the tank be filled every 30

sec with bore water, so that whenever the pump is activated, the tank is filled with bore water

and is pumped out to the irrigation.

d) Figure 26 shows the level of GW tank to have dropped by about 1.2 metres since June 2012.

The contractor explained this sudden change occurred because the bore having been switched

off during winter has not been turned on again for summer. He was unaware of this incident

and was not implicated himself. The event probably occurred during the handover to the new

shire, the GW bore top up being omitted with no person having the responsibility for

switching the bore top up back on.

92

Brown Water (BW)

a) The BW system is comprised of a Biogrinder and two Biolytix tanks wherein the BW is

treated by bacteria and worms, one pump chamber, and filters. The treated BW was used for

subsurface irrigating of the lawns. Figure 48 depicts the inside of an un-operational Biolytix

tank.

b) The Biolytix tanks were flooded due to high volume of bore water coming into them when

the pump was clogged as a result of high material turbidity, and the geotextile layers not

draining properly. The system was posing so much trouble that it was decided to remove the

BW completely from the irrigation line.

c) The effluent quality was poor and the Biolytix system started to fail and cause problems. The

reason behind the poor quality of the effluent was that the environment for the worms and

bacteria was not optimal. The worms were dying due to high temperatures. At the time of the

site visit the Biolytix tanks were dry and no evidence of macro-organisms life was present

(Figure 48).

It is now known that the lids of the Biolytix should be covered in mulch to reduce the heat

and thus provide the appropriate environment for the bacteria and worms, this not being

realised previously.

d) Also the BW system’s components need to be serviced regularly using improved servicing

methods which will allow reuse of the Biolytix tanks. The current service requirement of

these tanks is once a year while in practice more frequent servicing is required, as regularly

as once a month if the decision is to keep and make use of the current system. However, due

to the previous uncertainties, the Shire has decided not to spend any more money on

servicing or caring for the BW systems.

93

Figure 48 A picture of inside of the Biolytix tank at The Grove

e) One area needing action, if the Biolytix tanks continue in use, is the amount of BW treated

and used being only a small portion of the total BW produced, the remainder being diverted

to the sewer. A parameter in the BMS must be changed in order to allow the produced BW to

stay in the Biolytix tanks and be treated. This will improve the amount of water available for

irrigation of the lawn area whereas at the moment it relies on the mains water.

f) Figure 30 represents the trends produced from the BMS data, showing some flat-lining

periods in the level of BW. The contractor explained these as the pump being clogged before

servicing. After the pump service in February 2012, the level of BW in the tank has

increased. The reason for this high level is not due to higher BW production but because

when the bore top up enters the tank the raised levels could not be discharged due to the

pump being clogged.

94

g) The pump is still activated in order to remove the BW when, at a certain level, a signal

informs it to operate and pump the BW out. This will explain the fluctuation on the BW tank

level after its removal from the water system (Figure 31). However if the pump gets clogged,

it will not pump the water out and the water level keeps increasing and eventually floods

again. Therefore, although the BW system is disconnected from the irrigation system, regular

service is required to prevent the pump clogging and flooding the area.

Irrigation

a) Irrigation is a big problem as drip-lines are damaged because the reinjection bore machinery

for digging the bore severely damaged the irrigation setup and the associated turf.

b) Presently, sprinklers are employed for all the lawn areas using mains water. The sprinklers

are engaged instead of the drip-line because of their wide cover, but wasting much water.

They have been in use since late last year after a Halloween event at the library.

c) A means has already been set up in the system to make it possible to use bore water instead

of wastewater from the system; however, this capability to use the bore water has not been

used; mains water is used instead. Michael Whitbread, Shire of Peppermint Grove informs

that the cost of water used is not considerable though, being $24 per day.

d) As matters stand, all the irrigation must be restored if the system is to be used as it was

designed. This work is in addition to the regular maintenance contract; it requires urgent

attention from the Shire of Peppermint Grove.