Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
Insulation coordination for wind power
plants
EMTP-RV Satelite meeting
Paris, FRANCE – August 30, 2018
Prof. Dr. Ivo Uglešić
Božidar Filipović-Grčić, PhD
Bruno Jurišić, PhD
Nina Stipetić, mag.ing.
Faculty of Electrical Engineering and Computing
University of Zagreb, Croatia
• Insulation coordination definition
• Wind Power Plant characteristics
• Challenges of insulation coordination in WPPs
• Examples in EMTP-RV
Temporary overvoltage due to SLGF
Vacuum circuit breaker switching
Direct lightning strikes
Overview
1
• The goal of insulation coordination is uninterrupted and reliablepower supply in all technical and atmospheric conditions.
• Definition by IEC 60071-1:
Insulation coordination is the selection of the dielectric strength
of equipment in relation to the voltage which can appear on the
system for which the equipment is intended and taking into
account the service environment and characteristics of the
available protective devices.
The insulation in a power system (with all its components) should
be designed on the way to minimize damage and interruption to
service as a consequence of steady state and transient
overvoltages and this should be done economically.
Insulation coordination
2
• Transmission system: MVAC, HVAC, HVDC
• Collector system: MVAC cable network, different topologies
• Reactive compensation, filters at POI
• Main components:
wind turbine generators (Type 1 – Type 5)
vacuum circuit breakers
transformers (step-up and power transformer)
cables
3
Wind power plant characteristics
WPP – typical layout
WTGs
LV/MV
step-up transformers
feeder
breakers
substation
MV/HV
transformer
4
Lightning transients Coupling through substation
transformer From direct tower strikes
Switching transients Coupling through substation
transformer Feeder energization Vacuum circuit breaker switching
(VFFT due to prestrikes and restrikes)
Temporary overvoltages Ground faults Feeder islanding, loss of ground
reference Can be higher than 1.73 pu
Continuous operating voltages Higher voltage at remote ends
Overvoltages in WPPs
Surge arrester selected
to protect equipment
from these
Surge arrester selected
to survive these
5
Surge arrester typical placement in MV network
6
• adjacent to the substation power transformer
• on the feeder side of each feeder breaker
• at each interface between overhead and underground
feeder sections
• at the end of each feeder and branch
+ LV surge arresters in the tower
7
Conventional process from
standards (IEEE C62.22, IEC 60071)Procedure for WPPs
1. Select the surge arrester to be used
(MCOV, TOV)
1. Select the available insulation level
(limited range)
2. Determine the protective level of
selected surge arrester
2. Select arresters needed to protect
that insulation level
3. Determine the locations for surge
arresters
3. Determine amount of TOV that can
be withstood
4. Determine the voltage at terminals
of the protected equipment
5. Select equipment insulation level
Evaluate voltage protection margins
Insulation coordination steps
if margins are inadequate, consider alternatives:
different arrester locations, higher insulation
level...
TOV mitigation methods
Temporary overvoltage due
to SLGF
8
9
Example 1
Temporary overvoltage: single-line-to-
ground fault, feeder disconnection and
loss of ground reference
1.
2.3.
R. Walling, WESC10
Example 1
• Overvoltage of healthy phases depends on grounding and WTG type
• TOV mitigating options: Transfer tripping (normaly used in new WPPs)
High-speed grounding switch
Grounding transfomer on each feeder
• The choice depends on WTG type
11
Example 1
voltage measurement
faultGT2
GT1
X
+
Vw
Z1
0.6
9kV
/_0
VM+m2
?v/?v/?v
LF
Phase:0
Slack: 132kVRMSLL/_0
LF1
+132kVRMSLL /_0
BUS:
VwZ10
FDQ+
FDQ2
FDQ+
FDQ12
CABLE DATA
model in: cable_sc_100m_33_6fd_rv.pun
cabledata4
FDQ+
FDQ13
CABLE DATA
model in: cable_33_800_6ph_fd_rv.pun
cabledata5
+ Vw
Z11
0.6
9kV
/_0
FDQ+
FDQ14
1 2
+30
DY_2
33/132+
1nFC1
+
1nFC2
+ Vw
Z12
0.6
9kV
/_0
+
-1|1
E15|0
SW
4
FDQ+
FDQ15
+ Vw
Z13
0.6
9kV
/_0
+
-1|1
E15|0
SW
11
FDQ+
FDQ16
+ Vw
Z14
0.6
9kV
/_0
+
-1|1
E15|0
SW
12
FDQ+
FDQ17
+ Vw
Z15
0.6
9kV
/_0
+
-1|1
E15|0
SW
19
FDQ+
FDQ18
+ Vw
Z16
0.6
9kV
/_0
+
-1|1
E15|0
SW
20
FDQ+
FDQ19
+ Vw
Z17
0.6
9kV
/_0
+
-1|1
E15|0
SW
21
FDQ+
FDQ20
12
+3
0
33/0
.69
+
-1|2
00m
s|0
SW
26
+
-1|1
E15|0
SW
27
+
-1|1
E15|0
SW
28
12
+3
0
33/0
.69
+
-1|2
10m
s|0
SW
29
CABLE DATA
cabledata6
VM+
?v
m8
Vacuum circuit
breaker model
DEV9
Vacuum circuit
breaker model
DEV10
Vacuum circuit
breaker model
DEV11
12
+3
0
33/0
.69
+
-1m
s|2
15m
s|0
SW
30
12
+3
0
33/0
.69
+
-1m
s|2
20m
s|0
SW
31
12
+3
0
33/0
.69
+
-1m
s|2
25m
s|0
SW
32
12
+3
0
33/0
.69
+
-1|2
30m
s|0
SW
33
12
+3
0
33/0
.69
+
-1m
s|2
15m
s|0
SW
34
12
+3
0
33/0
.69
+
-1m
s|5
00m
s|0
SW
35
VM+
?v
m10
VM+
?v
m11
+R
13
1m
+
R14
1m
+
R15
1m
+R16
100M
+
R17
100M
+R18
100M
+
RL7
?i
2,4
Ohm
+
RL8
?i
2,4
Ohm
+
RL9
?i
2,4
Ohm
+
12
Tr0
_7
1
+
12
Tr0
_8
1
+
12
Tr0
_9
1
+
20m
s|1
20m
s|0
?vi
SW
36
+R
19
1m
+
R20
1m
+
R21
1m
+
R22
100M+
R23
100M+
R24
100M
+
RL10?
i12,2
5O
hm
+
RL11?
i12,2
5O
hm
+
RL12?
i12,2
5O
hm
+
12
Tr0
_10
1
+
12
Tr0
_11
1
+
12
Tr0
_12
1
+
20m
s|1
E15|0
?vi
SW
37
+A ?
i
m12
+A?
im
13
+
20m
s|1
E15|0
?vi
SW
38
scope
?s
scp1
scope scp2
?sscope scp3
?s
+ A
?i
m1
+ A?i
m3
Data function
ZnO
arrester abb.dat
model in: arrester abb.pun
+Zn
O
ZNOc
?vi>e
66000+Z
nO
ZNOb
?vi>e
66000+Z
nO
ZNOa
?vi>e
66000
b
c
a
c
b
a
BUS_A2cc aa bb
BUS_A3
c cb ba a
BUS_A4
b ba ac c
BUS_A5
cc aa bb
BUS_A7
cc aa bb
BUS_A6
cc aa bb
BUS_A1
cc bb aa
c
a
b
a ab bc c
BUS_A8
a a
cc
bb
e_ZNOa
e_ZNOb
e_ZNOc
ynD 0.69/33 kV
dYn
33/132 kVGrounding transformer
zig-zag
33 kV cable network
VCB
WTG
1. SLGF occurs at 20 ms on phase C
2. Feeder breaker opens at 100 ms – loss of ground reference
3. WTGs continue to generate
12
Example 1 – GT 2 excluded
1. 2.
overvoltage limited
13
Example 1 – GT included
1. SLGF occurs at 20 ms on phase C
2. Feeder breaker opens at 100 ms – loss of ground reference
3. WTGs continue to generate
1. 2.
overvoltage remains limited
Vacuum circuit breaker
switching
14
15
Practical problems with VCB switching in wind farms
• The first off-shore wind farms were faced with substantialtransformer failures in a very early operation stage.
• In the first large offshore wind farms Horns Rev andMiddelgrunden (Denmark), almost all of the transformers had tobe replaced due to insulation failures.
• It is suspected that the switching of the vacuum circuit breakers(VCB) caused the transformer failures.
• In order to investigate this phenomenon, a laboratory setup wasbuilt, designed to give an insight into high frequency transientsgenerated during breaker switching in offshore wind farms andsimilar cable systems.
„ELECTRICAL TRANSIENT INTERACTION BETWEEN TRANSFORMERS AND THE POWER SYSTEM”, CIGRE WG A2/C4.39
16
Vacuum circuit breaker switching
17
Restrike phenomena during breaking of small
inductive current
18
Restrikes caused by VCB switching
„ELECTRICAL TRANSIENT INTERACTION BETWEEN TRANSFORMERS AND THE POWER SYSTEM”, CIGRE WG A2/C4.39
19
Example 2 – Failure of power transformer 110/25 kV
Failure of 25 kV winding
20
Example 2 – EMTP-RV model
• Detailed model of VCB
• Detailed model of power transformer (high-frequency behaviour)
VCB
MV cable network (capacitive load)
Power transformer
Trafo -A5
+ C30.100nF
VM+ m1?v
Data function
ZnO
model in: polimh29.pun
+L1
482mH
+
ZnO
72600
ZnO1
Vacuum circuit breaker model
DEV1
+
C2
3.5
uF
+
ZnO
72600
ZnO2
State
Space4
SS2
d__1
d__2
c
d__4
+
AC2
110kVRMSLL /_0
cb
a
d__2
GND
GND
GND
GND
VCB
Cable network
Power transformer
110 kV network
Simulation results
VCB voltage
21
Simulation results
VCB current
22
Simulation results
VCB current
23
Simulation results
Overvoltage at 25 kV winding of power transformer
24
Simulation results
Overvoltage at 25 kV winding of power transformer25
Direct lightning strike to wind
turbine
26
Damages caused by direct lightning strike
27
28
Lightning and surge protection for the wind turbine
29
Placement of the SPDs
SPD according to EN 61643-11/IEC 61643-11 type 2/class II
Nominal AC voltage (Un) 480 V (50/60 Hz)
Max. continuous operating voltage (Uc) 600 V (50/60 Hz)
Nominal discharge current (8/20 µs) (In) 15 kA
Max. discharge current (8/20 µs) (Imax) 25 kA
Voltage protection level (UP) ≤ 3 kV
Temporary overvoltage (TOV) 900 V / 5 sec.
Example:
protection for
the generator
30
Example 3 – Direct lightning strike to WT blade
SM
SM1
VM+w1B1a
?v
VM+w1B1c
?v
1 2
-30
YD_1
0.69/22
VM+w1B1b
?v
VM+m4
?v1 2
+30
DY_1
22/110
VM+m5
?v
+
VwZ1
?vi
123kVRMSLL /_0
VM+m1
?v
VM+m2
?v
+
100kA/3us?iIcigre1
FDQ+
CABLE DATA
model in: lv_cable_rv.pun
LV_cable
CP
+40
TLM
4
CP
+80
TLM
3
CABLE DATA
model in: cabledata1_rv.pun
cabledata1
FDQ+
FDQ2
+
I
YIY
0.04
?vi>i
Rn1
if(u) 1
Fm1
f(u) 1
Fm2
c0.02
C1
1
2
select
Sel1
+
1.155nFC2+
2.21nFC3
+
2.4
64nF
C4
Data function
ZnO
model in: arresterlv.pun+Zn
O
700
?vi
ZnO1
c
ba
BUS4
a
b
c
BUS3BUS3
c
b
a
BUS2
c
b
a
BUS7
GND
GND
GNDGND
SPD
22 kV cable
2 km
0,7 kV cable 80 m
TR1 0.69/22 kV
3 MVATR2 22/110 kV
15 MVA
110 kV
network
WTG
3 MVA
Tower
80 m
Blade
40 m
Grounding resistance 50 Ω
(ionization included)
Single WTG 3 MVA operating in the vicinity of substation 22/110 kV.
Lightning current 100 kA
31
Lightning current Current through grounding resistance
Potential rise at grounding resistanceGrounding resistance
Example 3 – lightning current distribution / ionization
32
Overvoltages at 0.69 kV side of TR1 Transferred overvoltages at 22 kV side of TR1
Overvoltages at WTG terminals
Example 3 – overvoltages at TR1 and WTG terminals
Example 3 – SPD connected in neutral point of TR1
and ideally grounded
33
Overvoltages at 0.69 kV side of TR1 Transferred overvoltages at 22 kV side of TR1
Overvoltages at WTG terminals
Conclusion
34
• Different approaches for reducing TOVs due to SLGF areinvestigated. Simulations have shown that application ofgrounding transformer efficintly reduces TOVs during SLGF.
• EMTP-RV simulations confimed the fact that VCB switchingproduces VFTOs which are not high in magnitude, but due tohigh freqency, the distribution across the transformer winding isnonlinear. This may cause dielectric breakdown of transformerinsulation system.
• The results of direct lightning strike simulation indicate that useof appropriate SPDs is crucial in order to protect the vulnerableelectronic equipment. However, the efficient operation of SPDsdepends on grounding resistance value which should be kept aslow as possible.
Insulation coordination for wind power
plants
EMTP-RV Satelite meeting
Paris, FRANCE – August 30, 2018
This work has been supported in part by the Croatian Science
Foundation under the project “Development of advanced high voltage
systems by application of new information and communication
technologies” (DAHVAT)