    Engineeringpapers.blogspot.comFIC : FLOW INDICATING CONTROLLER

    FS : FLOW SWITCH

    FY : FLOW CONVERTER

    FA : FLOW ALARM

    FR : FLOW RECORDER

    FRC : FLOW RECORDING CONTROLLER

    LEVEL

    L : LEVEL

    LI : LEVEL INDICATORLG : LEVEL GAUGE

    LIT : LEVEL INDICATING TRANSMITTER

    LCV : LEVEL CONTROL VALVE

    LDT : LEVEL DISPLACER TRANSMITTER

    LIC : LEVEL INDICATING CONTROLLER

    LRC : LEVEL RECORDING CONTROLLER

    LS : LEVEL SWITCH

    LSH : LEVEL SWITCH HIGH

    LSL: LEVEL SWITCH LOW

    LA : LEVEL ALARM

    RLT : RADAR LEVEL TRANSMITTER

    GENERAL

    DCS : DISTRIBUTED CONTROL SYSTEM

    SCADA: SUPERVISORY CONTROL AND DATA ACQUISITION SYSTEM

    PLC : PROGRAMMABLE LOGIC CONTROLLER

    HART : HIGHWAY ADDRESSABLE REMOTE TRANSDUCER

    HHT : HAND HELD TERMINAL

    SFC : SMART FIELD CONFIGURATOR

    ESD : EMERGENCY SHUT DOWN

    AOV : AIR OPERATED VALVEMOV : MOTOR OPERATED VALVE

    SV : SOLENOID VALVE

    XVE : VIBRATION PROXIMITOR

    XVT : VIBRATION TRANSMITTER

    AE : ANALYZER

    JB : JUNCTION BOX

    ILD : INSTRUMENT LOOP DIAGRAM

    P&ID : PIPING AND INSTRUMENT DIAGRAM

    IIS : INSTRUMENT INSTALLATION SCHEDULE

    TDR : TIME DELAY RELAY

    SP : SET POINT

    NC : NORMALLY CLOSED

    NO : NORMALLY OPEN

    MCC : MOTOR CONTROL CENTRE

    IAS : INSTRUMENT AIR SUPPLY

    IGS : INSTRUMENT GAS SUPPLY

    ACFO : AIR TO CLOSE FAIL OPEN

    AOFC : AIR TO OPEN FAIL CLOSE

    FFA : FLAME FAILURE ALARM

    P/I P to I : PNEUMATIC TO CURRENT CONVERTER

    I/P I to P : CURRENT TO PNEUMATIC CONVERTERPB : PUSH BUTTON

    Page 2 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    3/15

    Engineeringpapers.blogspot.comPID : PROPORTIONAL, INTEGRAL AND DERIVATIVE

    E/H: ELECTRO HYDRAULIC ACTUATOR

    BOV : BLOW DOWN VALVE

    A/M : AUTO / MANUAL 2 POSITION SWITCH

    ZS : POSITION SWITCH

    HS : HAND SWITCH

    Page 3 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    4/15

    Engineeringpapers.blogspot.com

    2) INSTRUMENT LINE SYMBOLS

    2.1) INSTRUMENT SUPPLY or CONNECTION TO PROCESS ___________________

    2.2) PNEUMATIC SIGNAL ___________________

    2.3) ELECTRICAL SIGNAL (ANALOG SIGNAL) (mA DC (OR) VDC) ------------------------

    3.4) ELECTROMAGNETIC or SONIC SIGNAL ___________________

    3.5) HYDRAULIC SIGNAL ___________________

    2.6) CAPILLARY TUBE(FILLED SYSTEM) ___________________

    2.7) PULSE TRAIN _ _ _ _ _ _ _

    2.8) INTERNAL SYSTEM LINK(SOFTWARE or DATA LINK)

    -----------------------------------------------------------------------------------------------------------------

    3) TYPES OF SUPPLY

    3.1) AS - AIR SUPPLY IA INSTRUMENT AIRPA PLANT AIR

    3.2) ES ELECTRICAL SUPPLY

    3.3) GS GAS SUPPLY

    3.4) HS HYDRAULIC SUPPLY

    3.5) NS NITROGEN SUPPLY

    3.6) SS STEAM SUPPLY

    3.7) WS WATER SUPPLY

    The ES or AS symbol is to be used only for Field Devices requiring supply. Forpanel mounted instruments power supplies are not shown on flow sheet.

    Page 4 of 15

    Options

    IAS 130 kPa

    ES 24 V DC

  • 8/7/2019 Instrumentation Symbols & Standards

    5/15

    Engineeringpapers.blogspot.com

    4) GENERAL INSTRUMENT SYMBOLS

    Page 5 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    6/15

    Engineeringpapers.blogspot.com

    Page 6 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    7/15

    Engineeringpapers.blogspot.com

    5) IDENTIFICATION LETTERS

    TABLE 1

    FIRST LETTER (4) SUCCEEDING LETTER (3)

    MEASURED / INITIATINGVARIABLE

    MODIFIER READOUT /PASSIVE

    FUNCTION

    OUTPUTFUNCTION

    MODIFIER

    A ANALYSIS (5, 19) ALARM

    B BURNER, COMBUSTION USERS CHOICE (1) USERS CHOICE (1) USERS CHOICE (1)

    C USERS CHOICE (1) CONTROL (13)

    D USERS CHOICE (1) DIFFERENTIAL(4)

    E VOLTAGE SENSOR (PRIMARYELEMENT)

    F FLOW RATE RATIO(FRACTION) (4)

    G USERS CHOICE (1) GLASS, VIEWINGDEVICE (9)

    H HAND HIGH (7,15,16)

    I CURRENT (ELECTRICAL) INDICATE (10)

    J POWER SCAN (7)

    K TIME, TIME SCHEDULE TIME, RATE OFCHANGE (4, 21)

    CONTROL STATION(22)

    L LEVEL LIGHT (11) LOW (7, 15, 16)

    M USERS CHOICE (1) MOMENTARY(4)

    MIDDLE,INTERMEDIATE (7,

    15)

    N USERS CHOICE (1) USERS CHOICE (1) USERS CHOICE (1) USERS CHOICE (1)

    O USERS CHOICE (1) ORIFICE,RESTRICTION

    P PRESSURE, VACUUM POINT (TEST)CONNECTION

    Q QUANTITY INTEGRATE,TOTALIZE (4)

    R RADIATION RECORD (17)

    S SPEED, FREQUENCY SAFETY (8) SWITCH (13)

    T TEMPERATURE TRANSMIT (18)

    U MULTIVARIABLE (6) MULTIFUNCTION (12) MULTIFUNCTION (12) MULTIFUNCTION (12)

    V VIBRATION, MECHANICALANALYSIS (19)

    VALVE, DAMPER,LOUVER (13)

    W WEIGHT, FORCE WELL

    X UNCLASSIFIED (2) X AXIS UNCLASSIFIED (2) UNCLASSIFIED (2) UNCLASSIFIED (2)

    Y EVENT, STATE / PRESENCE(20)

    Y AXIS RELAY, COMPUTE,CONVERT(13,14,18)

    Z POSITION, DIMENSION Z AXIS DRIVER,ACTUATOR,

    UNCLASSIFIEDFINAL CONTROLELEMENT

    NOTE: Numbers in parentheses refer to specific explanatory notes.

    Page 7 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    8/15

    Engineeringpapers.blogspot.com

    6) TYPICAL LETTER COMBINATIONSTABLE 2

    Page 8 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    9/15

    Engineeringpapers.blogspot.com

    7) FUNCTIONAL BLOCKS FUNCTIONAL DESIGNATIONS

    THE FUNCTION DESIGNATIONS ASSOCIATED WITH CONTROLLERS, COMPUTING DEVICES, CONVERTERSAND RELAYS MAY BE USED INDIVIDUALLY OR IN COMBINATION (ALSO SEE TABLE 1, NOTE 14). THE USE OFA BOX AVOIDS CONFUSION BY SETTING OFF THE SYMBOL FROM OTHER MARKINGS ON A DIAGRAM ANDPERMITS THE FUNCTION TO BE USED AS A STAND ALONE BLOCK ON CONCEPTUAL DESIGNS.

    TABLE -3

    Page 9 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    10/15

    Engineeringpapers.blogspot.com

    Page 10 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    11/15

    Engineeringpapers.blogspot.com

    Page 11 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    12/15

    Engineeringpapers.blogspot.com

    Page 12 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    13/15

    Engineeringpapers.blogspot.com

    Page 13 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    14/15

    Engineeringpapers.blogspot.com

    Page 14 of 15

  • 8/7/2019 Instrumentation Symbols & Standards

    15/15

    Engineeringpapers.blogspot.com

    8. APPLICATION EXERCISE