Upload
ashlie-garrison
View
216
Download
1
Tags:
Embed Size (px)
Citation preview
Institutional and Technical Analysis of Wind Integration Challenges in Northeast China
Michael DavidsonAdvisors: Ignacio Perez-Arriaga, Valerie J. Karplus
TMP – June 2014
2
Motivation
2013 Actual 2015 2020*
Thermal 862
Hydro 280 290 370
Wind 75 104 220
Nuclear 15 40 60
Solar 15 35 91
Biomass < 9 13 26
Source: China Electricity Council, NEA, ERI*Final 2020 targets are still under discussion
Wind is key focus of low-carbon electricity policy efforts in China.
Grid-connected wind capacity is expected to triple by 2020, and
may reach 400 / 1000 GW in 2030 / 2050.
Generation (2000-2013) Non-Fossil Capacity Targets
Wind integration challenges led to additional 9 Mt coal burned in 2012
Curtailment: Available wind turbines are instructed to not put power on the grid for economic, grid stability and other reasons
Spilled wind
3
Some technical causes
4
Some institutional causes
• Tariffs set administratively by NDRC for each province reflecting economic costs and affordability
• Annual “generation quotas” for each coal plant to recover costs
• Transmission quotas/limits between provinces most balancing is done within province
• “Energy efficient dispatch” piloted since 2007: implementation uneven, and inconsistent with power sector market reform
5Sources: Ma, 2011; Kahrl et al., 2013; Gao & Li, 2010
Research question
• What is the relative contribution of technical and institutional causes to wind curtailment in the Northeast?
• Evaluate the potential of the following solutions to reduce costs and wind curtailment:– More flexible operation of coal plants– Dynamic minimum outputs of CHP units based on heat load– Heat storage– Greater transmission interconnection
6
Model
Unit commitment optimization:
– Minimizes total operating cost = variable + startup costs– Week time period: T=168 hours– Fixed heating load constrains CHP plant operation– Hydropower dispatch with historic inter-season storage rates– Up and down spinning reserves– All prices in yuan ($1 = 6.2 Yuan)
7
Data
8
6 representative wind resource weeks Fixed weekly electricity load
(MW) %Thermal 71,459 80.2%Hydropower 7,005 7.9%Wind 10,606 11.9%
Total 89,069
Capacity (end of 2010)
Unit composition
• Database of all generators: CEC (2010)• Updated unit breakdowns, cogeneration status
9
Daily Heating Load Power-Heat Curve
Heat demand
10
11
Modeling institutional constraints
• “Generation quotas”: set minimum capacity factor of coal generators based on provincial average and reasonable summer/winter difference
• “Provincial dispatch”: (1) Set transmission limits and transmission directions between provinces. (2) Meet reserve requirement at provincial level.
Source: Kahrl et al., 2013; Gao & Li, 2010
Results
12
Reference Case (Technical Factors Only)
Objective (mil RMB)
Coal Use (Mtce)
Wind Generation (GWh)
Wind Share (% Generation)
Wind Curtailment (%)
Ja1 1,454.3 2.066 504.7 7.6% 5.0%Ja2 1,481.4 2.109 358.6 5.4% 5.9%Ja3 1,425.7 2.028 629.7 9.5% 5.9%
Ma1 1,432.4 2.035 606.2 9.1% 9.6%Ma2 1,443.9 2.050 555.5 8.4% 6.9%Ma3 1,390.3 1.972 815.2 12.3% 6.1%Avg 1,438.0 2.043 578.3 8.7% 6.6%
13
0 9 18 27 36 45 54 63 72 81 90 99 108 117 126 135 144 153 1620
5000
10000
15000
20000
25000
30000
35000
40000
45000
50000
Wind Profile: Ma1
wind
hydro
coal25
coal50
coal135
coal200
coal350
coal600
cogen25
cogen50
cogen135
cogen200
cogen350
cogen600
Hour
Gen
erat
ion
(M
W)
Ja – JanuaryMa - March
Flexible coal
• Lower minimum outputs (from 54% to 40%) improve cost and wind integration
• Startup/shutdown times, ramp limits have little effect • Startup costs have noticeable effect
14
Objective (% Change from
Reference)
Wind Curtailment (% Change from
Reference)Pmin 40% -1.0% -47.9%Ramp Rates 50% 0.0% 4.2%Startup/ 24,24,6 0.0% 4.2% Shutdown 12,12,6 0.0% 0.0% Times 6,3,3 0.0% 0.0%Startup Costs 500 -0.1% -25.0% 400 -0.3% -42.7%
Heat
• Dynamic outputs in dispatch worsens curtailment Economic curtailment from not shutting down a
high must-run baseload unit• Storage has potentially huge impact
15
Objective (% Change from
Reference)
Wind Curtailment (% Change
from Reference)
Dynamic, No Shift -0.9% 31.6%Dynamic, 4 Hour Shift -1.2% -4.2%Dynamic, 8 Hour Shift -1.8% -67.8%
Regulatory Features: Provincial Dispatch
• Reserve requirements at provincial level increase curtailment:
16Ja1 Ja2 Ja3 Ma1 Ma2 Ma3 Avg
0.0%
2.0%
4.0%
6.0%
8.0%
10.0%
12.0%
14.0%
RegionalProvincial
Generation Quota
• Highest curtailment for provincial dispatch with generation quota
• Difficulties w/model convergence
(Ma1 wind scenario)
17
Objective (mil RMB)
Wind Curtailment (%)
Regional Reference 1,432.40 9.6%Regional (Min CF) 1,442.90 11.3%Provincial Reference 1,444.30 12.0%Provincial (Min CF) 1,454.30 11.7%
18
Conclusions (1)
Technical
• Absent regulatory design issues, there is curtailment (6.6% average), but still below observed levels of curtailment (15-40% in winter months)
• Heat-electricity interactions can be measured: large impact of storage implies significant coupling and potential benefits from coordination
• Some flexibility changes in coal (e.g., lower mins and reduced startup costs) will reduce curtailment…but not all (e.g., shorter startup/shutdown times, higher ramp rates)
Conclusions (2)
Regulatory
• Provincial dispatch with minimum generation quotas increases curtailment on order of technical causes
• More broadly, this methodology helps identify province-level dynamics in an otherwise opaque system
• Future research: Due to economic curtailment, does cost-minimizing dispatch guarantee elimination of integration challenges?
19
20
Thank you谢谢
21
References
Gao, C., and Li, Y. (2010). Evolution of China’s power dispatch principle and the new energy saving power dispatch policy. Energy Policy, 38(11), 7346-7357.
Kahrl, F., Williams, J., Ding, J. H., & Hu, J. F. (2011). Challenges to China's transition to a low carbon electricity system. Energy Policy, 39(7), 4032-4041.
Kahrl, F., Williams, J. H., & Hu, J. (2013). The political economy of electricity dispatch reform in China. Energy Policy, 53(0), 361-369.
Kerr, T. (2008). CHP/DHC Scorecard: China. International Energy Agency. Liu, W., Lund, H., & Mathiesen, B. V. (2011). Large-scale integration of wind power into the existing
Chinese energy system. Energy, 36(8), 4753-4760.Ma, J. L. (2011). On-grid electricity tariffs in China: Development, reform and prospects. Energy Policy,
39(5), 2633-2645. Schuman, S. & Lin, A. (2012). China’s Renewable Energy Law and its impact on renewable power in
China; Progress challenges and recommendations for improving implementation. Energy Policy 51 (2012): 89-109.
Zhao, X., Zhang, S., Yang, R., & Wang, M. (2012). Constraints on the effective utilization of wind power in China: An illustration from the northeast China grid. Renewable and Sustainable Energy Reviews, 16(7), 4508-4514.
Zhang, D., Davidson, M., Gunturu, B., Zhang, X. & Karplus, V. J. An Integrated Assessment of China’s Wind Energy Potential (Report No. 261). (MIT JPSPGC, Cambridge, MA, 2014)
22
China power sector reform• 1949-1985: Vertically-integrated state-run utility (Ministry of
Water Resources and Electric Power, later Ministry of Electric Power)
• 1985-1997: Private & foreign investors allowed to invest in generation, “competed” with local utilities
• 1997-2002: Ministry broken up– Regulatory fns SETC, SDPC and later NDRC– State-owned generating assets Big Five SOEs– T&D assets, system operation State Grid, Southern Grid
• 2003-present: Reform slowed – markets, indep system operator were not created
• China does not fit either model – only partially unbundled
23
Why the Northeast
Kerr (2008)Zhang et al. (2014)
High proportion of combined heat and power (CHP) units
Regional electricity/heat institutions
24
State Grid Provincial Governments
Northeast Grid
Provincial Grids
Coal Generators
Wind Subsidiaries
Energy SOEs Wind
IPPs
GovernmentQuasi-gov’tSOEOther
Municipal Governments
Ele
ctri
city
Distric
t Hea
ting
Monthly Curtailment Figures
25
Jan Feb Mar Apr May Jun Avg
Jilin 30.5% 34.8% 42.5% 30.3% 19.5% 11.0% 28.1%
E. IM 24.1% 27.9% 23.6% 22.3% 12.7% 6.1% 19.4%
Gansu 25.3% 25.7% 20.9% 14.2% 14.2% 10.5% 18.4%
W. IM 25.8% 26.1% 24.5% 9.6% 5.1% 4.9% 16.0%
Liaoning 23.6% 20.4% 19.1% 13.8% 3.5% 1.4% 13.6%
Heilongjiang 19.2% 20.2% 22.3% 15.9% 2.7% 0.8% 13.5%
Wind curtailment (generation) by province (1st half 2012)
Source: China Association of Agricultural Machine Manufacturers
26
In a region with high overcapacity
Transmission
27
Transmission (Provincial Dispatch)
28