Installation, Operation and Maintenance of Batteries

Embed Size (px)

Citation preview

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    1/48

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    2/48

    110V 300AH BATTERY

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    3/48

    USB RECHARGE CELL

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    4/48

    FUEL CELL(Electricity not required to

    charge)

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    5/48

    SIMPLE CONSTRUCTION OF FUELCELL

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    6/48

    WORKING PRINCIPLE OF FUEL CELL

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    7/48

    TYPE OF CHARGING

    1.INITIAL CHARGING,2.TRICKLE CHARGING,3.BOOST CHARGING,4.QUARTLY EQUALISINGCHARGING,5.SPECIAL CHARGING.

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    8/48

    INITIAL CHARGING

    Batteries received in dry state,Clean the outer surface of each cell,Clean the inside of the container withdry compressed air gently,Check for any crack or damage ,

    CONT..

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    9/48

    Confirm the polarity of each cell , Arrange the cells with correctpolarity ,

    Apply a thin layer of Vaseline aftercleaning of studs with sand paper,

    Connect the cells with strapsproperly.

    cont..

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    10/48

    Acid of 1190 sp.gr to be pouredslowly in all the cells with requiredlevel.Cells are to be allowed to absorbthe acid for more then12 to not

    exceeding 24 hours cont..,

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    11/48

    Connect the battery set to chargerwith correct polarityKeep the variac in minimumpositionPrepare a log sheetSwitch on the charger and rise thecharger current by varying theposition of variac to the level asspecified by the manufacture or

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    12/48

    Normally the first charging current is 5%of capacity,Period of 1st charging is 100Hrs,For every 8 Hour Log reading of voltageand sp. gravity up to 90Hour,Temperature of the cell should notexceed 50 deg,

    After 90 hrs equalize all cells by meansof adding acid or distilled water duringbalance 10 hrs period.STOP CHARGING.

    Allow rest 12 to 24 hrs .

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    13/48

    First Discharge

    Connect the load through a switch,ammeter and fuse unit,Load may be resistor bank, waterrheostat, lamp bank, heater etc,Discharging current may be adjustedaccording to the capacity of the

    battery or stated by the manufacturer.

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    14/48

    Normally 10 hour rating of AH will bethe discharging current

    For 300 AH Battery is 30ASp. Gr. and voltage readings to betaken every hour initially and every

    15 minutes when battery voltagenearing 1.85 V * no. of cells(101.75Vfor 110V, 203.50 for 220V & 27.9 for30V Battery)

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    15/48

    When the voltage of the batteryreaches 1.85V * no. of cells thedischarging should be stopped If any cells Sp. Gr. reduced below1160 discharging should be

    stoppedIf any cells voltage reduced below1.85V the discharging to be

    stopped

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    16/48

    SECOND CHARGING

    Restart the charging with fullcapacity of battery current,Log the reading ,Stop charging when threeconsecutive readings of Specific

    gravity, Allow 12 to 24 hours rest,

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    17/48

    SECOND Discharge

    Same procedure asfirst discharge cycle .

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    18/48

    THIRD CHARGING

    Restart the charging with full capacityof battery current,Log the reading ,Stop charging when three consecutivereadings after reach rated values,

    Now the battery ready foruse

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    19/48

    BATTERYMAINTENANCE

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    20/48

    Keep the battery Room clean & wellventilatedExhaust fan / fans always kept ONClean the battery and battery standregularlyClean the battery terminals and applypetroleum jelly when ever necessary

    cont.

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    21/48

    Add distilled water to a requiredlevel,Take voltage, Sp.Gr. andtemperature of every cell weekly,

    Analyze the readings and give

    attention to the abnormality ifnoticed.

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    22/48

    Pilot Cell

    Choose 3 cells as pilot cells,In every shift one of the pilot cellreading to be taken,

    Pilot cell should be changed once in ayear, every month is preferable.Voltage, Sp.Gr. and temperature ofpilot cells to be analyzed regularly toascertain the performance of thebattery.

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    23/48

    Maintenance schedules as perCBIP PUBLICATION

    Measurement of Sp.Gr. and cell voltage Monthly

    Checking of electrolyte and topping up if necessaryMonthly

    Checking of emergency DC lighting to control room

    Monthly

    Checking of earth fault Yearly

    Checking of strap connection and applying of petroleum jellyYearly

    Battery impedance test Yearly

    Discharge test 3 years

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    24/48

    FLOAT Charging

    After completion of charging cycle ifload is not connected - due tointernal resistance and surface

    leakage, the battery will be drainedslowly. This should be compensatedby applying constant charging current

    with specified value ,

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    25/48

    Trickle Charging

    Due to internal resistance and surfaceleakage, the battery will be drainedslowly. +load current by the batterycharger . AGE charging current 1-2 yrs 1mA/cell 2- 4 2 4- 6 3 6- 8 4 8- 10 5

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    26/48

    ROUTINE CHARGING

    The cells are to be charged atnormal rate. The cells areconsidered to be fully chargedwhen cells gas freely and the cellvoltage and sp. gravity reachnearer specific value. Thecharging current should bereduced to 50% of normal value.

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    27/48

    BOOST CHARGING

    Required to restore the sp.gravity ofelectrolyte .

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    28/48

    Equalizing Charging

    The trickle charging currentcould not be maintainedconstantly, hence due to low

    charging current the batterywill discharge slowly. Tocompensate this discharge

    equalizing charge should begiven every quarterly.cont,

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    29/48

    1.SP.Gravity falls below 5 points2.AH Discharge is more then 10% of

    rated capacity3. Less then 1.85 V of any one cell

    volt duration2.48 v 3to 8 Hrs2.39 v 4 to 12 Hrs

    2.36 v 6 to 16 Hrs2.33 v 8 to 24 Hrs2.30 v 11 to 34 Hrs

    2.27 v 16 to 48 Hrs

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    30/48

    Special Charging

    If any major interruption to the stationi.e.

    major tripping like Bus Bar protectionor LBB

    tripping or interruption of stationsupply for a long duration or B/D ofcharger etc

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    31/48

    PROBLEM AND CAUSES

    Buckling effect

    This is due to too much chargingresulting in unequalexpansion of Positive plates.

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    32/48

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    33/48

    Sulfating

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    34/48

    Causes of SulfatingDuring this process, some of the sulphate

    enlarge to the point where they can'taccept energy so they stay on the platein a very stable crystalline form. Over

    time these sulphate crystals can build-upuntil efficiency is reduced and the batterydies. This process is the main reason forover 80% of all battery problems andfailures.

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    35/48

    SulphatingGood lead acid battery supposed to last 10years and more currently we only get 4 yearsout of it in the best case. In about 80% of the

    cases the reason for decreased batteryperformance is a sulfate buildup on the plates.

    This is due to too little charging. If the batteryis not sufficiently worked, abnormalsulphating results.

    Symptoms of Sulphation

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    36/48

    Symptoms of Sulphation...

    How can you tell if your battery is sufferingfrom excessive sulphation? Highertemperatures are observed during bothcharging and discharging (since a sulfatedbattery puts out a lower voltage, but powerrequirements remain the same so the current

    increases).The net result is that running times of battery

    powered equipment are shorter, electrolytespecific gravity decreases, output is reduced,and charge acceptance is slower and lessefficient.

    Terminal corrosion also increases because thehigher operating temperatures increase water

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    37/48

    Hydration

    Hydration is the action of water onthe lead plates. If a battery isexhausted to a point where theelectrolyte is practically water andcharging is not given at once, or Ifthe plates are not entirelyimmersed continuously in the

    electrolyte.

    Hydration will set up as a white

    creamy substance .

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    38/48

    STRATIFICATIONIn this case a layer of strong acid lies at the

    bottom of the cell for lack of circulation. Strongacid is liberated from the plates under theaction of the charging current and beingheavier than the weak electrolyte, falls bygravity to the bottom of the cell whereeventually a layer of acid with specific gravityas high as 1.4 may gradually buildup. It tends

    to irregular working of plates. It could beovercome by circulation either through stirringup with a paddle or blowing up with an airpump.

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    39/48

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    40/48

    The VRLA Technology(Valve Regulated Lead Acid)

    Evolution of battery design contd

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    41/48

    Evolution of battery design contd.

    Closed Acid starved

    Immobilized Acid

    Vented

    Less Top Acid

    Free Acid

    Conventional

    VentedMore Top Acid

    Free Acid

    Low maintenance Valve regulated

    Oxygen recombination principle

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    42/48

    Oxygen recombination principle

    Oxygen Formed

    during charge

    Oxygen Combined

    Indirectly with Hydrogen

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    43/48

    Special hybrid alloy utilized

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    44/48

    Special hybrid alloy utilized

    Improved cycle life over lead antimony

    Float characteristics of lead calcium

    Excellent deep discharge recovery

    Float current stable throughout life

    Deep discharge cycle test

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    45/48

    Deep discharge cycle test

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    46/48

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    47/48

    ANY QUESTION

    ?

  • 8/13/2019 Installation, Operation and Maintenance of Batteries

    48/48