Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Australian WatertowersInstallation and Set-up Training Package
MONAND Pty Ltd T/A
Safetylec Management Solutions
S
M
S
Phone (07) 40353533 Fax (07) 40353561 Email: [email protected] Box 35 Redlynch Unit 2A 84 Aumuller St Cairns ABN 19 633 938 370
Introduction
• Please take a moment to view this training presentation to assist with worker safety, by learning the correct procedures for handling
the water tower.
• This presentation is a general guide only. Individual towers may vary slightly due to our product improvement program.
Introduction
• Contact the supplier if you are unsure of any aspects of your tower.
• This training package aims to assist the installer to gain a certificate of competency, in the procedures for handling of Quickfill water towers.
General Notes For all Towers
• Do not climb tower under any circumstances
• Regularly check the tower platform has not subsided, and the tower remains level
• If a storm capable of destructive or cyclonic winds threaten, ensure the tank remains full, or lay tower down
• The tower must be emptied and laid down before being relocated
Before Standing The Tower
• It is essential to be fully prepared, prior to the tower being stood.
• Following these guide lines, should ensure safe operation of the fully engineered and patented water tower.
The PadProvide an earth pad, (or a suitable alternativelike concrete strip footings), as a workingplatform to support the Quickfill®.Minimum bearing capacity to be 100 kpa, as a full tower weighs approximately 27 tonnes.
The Pad
• Needs to be a minimum of 7mtrs x 7mtrs• Should be level, with a minimum 100mm step to the
truck filling area, to avoid water damage to the pad.• Clearance for trucks up to 3200mm overall height is
available from a tower erected on flat ground. You must create a higher pad, or lower the truck roadway, to compensate for larger vehicles.
The Pad
The Tower Arrives
• The tower will be delivered laying down on it’s skids
• There are two lifting points located in the middle of the tower
• Note: the tower weighs approx 6.5tonnes empty.
The Tower Arrives
Skids & Lifting Points
Skid
Lifting pointsfor unloadingor relocating
Toolbox
Unloading and Positioning• Engineered lifting points
attached, to be used for loading and unloading.
• Ensure only accredited machinery & lifting equipment is used.
• Ensure competent operators are used for lifting
• Position the tower so when stood, it will be at the centre of the pad Engineered lifting points
Tools & Spares
• Tools are supplied to assist in tower assembly
• Spares are provided to assist in case of gasket or valve damage
The Float Valve Lock
Remove the internal valve float arm travel lock, before the tower is stood
Attaching the Truck Fill Pipe
• Before the tower is stood, the black 300mm outlet water pipe requires attachment
• Remove black pipe & pipe stays from travel brackets• Bolt pipe to valve adaptor flange – a fixed cradle is
provided to assist location. Find 6 x bolts required in toolbox, or on the flange
• Attach the pipe support stays to complete the above process
Travel brackets
Travel chain
Flexible water sock(packed for travel)
Black Pipe in Transport Mode
Pipe in Transport Mode
Attaching the Truck Fill Pipe
Flange
Pipe stay brackets
Pipe stays - travel mode
Standing The Tower
• Ensure the tower is positioned so when stood, it will be at the centre of the pad
• Detach master link from the travel shackle
• Attach the lifting machinery directly to the link – do not add extra chain/sling. Master LinkMaster link & shackle
Standing the Tower
The tower must be raised slowly &
smoothly
Boom must remain as close as possible to
top of tank
Caution re lid damage with hook
Standing the Tower
• Release the lifting chain by unhooking from the lifting ring at the bottom of the tower
• Use machine attached to the master link to draw the chain thru the top beam, so disconnection is within easy reach of ground staff
• Disconnect master link. Lock to lifting ring using the recovery chain, to prevent tampering
Standing the Tower
Release hook from lifting ring
Master link attached to crane hook
Standing the Tower
Drawing chain thru top beam to bring machine disconnection to ground staff
Hook
Master link
Hook recovery chain
Securing the Lifting Chain
Master link locked to lifting ring, using recovery chain
Lifting ring
Recovery chain & lock
Master link
Securing the Standing Tower
• Swing all four legs out to approx 45 degrees, & secure in position with the pivot pins provided – replace locks
• Remove sole plates from storage. Place on level ground, centrally under the screw jacks
• Wind the jacks down, and use to raise the tower support frame to the level position
• Pack under the tower support frame (if levelling required), and lower onto packers. The levelling jacks must maintain a light support to provide stability, and to secure the sole plates
• Lock the jack handles to avoid tampering, or sole plate theft.
Caution:* Only adjust the screw jacks while the tank is empty* Ensure jacks do not carry the weight of a fully laden tower
Securing the Standing Tower
Swing out legs
Tower support frame (skid)
Screw jack on sole plate
Pivot pins
Handle Lock
Pivot pin lock
Plumbing Connections
• Connect 100mm inlet piping to allow filling by either a standpipe, or a pump. A poly pipe adaptor is supplied in toolbox
• If using a pump, you may need to connect the 80mm bypass return line. Check the 80mm bypass valve is open before pumping
• Note: If pump flow rate is greater than 25 litres/sec (1500 l/min), the excess water may flow out the 80mm bypass, while the tower is filling. This can be reduced or eliminated, by slowing the pump flow rate
• If two or more towers are to be linked, connect via the 150mm pipe work to allow water levels to equalize
Plumbing Connections
150mm pipe for joining towers together if larger storage capacity required
80mm Valve
80mm return outlet40mm general purpose valve 100mm inlet
Ready To Operate !!
The
patented and fully engineered water toweris now ready for use!
A Quickfill In Operation
Lowering The Tower• Disconnect all plumbing connections
• Before lowering the tower ensure the tank is fully drained – this includes all plumbing pipes (note to open the 40mm valve to drain the 150mm linking pipe).
• Jacks must be fully raised and the pivot pins removed, before the four legs are folded in to meet the tower.
• Replace & lock the pivot pins. Lock the jack handles.
• Secure the outer legs, using the turnbuckle which connects the screw jack to the tower support frame (skid).
• Store the sole plates using the pin & lock provided.
Lowering The TowerJacks raised
to fit into skid
Open all valves to drain pipes completely
Pin & lock to sole plates Turnbuckle to jack
Handle locked
Pivot pin locked
Lowering The Tower
• Unlock master link from the lifting ring, and attach to the machine
• Have machine raise the chain, while pulling the lifting hook down, using the 6mm recovery chain attached
• Attach the lifting hook to the lifting ring & arrange hook recovery chain in the travel position. Lock chain.
• Move the machine backwards to allow it to gently lay tower down
• Unhook machine from the master link and attach link to the travel shackle
Lowering The Tower
Unlock master link from lifting ring
Raising master link to recover hook and attach to lifting ring
Attach hook to ring
Chain travels on hook Chain lock
Lowering the Tower
The tower must be lowered slowly &
smoothly
Boom must remain as close as possible to
top of tank
Caution re lid damage with hook
Preparing the Tower for Travel
• Lock the internal float arm & tank lid• Secure the master link to the travel shackle• Remove the 300mm outlet pipe • Store outlet pipe and pipe stays in travel brackets, and
secure for travel. Fold water sock into end of pipe.• Place bolts, tools and spares in toolbox• Ensure 17 locks (13 std & 4 long shank) are in place
Preparing the Tower for Travel
Master link to shackleLock the float valve arm & the tank lid before transportation
Pipe in Transport Mode
Preparing the Tower for Travel
Flange
Pipe stay brackets Pipe stays - travel mode
Note: 1/M20 pipe stay bolt is used to secure pipe stays in travel mode. Nip up bolt remaining on big pipe, or store in toolbox.
M20 bolt
Preparing the Tower for Travel
Travel brackets
Flexible water sock(packed for travel)
Travel chain
Toolbox with Spares & Bolts
Document box Containing manual
Lock Location Photos – 17 total
Float
Tank lid Jack - erected
Jack - travel
Pivot pin
Lock Location Photos – 17 total
80mm valve & 40mm valve
Recovery chain securing master link
Toolbox, documents, valve handle
Recovery chain, sole plates
Ready for Transport ??
Are bolt & pins in place?
Are outer legs secured to frame?
Are all locks (17off) fitted?
Is black pipe secure & travel chain attached?
Lifting points for unloading or relocating
Document Holder
• The information in this training package is usually supplied on each tower in printed format
• There should be a document holder attached to the toolbox lid
• Please refer to the printed document if you need to confirm any detail of the recommended procedures for the safe operation of your tower
• Alternatively, revisit this website
Thank you
from Australian Watertowers P/L for considering our patented and fully engineered system,
and trust you experience the economies and convenience, intended in the product design
Assessment
• Your assessment is 10 questions with multiple choice answers.
• You must have 10 correct answers to be deemed competent.
• You may refer to the presentation at any time during the assessment.
• Once completed, click on the “send” button. Your assessment will be sent electronically to the training coordinator, & your results given immediately.
• A “Certificate of Competency” and wallet card, will be emailed back to those who have successfully completed the assessment (generally within 7 working days)
Assessment
Click picture to commence assessment.