46
BETTER PROJECTS TOGETHER - INNOVATIONS IN COLLABORATIVE WORKING PRESENTED: CALGARY FOR PMI-SAC: NOVEMBER, 4, 2019

INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

BETTER PROJECTS TOGETHER -INNOVATIONS IN COLLABORATIVE

WORKING

PRESENTED: CALGARY FOR PMI-SAC: NOVEMBER, 4, 2019

Page 2: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

YOUR FACILITATORS

Page 3: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

YOUR FACILITATORS

Page 4: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

VENERUS ADVISORY PARTNERS

SERVICE OFFERINGS

• Procurement and Negotiations Advisory

• Collaboration Working (44001) Advisory

• Claims Management & Dispute Resolution

• Learning and Coaching

https://veneruspartners.com/

4

Page 5: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

PRACTICAL PROCUREMENTTM

WHY ARE WE HERE TODAY?

Page 6: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

LEARNING OBJECTIVES

In this session, we will:

• Review the relationship challenges that typically arise in the project context;

• Identify how collaboration methodologies can ameliorate these challenges;

• Review key elements of these methodologies and explain how they work;

• Show real-life projects that resulted in successful implementations and benefits;

• Discuss strategies for “turning the wheel of change”

Page 7: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

SOME INTERESTING EMPIRICAL DATA

Page 8: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

COLLABORATION AND PRODUCTIVITY

SOURCE:McKinseyConstructionProductivitySurvey

5,000construction-industryCEOsrepresenting:assetowners,engineeringandconstructionfirms,suppliers,otherinstitutionssuchasconstructionconsultingfirms,academics,andindustryassociations.E.g.CSI

Tested10causesforlowconstructionproductivity

Page 9: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

COLLABORATION AND PRODUCTIVITY

SOURCE: McKinsey Construction Productivity Survey:

“There is a need to move away from the hostile contracting environment that characterizes many construction projects to a system focused on collaboration and problem solving”

Page 10: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

COLLABORATION AND PRODUCTIVITY

SOURCE: The American Institute of Architects: Integrated Project Delivery: Case Studies (2010)

“Traditional design and construction contracts seek to manage risk by narrowly defining roles and responsibilities. Each participant must then be vigilant to limit the scope of their activities to prescribed parameters, which reinforces isolating “silo” behavior, limiting collaboration and precluding an aligned focus on the good of the project.”

Page 11: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

TRADITIONAL VERSUS COLLABORATIVE RELATIONSHIP

Page 12: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

TOP “COMPONENTS” OF THE SUCCESS OR FAILURE OF COLLABORATIONS

Presence (favourable) or absence (detrimental) of:

1. Alignment on Objectives2. Effective Communication (internal/external)3. Trust4. Leadership

5. Incentive/KPI’s6. Process/Governance7. Plan for “evolution” e.g. major change, renew, exit8. Defined Roles/Responsibilities

Source:2015McKinsey– JointVenturesandAlliancesSurvey.Andourcollectiveexperience

Page 13: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

IS COLLABORATION ALWAYS A GOOD IDEA?

• Collaborative relationships take investment; And deserves an appropriate return

• Because of the investment, collaboration should have a strong link to strategic goals

• Relationships can incorporate varying degrees of collaboration (not always “all in”)

• Collaboration is not useful to all relationships.

Page 14: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

TYPES OF PROJECTS WHERE COLLABORATION MAY BE BEST SUITED

• High Complexity• a High risk and innovative endeavour where significant knowledge transfer will be required

• Market Capability• A project where no one supplier has the market capability or breadth of operations to

undertake without incurring significant enterprise risk

• Longer term alliance • A project that forms the basis of a longer term program wishing to formalise the value add

and improvement over the cycle of projects within the program

Page 15: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

COLLABORATIONMODELS

Page 16: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

• Project Alliances: Any Industry

• NEC 4 (New Engineering Contract v.4, 2017): Construction-specific

• Integrate Project Delivery (IPD) : Construction-specific

• ISO 44001 : Any Industry

AN INVENTORY OF COLLABORTION MODELS

Page 17: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

• Joint Purpose (which explains the need for the collaboration)• Shared Vision/Aligned objectives for what the collaboration should be

• Commitment to the Purpose (with accountable leadership/sufficient resources)

• Establish, Develop and Maintain Trust (including the “right” communication methods)

• Use a SYSTEM for Collaboration (a collection of resources: leadership, governance structures, processes, tools, etc. that enable collaboration)

• Monitor and Measure Collaboration• Create a measurement method. e.g. “SMART KPI’s”, etc., liked to Vision/Goals

• Evolve the Collaboration - Or Exit (if not remaining well aligned to vision/goals)

COMMON CHARACTERISTICS AMONG MODELS

Page 18: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

FOCUS ON IPD

Page 19: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

• Originated in the United States, mid-late 2000’s.

• A “project delivery method” with a complimentary form of contract. Incorporates:

• Lean Construction Methods• Building Info. Modeling (BIM) Technology• Collaboration Techniques

• See: http://ipda.ca

INTEGRATED PROJECT DELIVERY (IPD)

Page 20: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

WHAT DOES THE IPD MODEL LOOK LIKE?

Source:IPDFrameworkbyHowardW.Ashcraft

Page 21: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

HOW DOES IPD WORK?

Source:IPDFrameworkbyHowardW.Ashcraft

Page 22: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

HOW DOES IPD WORK?

Source:IPDFrameworkbyHowardW.Ashcraft

Cross-FunctionalTeamworksoutof“BigRoom”:

• Architect;• Engineer;• Contractor’s• Superintendent,• TradesForemen

Page 23: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

FOCUS ON ISO 44001

Page 24: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

ISO 44001 OFFERS A CONSISTENT, SYSTEMS-BASED APPROACH

New ISO 44001 - Collaborative business relationship management systems:

“A strategic lifecycle framework toimprove collaborative businessrelationships in and between

organisations of all sizes.”

First international standard of its type

Page 25: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

ISO 44001 – ORIGINS

Page 26: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

ISO 44001 – SUMMARY VIEW

• ISOusesa“10Clause”structureformanyofitsstandards.

• Clauses1-3,aremereformalism.3-10Clausesare“operative”

• Clause8isborrowedfromtheoriginalBSI11000,Lifecycle

Page 27: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

ISO 44001 FUNDAMENTALS

• Collaboration between individuals is relatively common but transitioning this to collaboration between organisations is more complex and requires a systems base approach.

• ISO provides a framework within which to create a Relationship Management Plan (RMP).

• Integration can be optimised by focusing on the interfaces between organisations and leveraging what each does best – enabled through a joint business process and aligned objectives.

• A collaborative approach has been shown to release potential value and innovation.

• Collaboration is not a solution but does offer an alternative perspective to the value chain.

Page 28: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

ISO 44001 – HOW IT WORKS

Page 29: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

SUCCESSFUL IMPLEMENTATIONS AND BENEFITS

Page 30: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

SUCCESSFUL IMPLEMENTATIONS AND BENEFITS – UK RAIL SECTOR

• 90% decrease in Owner PM costs (from ~ 6-7% to ~ 0.56%) vs. conventional contract

• 65,000m3 excavated material saved

• 80% reduction in design rework through integrated team and self-assurance model

• 18 month betterment in achieving regulatory milestone

• Industry leading safety

• The same alliance team secured the a new project where it aims to replicate success

Page 31: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

SUCCESSFUL IMPLEMENTATIONS AND BENEFITS – UK NORTH SEA FEEDBACK ON COLLABORATIVE CONTRACTS EXCUTED

• Case study 1 - Collaboration meant that each organisation understood the key drivers of the other collaboration partners. The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost performance.

• Case Study 2 - The existing relationship between client and contractor was already collaborative and successful, but the tight timeline and added complexity of re-using existing plant and materials required extremely close communication and open dialogue. The ECITB Project Collaboration Toolkit provided a framework to take a fresh look at the relationship and how it could be strengthened to overcome the particular challenges of the project. Project has demonstrated that applying a collaborative strategy to small / medium sized project scopes can deliver similarly enhanced project delivery performance to that which major ECITB PCT pilot project scopes have experienced and reported

• Case Study 3 - many projects lose efficiency because of multiple versions of the same reports, role duplication and man marking etc. The project strongly followed its axioms of ‘one team, one project, one source of the truth’ and a fit for purpose approach to the use of corporate standards and standard industry practice.

• Case Study 4 - The Callater project discovery well results came in during August 2015 and it achieved first oil in May 2017. A rapid development, 23 months after discovery. It was five weeks ahead of the field development schedule and achieved 10% savings on budget. The project had an outstanding safety record. The project team put their success down to following an effective collaborative approach from the very beginning using pre-existing arrangements with topsides and subsea contractors. They all know the Callater project is a repeatable, transferable and sustainable example of delivery with collaboration at its core.

• Reference - https://www.ecitb.org.uk/portfolio-items/project-collaboration-toolkit-2/

Page 32: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

IPD PROJECTS HAVE SHOWN BETTER RESULTS

J.Constr.Eng.Manage.2013.139

Page 33: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

MANY IPD PROJECTS HAVE BEEN EXECUTED IN US/CANADA (2010)

Page 34: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

AUSTRALASIA EXPERIENCE - COST

Reference;PerformanceofProjectAlliancinginAustralasia:aDigestofInfrastructureDevelopmentfrom2008to2013,DerekHenryThomasWalker,JamesHarleyandAnthonyMills

Page 35: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

AUSTRALASIA EXPERIENCE – CLIENT PROJECT VALUE STATEMENT

Reference;PerformanceofProjectAlliancinginAustralasia:aDigestofInfrastructureDevelopmentfrom2008to2013,DerekHenryThomasWalker,JamesHarleyandAnthonyMills

Respondentsalsonotedthat,duetotheflexibilityofprojectdeliveryapproach,alliancingeffectivelyallowsprojectsthatareofhighriskorhavecomplexunknownfactors,tobemanagedefficientlywhilstalsoengagingininnovativepractices.

Page 36: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

“TURNING THE WHEEL OF CHANGE”

Page 37: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

TURNING THE WHEEL - DEMONSTRATING VALUE FOR MONEY

How do you convince your organisation that changing its existing practices to adopting a methodology based on trust is actually reducing their risk rather than increasing it?

Page 38: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

5. TURNING THE WHEEL – CHANGING PERCEPTIONS OF KEY STAKEHOLDERS

Stakeholders Perceptions/Concernsre:CollaborativeContracting

Mitigatingactions/demonstrations

ExecutiveLeaders Howwillthisdeliverbetterresults?WhatistheBusinesscase?

Showthebusinesscase

BudgetHolders(allparties) Howmuchcontrolarewegivingup? Aligntheprojectobjectives;Understandtheobjectiveofotherandtheyarenotincompatiblewithoverallprojectobjectives.

SupplyChain Withouttheusualsourcingstrategyhowdoweensurethelowestcost?

Focusonoverallvalue.OpenbookapproachandactionplantoverifyTOC/Contractorestimates

CommercialandRisk Whocarriestherisk?WhereistheRiskallocationcarried?

RiskSharingversuslayeredriskineachcontract.Equityissharedriskandreward=aligningcommonobjectivesandbehaviors

EngineeringandDesign Howdowemaintainquality? Alignedobjectivestohaveupfontengagementandearlyandongoingvalueengineeringwithoutjeopardisingengineeringverification.

Legal Whatdoesthecontractslooklike?Whatlegalremediesarewegivingup?

Contractelementsreflectbothpositiveandnegativeoutcomesandaddressprocessesforboth.

ContractorProjectManager Disputeresolutionofprojectdecisions- Whohasfinaldecision?

Ensureunderstandingofcommongoalsandtheprocessforbestforprojectdecisionmakingatsteeringcommitteelevel

ClientProjectManagement Whomakestheprojectfinaldecisions? Facilitatetheengagementwithpartnerstoenablefrontendplanningandearlyalignment.Ensureunderstandingofcommongoalsandtheprocessforbestforprojectdecisionmakingatsteeringcommitteelevel.

Page 39: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

TURNING THE WHEEL - DEMONSTRATING VALUE FOR MONEY (VFM)

Key to motivating the move to Collaboration, is show the VfM to leaders who control resources useful to support collaboration. In a construction context, this will involve:

• Understanding the preferred contractor’s processes

• Evaluating the Target Cost

• Ongoing verification of Actual vs. Target

Page 40: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

SUPPORTING THE CHANGE TO COLLABORATIVE METHODOLOGIES

Page 41: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

CONSTRUCTION OWNERS ASSOCIATION (COAA)

COAA Leadership identified that Collaborative Contracting is the top rated initiative to improve productivity on projects:

• A “Collaborative Contracting Committee” was created by the Board

• Committee tasked to investigate/develop a Collaborative Contracting Framework

• Nicki and Richard are members of this Committee

Page 42: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

COAA COLLABORATIVE FRAMEWORK

Reference:COAA

Page 43: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

FRAMEWORK COMPONENTS

The Framework shall be in the form of a white paper, posted on the COAA website (in early 2020) and shall include:

• Flowcharts

• Checklist

• Comparison of a global sample of Collaborative Contract Model (T&C’s)

• Risk Management methodology

• Maturity Assessment

Awareness and Knowledge will be provided by willing COAA collaboration partners

Page 44: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

INDUSTRY COLLABORATION

Reference:COAA

PMISCMA

VAP

Page 45: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

QUESTIONS?

Feel free to contact us at:

e: [email protected]: [email protected]

Page 46: INNOVATIONS IN COLLABORATIVE WORKING - PMI …...The parties were therefore aligned on management of risk and the project was delivered safely, on-time and with a top quartile cost

THANK YOU!